FORM KUA-SHES-OS-F-005
TITLE: JOB HAZARD ANALYSIS REV: 01
JOB STEPS RISKS IDENTIFIED EXISTING CONTROL MEASURES ADDITIONAL CONTROL MEASURES
LANGKAH KERJA RISIKO YANG DIKENALPASTI LANGKAH KAWALAN SEDIA ADA LANGKAH KAWALAN TAMBAHAN
3 Installation indoor and outdoor 3.1 Miscommunication with team work. 4.1.1 To discuss with team before
unit, make a hole for bracket and start installation work.
for piping unit
3.2 Hand injury 4.2.1 To wear cotton glove.
3.3 Back pain during install unit 4.3.1 To create proper communication
and understanding.
4.3.2 To provide sufficient manpower.
4.3.3 Always work in correct body
posture.
3.4 Sensitive equipment damage. 3.4.1 To protect (if necessary) all 4.4.1.1 Do inspection for all Equipment
sensitive equipment or gears. before use
4 Lay cable and connect all cable 4.1 Shock circuit electric arc. 5.1.1 To ensure power supply is off 5.1.1.1 Competent person do
connection before do the connection. the connection.
5.1.2 To double check on each cable
connections. Make sure it all not
loosed.
JOB STEPS RISKS IDENTIFIED EXISTING CONTROL MEASURES ADDITIONAL CONTROL MEASURES
LANGKAH KERJA RISIKO YANG DIKENALPASTI LANGKAH KAWALAN SEDIA ADA LANGKAH KAWALAN TAMBAHAN
7 Charging Freon gas to system. 7.1 Gas leak to environment. 7.1.1 To ensure proper connection 7.1.1.1 Use manifold gauge in
manifold gauge to system. good condition.
7.1.2 To perform leak test on each
connection using soap solution
liquids (snoopy).
7.2 Cold burn 7.2.1 Wear suitable glove to open 7.2.1.1 Make sure use proper
hose manifold gauge. glove.
7.3 High pressure system 7.3.1 To ensure charging Freon does 7.3.1.1 Competent person do
not exceed standard rate. charging.
8 Testing and Commissioning 8.1 Expose to noise 8.1.1 To ensure wear ear plug.
8.2 Cold surface on refrigerant pipe. 8.2.1 To ensure wear cotton glove.
9.2 PTW remain unclosed. 9.2.1 To close out / hand back the
PTW after completion of work.
DOCUMENT No:
FORM KUA-SHES-OS-F-005
TITLE: JOB HAZARD ANALYSIS REV: 01
For Low & High Risk Approval / Untuk kelulusan berisiko rendah dan tinggi :
Prepared by Reviewed by Approved by
Disediakan oleh Disemak oleh Diluluskan Oleh
Weekly Approval by Area Owner or Delegates / Kelulusan Mingguan Oleh Pengurus Kawasan atau Wakilnya
Extend to / Melanjutkan ke
NOTE: This approved JHA can be used for three (3) months period; subjected to weekly approval by Area Manager.
NOTA: JHA yang telah diluluskan ini hanya boleh digunakan untuk tempoh tiga (3) bulan sahaja; tertakluk kepada kelulusan mingguan dari Pengurus Kawasan.
DOCUMENT No:
FORM KUA-SHES-OS-F-005
TITLE: JOB HAZARD ANALYSIS REV: 01
Proclaimer
Kenyataan
2. I have assessed the job site for new or changed hazards, and I have prepared control for those extra hazards and had incorporated
into this JHA.
Saya telah menaksir kawasan kerja dengan mengambilkira perubahan hazad atau hazad baru, dan saya telah menyediakan kawalan untuk lebihan hazad tersebut
serta memasukkan hazad itu ke dalam JHA ini.
TABLE BELOW TO BE ENDORSED BY JOB SUPERIOR WHO ARE RESPONSIBLE FOR THE TASK/WORK.
I have conducted a briefing/toolbox session in considerations of item 1 & 2 above before start works to all the team members as mentioned on the
following table.
Saya telah menjalankan taklimat/sesi toolbox dengan mengambilkira perkara 1 & 2 di atas kepada semua ahli kumpulan seperti dinyatakan pada senarai
berikut sebelum kerja-kerja dijalankan.
Job Superior Full Name / ID No. / No. ID Designation / Jawatan Company / Syarikat Date / Tarikh Signature/Tandatangan
Nama Penuh Ketua Kerja
DOCUMENT No:
FORM KUA-SHES-OS-F-005
TITLE: JOB HAZARD ANALYSIS REV: 01
TABLE BELOW TO BE ENDORSED BY ALL PERSONNEL INVOLVED IN EXECUTING THE TASK/WORK ON DAILY BASIS.
NOTE: At least one (1) worker’s details MUST BE provided before seeking JHA approval.
NOTA: Sekurang – kurang satu (1) maklumat terperinci pekerja hendaklah diberikan sebelum memohon kelulusan JHA.
DOCUMENT No:
FORM KUA-SHES-OS-F-005
TITLE: JOB HAZARD ANALYSIS REV: 01
Health & Safety Prompts : (Below are Hazards that you could be exposed to while undertaking the job, use them as prompts to help fill out the JHA)
Kekunci Keselamatan & Kesihatan : (Berikut adalah Hazad yang anda boleh terdedah sewaktu menjalankan kerja, gunakannya sebagai kata kunci sewaktu mengisi borang JHA)
Pinch points Working above shoulder height Noise Vehicles Fall from height
Titik Potongan Bekerja melebihi ketinggian bahu Bunyi bising Kenderaan Jatuh dari tingkat berbeza
Remote working e.g. poor visibility/ Temp extremes - gas, liquid, surface,
Stored energy Hand tool use communication conditions Lighting
Tenaga tersimpan Penggunaan alatan tangan Kerja berjauhan cth. Kurang kelihatan / komunikasi Suhu melampau – gas, cecair, permukaan, Pencahayaan
yang lemah keadaan
Correct tooling Vibration - whole body Wet/slick/slippery conditions Chemicals – Inhaling, absorbing, ingesting Glare
Perkakas yang betul Getaran – seluruh badan Basah/Tergelincir/Licin Kimia – terhirup, terminum/serap, tersedut Silau