Work Method Statement For Excavation Works
Work Method Statement For Excavation Works
Ref. no:
Prepared by:
(Signature)
Revision: 00
Name:
Date:
Contact no.:
Company: Page 1 of 8
Excavation Works
Signature
:
Name:
Date:
Time:
Table of Content
Ref. no:
Prepared by:
(Signature)
Revision: 00
Name:
Date:
Contact no.:
Company: Page 2 of 8
Section Description
1.0 Introduction
2.0 Resources
2.1 Material
3.3 Receiving
3.4 Handling
3.5 Storage
Ref. no:
Prepared by:
(Signature)
Revision: 00
Name:
Date:
Contact no.:
Company: Page 3 of 8
1.0 Introduction
This document shall address the excavation works for Lift Station, New Support Room, Motorcycle
Park and Walkway.
IMCS Specification: -
2.0 Resources
2.1 Materials
All materials used on site must be approved type and they are as follows: -
Ref. no:
Prepared by:
(Signature)
Revision: 00
Name:
Date:
Contact no.:
Company: Page 4 of 8
3.2.2 Location for storage and the type of material to store must be approved by
Kinetics.
3.3 Receiving
3.3.1 All delivery materials to the site shall be informed to the site manager/ to have the
plan for unloading. Upon arrival of materials at the storage yard, the materials
controller will match delivery notes and shall verify the consignment.
3.3.3 Upon arrival of the material, the consignment shall be verified by the supervisor to
match the packing list and inspected by Kinetics QAQC & Client.
3.3.4 All material received at site shall be visually inspected for any damages in order to
avoid of work.
3.3.5 Deliver each container with labeling intact which identifies manufacturer, type of
material, brand name, brand code, coverage, surface preparation, drying time,
cleanup, color designation, and instructions for mixing and reducing.
Ref. no:
Prepared by:
(Signature)
Revision: 00
Name:
Date:
Contact no.:
Company: Page 5 of 8
3.4 Handling
3.4.1 Proper methods & equipment, i.e., trolley or pallet jack to be used for transferring
of the materials or tools.
3.4.2 Supervisor shall monitor the work and ensure the work is complied with all safety
requirements.
3.5 Storage
3.5.1 Proper barricade & barrier ownership tag to be used for materials storage.
3.5.3 Store materials in a sheltered dry place that is free from excessive moisture.
3.5.4 Daily housekeeping shall be carried out to ensure the cleanness of the area.
4.1.2 Investigate & coordinate of existing buildings, structure, M&E which may affected
the progress of the works.
4.1.3 Identify the storage location for materials, tool and equipment.
4.1.4 The working areas must be barricade using barricade cone and safety tape to
avoid people to enter the working areas.
No Activity Sequence
1 a) To inform related Project Manager, System Owner and KINETICS EHS
management before start work for the day.
b) To obtain the entire relevant valid EHS document, SIPP and PTP before
start work.
c) To assign all the workers, stuff to attend safety induction before start work.
d) Get the valid permit for the workers and machinery to enter the site.
Ref. no:
Prepared by:
(Signature)
Revision: 00
Name:
Date:
Contact no.:
Company: Page 6 of 8
d) During the progress of activity, the work shall be under the continuous
supervision of an experienced foreman.
b) Obtained the entire relevant valid EHS document before start work.
d) Shall be use manpower to mobilize the materials into the work location and
storage area.
e) Get advised from KINETICS project management team for the location for
material storage.
f) Shall be used forklift to mobilize the materials into the work area if
necessary.
g) Pallet Jack shall be used during work where necessary for mobilize the
material to work location needed.
4 To brief the workers on the job sequence and streamline their job for hazard
avoidance prior work starts.
6 To prepare the power supply to the working area by using extension wire for
temporary lighting at night.
Method statement
7 Preparation of work
Construction will not commence until confirmation that all pre-construction
Ref. no:
Prepared by:
(Signature)
Revision: 00
Name:
Date:
Contact no.:
Company: Page 7 of 8
Excavation
Excavation is unclassified. Complete all excavation regardless of the
type, nature, or condition of the materials encountered. Make own
estimate of the kind and extent of the various materials to be excavated in
order to accomplish the work.
Excavation will be executed in open cut
Install and maintain shoring, sheeting, bracing, and sloping necessary to
support the sides of the excavation, to prevent any soil movement which
may damage adjacent pavements, utilities, or structures, damage or
delay the work, or endanger life and health.
Survey will verify setting out and bottom founding level of excavation
Excavation will be carried out with excavator/backhoe and the excavated
material loaded directly into dump truck and transported to temporary
stockpile area.
Excavation that cannot be accomplished without causing damage to or
soil movement under or adjacent to the present or new structures shall be
performed with hand tools or by vacuum excavation.
All equipment has been cleaned and stored correctly away from
access areas
All fire exits and emergency access points are kept clear at all times
and is never blocked by equipment or rubbish
Ref. no:
Prepared by:
(Signature)
Revision: 00
Name:
Date:
Contact no.:
Company: Page 8 of 8
the gear is consolidated and is all out of harm’s way when handing
over scaffold
Before leaving the site each day, make sure that clean-up has been
finalized and no hazards are visible.
ITP shall also address the “Hold Point”, where approval on the work activity is required.
Refer to Attachment 1: Inspection and Test Plan
ITP Reference Number