Professional Documents
Culture Documents
Quarterly Progress Report of July - September, 2021
Quarterly Progress Report of July - September, 2021
2021
April-June, 2021
Quarterly Progress Report July - September, 2021
ABSTRACT
This report describes the activities of the project's present situation and progress of the Rural
Transport Improvement Project-II Additional Financing by World Bank to repair/ rehabilitate the
damage & dilapidated works by the flood, 2017 during the July - September, 2021. This
additional financing has three components a) Accessibility Improvement, b) Institutional
strengthening, Capacity Building & Governance Enhancement c) Rural Transport Safety.
Accessibility Component: Design & Supervision Consultant has prepared all of the design
drawing for the damaged or repair work packages as per the procurement plan. There are 152
packages out of which 10 packages dropped for different reasons, such as work taken by other
projects; the estimated cost was surpassed from DPP cost and considering the importance of the
adopted road. upto the end of June/2021, 123 packages of civil contracts are awarded and 01
package is in IFT stage & 18 packages are in Evaluation stage, totaling 142 effective packages.
Despite COVID-19 pandemic, works of 35 packages have been completed, 5 packages cancelled
due to non-performance of the contractors and the rest 59 packages are going on presently out of
the total awarded 99 packages in first tranche. Works of 24 newly awarded packages are yet to
start. The cumulative physical progress of awarded 99 packages achieved up to this quarter is 76%
& financial progress is 69%. As works of newly awarded 24 packages are not yet started, the
overall physical & financial progress in terms of money come down to 65% and 58% respectively.
So far, 285km roads in 35 packages is completed 100% & 286km roads in 21 packages is more
than completed 90%.
Road Safety: It is one of the vital components in additional financing project, which includes
Engineering, Enforcement, Education, and Awareness & Audit. To accomplish this, we have
incorporated the items related to road safety in the Estimate and Bill of quantity. The Road Safety
expert is designing & in corporating this issue in civil work contracts.
Climate resiliency also addressed in the sub project design by keeping formation level of roads
above HFL & providing bridge/ culvert/ drainage/ slope protection/ RCC pavement as required
considering the hydrological characteristic of the area.
In Bangladesh, Government has declared general leave & lockdown from 26 th March/2020 to
prevent/ transmission of the COVID-19 pandemic. Everybody was ordered to stay home. Other
Offices, business centers, Banks, etc. were closed and movement was restricted. This situation
drastically deterred the progress of the project. Some contractors have demobilized their working
labors. Consultant key/ non-key Professional was working at duty stations staying at home. This
situation is continuing that effects the Progress of RTIP-II-AF.
From 31st May/2020 the lockdown relaxed with some conditions such as limit the movement of
individuals, maintain personal safety, social distancing, wear musk, clean hand frequently ensure
PPE and maintain other health and regulations. These relaxations also aggravate this situation of
i
Quarterly Progress Report July - September, 2021
infections. More & more people were going infected as detected by increase in testing. Due to such
an unprecedented outbreak of COVID-19 and heavy rains causing flood, which was unusual,
deterred the physical progress. However, floodwater recession started at the end of
November/2020. Considering the situation & apprehended second wave of COVID, LGED & World
Bank mutually agreed to extend the project completion time for a duration of 18 months. A formal
letter was transmitted to World Bank for extension of the project by another 24 months upto 30 th
June/2023. In this respect restructuring & recasting (Development Project Proforma-DPP) is done
& under process for approval by GOB & WB.
The Design & Supervision Consultant continued working in association with PMU. The consultants
have advised PMU for doing the jobs defining some targets.
A World Bank Supervision Mission launched starting from 24 th, January to 2nd, February/2021. The
Mission paid an in depth review of all different aspects of the projects, implementation status,
procurement, social & environmental safeguard issues, governances, consultancies, different
services contacts related to governance & capacity building, reimbursement disbursement. The
mission has critically analyzed the project period, apprehended second wave of COVID-19, the
project present pace of progress, remaining implementation periods, audit status & also future
investment dimensions. A lot suggestion & recommendations were agreed between LGED & the
WB.
Hence, some more measures are taken to expedite the progress of project, which are as follows:
Conduct regional review meeting with the district Executive Engineers, Consultants &
Contractors.
Conducting Virtual Meeting with the 18 districts Executive Engineers, AREs, FSEs to prepare
work schedule, expedite the progress in this pandemic situation, and monitor their
activities.
Start virtual progress review meeting at the last Tuesday of each month with PMU & WB
where representative of WB will participate which is continuing.
Continue field visit with the consultants to supervise the ongoing works as well to give the
technical decision of the new packages concurred by WB.
Advice Executive Engineers to initiate the starting of the physical works of the packages
which are awarded but mobilization not yet started although peak working season is
running.
Address the issues relevant to COVID-19 at work site, Occupational health safety, to
prevent transmission & ensure to follow the guidelines of WHO & ILO.
Continue follow up the Comprehensive Plan to combat COVID-19 as an emergency
measure by assigning milestone & by imparting training at field level professionals,
supervisors & workers & monitor the activities.
It is also decided to include items relevant to restrict COVID-19 transmission in Bill of
Quantity of Construction subprojects henceforth.
ii
Quarterly Progress Report July - September, 2021
Abbreviation
AADT : Annual Average Daily Traffic
ADB : Asian Development Bank
AF : Additional Financing
APO : Annual Plan of Operation
ARE : Assistant Resident Engineer
BM : Bench Mark
BMD : Bangladesh Meteorological Department
BOQ : Bill Of Quantity
BWDB : Bangladesh Water Development Board
CBR : California Bearing Ratio
CVD : Commercial Vehicles Per Day
DCP : Dynamic Cone Penetrometer
DDC : Development Design Consultants Ltd.
DFID : Department For International Development
DPP : Development Project Proposal
D&SC : Design and Supervision Consultancy
EA : Environmental Assessment
EDM : Electronic Distance Measuring
EMP : Environmental Management Plan
FGD : Focus Group Discussion
GAD : Gender And Development
GCM : Growth Centre Market
GOB : Government of Bangladesh
GPS : Global Positioning System
GRC : Grievance Redress Committee
HFL : Highest Flood Level
HQ. : Head Quarter
ICT : Information And Communication Technology
IDA : International Development Association
IDB : Islamic Development Bank
IEM : Information Exchange Meeting
IFT : Invitation For Tender
IP : Indigenous People
ISO : International Organization For Standardization
JICA : Japan International Cooperation Agency
Km : Kilometer
LAP : Land Acquisition Plan
iii
Quarterly Progress Report July - September, 2021
iv
Quarterly Progress Report July - September, 2021
2. Rationale For Additional Financing (AF) And Location Maps Rationale for RTIP-II Additional
Financing...........................................................................................................................................................................................................
5. Components of project:..................................................................................................................................................................
5. 1. Accessibility component...............................................................................................................................................................
5. 2. Engineering Design..........................................................................................................................................................................
5. 3. Climate Resilience and Environmental Consideration:....................................................................................................
5. 4. Road Safety Consideration...........................................................................................................................................................
10. Base Data of Contract with Physical and Financial Progress against Planned Physical Progress..............
14. Typical Material Test Results, Test Results Which Failed & Had To Be Reworked and Retested..............
v
Quarterly Progress Report July - September, 2021
20. Environmental.................................................................................................................................................................................
20.1. THE EMP COMPLIANCES/IMPLEMENTATIONS............................................................................................................................
20. 2. EMP COMPLIANCES OF THE AF SUB-PROJECTS..........................................................................................................................
20. 3. OCCUPATIONAL HEALTH AND SAFETY..........................................................................................................................................
20. 4. FIRST AID BOX..................................................................................................................................................................................
20. 5. USE OF PPES....................................................................................................................................................................................
24. Procurement Status of Civil Works The following Table shows procurement status of schemes
under Additional Financing of RTIP-II, LGED.................................................................................................................................
vi
Quarterly Progress Report July - September, 2021
LIST OF TABLE
Table 1 : Summary of Tender Document Submission............................................................................................18
LIST OF FIGURE
Figure 1 : Geographical Coverage of Additional Financing of RTIP-II, LGED...............................................6
Figure 3: Work plan for remaining payment to project affected persons under RTIP-II..........................35
LIST OF GRAPH
Graph 2 District wise Physical Progress Achieved (Monetised Quantity) Verses Financial Achieved.…..20
vii
Quarterly Progress Report July - September,
2021
EXECUTIVE SUMMARY
Local Government Engineering Department (LGED), under Ministry of Local Government Rural
Development & Cooperative was implementing (GOB) & International Development Association
(IDA) financed Second Rural Transport Improvement (RTIP-II) since 2012. It is recognized that
the Project has successfully implemented. The project RTIP-II is aimed to improve and
maintain/ rehabilitate rural transport related infrastructure including rural water transport in
26 districts covering mainly eastern parts of Bangladesh (excluding Chittagong Hill Tracts). The
total cost of the project was estimated US$ 417 million with IDA credit facilities US$ 300 million
and the GOB contribution of US$ 117 million. In 2017, Bangladesh has experienced a
devastating widespread and prolonged flooding due to extensive rainfall from June to
October/2017 and the excessive water flow from the upstream rivers originating from India
and disrupted the people’s normal life and damaging the properties. The flood resulted the
interruption of transportation network of Bangladesh damaging numerous LGED roads, bridges
and culverts constructed and maintained by RTIP-II and other projects. These circumstances
dictated urgent rehabilitation and maintenance of rural infrastructures in order to ensure the
smooth connectivity of the rural area. As a result, IDA decided to come forward with additional
financing under RTIP-II in response to the request of Bangladesh to rehabilitate and maintain
the damaged roads to revitalize the socio- economic activities of country. The aim is to improve
the rural accessibility in the 18 districts out of 26 RTIP-II districts in Bangladesh. These districts
are Pabna, Sirajgonj, Tangail, Dhaka, Manikganj, Gazipur, Narayanganj, Narshingdi, Munshigong,
Mymensingh, Jamalpur, Sherpur, Netrokona, Kishoreganj, Sylhet. Hobiganj. Moulvibazar and
Sunamganj. The Total cost of RTIP-II (Additional Financing) is therefore, estimated at about
USS$ 170 million (US$ 100 million from IDA and the remaining US$ 70 million from GOB
funding)
To implement this accessibility component of the project, a Design and Supervision Consultancy
(D&SC) Services is procured for the project. For institutional strengthening, capacity building
governance & road safety work procurement to get the expert services are under way.
The overall objective of the D&SC Service is to provide technical, socio-environmental and
management support to PMU and the districts level officials of LGED to implement the project,
ensuring compliance with the polices/guidelines of the Government of Bangladesh (GOB) and
the International Development Association (IDA).
This Additional Financing (AF) will meet up the cost for rehabilitations and maintenance of
about 1555.68km of Upazila and Union roads in the 18 districts including project supervision. A
procurement plan of the work has been prepared after packaging.
Out of 152 packages, 10 packages have been dropped due to some valid reasons such as work
under taken by others projects, the estimated cost of some packages are abnormally high,
considering the importance of the road and others factors. Design & Supervision Consultant has
prepared all of the Design Drawing for the damaged or repair work packages as per the
procurement plan. Until today, out of 142 effective packages, 123 packages of civil contracts
have been awarded and 19 packages are under evaluation & 01 package is in IFT stage Despite
COVID-19 pandemic, works of 35 packages of civil works have been completed, 59 packages are
going on presently out of total awarded 99 packages in first tranche. Work of 24 package is yet
1
Quarterly Progress Report July - September,
2021
to start and 05 packages have been cancelled due to non-performance of contractor which are
under process of finalization & re bidding. Some of the awarded packages are affected by the
recent Flood/2020, washed away and submerged under water. Proper measure is under taken
to restore the work in order to maintain uninterrupted communication. From previously
awarded 99 packages, the cumulative physical average progress achieved up to this quarter is
76% & financial progress is 69%. As works of newly awarded 24 packages are not yet started,
the overall physical & financial progress come down (in terms of money) to 65% and 58%
respectively at the end of this quarter. It is to be mentioned that so far, 285km roads in 35
packages is completed 100% & 286km roads in 21 packages is more than completed 90%.
It is to be mentioned here that D&SC has checked the submitted schemes and designed,
considering thickness chart, CBR of sub-grade, cross-sectional, level survey, road condition
survey, including road furniture (traffic sign, signal, tree & pole, traffic count etc.) and addressed
the Climate Resilient Issues by providing some relevant components.
Meanwhile the pandemic COVID-19 outbreak in this country starting from 8 th March/2020.
Government has declared general leave and lockdown starting from 26 th March/2020. This is
the global disaster, which severely restricts the progress of work of the project in office as well
as in the field. In some cases, contractors have demobilized the working labors and the stop the
work. Almost all the consultant staffs in the package D&SC-RTIP-II-AF-S1 have been mobilized.
They were working in their duty station as COVID-19 infection decreasing & Government
relaxed lockdown with some conditions such as limit the movement of individuals, maintain the
personal safety, social distancing, wear musk, clean hand frequently ensure PPE and maintain
other health and regulations. At the end of February/2021, there was a decreasing trend of
COVID-19 infections; however, scare exists of the second wave.
A COVID-19 Contingency Plan is formulated & transmitted to Field XENs & AEs as an emergency
step to combat the contagious disease. A Comprehensive plan in the respect is also prepared &
sent to field officials.
It is also noted that devastating flood also hit the project area, which submerged some sub
project disrupting the communication. Some project Roads was away in the flood prone districts
viz Sylhet, Sunamganj, Jamalpur, Kishoreganj etc. However, flood situation stars improving and
2
Quarterly Progress Report July - September,
2021
the work is going on in full swing. It is expected significant progress would be achieved in the
following month.
The works of instructional strengthening, capacity building, and road safety component has got
a new momentum after the WB Supervision Mission held from 20-28 th July/2020. To procure
the services quick action is taken. PMU is working relenting. The safety issue is addressed with
utmost care in BOQ and in field implementation. A World Bank Supervision Mission launched in
the last quarter starting from 25th January to 2nd February/2021. The Mission paid an in-depth
review of all different aspects of the projects, - implementation status, procurement, social &
environmental safeguard issues, governances, consultancies, different service contracts related
to governance & capacity building, reimbursement disbursement. The mission has critically
analyzed the project period, the project present pace of progress, remaining implementation
periods, audit status & future investment dimensions. A lot suggestions & recommendations
were agreed between LGED & the WB.
The following measures are to be taken by PMU & D&SC Consultants to expedite the physical
progress, governance & institutional strengthening, capacity building & road safety issues:
3
Quarterly Progress Report July - September,
2021
1. INTRODUCTION :
Rural Transport improvement Project (RTIP-II) was implementing under Local Government
Engineering Department (LGED) since 2012 with the assistance of World Bank & Government of
Bangladesh (GOB). It is recognized that the Project has successfully implemented. The project
RTIP-II is aimed to improve and maintain/ rehabilitate rural transport related infrastructure
including rural water transport in 26 districts covering mainly eastern parts of Bangladesh
(Excluding Chittagong Hill Tracts). The total cost of the project was estimated US$ 417 million
with IDA credit facilities US$ 300 million and the GOB contribution of US$ 117 million. In 2017,
Bangladesh has experienced a devastating widespread and prolonged flooding due to extensive
rainfall from June to October and the excessive water flow from the upstream rivers originating
from India, disrupted the people’s normal life, and damaging the properties. The flood resulted
the interruption of Transportation network of Bangladesh damaging numerous LGED roads,
bridges and culverts constructed and maintained by RTIP-II and other projects. These
circumstances dictated urgent rehabilitation and maintenance of rural infrastructures in order
to ensure the smooth connectivity of the rural area.
To reinstate the communication system so as to revitalize the rural economy economic world
bank come forward with an assistance of US$ 100 million in response to the request of GOB as
an additional financing. Accordingly, the Project Period is extended up to June/2021. However,
due to COVID-19 the progress of AF packages slows down, GOB & WB mutually agreed to extend
the project period for another 24 months, according restructuring of the project is done.
2. RATIONALE FOR ADDITIONAL FINANCING (AF) AND LOCATION MAPS RATIONALE FOR RTIP-
II ADDITIONAL FINANCING
The country experienced devastating and prolonged flooding in 2017 as a result of the extensive
rainfall recorded from June to October as well as due to excessive water flow from the upstream
rivers in India disrupting normal life and damaging properties in several districts. This flood
caused severe interruptions in the transportation network in the vast area of the country and
induced damages to numerous LGED roads, bridges and culverts constructed and maintained
under RTIP-II as well as other projects. The situation lead to the recognition of the urgent need
for rehabilitation and maintenance of rural infrastructures in order to support the smooth
connectivity of road network in the rural area. Consequently, IDA and GOB came to a decision
on additional financing under RTIP-II to rehabilitate/ maintain the flood-damaged roads in
relatively more affected 18 districts of the 26 RTIP-II districts.
Annually, flooding in Bangladesh claims hundreds of lives and causes serious damages to
thousands of houses and public infrastructure, especially in transport sector. During 2017, rise
of water levels in the various rivers in the northern part of the country due to heavy rainfalls as
well as water flow from the upstream hills led to the inundation of the river basin areas in the
northern parts of Bangladesh. After the devastating floods of July 2017, second monsoon
flooding occurred in July - September/2020 affecting 31 districts out of 64 districts of the
country. Huge damages were recorded estimated at about US$ 1 billion. Disasters affected the
quality of life or well-being at the personal or household level, especially to more vulnerable
groups, including women, children, and the elderly. There seems to be a correlation between
low quality of life and vulnerability to external shocks: high exposure to disasters was found to
coincide with a significant decline in post-disaster quality of life. Damages to roads and bridges,
4
Quarterly Progress Report July - September,
2021
specially the core network in the rural areas in Bangladesh, cut off the connectivity of the people
to their daily provided services, such as schools, markets and clinics. Such no/ poor connectivity
exists not only during the flooding time, ranging from few hours to a number of days, but also
for months later until the damaged roads and bridges are repaired.
The Additional Financing will address the rural accessibility in a sustainable way under the
climate change scenario. More than 5,000 km of rural roads have been improved/ rehabilitated
under the scope of parent project (RTIP-II). This improvement has provided a better year-round
accessibility to millions of people in the project area. However, climate change has not been
factored in the improvement/ rehabilitation works, posing a risk to the network, including the
roads improved/ rehabilitated under parent project, to be more frequently and seriously
damaged under the events of disaster. With the high level of vulnerability of the transport
network to the climate change in Bangladesh, it is important to take into account the climate
resilient factor throughout the whole life of the infrastructure, from planning to technical
design, implementation and maintenance. This is being addressed under the scope of the AF.
Further, successful implementation of the road safety program in RTIP-I and RTIP-II will be
continued in the proposed AF to ensure traffic safety under the scenario of increasing
motorization rate in rural area of Bangladesh. The most vulnerable road users – pedestrians,
poor people and especially women and children, suffer the most serious consequences of road
crashes. The road crash figure is increasing with the increase in the number and the speed of
motorized vehicles passing through the rural areas. Further institutionalization of the traffic
safety program will be promoted under scope of the proposed Additional Financing.
The proposed Additional Financing by WB is fully aligned with the GOB’s Seventh Five-Year Plan
(2016-2021). The Government has a national strategic vision – Vision 2021. It also has a
Perspective Plan (2010-2021). This plan along with its forerunner (Sixth Five-Year Plan, 2011-
2015) provides strategies for achieving economic and social outcomes of the Vision 2021 and
the Perspective Plan. The Seventh Plan has identified the development of rural infrastructure as
one of its priority areas. The development of upazila and union roads has been set as strategic
priority areas by the plan. The proposed Additional Financing is also fully aligned with the
World Bank Group’s Country Partnership Framework (CPF) (FY 2016-2020). The CPF includes
three strategic focus areas for intervention – (i) growth and competitiveness, (ii) social
inclusion, and (iii) climate and environment management. The Systematic Country Diagnostic
(SCD), which underpins the CPF preparation process, has identified five transformational
priority areas where concerted efforts would produce the highest returns for achieving
sustainable growth and creating jobs. One of the five transformational areas is inland
connectivity. The CPF has resolved that in order to remove the stubborn impediments to job
creation and growth, the World Bank will shift more financing towards energy and transport
infrastructure.
The Additional Financing for the activity will cost around US$ 170 million consisting of US$ 100
million from IDA and US$ 70 million from GOB.
This Additional Financing in the project initially was from 1st July 2019 to 30th June 2021. But
COVID-19 & flood 2020 it agreed by GOB WB to extend the project Period up to 30 June/2023.
The coverage of Additional Financing of RTIP-II is shown in map below.
5
Quarterly Progress Report July - September,
2021
6
Quarterly Progress Report July - September,
2021
It has been mentioned in earlier article that due to many valid factors, physical works under
different components of RTIP-II, LGED could not be completed by June/2018. One of those
factors are heavy rainfall and flood in 2015 and 2017. The damage to infrastructures including
some infrastructures improved/ rehabilitated under RTIP-II, LGED was significant, caused by
2017 flood. This was prominent in 18 districts out of 26 districts covered by RTIP-II, LGED
financed by World Bank. Under those circumstances, World Bank decided to provide Additional
Financing for Rehabilitation of infrastructures damaged by 2017 Flood.
*As a Sr. Procurement and Contract Management Specialist is already working with PMU and as per direction
of Project Director, Procurement Specialist from D&SC has not been posted.
7
Quarterly Progress Report July - September,
2021
Most of the consultant’s key/ non-key staff were mobilized. A consultant office (Head Office)
was housed at 205/4, Hallmark Tower, Rokeya Sarani, Taltola, Dhaka-1207. Consultant Key/
Non-Key Professionals were working at duty stations staying at home. Their works includes,
preparation of estimates/ BOQ, checking bills, checking variation orders. This exceptional
situation eats up almost one working season and restricts the progress of the Project. Now the
situation is improving day by day & consultant continued working at their duty station.
Presently lockdown relaxed & people order to resume their day-to-day activity abiding the
health regulation. Accordingly, most the works started & running full swing during this quarter.
However, unusual rains, flood & COVID-19 continued deterred the expected progress. In this
quarter works of most of the sub project works have started & working.
5. COMPONENTS OF PROJECT:
5. 6. ACCESSIBILITY COMPONENT
A total 1555.68 km road which are damaged by the flood 2017 is approved for rehabilitation
under additional financing. These are located in northern, north eastern and central 18 districts,
the mostly flood affected areas. The topographical situation of these areas is low to medium
terrain. Flood occurs frequently every year. So, if there occur heavy rainfall or even rain fall in
upstream other country the rivers swell, can’t take the excess water that inundates the area-
causing flood.
5. 6. ENGINEERING DESIGN
In designing roads for rehabilitation, first the topography and hydrological character of the area
passing the road is considered & analysed. It is observed that in some cases flash flood occur
that submerges the area and sometimes washed away road, disrupting the communication. The
floodwater stays some hours to day’s even months. Special attention is given in these cases.
There exists a Rural Road Design Standard approved by Government of Bangladesh based on
extensive research.
Earlier Rural Road Design Standard 2005 issued by Government of Bangladesh was being used
in this project. Later on, Rural Road Design Standard developed by Bangladesh University of
Engineering and Technology (BUET) with the assistance of RTIP-II is being used. Both types of
Standards have been followed in Additional Financing Schemes under RTIP-II, LGED. First type
has been used in initial schemes and second type has been followed in later schemes. It needs to
be mentioned that full section is taken for widening with new pavement in case of narrow roads
with overlay in existing portion to achieve required design thickness & strength. For
rehabilitation of existing pavement, required pavement thickness is derived using traffic count
8
Quarterly Progress Report July - September,
2021
and sub-grade CBR data, thickness of overlay is derived by deducting existing pavement layer
thickness from total required as per design. Design type is determined based on traffic count
converted into CVD.
Conducted Road safety field audit of 36 no’s sub project of additional funding by Road
Safety Specialist.
Identified justified required safety measure as per field audit with showing on layout
drawing.
Prepared Road safety Report, Estimate and Layout Drawings (Not to Scale) of 36 no’s
sub projects as per road safety field audit up to June, 2021.
Continuous efforts are given in Road Safety Issues during implementation of the sub-
projects.
List of conducted Road safety field audit of 36 no’s sub projects are shown in following
table:
9
Quarterly Progress Report July - September,
2021
Road Safety issue considered in 36 no’s additional financing Sub Projects up to June ’2021 are as
follows:
Sl.
No District Upazila Package No. Road Name Remarks
.
Sreerampur GC -Basgari
01 Narsingdi Raipura NAR/AF-129
GC
Narkona RH -
KeshoreganJ GC
02 Tangail Madhupur TAN/AF-109
(Fulbaria ) via Kuralia
Hat Road
Konabari GC -
05 Tangail Gopalpur TAN/AF-112 Mahamudpur RHD via
Hadira bazar Road
Daragram GC-Nagorpur
06 Manikganj Saturia MAN/AF-122 GC via Savar & Sonka
bazar Rd.
Kamarkhara Bazar-
08 Munsiganj Tongibari MUN/AF-14
Tongibari -Hasail Road
Kandigaon UP – Sonatola
09 Sylhet Sylhet Syl/AF-101(1)
Bazar Road
Keshobpur-Rasulganj-
11 Sunamganj Jagannatpur SUN/AF-146 TukerBazar -Punaullah
Bazar Rd.
Satbaria-Khairan-
12 Pabna Sujanagar PAB/AF-135
Chinakhoea road
Purnimagati UP-Rajman
13 Serajganj Ullapara SER/AF-137(A)
Hat via Koyra Hat Road
10
Quarterly Progress Report July - September,
2021
Nimgachi GC -Solonga GC
15 Serajganj Rajganj SER/AF-138
Road
Mohirampur RHD-
16 Jamalpur Melendah JAM/AF-115 Hazipur GC
Shabazpur UP-Titpallah
18 Jamalpur Jamalpur JAM/AF-117
Bazar Road
Baijuri GC-Jharkata
19 Jamalpur Maderganj JAM/AF-118 Bazar via Charpakerdah
UP Rd. (Madergonj part)
Mohanganj G.C-Gaglajuri
20 Netrokona Mohanganj NET/AF-131
G.C Road.
Netrokona -Atpara
Netrokona
22 Netrokona NET/AF-133 Brojer Bazar G.C Road
Sadar
(Sadar Part)
Tangail (Tangail
Tangail Mymenshing NHW at
24 Tangail TAN/AF-144
Sadar LGED moor) Aynapur
Road.
Chunarughat - Paikpara
25 Habiganj Chunarughat HAB/AF-114
UP office Road.
Sreebordi-Karnojhora GC
26 Sherpur Sreebordi SHE/AF-140
Road
Sherpur Sherpur-Kamarerchar
27 Sherpur SHE/AF-139
Sadar Road
Nandail HQ – Dewanganj
28 Mymenshing Nandail MYMN/AF-124
GC Road.
11
Quarterly Progress Report July - September,
2021
Keshorgonj GC –
29 Mymenshing Fulbari MYMN/AF-127
Madhuppur GC Road.
Duldia GC - Adarshapara
30 Kishorganj Katiadi KIS/AF-119
GC Road
Nandail Bazar –
33 Mymenshing Nandail MYMN/AF-125
Jahangirpur UP Road.
Gaffargaon HQ -Bormi
34 Mymenshing Gaffargaon MYMN/AF-126 RHD(Maizbari) Boraihati
GC
Dhaka – Mymenshing
35 Mymenshing Trishal MYMN/AF-128 RHD (Bailor) –
Kalirbazar GC Road
Dhaka- Mymenshing
Highway (Seed Store
36 Mymenshing Bhaluka MYMN/AF-32 A
GC)-Shakhipur H/Q Road
(Bhaluka Portion)
12
Quarterly Progress Report July - September, 2021
13
Quarterly Progress Report July - September, 2021
14
Quarterly Progress Report July - September, 2021
15
Quarterly Progress Report July - September, 2021
16
Quarterly Progress Report July - September,
2021
17
Quarterly Progress Report July - September,
2021
MYM/AF-126
07 (AF-32A, 68,
Dropped &
Mymensingh 9 8 107, 124, 127,
MYM/AF-32
125, 128
Cancelled
04 (AF-15, 69, 70,
Narayanganj 4 4
71)
12 (AF-16, 17, 18,
Narshingdi 12 12 72, 73, 74, 75, 76,
77, 38, 129, 130)
05 (AF-131, 132,
Netrokona 5 5
133, 134, 19A)
11 (AF-20, 21, 22,
Pabna 11 11 78, 79, 80, 81, 82,
83, 135, 136)
11 (AF-23, 24, 25,
SER/AF-86
Serajganj 12 12 85, 86A, 87, 88,
Cancelled
89, 89a, 137, 138)
07 (AF-26, 90, 91,
Sherpur 7 7
92, 93, 140, 139)
SUN/AF-31 &
04 (AF-27, 106,
Sunamganj 6 4 SUN/AF-94
141, 146)
Dropped.
10 (AF-28, 95, 96, SYL/AF-29 &
Sylhet 12 10 97, 98, 99, 100, SYL/AF-104
101, 101(A), 142) Dropped
10 (AF-30, 34,
102, 109, 110, TAN/AF-103
Tangail 11 10
111, 112, 143, Dropped.
144 & 145)
Cancelled 05
Total 152 142 137
Dropped 10
Total 10 (ten) packages have been dropped. Out of 142 effective packages, D&SC HQ received
142 packages. Out of this, submitted all packages (142 nos) to PMU, RTIP-II, LGED, 123 packages
awarded (including 05 cancelled packages) & 01 package is under IFT and 18 packages are at
Evaluation stage.
18
Quarterly Progress Report July - September,
2021
physical & financial progress in terms of money come down to 65% and 58% respectively. So
far, 285km roads in 35 packages is completed 100% & 286km roads in 21 packages is more
than completed 90%.
19
Quarterly Progress Report July - September,
2021
Graph 2 District wise Physical Progress Achieved (Monetised Quantity) Verses Financial
Achieved.
Gap between physical and financial progress (Above 20%) is only in case of 03 packages. Gap
between physical and financial progress (less than 20%) is only 56 packages. ANNEX-II
The details of all the contract packages as per procurement plan and present status which
shows district name, package name, road name, name of contractor, contract amount, date of
star, date of finished, physical progress, financial progress etc. is shown in ANNEX-III
The data for S curve would be generated/ collected from filed offices. We have instructed the
field Assistant Resident Engineer to send these from the contractors work program or assist the
contractor to prepare work program with respect to time & cash flow. We understand that it is
tough to show the progress in meter/kilometer, as we cannot say single meter/kilometers is
completed until last operation i.e. Shoulder dressing leveling & erection of Road safety items
are done although 90% work of a particular sub project is completed as advised in the comment
on August/2020, MPR. However, we are also exploring to devise a system to address this in S
curve format.
20
Quarterly Progress Report July - September,
2021
10. BASE DATA OF CONTRACT WITH PHYSICAL AND FINANCIAL PROGRESS AGAINST PLANNED
PHYSICAL PROGRESS
Management Information Sheet attached with report shows. The cumulative physical progress
of awarded 99 packages (in first tranche) achieved up to this quarter is 76% & financial
progress is 69%. As work newly awarded 24 packages are not yet started, the overall physical &
financial progress in terms of money come down to 65% and 58% respectively. It can be seen
that in case of some contracts, achieved cumulative Physical Progress is quite close to Planned
Physical Progress, which indicates good performance and initiative from Contractor. If
difference between Planned and Actual Physical Progress achieved ranges between 22%-30%,
as graphical data it is satisfactory. Some contracts are slow performing, such contracts are
MAN/AF-56, MOU/AF-61, SER/AF-25, SYL/AF-101 If the difference between Planned and
Actual Physical Progress achieved is more than 30%, and the contract may be termed as Non-
Performing. Few such contracts are DHA/AF-01, GAZ/AF-35, HOB/AF-36, MAN/AF-59,
MOU/AF-65, SUN/AF-27, MYM/AF-32, N.Gonj/AF-70, N.Gonj/AF-71, SER/AF-87, SER/AF-88,
SYL/AF-28, SYL/AF-97, SYL/AF-98, TAN/AF-30. Possible reasons behind Slow Performing and
Non-Performing Contracts is reluctance of Contractor in following work Plan submitted during
Tender.
Basic Data of Individual Additional financing Scheme & detail information of individual AF
schemes Appended in ANNEX-I. PMU issued warning letter to expedite the work otherwise,
liquidated damage may be imposed due to delay in execution, which causes economic
cost.
21
Quarterly Progress Report July - September,
2021
D&SC HQ Professional Staff, after receiving Detail Estimate of sub-project, carryout desk review
and field appraisal. If there is no problem with relevant papers and unit cost, D&SC-HQ prepares
Engineering Estimate and Bill of Quantity against appraised Detail Estimate and subsequently
submits Tender Document to PMU, RTIP-II, LGED.
After receiving Tender Document from D&SC, PMU RTIP-II, LGED start processing to gets
approval from Head of Procuring Entity (HOPE) and provides approval on Estimate. If any
ambiguity is found, PMU, RTIP-II, LGED requests clarification/ correction/ amendment either
from D&SC or from Procuring Entity. Procuring Entity, after receiving approval on Estimate,
floats Invitation for Tender. After receiving tender, evaluation is carried out by Procuring Entity
and recommendation is adopted based on evaluation. Procuring Entity either decides for Re-
Tender or sends Evaluation to PMU, RTIP-II, LGED. If Tender is approved by PMU, RTIP-II, LGED
22
Quarterly Progress Report July - September,
2021
send approval for Notification of Award. Procuring Entity, after getting approval on tender,
issues Notification of Award, Proceeds on Contract Signing and commencement of work. Based
on evaluation done at Procuring Entity level, HOPE may not approve Tender rather suggests Re-
Tender while Procuring Entity needs to follow that.
After commencement of subproject, supervision, quality control and monitoring are done by
Upazila and District LGED & Project staff as well as by Consultants ARE & FSE at District and HQ.
Level. Payment Certificate is initiated by Upazila Engineer of Project Manager at district. And
D&SC Staff at district level check & verify, forward to D&SC Head Quarter which are finally
forwarded to PMU, RTIP-II, LGED.
D&SC HQ appraises all variation, which are forwarded to PMU, RTIP. Besides that, D&SC is
responsible for different types of report such as Field Visit Report, Monthly/ Quarterly/
Completion etc. as well as Report on Environmental and Social Safeguard issues.
MYM/AF-32 (Cancelled),
MYM/AF-124,127
68 ,107, 125, 128
23
Quarterly Progress Report July - September,
2021
NAR/AF-18, NAR/AF-75,
130
NAR/AF-77
SHE/AF-139, 140 SHE/AF-26,91,92,93 SHE/AF-90
PAB/AF-22, 78, 79, 80, 81,
82, 83, 136, 135 PAB/AF-20, 21
SYL/AF-28, 95, 97, 98, 99,
SYL/AF-101(A) 100, 101, 142 SYL/AF-96
TAN/AF-30, 34, 109, 110,
TAN/AF-145 111, 112, 143, 144 TAN/AF-102
19 Nos 88 Nos 35 Nos
14. TYPICAL MATERIAL TEST RESULTS, TEST RESULTS WHICH FAILED & HAD TO BE REWORKED
AND R ETESTED
Two types of Test have been specified in RTIP-II, LGED. Tests have been specified for all
materials to be used in construction or rehabilitation. Coarse Aggregates need to be tested for:
(i) Gradation, (ii) Water Absorption, (iii) AIV or Los Angeles Abrasion, (iv) Specific Gravity and
(v) Soundness test. Fine Aggregates needs to be tested for: (i) Grading and (ii) F.M. Cement
needs to be tested for: (i) Setting Time and (ii) Strength.
Bitumen needs to be tested for: (i) Penetration Grade, (ii) Specific Gravity, (iii) Softening Point,
(iv) Flash and Fire Point, (v) Solubility and (vi) Ductility.
Concrete needs to be tested for: (i) Workability, (ii) Unit Weight and (iii) Strength. Reinforcing
Bar needs to be tested for: (i) Diameter, (ii) Unit Weight and (iii) Tensile Strength.
Besides Tests of Construction Materials, Quality Control Test has been specified for work done
also. Embankment Fill and Subgrade need to be tested for: (a) PI Value, (b) 4 days Soak CBR, (c)
Field Dry Density and (d) Maximum Dry Density. Improved Subgrade needs to be tested for: (a)
Gradation, (b) 4 days Soak CBR, (c) Field Dry Density and (d) Maximum Dry Density. Sub Base
and Base Course need to be tested for: (a) Gradation, (b) 4 days Soak CBR, (c) LAA, (d)
24
Quarterly Progress Report July - September,
2021
Maximum Dry Density and (e) Water Absorption. Bituminous Carpeting needs to be tested for:
(a) Bitumen Content, (ii) Stability and (c) Density of Mixture.
Contract wise test are performed as per defined type and frequency of test on different type of
items of works. We do not commence work until satisfactory test result is available for
construction materials & ensure the properties of the layers. In case of any type of work where
satisfactory test results are not achieved those works are declared unacceptable & is replaced/
redo to have satisfactory work. It is observed that some tests fails, in that case work is not
permitted to progress until/ unless satisfactory result achieved.
25
Quarterly Progress Report July - September, 2021
8 Munshiganj 3 11 1 4 16 93 109
26
Quarterly Progress Report July - September, 2021
27
Quarterly Progress Report July - September,
2021
MOU/AF-12 PAB/AF-135
28
Quarterly Progress Report July - September,
2021
Key Correspondents during Month of April: No field visit were sanctioned due to imposed
lockdown.
TL IN CHARGE &
2 19/5/2021 21/5/2021 PABNA VISIT SUB PROJECTS
JHDE
VISIT SUN/UZR-79-
3 23/5/2021 PE & JHDE 24/5/2021 SUNAMGANJ
STR-34 & RPM-266B
VISIT GAZ/GCM-31 &
4 24/5/2021 MMS & JMO-2 25/5/2021 GAZIPUR
UNR-17-STR-3
29
Quarterly Progress Report July - September,
2021
VISIT SUN/UNR-34-
5 27/5/2021 JHDE & ARE 30/5/2021 SUNAMGANJ
STR-18A
VISIT NAR/AF-
5 07/06/21 MMS,JMO 09/06/21 GAZIPUR,NARSHINGDI 18,GAZ/RPM-
351A,GAZ/AF-40
VISIT TAN/AF-
6 14/6/21 RSS 15/6/21 TANGAIL,MYMENSINGH 145,143, MYM/AF-
125,128,126
7 15/6/21 SURVEYOR-1,2 15/6/21 JAMALPUR VISIT JAM-AF-05
8 15/6/21 JHDE,ARE 16/6/21 HABIGANJ VISIT HAB/AF-45
9 15/6/21 PE,JHDE & JMO 17/6/21 JAMALPUR VISIT JAM-AF-05
1
17/6/21 MMS & JMO 20/6/21 NARSHINGDI VISIT NAR/AF-74
0
VISIT CHA/UZR-
1
20/6/21 PE & JHDE 21/6/21 CHANDPUR 49A,CHA/RPM-
1
179A
1
20/6/21 RSS 21/6/21 MYMENSINGH VISIT MYM/AF-32A
2
1
21/6/21 MMS & JMO 22/6/21 NARSHINGDI VISIT NAR/AF-73
3
1
21/6/21 SURVEYOR-1,2 21/6/21 NETROKONA VISIT NET/AF-19
4
1 VISIT DHA/UZR-8-
27/6/21 SURVEYOR-1,2 28/6/21 DHAKA
5 STR-26A
30
Quarterly Progress Report July - September,
2021
problems that need to be mitigated. Stakeholder's views and suggested solutions are supposed
to be recorded through Stakeholders' Consultation. It has been emphasized special attention for
the protection of Vulnerable Group (Like Women Headed Family), Indigenous People (IP), and
Historical Places (Religious, Heritage, and Cultural).
This report prepared on the above-mentioned conceptual framework; Social Screening has been
carried out using an approved format. Based on filled-in Social Screening Format, required
items have been included in the cost estimate. Implementation of concerned items shall be
monitored during implementation.
This report prepared on conceptual framework; Social Screening has been carried out using an
approved format. Based on filled-in Social Screening Format, required items have been included
in the cost estimate. Implementation of concerned items shall be monitored during
implementation. Based on findings of the Social Impact Assessments (SIAs), major activities are
carried out and included, these are as follows:
31
Quarterly Progress Report July - September,
2021
The subprojects are already submitted of Social Safeguards Screening Reports by the D&SC
Consultant to PMU and IFT but at present PMU is approving the additional proposals which are
at various stages of finalization. The ARE, FSE, CO and District Sociologist are in the process of
preparing the Social Screening Reports for the finalized subproject proposals.
From 1st April to 30th June, 2021, the following social screening reports (SSR and Social and
Resettlement Action Plans (SRAP) have been prepared and submitted by the D&SC.
32
Quarterly Progress Report July - September,
2021
2. Jagannathpur submitted
Sylhet 1. Gowainghat SYL AF-142 SMP
submitted
Land acquisition will not be required for improvement for the above sub projects. Furthermore,
issues of relocation and population displacement are also not expected to arise during the
construction of the sub projects. The proposed roads will be implemented on government land
within sufficient existing Right of Way (RoW) which is enough for implementation of the
proposed sub projects. A Management Plan has been prepared for mitigation of problems if
arise any problem during the construction. Additionally, the proposed sub projects are not
expected to affect any community/common property/cultural center /archeological properties.
Hence, sub-projects implementations are not expected to generate any significant negative
social impacts. The social benefits of these sub-projects are diverse. Through the
implementation of the sub projects, direct and indirect employment will be generated through
the engagement of construction work, which will positively impact the local community. The
project will also require a good number of unskilled workers that will also be taken from the
local community which also contribute to the local economy. People are expected to introduce
modern health facilities for disadvantaged people such as women, PWD (Persons with
Disability), children, the elderly, pregnant women and other vulnerable groups of the society. All
these factors have incremental value on socio-economic aspects as well as the local economy.
Therefore, implementations of the proposed packages of sub projects are safely and highly
recommended.
As recommended by the World Bank Mission 20-28 July/2020 a contingency plan of COVID-19
responds to prevent transmission were issued instantly to field XEN & ARE with direction to
build awareness among workers & field supervision Engineers/ staff. The project Sr. Social
Development Specialist & regional Sociologist will put the utmost effort to address the issues.
33
Quarterly Progress Report July - September,
2021
The Project Director (PD), RTIP-II, LGED is the head of Project Management Unit. The
Resettlement Plans were prepared and implemented under the authority of Project Director.
The PD had to oversee the preparation and implementation of phase-wise land acquisition and
resettlement action plans. The PD is accountable to the Chief Engineer, LGED. The PD followed
up land acquisition, resettlement and Grievance redress processes. It was his responsibility to
ensure that SRAPs are fully implemented, including compensation payment, before the civil
works start on the ground. In this regard, a Senior Sociologist at PMU assisted the PD in land
acquisition and resettlement process including gender and vulnerability. In carrying out the
resettlement activities, LGED utilized its existing staffs at the District & Upazila levels, and has
appointed additional field staffs under this project. The key LGED staff consists of an Executive
Engineer (XEN) in each district, an Upazila Engineer (UE), Assistant Engineer, Community
Organizer and a Surveyor, with other supporting staffs at the Upazila. The project appointed
full-time District Sociologist (DS), Assistant Engineer (RTIP-II) in each district. The Deputy
Commissioner (DC) offices are the acquiring body for land acquisition and pay CUL payments on
behalf of the requiring body, LGED. District Sociologist (DS), Assistant Engineer (RTIP-II)
followed up the acquisition cases at the DC office. In this effort, the PMU was actively assisted by
the Social Scientist and Resettlement Specialist and Social Development/Resettlement Specialist
of D&S Consultants for land acquisition and resettlement services. D&SC Professionals provided
all kinds of the technical services required for preparation and implementation of the SRAP
along with monitoring and reporting. The XENs and UEs coordinated all these activities at the
district and Upazila level and maintained liaise with the concerned DCs and Upazila Nirbahi
Officers (UNOs). The DSs and COs directly worked with the D&SC professionals and participated
in carrying out the process tasks for TPDP preparation an implementation. The PMU also set up
information processing facility to collate and update the resettlement database to monitor
progress in land acquisition and delivery of entitlements with the required number of
appropriately qualified persons.
The process of land acquisition in Bangladesh is very lengthy and cumbersome. Staff resources
and logistics available with the Land Acquisition Section of the DC offices are inadequate.
Incomplete land transaction and lack of updated title documents are among the key constraints
in the land acquisition process. Low level of knowledge of documentary requirements and costs
associated with compensation collection is also affecting payments. Despite all these, the project
has achieved a progress of 94% in compensation payment.
34
Quarterly Progress Report July - September,
2021
Figure 3: Work plan for remaining payment to project affected persons under RTIP-II
All the GRC and SCC Members of RTIP-II already have orientation on their roles, responsibilities
and the function and process of GRC and SCC resolutions through participating in SCM
35
Quarterly Progress Report July - September,
2021
Disclosure Workshops. SCM/GRM Registers and guidelines have already been provided to the
GRC and SCC. It is mandatory to arrange at least one meeting in a month of both committees
even no complaint be received.
It has been reported by the GRCs and SCCs that the committees are organizing at least one
meeting in a month. Sociologists monitor and receive monthly progress reports from the
concern GRCs/SCCs. The Sociologists send the concise report of GRCs along with the progress
report of SCC to the PMU through the concern XEN. All the reports received from the office of
the XENs were reviewed by the Senior Sociologist at PMU. The reports show that no complaints
have been received by the committees during the reporting period. However, the Committees
are maintaining the Registers and writing resolutions of the meetings held.
The reports show that no complaints have been received by the committees during the
reporting period. However, the Committees are maintaining the Registers and writing
resolutions of the meetings held.
In addition to this, the Project Director, RTIP-II noticed that in the month of June, 2021 GRC and
SCC workshop meetings should be arranged in project districts. According to that a daylong
training program/ workshops were conducted in 11 districts out of 18. The Social Scientist cum
Resettlement Specialist attended the programme from D&SC with Sr. Sociologist and Training
Specialist of PMU. The Social Scientist cum Resettlement Specialist presented his subject with the
PowerPoint in the workshop programme. As advised by the Team leader in charge & with the
guidance of Project Director a People’s Perception Survey was devised and conducted with defined
questionnaire on the impression/ benefit of people by the World Bank financed RTIP-II project. A
separate report was also generated and transmitted to PIU.
For the social impacts, each subproject is screened to assess the likely impacts, categorized.
After selection of subprojects, the LGED with the assistance of D&S Consultants has completed a
social screening for the subprojects using an inclusive and participatory approach.
According to engineering design, implementation of these subprojects will be carried out within
the existing right-of-way. The works involve geometric correction and slope improvement for
stability but require no additional land to be acquired.
Results from the social screening for reporting month (June, 2021) are given below.
36
Quarterly Progress Report July - September,
2021
No additional public or private lands will be required for the subprojects outside the
existing right of way.
No private, public, community, or cultural property of any kind of service delivery
facilities as well as commercial activities will be affected.
Preparation of RAP will not be required for implementing the subprojects.
Agricultural or industrial productivity will not be hampered by the proposed subproject areas.
The outcomes of social screening also confirm that local people across the subprojects are
positive about its implementation
A dramatic change has come up in the social and environmental aspect; because of intensive
field visit/monitoring. The use of monitoring checklist has improved awareness among the
contractors, labors and relevant technical personnel. However, the mechanism of motivation is
the major arena to be focused for the implementation of project related environmental and
social activities. It is a regular procedure of project appraisal.
20. ENVIRONMENTAL
As per Project Document, LGED officials in close association of Design Supervision Consultant
and key stakeholders are expected to identify and assess potential positive and adverse
environmental impacts as well as environmental settings. Environmental Screening report has
been prepared for each Package. Based on that, required items have been included in cost
estimate. Implementation of concerned items shall be monitored during implementation.
37
Quarterly Progress Report July - September,
2021
category is below the moderate level, where no sufficient care has been taken for compliances
and there remains more room for compliances.
140
123
120
100
80
60 54
40 35
25
20
2 2
0
Total 100% Satisfactory Moderate Unsatisfactory Yet to Start
Completed
38
Quarterly Progress Report July - September,
2021
The following objectives have been identified to create a positive approach to health and safety
during all activities of the Project:
To avoid all personal injuries during the execution of the Project.
To complete the Project without incurring any significant casualty.
To encourage and motivate both contractor and labor about health safety issues that
supports the achievement of personnel safety.
To appraise the contractor and the labors, who uses the PPE.
To monitor continually HS activities and its improvement.
Proper Emergency Response & Awareness System.
Regular supervision and monitoring are carried out during the construction period to comply
with the Health and Safety requirements as per standard specifications outlined in EMP and in
the Contract. In some sub-projects the practices are not fully complied with the health and
safety requirements as instructions given in the EMP. As such the contractors are advised to
resolve the issues according to the EMP as early as possible.
20. 21. FIRST AID BOX
According to the EMP the contractors have to keep a first aid box for the labors and staffs to be
used as an initial medical treatment. But in some cases, the negligence of the contractor was
noted. Those contractors are advice to refrain from it. The first aid box should contain sufficient
emergency first aid medicine and saline in it to mitigate any adverse situation .
During the visits, monitoring on the level of compliances of environmental issues in the sub-
projects were made and identified the gap of non-complied issues and on-spot consultation
were provided to the concerned contractor/representative to take remedial measures within
the shortest possible time. The contractors/representatives were encouraged and motivated on
the importance and significance of compliances and the methods to be followed as envisaged in
the LGED’s ECP and EMF for improving environmental compliances. Besides, field visit reports
are made on each and every visit, which is delivered to the EMU/PMU for remedial measures
and necessary action.
39
Quarterly Progress Report July - September,
2021
upload the, “Screening Report”, “Environment management Plan”, “Monitoring Report” etc. in
the EMIS.
Regular monitoring has been carried out by the environmental specialist and project team. It
can be observed from the field visits and monitoring checklist that the environmental
compliances scenario has improved remarkably. In most of the areas of compliances, via
environmental signboard, drinking water facility, water and sanitation facility, use of personal
protective equipment (PPE), waste management facilities and labor sheds etc. were found at a
satisfactory level. “Safety First” is a prime issue of any construction work and in this project,
staffs are always trying to encourage all the workers for using Personal Protective Equipment
(PPE). During field visits by the field professionals, various environmental issues were
addressed and recommendations forwarded to the concerned LGED officials and contractors or
their representatives for the remedial measure (if any).
A dramatic change has come up in the environmental aspect; because of intensive field
visit/monitoring. The use of monitoring checklist has improved awareness among the
contractors, labors and relevant technical personnel. However, the mechanism of motivation is
the major arena to be focused for the implementation of project related environmental
activities. It is a regular procedure of project appraisal.
21. CLIMATE RESILIENT ISSUES:
Bangladesh is one of the climate vulnerable country. There exists a distinctive seasonable
variation in climate. Three side of the country is surrounded by the by land boundary of India.
Only the southern side is Bay of Bengal. 53 (Fifty-Three) big rivers originating from India & 04
(Four) from Myanmar is flowing over Bangladesh. So, the country faces natural disaster like
cyclone, flood each year. Sometime during monsoon, there occurs flash flood due to water
coming from upstream India by the flowing rivers & heavy rain, which cause damage of roads &
disruption of communication. The monsoon season is critical for Construction due to
continuous rains & thunder, scarcity of construction materials & labors etc. which slows down
the progress of physical works.
While designing the roads with appurtenant structures in selected alignment we have
seriously addressed the climate resilience issues. We have taken information of HFL of the road
& flow trend of the water, hydrological & topographical characteristics of the area. This also
dictates to observe the level difference or head difference of two sides of the road & the water
flow trend. Considering those issues, we have provided required drainage structures with
required length. We have tried to provide the formation level of the road 600mm above HFL as
defined in Road Standard.
D&SC is exploring the innovative material and method for slope protection of the embankment
substituting the CC block protection with Jute tex, Vetiber Grass etc which eventually would
reduce the cost of embankment protection making climate resiliency. We have already trying to
contact with Jute Research Institute.
40
Quarterly Progress Report July - September,
2021
41
Quarterly Progress Report July - September,
2021
42
Quarterly Progress Report July - September,
2021
Geo-hazard Risk
Management
43
Quarterly Progress Report July - September, 2021
Package Length
SL Progress in (%) Package Name
Number (Km)
GAZ/AF- 2,GAZ/AF-41,HAB/AF-3,HAB/AF-4,HAB/AF-37,HAB/AF-43,HAB/AF-44,HAB/AF-
46,JAM/AF-05, JAM/AF-47,JAM/AF-48,JAM/AF-49,KIS/AF-7,KIS/AF-8,KIS/AF-53,MAN/AF-
10,MOU/AF-12,Mun/AF-13,
1 35 100% 285.34
Mun/AF-66,N.Gonj/AF-15,NAR/AF-16,NAR/AF-17,NAR/AF-18,NAR/AF-75,NAR/AF-77,NET/AF-
19(A), PAB/AF-20, PAB/AF-21,SER/AF-24,SER/AF-25,SER/AF-85,SHE/AF-90,SUN/AF106,SYL/AF-
96,TAN/AF-102
GAZ/AF-39,GAZ/AF-42,JAM/AF-50,KIS/AF-51,KIS/AF-54,KIS/AF-55,KIS/AF-64,KIS/AF-84,
2 21 90-99% 285.88 MOU/AF-62,MYM/AF-107,NAR/AF-72,NAR/AF-73,NAR/AF-76,PAB/AF-79,PAB/AF-81,PAB/AF-
82, SHE/AF-26,SHE/AF-91,SHE/AF-92,SHE/AF-93,SYL/AF-100
44
Quarterly Progress Report July - September, 2021
24. PROCUREMENT STATUS OF CIVIL WORKS THE FOLLOWING TABLE SHOWS PROCUREMENT STATUS OF SCHEMES UNDER ADDITIONAL FINANCING OF
RTIP-II, LGED.
45
Quarterly Progress Report July - September, 2021
DHA/AF-
Dhaka 3 3 3 3 - - 2 DHA/AF-01, 105 (AF-105 Cancelled)
105(A)
- - 0 1 18
Total 152 10 142 142 142 123
- 0 19
46
Quarterly Progress Report July - September,
2021
Disbursement FORECAST:
47
Quarterly Progress Report July - September,
2021
2012- 3 3 x 1 1 x x
2013
2013- 5 5 x 9 9 x x
2014
2014- 1 1 x 22 22 x x
2015
2015- 8 8 x 5 5 x x
2016
2016- 14 12 2 5 4 1 3
2017
2017- 17 17 x 10 4 6 6
2018
2018- 2 1 1 5 2 3 4
2019
2019- 8 5 3 17 x 17 20
2020
Total 58 52 6 74 47 27 33
It observed that there 132 audit observations were raised during the period 2012-2013 to
2019-2020 out of which 99 resolved till June/21. There are 33 unresolved Audit observations of
which 6 ordinary & 27 advanced para in this project.
Actions taken:
a) Ordinary para: Revised reply of 2 (two) ordinary para with relevant documents were
submitted to DG FAFAD. Reply of 4 (four) para is under process at PMU.
b) Advance para: Revised reply of 8 (eight) advance para with relevant documents were
submitted to DG FAFAD, 13 (thirteen) para is under process at Ministry for Tripartite meeting &
6 (six) para is under process at PMU.
PMU exert utmost effort to resolved this by presenting necessary documents but the concerned
authority seems to be reluctant in this respect as the revised reply with documents are lying in
Ministry for Tripartite meeting and settlement of DG FAFAD long time, this may be due to
volume of work or scarcity of competent officials at present stage.
However, PMU is continuously persuading Ministry, FADAD for tripartite meeting, but it seems
reluctance due to the pandemic situation of COVID 19. The meeting was not held yet. However,
48
Quarterly Progress Report July - September,
2021
Project authority expect it would be in good/ acceptable status if the situation of COVID-19
improves near future.
From 31st May/2020 the lockdown relaxed with some conditions such as limit the movement of
individuals, maintain the personal safety, social distancing, wear musk, clean hand frequently
ensure PPE and maintain other health and regulations. These relaxations also aggravate this
situation of infections. More & more pupils were going infected as detected by increasing
testing. Due to such precedent situation, no significant physical progress is achieved in this
month. Government is imposed lockdown demarking the area RED, Yellow & Green for certain
period of time base on scale of infection to prevent spreading. It now appears that the country
is facing a major economic crisis caused by COVID-19 pandemic. For revitalizing of the
economy, the country has started to relaxing lockdown in various places amid demands from
certain section of population. At the end of May/2021 official death stands 21,162 & people
infected accounts near about 1,280,000 in the country.
The situation drastically deterred the progress of the project. Some contractor has stopped the
work & demobilized their working labors. Consultant key/ non-key professional was working
49
Quarterly Progress Report July - September,
2021
from duty stations staying at home. Their works includes, preparation of estimates/ Bill of
Quantity, checking bills, checking variation orders. This is exceptional situation that exhaust one
working season and restricts the progress of works. This situation is continuing that effects not
only Progress of RTIP-II but also the all others sectors of Government Projects.
The COVID-19 issue was discussed in the World Bank Mission commenced from 20-28 th July,
2020. This was a virtual meeting, where the guidance notes of additional measures in view of
the prevailing COVID-19 to avoid the spread of the disease or risk of infection is delivered to
apply to the services/ civil works activities/ other components. PIUs are requested to depute a
Focal Officer to work with the contractors & monitor the activities. The PIU relevant officials
and the WB take necessary measures to comply the relevant COVID-19 Pandemic guidelines and
National regulation at work sites.
The minimum requirements at construction sites but not limited to are as follows:
Cleaning of Construction site: clean and disinfect frequently touched objects and
surfaces, construction equipment, construction material including all reusable PPEs
Ensure health and safety of surrounding communities
Ensure the PPE as required for COVID-19 protection and as required for occupational
health-safety.
Minimize in person meetings and encourage remote meeting for taking decision on
construction and site management.
Track the worker's status on-site and off-site (e.g. fit to work, list of all quarantined
workers, sick, etc.).
Minimize workforce, and conduct periodic audits to verify that the appropriate
measures have been implemented and are maintained.
Ensure effective screening mechanism at entry of construction site based on the
boundaries of construction sites.
50
Quarterly Progress Report July - September,
2021
Steps were taken to make awareness building and campaigning about COVID-19 contagious
disease and it severity to the technical personnel and the workers at the sub project level.
Accordingly, the senior environmental specialist has visited the subproject sites at district level.
In this two packages although the environmental compliances like PPE, labor shed, sanitation
and drinking facilities along with ‘First aid box” were maintained but awareness regarding
COVID-19 and health safety guidelines to combat the global pandemic were observed on an
unsatisfactory stage.
Therefore, a mini training session was arranged at the field level, to keep the technical
personnel together with the laborers aware about the methodology to curb the potential spread
of corona virus disease, as it was going from worrying to critical level.
They were taught the remedial/safety measures to be taken to choke the spread of the Corona
virus disease, which was main objectives of this trip.
A mini meeting also was arranged at the site where the ARE, laboratory technician, UZ work
assistants, the contractor (himself), contractor’s site Engineer, contractor’s manager & workers
were present.
An additional training session was arranged in the office of the Executive Engineer with a part of
the technical personnel, who failed to attend the field level training session due to time
constraints, pressure of work at office & health ground.
They were taught about health, safety & hygiene measures. COVID-19 protocol as well as
prevention & control mechanism with rigorous operating process at the field level. Explained
the crisis posed by COVID-19 outbreak.
In June/2021 the Project Director, Team Leader in charge D&SC and other project officials
reviewed the turmoil situation of Covid-19 in the project area where second wave of Covid-19 is
running. So to prevent the infection also to make aware about the seriousness this contagious
diseases; specially the Delta Variant it becomes imperative to award Training and awareness
campaign. Accordingly, the awareness campaign and Training on COVID-19 was accommodated
to the schedule of GRC & SSC Workshop at field level. The Training & awareness campaigning
was performed in 11 project districts. It is to be noted that another program namely People’s
Perception Survey of RTIP-II was also devised to get the general impression and the fruitfulness
of this World Bank financed RTIP-II Project. A Separate Report was also generated by D&SC and
transmitted to Project Director in due course.
51
Quarterly Progress Report July - September,
2021
52
Quarterly Progress Report July - September,
2021
Labors doing construction work wearing Labors doing construction work wearing mask
mask: Sylhet, AF-98 and safety shoe: Sunamganj, AF-106
COVID-19 awareness poster: Sherpur/AF- Labour working at the site without wearing
92 PPE
53
Quarterly Progress Report July - September,
2021
Yes No
54
Quarterly Progress Report July - September,
2021
55
Quarterly Progress Report July - September,
2021
56
Quarterly Progress Report July - September, 2021
In Bangladesh, Government has declared general Leave & lockdown from 26.03.2020 to
prevent/transmission of the COVID-19 pandemic. Everybody was ordered to stay home. Other Offices,
business centers, Banks, etc. were closed and movement was also restricted. This situation drastically
deterred the progress of the project. Some contractors have demobilized their working labors.
Consultant key/non-key Professional was working at duty stations staying at home. Their works
include preparation of estimates/Bill of Quantity, checking bills, checking variation orders. This is an
exceptional situation. Basically, the construction work in this country starts from early November each
year. This works continues up to early June as the rainy season starts from June but in this year due to
outbreak of COVID-19 the progress of work deterred although most of the contractors who were
engaged to work has started and continued to achieve progress. Some contractor demobilizes their
labor forces, some continues with slow pace. This situation is continuing that effects the Progress of
RTIP- II AF.
From 31st May/2020 the lockdown relaxed with some conditions such as limit the movement of
individuals, maintain personal safety, social distancing, wear musk, clean hand frequently ensure PPE
and maintain other health and regulations. These relaxations also aggravate this situation of infections.
More & more people were going infected as detected by increase in testing. Due to such an
unprecedented outbreak of COVID-19 and heavy rains causing flood, expected physical progress has not
been in this working season. So, to accomplish the whole works or to achieve the Project objectives, the
project is being extended for another 24 months up to June/2023. Economic Relation Division (ERD) of
GOB forwards a formal letter to World Bank with a request to extend the Project Period. Restructuring
was done .PMU as well as the field officials in association with the Consultants has taken utmost steps
to continue the works, visiting field, conducting meeting with all , also sometimes by virtual
conferencing. Most of the awarded contracts are progressing.
Recurrent flood: Every year recurrent flood occurred starting from May by heavy rainfall and the
water coming from upstream through the Transboundary Rivers. These rivers flow above the danger
lever & inundates the adjacent areas. Severe submergence is forecasted in most of the project districts
specifically northern and northeastern districts in this FY. In some districts specifically Sunamganj, the
flash flood washed away the road and communication disrupted. Executive Engineers is trying to
restore the movement by felling the broken piece of bricks over earth as an emergency measure. Works
in those districts is running slowly. However, the contractor has also rescheduling their work plan so
that they can start the work immediately after recession of floodwater. Presently most the work except
a few are running.
57
Quarterly Progress Report July - September, 2021
Delay in procurement of works and services : Procurement in this fiscal year takes more time as
there was lockdown starting from late March/2020. Intermittent lockdown / public holiday occurs
frequently in this financial year due to COVID-19 which delayed more time for procurement. Officials,
professional staff worked staying at home as per Government orders. No office runs in full swing.
Amidst these odd situations, the project has near about completion for sub-projects procurement and
also achieved moderately satisfactory progress.
Contractor’s Reluctancy: Some contractors in some districts do not perform well in execution
willingly, although there were favorable site conditions. This affect the progress of works. In case of
non-performing contracts cancellation/ rebidding, warning letters etc are issued as punitive steps in
contract administration.
58
Quarterly Progress Report July - September, 2021
59
Quarterly Progress Report July - September, 2021
JAM/AF-48
SUN/AF-106
60
Quarterly Progress Report July - September, 2021
HAB/AF-03
Photo 1: SYL/AF-96
61
Quarterly Progress Report July - September, 2021
HAB/AF-03
Photo 2: SYL/AF-96
62
Quarterly Progress Report July - September, 2021
COVID-19 Awareness campaign among Field level personnel & laborers; AF-107,
Mymensingh
A World Bank Supervision Mission launched in this quarter starting from 24 th January to 2nd
February/2021. The Mission paid an in depth review of all different aspects of the projects,-
implementation status, procurement, social & environmental safeguard issues, governances,
consultancies, different services contacts related to governance & capacity building, reimbursement
disbursement procurement & Audits etc. The mission has critically analyzed the project period,
apprehended second wave of COVID-19, the project present pace of progress, remaining
implementation periods, audit status & future investment dimensions. A lot of suggestion &
63
Quarterly Progress Report July - September, 2021
recommendations were agreed between LGED & the WB. The following measures are to be taken by
PMU & D&SC Consultants to expedite the physical progress, Governance& institutional strengthening,
capacity building & road safety issues:
64