Work Method Statement Excavation Works

Ref. no:
Prepared by:
(Signature)
Revision: 00
Name:
Date:
Contact no.:
Company: Page 1 of 8

Method Statement Title:

Excavation Works

Reviewed by Kinetics Approved by


KSM Project
Submitted by Manager
Contractor Project Engineer Construction
QA/QC EHS
Manager

Signature
:

Name:

Date:

Time:

Table of Content

Rev. 5 Rev. date: 20210810


Work Method Statement Excavation Works

Ref. no:
Prepared by:
(Signature)
Revision: 00
Name:
Date:
Contact no.:
Company: Page 2 of 8

Section Description

1.0 Introduction

2.0 Resources

2.1 Material

2.2 Machinery & Equipment

2.3 Manpower Involved/Plan

2.4 Contractor Involved

3.0 Primary Requirement

3.1 Coordination Requirement

3.2 Others Operation Requirement

3.3 Receiving

3.4 Handling

3.5 Storage

4.0 Work Activity Methodology/ Arrangement

4.1 Site Preparation

4.2 Mobilization & Installation

5.0 Inspection, Testing, and Commissioning Proposal

6.0 List of Attachment / Appendices / References / Drawing

7.0 Hirarc Assessment

Rev. 5 Rev. date: 20210810


Work Method Statement Excavation Works

Ref. no:
Prepared by:
(Signature)
Revision: 00
Name:
Date:
Contact no.:
Company: Page 3 of 8

1.0 Introduction
This document shall address the excavation works for Lift Station, New Support Room, Motorcycle
Park and Walkway.

1.1 The construction standard above is shown as following: -

IMCS Specification: -

IMCS SECTION DESCRIPTION


IMCS 31_20_00_00(02300) Earth Moving

2.0 Resources

2.1 Materials

All materials used on site must be approved type and they are as follows: -

No Type / Brand Name Description of Materials


As excavation not use materials N/A

2.2 Machinery and Equipment

No Type / Model Quantity


1 Lorry truck 1 lot
2 Backhoe 1 lot
5 Barricade cone & red tape / Plastic Barrier Various
6 Trowel 2 sets
7 Wheel barrow 2 Set
10 Portable exhaust fan 1 Set
11 Compacter Various

2.3 Manpower Involved / Plan

Designation / Name (Kinetics) Key Person Quantity


Manager: / 1
Engineer: / 1
Supervisor: / 1
EHS: / 1
QA/QC: / 1

Rev. 5 Rev. date: 20210810


Work Method Statement Excavation Works

Ref. no:
Prepared by:
(Signature)
Revision: 00
Name:
Date:
Contact no.:
Company: Page 4 of 8

Designation / Name (DPV) Key Person Quantity


Manager: / 1
Engineer: / 1
Supervisor: / 1
EHS: / 1
QA/QC / 1
QA/QC: / 1

2.4 Contractor Involved

Company Type / Model Quantity


CSA Contractor 1 lot

3.0 Primary Requirement

3.1 Coordination Requirement


3.1.1 Identification of existing services and structure around the working area.

3.2 Other Operation Requirement


3.2.1 Work access to the construction area need to confirm and approved by Kinetics.

3.2.2 Location for storage and the type of material to store must be approved by
Kinetics.

3.3 Receiving
3.3.1 All delivery materials to the site shall be informed to the site manager/ to have the
plan for unloading. Upon arrival of materials at the storage yard, the materials
controller will match delivery notes and shall verify the consignment.

3.3.2 Receiving/Handling/Storage for all materials must comply manufacturer’s


recommendation & IMCS

3.3.3 Upon arrival of the material, the consignment shall be verified by the supervisor to
match the packing list and inspected by Kinetics QAQC & Client.

3.3.4 All material received at site shall be visually inspected for any damages in order to
avoid of work.

3.3.5 Deliver each container with labeling intact which identifies manufacturer, type of
material, brand name, brand code, coverage, surface preparation, drying time,
cleanup, color designation, and instructions for mixing and reducing.

Rev. 5 Rev. date: 20210810


Work Method Statement Excavation Works

Ref. no:
Prepared by:
(Signature)
Revision: 00
Name:
Date:
Contact no.:
Company: Page 5 of 8

3.4 Handling
3.4.1 Proper methods & equipment, i.e., trolley or pallet jack to be used for transferring
of the materials or tools.

3.4.2 Supervisor shall monitor the work and ensure the work is complied with all safety
requirements.

3.5 Storage
3.5.1 Proper barricade & barrier ownership tag to be used for materials storage.

3.5.2 Proper containment tray to be used for materials storage.

3.5.3 Store materials in a sheltered dry place that is free from excessive moisture.

3.5.4 Daily housekeeping shall be carried out to ensure the cleanness of the area.

4.0 Work Activity Methodology / Arrangement

4.1 Site Preparation


4.1.1 Planning the best route for the access to get in and out

4.1.2 Investigate & coordinate of existing buildings, structure, M&E which may affected
the progress of the works.

4.1.3 Identify the storage location for materials, tool and equipment.

4.1.4 The working areas must be barricade using barricade cone and safety tape to
avoid people to enter the working areas.

4.2 Mobilization & Installation

No Activity Sequence
1 a) To inform related Project Manager, System Owner and KINETICS EHS
management before start work for the day.

b) To obtain the entire relevant valid EHS document, SIPP and PTP before
start work.

c) To assign all the workers, stuff to attend safety induction before start work.

d) Get the valid permit for the workers and machinery to enter the site.

Rev. 5 Rev. date: 20210810


Work Method Statement Excavation Works

Ref. no:
Prepared by:
(Signature)
Revision: 00
Name:
Date:
Contact no.:
Company: Page 6 of 8

2 a) Inform the Project Manager or person in charge before start work

b) Detail of the activity to be performed shall be informed/briefed and


explained before starting work.

c) Precautions must be taken before and during activity in accordance with


DOSH standard and Intel Safety standard.

d) During the progress of activity, the work shall be under the continuous
supervision of an experienced foreman.

e) Provide safeguards, including related signages, barricades, temporary


fences, warning lights and other similar items that are required for protection
of all personnel during all activity involved.

3 Mobilization of tools and workers

a) To inform related Project Manager, System Owner and EHS Management


before start work for the day.

b) Obtained the entire relevant valid EHS document before start work.

c) All Vehicles to comply the wheel stopper when loading material.

d) Shall be use manpower to mobilize the materials into the work location and
storage area.

e) Get advised from KINETICS project management team for the location for
material storage.

f) Shall be used forklift to mobilize the materials into the work area if
necessary.

g) Pallet Jack shall be used during work where necessary for mobilize the
material to work location needed.

4 To brief the workers on the job sequence and streamline their job for hazard
avoidance prior work starts.

5 Hard barricade all working area by using tubular scaffolding.

6 To prepare the power supply to the working area by using extension wire for
temporary lighting at night.

Method statement
7 Preparation of work
 Construction will not commence until confirmation that all pre-construction

Rev. 5 Rev. date: 20210810


Work Method Statement Excavation Works

Ref. no:
Prepared by:
(Signature)
Revision: 00
Name:
Date:
Contact no.:
Company: Page 7 of 8

planning and safety checks are completed.


 Supervisor shall be familiar with the construction drawing and method of
statement.
 Clear the site at least 10 feet beyond the limit required for access and
execution of work.

Survey & Setting-out


 Survey to set out the footing location for excavation.
 Existing sewerage pipe and manhole location to mark out for reference
during construction of footing.

Excavation
 Excavation is unclassified. Complete all excavation regardless of the
type, nature, or condition of the materials encountered. Make own
estimate of the kind and extent of the various materials to be excavated in
order to accomplish the work.
 Excavation will be executed in open cut
 Install and maintain shoring, sheeting, bracing, and sloping necessary to
support the sides of the excavation, to prevent any soil movement which
may damage adjacent pavements, utilities, or structures, damage or
delay the work, or endanger life and health.
 Survey will verify setting out and bottom founding level of excavation
 Excavation will be carried out with excavator/backhoe and the excavated
material loaded directly into dump truck and transported to temporary
stockpile area.
 Excavation that cannot be accomplished without causing damage to or
soil movement under or adjacent to the present or new structures shall be
performed with hand tools or by vacuum excavation.

8 COVID 19 Safety Measures to be follow strictly throughout the setup.

9  Housekeeping at end of each working day is a must for any


scaffolding job. Scaffolders on the site must ensure that:

 All equipment has been cleaned and stored correctly away from
access areas

 Never leave equipment in walkways or doors

 All fire exits and emergency access points are kept clear at all times
and is never blocked by equipment or rubbish

Rev. 5 Rev. date: 20210810


Work Method Statement Excavation Works

Ref. no:
Prepared by:
(Signature)
Revision: 00
Name:
Date:
Contact no.:
Company: Page 8 of 8

 Report any hazards you might find to a supervisor promptly

 Dispose of rubbish quickly and safely

 the gear is consolidated and is all out of harm’s way when handing
over scaffold

 Before leaving the site each day, make sure that clean-up has been
finalized and no hazards are visible.

5.0 Inspection, Testing and Commissioning Proposal


Inspection and test plan (ITP) shall include at the following stage.

a) Perceiving of materials/ machinery


b) In-process inspection during installation
c) Final stage before handover

ITP shall also address the “Hold Point”, where approval on the work activity is required.
Refer to Attachment 1: Inspection and Test Plan
ITP Reference Number

6.0 List of Attachments / Appendices / References/ Drawing


Attachment layout of the location of wall re-painting that require cleaning, grinding, touch up and
skim coat.

Document Reference No. Document title