MONITORING PRA COMMISSIONING GI 150 kV ARGAMAKMUR

BAY LINE PULAU BAAI 1, LINE PULAU BAAI 2, LINE MUKO-MUKO 1, LINE MUKO-MUKO 2, TRAFO, KOPEL
SEPTEMBER WEEK 3 SEPTEMBER WEEK 4 OKTOBER WEEK 1 OKTOBER WEEK 2 OKTOBER WEEK3
N0 TASK NAME TIME
20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
1 CHECK SUPLAY AC and DC (LB Pulau -Baai 1)
Panel Control dan Proteksi
MK and Apparatus
2 ACTIVATION PANEL CONTROL dan PROTEKSI (LB Pulau Baai 1)
Check Internal and External panel Control & Proteksi
3 ACTIVATION APPARATUS BESERTA INTERLOCK LOCAL (LB Pulau Baai 1)
Disconecting Switch 1 (DS1)
Visual check and check Electrical
Check manual operation
Local Control
Disconecting Switch 2 (DS2)
Visual check and check Electrical
Check manual operation
Local Control
Disconecting Switch LINE (DSL)
Visual check and check Electrical
Check manual operation
Local Control
Circuit Breaker
Visual check
Check Electrical
Local Control
4 CHECK SUPLAY AC and DC (LB Pulau -Baai 2)
Panel Control dan Proteksi
MK and Apparatus
5 ACTIVATION PANEL CONTROL dan PROTEKSI (LB Pulau Baai 2)
Check Internal and External panel Control & Proteksi
6 ACTIVATION APPARATUS BESERTA INTERLOCK LOCAL (LB Pulau Baai 2)
Disconecting Switch 1 (DS1)
Visual check and check Electrical
Check manual operation
Local Control
Disconecting Switch 2 (DS2)
Visual check and check Electrical
Check manual operation
Local Control
Disconecting Switch LINE (DSL)
Visual check and check Electrical
Check manual operation
Local Control
Circuit Breaker
Visual check
Check Electrical
MONITORING PRA COMMISSIONING GI 150 kV ARGAMAKMUR
BAY LINE PULAU BAAI 1, LINE PULAU BAAI 2, LINE MUKO-MUKO 1, LINE MUKO-MUKO 2, TRAFO, KOPEL
SEPTEMBER WEEK 3 SEPTEMBER WEEK 4 OKTOBER WEEK 1 OKTOBER WEEK 2 OKTOBER WEEK3
N0 TASK NAME TIME
20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Local Control
7 CHECK SUPLAY AC and DC (LB Muko Muko 1)
Panel Control dan Proteksi
MK and Apparatus
8 ACTIVATION PANEL CONTROL dan PROTEKSI (LB Muko Muko 1)
Check Internal and External panel Control & Proteksi
9 ACTIVATION APPARATUS BESERTA INTERLOCK LOCAL (LB Muko Muko 1)
Disconecting Switch 1 (DS1)
Visual check and check Electrical
Check manual operation
Local Control
Disconecting Switch 2 (DS2)
Visual check and check Electrical
Check manual operation
Local Control
Disconecting Switch LINE (DSL)
Visual check and check Electrical
Check manual operation
Local Control
Circuit Breaker
Visual check
Check Electrical
MONITORING PRA COMMISSIONING GI 150 kV ARGAMAKMUR
BAY LINE PULAU BAAI 1, LINE PULAU BAAI 2, LINE MUKO-MUKO 1, LINE MUKO-MUKO 2, TRAFO, KOPEL
SEPTEMBER WEEK 3 SEPTEMBER WEEK 4 OKTOBER WEEK 1 OKTOBER WEEK 2 OKTOBER WEEK3
N0 TASK NAME TIME
20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Local Control
10 CHECK SUPLAY AC and DC (LB Muko Muko 2)
Panel Control dan Proteksi
MK and Apparatus
11 ACTIVATION PANEL CONTROL dan PROTEKSI (LB Muko Muko 2)
Check Internal and External panel Control & Proteksi
12 ACTIVATION APPARATUS BESERTA INTERLOCK LOCAL (LB Muko Muko 2)
Disconecting Switch 1 (DS1)
Visual check and check Electrical
Check manual operation
Local Control
Disconecting Switch 2 (DS2)
Visual check and check Electrical
Check manual operation
Local Control
Disconecting Switch LINE (DSL)
Visual check and check Electrical
Check manual operation
Local Control
Circuit Breaker
Visual check
Check Electrical
Local Control

13 ACTIVATION APPARATUS BESERTA INTERLOCK LOCAL (TRAFO )


Disconecting Switch 1 (DS1)
Visual check and check Electrical
Check manual operation
Local Control
Disconecting Switch 2 (DS2)
Visual check and check Electrical
Check manual operation
Local Control
Circuit Breaker
Visual check
Check Electrical
Local Control
14 ACTIVATION APPARATUS BESERTA INTERLOCK LOCAL (KOPEL)
Disconecting Switch 1 (DS1)
Visual check and check Electrical
Check manual operation
Local Control
Disconecting Switch 2 (DS2)
MONITORING PRA COMMISSIONING GI 150 kV ARGAMAKMUR
BAY LINE PULAU BAAI 1, LINE PULAU BAAI 2, LINE MUKO-MUKO 1, LINE MUKO-MUKO 2, TRAFO, KOPEL
SEPTEMBER WEEK 3 SEPTEMBER WEEK 4 OKTOBER WEEK 1 OKTOBER WEEK 2 OKTOBER WEEK3
N0 TASK NAME TIME
20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Visual check and check Electrical
Check manual operation
Local Control
Circuit Breaker
Visual check
Check Electrical
Local Control
15 CARACTERISTIC TEST HV APARATUS (BAY LINE 1,2,3,4)
Disconecting Switch ( DS1, DS2, DSL )
Contact Resisitance
Isolation Test
Circuit Breaker ( CB )
Contact Resisitance
Isolation Test
CB Analyzer ( Timing Test )
16 CARACTERISTIC TEST HV APARATUS (BAY TRAFO&KOPEL)
Disconecting Switch ( DS1, DS2 )
Contact Resisitance
Isolation Test
Circuit Breaker ( CB )
Contact Resisitance
Isolation Test
CB Analyzer ( Timing Test )
17 TEST GROUNDING HV APPARATUS (ALL BAY)
Test Grounding HV apparatus
Test Grounding Control Panel
18 CONTROL FROM PANEL (INTERLOCK FUNCTION ALL BAY )
Control and interlock via Mimik and BCU
Simulasi saat Onload Transfer
Simulasi rangkain BCBL
Control tap Changer (jika sudah siap)
19 TEST INDIKASI dan ALARM SAMPAI PANEL CONTROL (ALL BAY)
Alrm Marshalling Kiosk
Indikasi and Alrm DS1, DS2 and CB
Indikasi and Alrm (jika sudah siap)
20 CEK PANEL BUSPRO
Check kabel External Buspro baik CT, Trip dan Status
21 PENARIKAN KABEL KOMUNIKASI/ FO
Pengecekan model FO
Penarikan kabel FO bay LINE 1 , TRAFO, KOPEL
22 SAS CONFIGURATION
23 SECONDARY INJECTION CIRCUIT TEST
CURRENT CIRCUIT
MONITORING PRA COMMISSIONING GI 150 kV ARGAMAKMUR
BAY LINE PULAU BAAI 1, LINE PULAU BAAI 2, LINE MUKO-MUKO 1, LINE MUKO-MUKO 2, TRAFO, KOPEL
SEPTEMBER WEEK 3 SEPTEMBER WEEK 4 OKTOBER WEEK 1 OKTOBER WEEK 2 OKTOBER WEEK3
N0 TASK NAME TIME
20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Current Circuit ( Isolation Test, Resistance, Secondary Loop, Burden )
24 RELAY TEST AND COFIGURATION (NOTE DATA SETT READY)
Relay Differensial
Setting and Individual Test Differensial Relay
Relay Tapcon
Setting and Individual Test Tapcon Relay
Relay Over Current
Setting and Individual Test Over Current Relay
25 FUNCTION TEST
Bay LINE 1,2,3,4 TRAFO, KOPEL
Function Test Differensial Relay
Function Test Over Current Relay
Function Test Tapcon Relay & Digital Tap Poundful
26 CONTROL VIA HMI
Control Apparatus dan Tap Changer
27 INJECTION PRIMER
Current Transformer
28 POINT TO POINT WITH MASTER RCC
29 GENERAL CHECK
30 COMMISSIONING with JASER
31 STABILITY and TEST BUSPRO (vendor)
32 Penyesuaian Rangkain VT Bus dan Common Buswire ke Panel Existing

Tidak ada kegiatan (Libur)


Pekerjaan selesai
on going