Heat Shrinkable Sleeve Procedure

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 5

(ALFA EGYPT)

QA/QC DEPARTMENT

HEAT SHRINKABLE SLEEVES


PROCEDURE

Rev. Issue Date Reason for Issue Prepared By Checked By Approved By

RECORD SHEET

Revision Reason for issue Modification


TABLE OF CONTENTS

SECTION 1 INTRODUCTION.............................................................................4
SECTION 2 RESPONSIBILITIES......................................................................4
3.1. BARGE SUPERINTENDENT...............................................................................4
3.2. BARGE SITE MANAGER...................................................................................4
3.3. BARGE CAPTAIN............................................................................................4
SECTION 3 MATERIAL HANDLING AND CHARACTERISTICS...............4
SECTION 4 STEEL SURFACE PREPARATION............................................5
SECTION 5 HEAT SHRINKABLE SLEEVES APPLICATION.....................5
5.1. COVER FITTING..............................................................................................6
5.2. SHRINKING PROCESS......................................................................................6
5.3. INSPECTION AND TESTING...............................................................................6
5.4. HEAT SHRINKABLE SLEEVE REPAIR.................................................................6
SECTION 6

DOCUEMENTATIONS........................................................................... 6
Section 1 - Introduction

This document describes the procedure that will be followed for applying the pipeline's
field joints Heat Shrinkable Sleeves Application.
This procedure should be followed, except for extreme circumstances where it is deemed
impossible to continue without deviation.
The approved changes in the procedure, which were introduced during the offshore
works implementation, if any, shall be documented on site and included in the final as-
built dossier.
Section 2 - Responsibilities
1.1. Barge Superintendent

The Barge Superintendent is responsible for ensuring that the pipeline is laid in
accordance with the project specifications and approved procedure.

1.2. Barge Site Manager

The Barge Site Manager is responsible for ensuring the application of all contract terms
and conditions and deal with the Company Representatives on behalf of Contractor.

1.3. Barge Captain

The Barge Captain is responsible for all marine operations onboard the Lay Barge during
the offshore works, he is also responsible for the safety of the Lay Barge and all
associated marine spread.
Section 3- Material Handling and Characteristics

The sleeves must be delivered in boxes or containers and stored in suitable whorehouse,
sheltered from direct sunlight and far from any external heat source as per Manufacturer’s
recommendations.
On delivery, the packing of the sleeves must be examined and inspected for absence of
obvious damage, integrity and acceptance for installation.
The sleeves must be raised from the ground to avoid contamination from water and any
other foreign substances.
Section 4 - Steel Surface Preparation

Upon successfully completion of the line pipes field weld and non-destructive tests, the
field joint surface shall be cleaned and prepared for heat shrinkable sleeve application.
All rust, scale and weld spatter forms shall be removed prior to the pipe metal surface
cleaning.
Any foreign substance such as oil, grease, chemicals, mud … etc. shall be removed.
The steel surface can be cleaned only when it is completely dry that is when it has a
temperature 3OC higher than the dew point and the ambient relative humidity is lower
than 90%. If not, the field joint area shall be preheated to obtain the suitable cleaning
conditions.
The steel surface will be mechanically cleaned by power wire brush obtaining a minimum
finishing grade St 3.
Bevel the anti-corrosion coating edges on both sides of the joint be approximately 30 O or
less from the horizontal.
Preheat the pipe metal surface by propane torch up to the proper temperature
recommended from heat shrinkable sleeve Manufacturer, if required.

SECTION 5 Heat Shrinkable Sleeves Application

After completion of pipe metal surface preparation of field joint, the cut-back area of anti
corrosion coating will be protected by Heat Shrinkable Sleeve.
The preheating temperature shall be as per Manufacturer’s recommendations and shall
check by means of proper approved method.

Cover Fitting

Once the coating area has been cleaned and preheated, the protective film shall be
removed from the coating sleeve and the sleeve wrapped centrally around the field joint.
The overlap on existing anti-corrosion coating shall be at least 50 mm minimum on both
sides. The overlapping portion shall be heated and pressed by gloved hand.
The closure patch shall be applied after removal of the protective film from the pressure
sensitive adhesive strip in 12 O’clock position.

The heated closure patch shall be smoothed by gloved hand to eliminate any entrapped
air and to ensure good bonding.
Preheat the edge part by propane torch and press the heated part by gloved hand.
Shrinking Process

Heat and shrink the sleeve on the bottom part of the pipe, starting from the center
towards one end of sleeve by moving the torch up and down along the
circumference direction holding flame perpendicularly against the pipe surface.
And after from the center towards the other end.
The shrunk part of the sleeve shall be massaged with a gloved hand, a roller or both to
eliminate any air bubbles between the sleeve and pipe metal surface.
The upper part of the sleeve shall be heated and shrunk in the same manner as the
bottom to complete the sleeve installation.
Inspection and Testing

On completion of heat shrinkable sleeves application, each sleeve shall be carefully


inspected to establish the sleeve is free of visual defects (e.g. non-adherent areas,
defective sealing of the mastic ate the edge of the sleeve, etc.).
The sleeve shall be checked to maintain at least 50 mm overlap on existing anti-corrosion
coating at both sides.
The coated field joint area shall be inspected using with pulse type DC “Holiday Detector”
employing audible and visible alarm.
The maximum voltage during sleeve holiday detection will be in accordance with
Manufacturer’s recommendations.
The holiday detection shall extend to cover the overlap areas.
Heat Shrinkable Sleeve Repair

If the field joint coating does not pass inspection, that one should be repaired according to
the approved repair procedure and re-inspected.
otherwise, the sleeve will be removed and apply new one.
SECTION 6. DOCUEMENTATIONS

A report as shown in the attached form No.


shall be prepared, includes as a minimum, the following information's:

a Client name and address


b Inspection test Equipment , Material type, size and manufacturer
c Test Results
c Operator name and signature
F Date of examination

You might also like