001-Annex 01 Preliminary Project Time Schedule
001-Annex 01 Preliminary Project Time Schedule
SENION MANAGER
MANAGER
ASST.MANAGER
21.2MW
WHRPP Project for Asia Cement Public Co.,Ltd.
Year
Year 1
1st Month 2nd Month 3rd Month 4th Month 5th Month 6th Month 7th Month 8th Month 9th Month 10th Month 11th Month 12th Month 1st Month 2nd Month
Year 2
3rd Month 4th Month 5th Month
Month Description
Design Schedule
Basic design General layout drawing Thermodynamic system design
P&I diagram Outdoor steam and water pipeline Heat insulation and painting Process design
Interface and arrangement design of PH boiler Interface and arrangement drawing of AQC boiler
Outdoor water and steam pipeline support Water demineralizer design Water supply and drainage design Electrical design Automation design
Design completion
Equipment procurement
Steam turbine procurement PH boiler procurement AQC boiler procurement Travelling crane procurement Cooling tower procurement Raw water and pure water equipment procurement Valve,expansion joint equipment procurement Other auxiliary equipment procurement Electric equipment procurement
2010-3-23 - R 0
SENION MANAGER
MANAGER
ASST.MANAGER
21.2MW
WHRPP Project for Asia Cement Public Co.,Ltd.
Year
Year 1
1st Month 2nd Month 3rd Month 4th Month 5th Month 6th Month 7th Month 8th Month 9th Month 10th Month 11th Month 12th Month 1st Month 2nd Month
Year 2
3rd Month 4th Month 5th Month
Month Description
Installation completion
Startup