Professional Documents
Culture Documents
A2-C2-1 Before Modify
A2-C2-1 Before Modify
GRID LOCATION HEAD MARK POST MARK MATERIAL + GRADE LENGTH QTY
UNIT TOTAL
SD-SS-B01_-A2-C2-1=4 REQ'D
A2-C2-1 B/3/12550.00-15051.00 A1-m-11 WF-200X100X5.5X8 SS400 1436 1 29.44 29.44
pl-21 PL20x200 SS400 250 1 7.85 7.85
A2-C2-1 B/4/12550.00-15051.00 38.29
A2-C2-1 P/3/12550.00-15051.00
A2-C2-1 P/4/12550.00-15051.00 MATERIAL FINISHING = PAINTED
pl-21
TOP
1:10
1456
20 1436
200
1376 60
pl-21 4 - Ø22
A
65 60 60 65
A1-m-11
250
40
40
50 50 50 50
2 - Ø22
A
A-A
1:10
FRONT
1:10
BEFORE MODIFY
A2-C2-1=4 REQ'D
DATE DRAWN
Tekla structures
DATE DATE OWNER CONSULTANT CONTRACTOR STATUS APPROVED PROJECT TITLE PROJECT NO. DRAWING NO.
Ir. Achmad Budi YIH QUAN FOOTWARE INDONESIA
25.01.2023 PHASE 1 PROJECT -
REVISION PT. YIH QUAN FOOTWARE INDONESIA PT. WAHANACIPTA BANGUNWISMA SD-SS-B01_A2-C2-1
SHOP DRAWING DATE ISSUED PROJECT LEADER SUB DRAWN DRAWING TITLE SCALE REVISION NO.
PT. INDONESIA XIN HAI - - SSM
WORKSHOP A2 R.00
STEEL STRUCTURE COLUMN DETAIL_A1-C2-1 1 : 10_(A3)