Koch Knight Inquiry 682 20 17261 - DoR

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Supplied By Paid By

KOCH KNIGHT BID INQUIRY 17261 KOCH Lining KOCH Lining


DIVISION OF RESPONSIBILITY Yanacocha KNIGHT Installer Yanacocha KNIGHT Installer
PERSONNEL
Monthly Payments X X
All transportation to/from Point-of-Origin to Cajamarca of Own Crew X X X X
Crew Acclamation to Elevation of Yanacocha site X X
Salary During Acclamation of Own Crew X X X X
All internal transportation (airport-site-social facility-site etc.) X X
Food ( 3 meals) X X
Accommodation X X
Busing from camp/worksite of crew X X
Light Duty Vehicle for Supervisory Staff of Own Crew X X X X
Work Visa Registration Expenses X X
GENERAL SITE FACILITIES
Mobilization of Own Crew X X X X
Construction Site Preparation X X
Site Acces and Security X X
General Area Lighting X X
Road Maintenance / Dust Control X X
Traffic Control X X X X
Internet Service X X
Cell Phone for Own Crew X X X X
Potable Water for Own Crew X X X X
Site offices, WC X X X X
Storage for machinery & equipment X X
Storage for project materials X X
Electricity (for site offices), service water X X
Electricity, water and pressure air for application site (all connections into SUBCON's power panel on
site) X X
Work Area site cleaning X X
Lighting for Work Area X X
CONSUMABLES
General hand tools and consumables X X
Brick saws and mortar mixers X X
Personal protection consumables X X
MACHINERY and EQUIPMENT
All necessary machinery & equipment X X
Scaffolding materials and assembly (local contractor will be used ) X X
Light Vehicle Fuel X X
Crane, forklift and truck X X
INSTALLATION MATERIALS
Supply of all project material (membrane primer, membrane, brick, mortar, titanium) X X
Sandblasting for membrane primer application on interior vessel surface X X
Primer application (roll or brush application only, no spray) X X
Primer quality inspections X X
All necessary entrance/exit, work permits X X
Membrane lining workmanship X X
Membrane lining assistance X X
Heating and cooling of vessel and autoclave (as needed) X X
Refractory lining quality inspections and project administration X X
Refractory lining workmanship andcrew supervision X X
Titanium internals and inserts installation personnel X X
Transportation of the project material from the storage to the application site (manpower) X X
Transportation of excess materials back to the storage from the site (manpower) X X
Brick pogo supports X X
All sampling and testing X X
HEALTH, SAFETY, ENVIRONMENT
Safety signs and safety tapes on application site X X
Personal protection equipment and suitable clothing X X
Health, first-aid and all emergency services on site X X
HSE personnel X X X X