Project : Control No.

Location: Date:
Sub-Con Name: Scope:

STRUCTURAL STEEL CHECKLIST


CONTRACT NO. : BUILDING AREA / LEVEL : GRIDLINE / AXES : INSPECTION DATE/TIME :

CHECK THAT THE FOLLOWING COMPLY WITH APPROVED SUBMITTALS , FOR CONSTRUCTION DRAWINGS AND TECHNICAL
SPECIFICATIONS:
ACCEPTED
COMPONENTS REMARKS / WHY NOT?
YES NO N/A

A. Pre - fabrication
1. Approved reinforcing steel bars cutting list
2. Steel Bender/Cutter certificates
3. Certificates of welders
4. Mill certificates of reinforcing steel bars
5. Reinforcing Steel Bars have passed both tensile and bending tests

B. Post - fabrication
1. Fabricated steel bars comply with the approved cutting list
a. Steel diameter/size
b. Correct number of pieces
c. Complies with proper splicing points
2. Reinforcing steel bars are free of unwanted bends
3. Free of rusts/muds/concrete laitance
4. Others

REMARKS :

PREPARED BY : CHECKED BY ( QAQC) :

________________________ _____________________ _____________________ _____________________


(Subcon QC Engineer)
APPROVED BY : NOTED BY :

_______________________ _______________________ ________________________


(QAQC Head) PIC Project Manager
DISTRIBUTION : Subcon Production CQC Project Documentation
Revision No. 000 (August 2011)