Professional Documents
Culture Documents
SRCS 2-8 Underground Works Eng
SRCS 2-8 Underground Works Eng
SRCS 2-8 Underground Works Eng
BELGRADE, 2018.
Editions: Public Enterprise Roads of Serbia, Bulevar kralja Aleksandra 282, Belgrade
Editions:
CONTENTS
2.8.1 INTRODUCTION........................................................................................................... 1
2.8.1.1 SUBJECT MATTER OF SPECIFICATION....................................................................1
2.8.1.2 TECHNICAL REGULATIONS.......................................................................................1
2.8.1.3 TERMINOLOGY............................................................................................................ 3
2.8.1.4 ABBREVIATIONS USED............................................................................................. 11
2.8.2 CLASSIFICATION OF ROCK MASSES.....................................................................12
2.8.2.1 GENRAL...................................................................................................................... 12
2.8.2.2 APPLICATION AND PROCEDURES..........................................................................12
2.8.2.3 GENERAL CLASSIFICATION SYSTEM - ACCORDING TO STANDARDS...............13
2.8.2.4 TUNNELLING CLASS MATRIX..................................................................................14
2.8.2.5 UNDERSTANDING THE MATRIX..............................................................................18
2.8.2.5.1 Application of the support type....................................................................................19
2.8.2.5.2 Determining the design parameters which refer to the payment for the support
elements...................................................................................................................... 19
2.8.2.5.3 Setting of progress rate parameters during excavation...............................................19
2.8.2.5.4 Calculating prices for non-tendered types of support..................................................20
2.8.3 UNDERGROUND EXCAVATION...............................................................................22
2.8.3.1 GENERAL................................................................................................................... 22
2.8.3.1.1 Documentation............................................................................................................ 22
2.8.3.2 EXECUTION............................................................................................................... 23
2.8.3.2.1 Equipment................................................................................................................... 23
2.8.3.2.2 Lighting and power during the construction phase......................................................23
2.8.3.2.3 Ventilation during construction....................................................................................23
2.8.3.2.4 Definition of the excavation profile...............................................................................23
2.8.3.2.5 Overbreak.................................................................................................................... 24
2.8.3.2.6 Excavation requirements............................................................................................. 24
2.8.3.2.7 Safety measures......................................................................................................... 25
2.8.3.2.8 Continuous working..................................................................................................... 25
2.8.3.2.9 Drainage during construction.......................................................................................25
2.8.3.2.10 Traffic at the construction site on the finished excavation grade level.........................26
2.8.3.2.11 Traffic at the construction site over the invert arch......................................................26
2.8.3.3 DIMENSIONS OF THE EXCAVATION........................................................................26
2.8.3.4 PAYMENT................................................................................................................... 28
2.8.4 CONTROL OF THE PROFILE AND PERMITTED DEVIATIONS...............................30
2.8.4.1 PROFILE CONTROL................................................................................................... 30
2.8.4.1.1 Control of the profile for the final concrete lining.........................................................30
2.8.4.1.2 Execution..................................................................................................................... 31
2.8.4.1.3 Records....................................................................................................................... 31
2.8.4.2 PERMITTED CONSTRUCTION DEVIATIONS...........................................................31
2.8.4.2.1 Permitted deviations for the initial lining......................................................................31
2.8.4.2.2 Permitted deviations from the excavation level of the invert arch................................31
2.8.4.2.3 Permitted deviations of the inner concrete lining.........................................................32
2.8.5 SECURING OF THE TUNNEL....................................................................................33
2.8.5.1 GENERAL REQUIREMENTS.....................................................................................33
2.8.5.1.1 Construction method................................................................................................... 33
2.8.5.1.2 Documentation that needs to be delivered..................................................................33
2.8.5.1.3 Implementation of tunnel supporting works.................................................................33
2.8.5.1.4 Records....................................................................................................................... 33
2.8.5.1.5 Equipment and the supply of material.........................................................................34
2.8.5.2 SHOTCRETE.............................................................................................................. 34
2.8.5.2.1 General........................................................................................................................ 34
2.8.5.2.2 Materials...................................................................................................................... 34
2.8.5.2.3 Mixture design............................................................................................................. 35
2.8.5.2.4 Batching, mixing and transportation............................................................................36
2.8.5.2.5 Applying shotcrete....................................................................................................... 37
2.8.5.2.6 Shotcrete testing......................................................................................................... 38
PE Roads of Serbia i
Underground Works Serbian Road Construction Specifications
ii PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
2.8.6.8.1 Pre-drilling................................................................................................................... 61
2.8.6.8.2 Grouting....................................................................................................................... 61
2.8.7 WATERPROOFING AND PERMANENT DRAINAGE OF GROUND WATERS........62
2.8.7.1 WATERPROOFING AND PROTECTIVE FELT..........................................................62
2.8.7.1.1 General........................................................................................................................ 62
2.8.7.1.2 Materials...................................................................................................................... 63
2.8.7.1.3 Execution..................................................................................................................... 65
2.8.7.1.4 Quality control of execution.........................................................................................66
2.8.7.2 PERMANENT DRAINAGE OF UNDERGROUND WATER.........................................67
2.8.7.2.1 General........................................................................................................................ 67
2.8.7.2.2 Materials...................................................................................................................... 67
2.8.7.2.3 Execution..................................................................................................................... 67
2.8.7.3 MEASURING............................................................................................................... 68
2.8.7.3.1 Waterproofing membrane............................................................................................ 68
2.8.7.3.2 The longitudinal drainage of underground waters.......................................................68
2.8.7.4 PAYMENT................................................................................................................... 68
2.8.7.4.1 Waterproofing membrane............................................................................................ 68
2.8.7.4.2 The longitudinal drainage of underground waters.......................................................68
2.8.8 CASTINGCASTING AND REINFORCEMENT...........................................................70
2.8.8.1 GENERAL................................................................................................................... 70
2.8.8.1.1 Description.................................................................................................................. 70
2.8.8.1.2 Documentation that needs to be delivered..................................................................70
2.8.8.1.3 Conditions for the execution of works..........................................................................71
2.8.8.2 MATERIAL.................................................................................................................. 71
2.8.8.2.1 Formwork.................................................................................................................... 71
2.8.8.2.2 Concrete...................................................................................................................... 71
2.8.8.2.3 Prefabricated concrete components............................................................................72
2.8.8.2.4 Injection mass for contact injecting..............................................................................72
2.8.8.2.5 Reinforcement............................................................................................................. 72
2.8.8.2.6 Coating........................................................................................................................ 72
2.8.8.3 CASTING.................................................................................................................... 72
2.8.8.3.1 Preparation of formwork prior to concrete works.........................................................72
2.8.8.3.2 Preparation for concrete placement............................................................................73
2.8.8.3.3 Placement of concrete................................................................................................. 73
2.8.8.3.4 Compaction of concrete for final lining.........................................................................74
2.8.8.3.5 Removal of formwork................................................................................................... 74
2.8.8.3.6 Curing of concrete....................................................................................................... 74
2.8.8.3.7 Remedial treatment of surfaces...................................................................................75
2.8.8.3.8 Prefabricated concrete elements.................................................................................75
2.8.8.3.9 Contact injecting.......................................................................................................... 75
2.8.8.3.10 Application of the protective coating............................................................................75
2.8.8.4 REINFORCING........................................................................................................... 76
2.8.8.4.1 Reinforcement mesh................................................................................................... 76
2.8.8.4.2 Reinforcing steel bars.................................................................................................. 76
2.8.8.5 QUALITY ASSURANCE.............................................................................................. 76
2.8.8.6 MEASURING............................................................................................................... 76
2.8.8.7 PAYMENT................................................................................................................... 77
2.8.9 EARTHING IN THE TUNNEL.....................................................................................79
2.8.9.1 GENERAL................................................................................................................... 79
2.8.9.2 MATERIALS................................................................................................................ 79
2.8.9.3 EXECUTION............................................................................................................... 79
2.8.9.4 MEASURING............................................................................................................... 79
2.8.9.5 PAYMENT................................................................................................................... 79
iv PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
Relevant standard Standard title in English language Standard title in Serbian language
SRPS EN 932- Tests for general properties of Ispitivanja opštih svojstava agregata
(grupa standarda) aggregates
SRPS EN 934- Admixtures for concrete, mortar and Dodaci betonu, malteru i injekcionoj
(grupa standarda) masi
SRPS EN 1008 Mixing water for concrete - Voda za pripremu betona - Specifikacije
Specification for sampling, testing and za uzimanje uzoraka, ispitivanje i ocenu
assessing the suitability of water, pogodnosti vode za pripremu betona,
including water recovered from uključujući vodu dobijenu iz procesa u
processes in the concrete industry, as industriji betona
mixing water for concrete
SRPS EN 1097- Tests for mechanical and physical Ispitivanje mehaničkih i fizičkih
(grupa standarda) properties of aggregates svojstava agregata
SRPS EN 1367- Tests for thermal and weathering Ispitivanja toplotnih svojstava agregata i
(grupa standarda) properties of aggregates otpornosti prema raspadanju
SRPS EN 1401- Plastics piping systems for non- Sistemi cevovoda od plastičnih masa
(grupa standarda) pressure underground drainage and za podzemno odvodnjavanje bez
sewerage - Unplasticized poly(vinyl pritiska i kanalizaciju - Neomekšani
chloride) (PVC-U) - polivinilhlorid (PVC-U)
PE Roads of Serbia 1
Underground Works Serbian Road Construction Specifications
SRPS EN 1744- Tests for chemical properties of Ispitivanja hemijskih svojstava agregata
(grupa standarda) aggregates
SRPS EN 1926 Natural stone test methods - Metode ispitivanja prirodnog kamena -
Determination of compressive strength Određivanje čvrstoće pri pritisku
SRPS EN 10080 Steel for the reinforcement of concrete - Betonski čelik - Zavarivi betonski čelik -
Weldable reinforcing steel - General Opšti deo
SRPS EN 12390-3 Testing hardened concrete - Part 3: Ispitivanje očvrslog betona - Deo 3:
Compressive strength of test Čvrstoća pri pritisku uzoraka za
specimens ispitivanje
SRPS EN 13179- Tests for filler aggregate used in Ispitivanja kamenog brašna koje se
(grupa standarda) bituminous mixtures koristi u bitumenskim mešavinama
SRPS EN 13990 Wood flooring - Solid softwood floor Drveni podovi - Podne daske od
boards masivnog četinarskog drveta
SRPS EN ISO 2431 Paints and varnishes - Determination of Boje i lakovi - Određivanje vremena
flow time by use of flow cups isticanja pomoću posuda za isticanje
SRPS EN ISO 13736 Determination of flash point - Abel Određivanje tačke paljenja - Metoda u
closed-cup method zatvorenom sudu po Abelu
SRPS ISO 10319 Geotextiles - Wide-width tensile test Geotekstil - Ispitivanje zatezanjem
metodom širokog laboratorijskog
uzorka
SRPS ISO 11058 Geotextiles and geotextile-related Geotekstil i geotekstilu srodni proizvodi
products - Determination of water - Određivanje svojstva permeabilnosti
permeability characteristics normal to vode upravno na ravan epruvete, bez
the plane, without load opterećenja
SRPS ISO 12236 Geotextiles and geotextile-related Geotekstil i geotekstilu srodni proizvodi
products - Static puncture test (CBR- - Statičko ispitivanje proboja (CBR
Test) ispitivanje)
2 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
SRPS ISO 12956 Geotextiles and geotextile-related Geotekstil i geotekstilu srodni proizvodi
products - Determination of the - Određivanje karakteristične veličine
characteristic opening size otvora
SRPS ISO 12958 Geotextiles and geotextile-related Geotekstil i geotekstilu srodni proizvodi
products - Determination of water flow - Određivanje kapaciteta protoka vode
capacity in their plane u ravni
2.8.1.3 Terminology
Behavior of the system rock – support –SB Ponašanje sistema stenska masa –
(ponašanje sistema stenska masa – podupirači podupirači – SB (behavior of the system rock
– SB) is the behavior of the entire system that – support – SB) je ponašanje celokupnog
stems from rock-excavation-support sistema koje potiče od uzajamnog delovanja
interaction. stenska masa-iskop-podupirači.
Calculation line (linija obračuna) is the line Linija obračuna (calculation line) je linija duž
along which the cost of individual works is koje se tokom gradnje vrši obračun pojedinih
calculated during construction and is defined in stavki rada i definisana je tenderskom
the tender documentation. The cost for support dokumentacijom. Za obračun elemenata
elements is calculated according to the line oslanjanja se koristi linija koja je određena
defined by the sum of the following: clearance zbirom: poluprečnika svetlog profila, debljine
radius, inner lining thickness, thickness of unutrašnje obloge, debljine poravnavanja za
leveling for waterproofing and waterproofing, hidroizolaciju i hidroizolacije, debljine
and thickness of the deformation nadvišenja deformacije koje tokom gradnje
superelevation that the commissioning party or određuje naručilac odn. njegov punomoćnik
its agent (supervisor, designer) defines during (nadzor, projektant).
construction).
PE Roads of Serbia 3
Underground Works Serbian Road Construction Specifications
Category of rock (kategorija stenske mase) is Kategorija stenske mase (category of rock) je
marking of rock with equal characteristics označavanje stenske mase sa podjednakim
related to excavation of entire cross section, as svojstvima u odnosu na iskopavanje
well as to time and space deformation during celokupnog poprečnog preseka, kao i na
excavation, regardless of supporting measures vremensku prostornu deformaciju tokom
and other additional measures. iskopavanja bez obzira na mere podupiranja i
ostale dodatne mere.
Cement concrete, Beton (cementni beton) is Cementni beton (cement concrete, Beton) je
a material obtained by mixing stone grain materijal, koji nastaje mešanjem mešavine
(course and fine aggregate), hidraulic cement kamenih zrna (krupnog i sitnog agregata),
binder, and water, with chemical and/or hidrauličnog veziva cementa i vode, po potrebi
mineral admixtures as needed; it develops its sa dodatkom hemijskih i/ili mineralnih
properties by cement hydration. dodataka (aditiva); hidratacijom cementa
razvija svoja svojstva.
Contractor (izvođač) is a legal entity or natural Izvođač (contractor) je pravno ili fizičko lice
person that has concluded a contract with the koje je sa naručiocem sklopilo ugovor sa
commissioning party with the obligation to obavezom da izvrši određeni posao po
complete a specific job according to the odredbama ugovora, odobrenim nacrtima i
provisions of the contract, the approved project drugim uslovima, koji su sastavni deo ugovora;
and other terms, constituting an integral part of takođe, to može da bude i pravno lice
the contract; it can also signify the legal entity odgovorno za proizvod, postupak i posao, koje
responsible for the product, procedure and job, realizuje uslove za garanciju kvaliteta.
which fulfills the quality assurance
requirements.
Cross passage (poprečni tunel) is a tunnel Poprečni tunel (cross passage) je tunel koji
which connects two tubes of a two- or multiple povezuje dve cevi dvo ili višetračnog tunela.
tunnel tubes. It facilitates necessary redirecting Omogućava nužno preusmeravanje
of traffic and evacuation of people in saobraćaja odnosno evakuisanje ljudi u hitnim
emergency situations and is used as an slučajevima i koristi se kao pomoćni objekat
auxiliary structure for tunnel maintenance. The kod održavanja tunela. Dimenzije preseka
dimensions of the cross section depend on the zavise od namene za koju se upotrebljava.
intended purpose of the tunnel.
Cut and cover (pokriveni iskop) is an Pokriveni iskop (cut and cover) je podzemni
underground structure with a curved or građevinski objekat zakrivljenog ili
rectangular form over the route of the road pravougaonog oblika na trasi puta, koji je
which is constructed in an open trench and izveden u iskopu i naknadno nasut.
subsequently filled in.
Cutting rock (sečenje stenske mase) is Sečenje stenske mase (cutting rock) je
mechanical rock crushing by using cutting mehaničko drobljenje stenske mase mašinama
machines for full or separated excavation za sečenje punog ili podeljenog profila iskopa.
profile.
4 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
Ditch (rov) is long underground horizontal area Rov (ditch) je dugačak podzemni horizontalan
or area without slope with excavated profile not prostor ili prostor bez nagiba čiji je iskopni
larger than 20 m2. presek do 20 m2.
Excavation line (linija iskopa) is the line along Linija iskopa (excavation line) je linija duž
which the cost of excavation is calculated koje se tokom gradnje vrši obračun
during construction and is defined in the tender iskopavanja i definisana je tenderskom
documentation. The cost for excavation is dokumentacijom. Za obračun iskopavanja se
calculated according to the line defined by the koristi linija koja je određena zbirom:
sum of the following: clearance radius, inner poluprečnika svetlog profila, debljine
lining thickness, thickness of leveling for unutrašnje obloge, debljine poravnavanja za
waterproofing and waterproofing, thickness of hidroizolaciju i hidroizolacije, debljine
the deformation superelevation that the nadvišenja deformacije koje tokom gradnje
commissioning party or its agent (supervisor, određuje naručilac odn. njegov punomoćnik
designer) defines during construction, and the (nadzor, projektant), i debljine mlaznog betona
thickness of the shotcrete as support element. kao elementa oslanjanja.
Excavation step (iskopni korak) is part of Iskopni korak (excavation step) je deo iskopa
excavation executed entirely in one cycle or izveden u potpunosti u jednom ciklusu ili deo
step by step (calotte, bench, invert arch made po deo (kalota, stepenica, podnožni svod od
of sprayed concrete). mlaznog betona).
PE Roads of Serbia 5
Underground Works Serbian Road Construction Specifications
Holders (koplja) are steel tubes or steel bars Koplja (holders) su čelične cevi ili čelične
built in front of excavation head and that play šipke koje su ugrađene ispred čela iskopa i
role in providing arch and sides of excavated imaju ulogu u obezbeđivanju svoda i strana
step during the excavation progress. iskopnog koraka tokom napredovanja iskopa
prostora.
Invert arch (podnožni svod) is a part of the Podnožni svod (invert arch) je deo tunelske
tunnel liner between the abutments; structure obloge iyme]u oporaca; faza iskopa ispod
in the form of an arch which spans and stepenice; konstrukcija u obliku luka koja
encloses an underground opening below the premošćuje i zatvara podzemni otvor ispod
pavement structure. kolovozne konstrukcije.
6 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
Mastic asphalt (liveni asfalt) is a voidless Liveni asfalt (mastic asphalt) je asfaltna
asphalt mixture, in a partially liquid state when mešavina bez šupljina, u vrućem stanju gusto
hot; compaction at implementation is not tekuća; pri ugrađivanju nije potrebno zbijanje.
required.
Middle pillar (središnji zid) is the central load Središnji zid (middle pillar) je središnja
bearing structure in a two- or multiple-tube potporna konstrukcija kod dvo- ili višecevnih
covered excavation, gallery or underpass, pokrivenih iskopa, galerija i podvožnjaka u
rectangular in shape, constructed as a wall or pravougaonom obliku, izvedena kao zid ili sa
with columns. If it is constructed with columns, stubovima. Ako je izveden sa stubovima, donji
the lower section between the columns, up to a deo između stubova mora do visine 1,20 m da
height of 1,20 m, must be covered with filler or bude ispunjen međuispunom ili šupljim zidom
a perforated wall (parapet) with a thickness (parapetom) jednake debljine kao i stubovi,
equal to the columns, so that the external tako da spoljna površina po celoj dužini zida
surface along the entire length of the wall is bude ravna. U objektima koji su namenjeni za
even. In structures intended for travel speeds brzinu vožnje do 80 km/h, ravnina između
of up to 80 km/h, the continuity between the stubova se umesto umetnutog zida može
columns can be constructed by placing postići postavljanjem višečlane sigurnosne
panelled safety barriers instead of an inserted ograde.
wall.
Open construction of the tunnel (otvorena Otvorena izgradnja (open construction of the
izgradnja) is a method of construction in which tunnel) je način izvođenja u kojem se
underground structures are partially or entirely podzemni građevinski objekti delimično ili u
built in an open trench and subsequently filled celosti grade u otvorenom iskopu i naknadno
in. zatrpavaju.
PE Roads of Serbia 7
Underground Works Serbian Road Construction Specifications
Open road rout (otvorena trasa) is part of the Otvorena trasa (open road rout) je deo puta
road outside the scope of underground van područja podzemnih građevinskih objekata
structures traffic lane, each of both lanes of the kolovozna traka svaka od obe trake
bidirectional road, on which the lanes for the dvosmernog puta, na kojoj su trake za pojedini
individual directions of travel are divided smer vožnje fizički ili samo horizontalnom
physically or by horizontal signalization only signalizacijom odvojene međusobno i kod
and with normal functioning of the road they normalnog funkcionisanja puta namenjene
are intended exclusively for travel in one isključivo za vožnju u jednom ili u drugom
direction or another. smeru.
Portal (portal) is the beginning or end of the Portal (portal) je početak odnosno kraj tunela
tunnel at the transition into an open route. In na prelazu u otvorenu trasu. U širem smislu je
the broad sense the portal area is the section portalno područje onaj deo otvorene trase
of open route in front of the tunnel where ispred tunela, gde su postavljeni objekti,
structures, equipment and devices are placed oprema i uređaji, potrebni za neometano i
which are necessary for the unobstructed and sigurno korišćenje tunela.
safe use of the tunnel.
Revision nishe (niša za čišćenje) is a small Niša za čišćenje (revision nishe) je manji
auxiliary area in the tunnel wall that serves to pomoćni prostor u zidu tunela, namenjen
maintain tunnel drainage system. održavanju drenažnog sistema i sistema za
odvodnjavanje tunela.
Ring (kampada) is the segment of the Kampada (ring) je deo konstrukcije objekta
structure between two construction or između dva radna ili dilataciona spoja.
expansion joints.
Road tunnel (putni tunel) is an underground Putni tunel (road tunnel) je podzemni
structure along the route of the road which građevinski objekat na trasi puta, kojim se
enables: maintaining the road profile within the omogućava: očuvanje poretka puta u
prescribed limitations of the geometric and propisanim granicama geometrijskih i tehničkih
technical elements of the road through relief elemenata puta kroz reljefne prepreke,
obstacles; providing protection around the road obezbeđivanje zaštite okoline puta od
from the extremely harmful effects of road preterano štetnog uticaja putnog saobraćaja.
traffic. Underground roads are designed and Izvođenje podzemnog toka puta u područjima,
constructed in areas where it is not possible to na kojim nije moguće graditi na površini zbog
construct them on the surface due to pejzažnih ili urbanih odlika.
landscape or urban features.
8 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
Rock (stena) is aggregate made of mineral Stena (rock) je agregat od mineralnih zrna
grains (parts) created naturally, characteristic (delova) koji je nastao prirodnim putem, koji je
for the type and group of existing mineral, with karakterističan za vrstu i grupu postojećeg
characteristic structure, texture etc. minerala, karakteristične strukture, teksture i
sl.
Rock behaviour (ponašanje stenske mase) is Ponašanje stenske mase (rock behaviour) je
a rock reaction ability during excavation of a reakcijska sposobnost stenske mase tokom
structure's entire profile, where effects of iskopavanja celokupnog profila objekta, pri
further excavation and primary supporting are čemu se ne uzimaju u obzir uticaji daljeg
not taken into account. iskopavanja i primarnog podupiranja.
Rock bolt (sidro) is a supporting element used Sidro (rock bolt) je potporni element koji služi
to support excavated open space and to da obezbedi otvoren iskopani prostor i da
improve rock characteristics. Commonly, these poboljša svojstva stenske mase. Često su to
are steel rods, steel tubes or ropes built into čelične šipke, čelične cevi ili užad koja se
drills filled with binding agents or empty drills ugrađuju u bušotine koje su ispunjene vezivom
(e.g. Swellex). ili su prazne (npr. Swellex).
Rock mass (stenska masa) is the part of crust Stenska masa (rock mass) je deo zemljine
made of solid rock and/or earth, including kore koju sačinjavaju čvrste stene i/ili zemljište,
anisotropic compounds, separation surfaces uključujući anizotropske sastojke, razdelne
and empty space filled with liquid or gasses. površine i prazni prostori ispunjeni tečnošću ili
gasovima.
Soil (tla) is accumulation of inorganic solid Tla (soil) je akumulacija anorganskih čvrstih
particles of various sizes which can contain čestica različitih veličina koja može da sadrži i
parts of organic substances. Characteristics of primese organskih materija. Svojstva zemljišta
soil are generally determined by granulometric uglavnom određuju granulometrijski sastav,
composition, consistency, compression, and konzistencija, stišljivost i sadržaj vode.
water content.
Steel lagging (talpe) are formwork steel Talpe (steel lagging) su čelični elementi
elements such as corrugated steel plates oplate, kao što su talasaste čelične ploče koje
which during the next excavation step rest on se uoči narednog iskopnog koraka oslanjaju na
steel distribution support and suppress or čeličnu lučnu potporu i potiskuju ili sabijaju
compact rock of low bearing capacity in front of stensku masu slabe nosivosti ispred čela
excavation head to protect excavation area iskopa da bi se prostor iskopa zaštitio od
from collapsing during excavation. urušavanja tokom iskopavanja.
Step (korak) is execution of entire excavation Korak (step) je izvođenje celokupnog ciklusa
cycle, load, transport and installation of iskopavanja, utovara, prevoza i ugradnje
supporting elements. potpornih elemenata.
PE Roads of Serbia 9
Underground Works Serbian Road Construction Specifications
Top heading, calotte (kalota) is the upper part Kalota (top heading, calotte) je gornji deo
(curved) of the excavation of the cross section (zakrivljen) iskopa poprečnog profila tunela.
of the tunnel.
Tunnel (tunel) is horizontal i.e. slightly inclined Tunel (tunnel) je vodoravan odnosno blago
longer underground space with excavation nagnut dalji podzemni prostor čiji je iskopni
profile larger than 20 m2, used for road or presek veći od 20 m2, namenjen drumskom ili
railway traffic.Tunnel has entrance and exit železničkom saobraćaju. Tunel ima ulaz i izlaz
from the rock. iz stenske mase.
Tunnel lenght (dužina tunela) is the specified Dužina tunela (tunnel lenght) je određena
length of the longest completely covered dužinom najduže potpuno pokrivene vozne
driving lane. trake.
Tunnel lining (obloga tunela) is a smaller Obloga tunela (tunnel lining) je betonska ili
auxiliary space in the wall of the tunnel armirano betonska konstrukcija koja služi kao
intended for maintenance of the tunnel zaštita prometa u tunelu.
drainage system and water removal system.
Type of rock mass – GT (vrsta stenske mase Vrsta stenske mase – GT (type of rock mass
– GT) is a rock mass with similar geological, – GT) je stenska masa sličnih geoloških,
geomechanical and chemical properties. geomehaničkih i hemijskih svojstava.
10 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
PE Roads of Serbia 11
Underground Works Serbian Road Construction Specifications
12 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
1. Stable rock mass Stable rock mass with the possibility of weight-induced
falling or sliding of blocks
2. Stable with the potential Deep reaching, discontinuity controlled, gravity induced
discontinuity controlled block falling and sliding of blocks, occasional local shear
fall failure
4. Deep seated shear failure Deep seated stress induced shear failures and large
deformation
5. Rock burst Sudden and violent failure of the rock mass, caused by
highly stressed brittle rocks and the rapid release of
accumulated strain energy
7. Shear failure under low Possibility for excessive overbreak and progressive
confining pressure shear failure caused mainly by a deficiency of side
pressure
PE Roads of Serbia 13
Underground Works Serbian Road Construction Specifications
11. Heterogeneous rock mass Rapid variations of stresses and deformations, caused
characterised by frequently by block-in-matrix rock situation (e.g. brittle fault zone,
changing behaviour tectonic melange)
14 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
Table 2.8.2: Example of the support types matrix for calotte or calotte and bench (ÖNORM B 2203-1)
excavation step
SECOND CLASIFICATION NUMBER
CLASIFICATION
to
NUMBER
FIRST
top head. or
SUPPORT NUMBER
top head.
+ bench
BENCH
1 2 3 4 5 6 7 8 9
no
lim it
2 4,0 m
3 3,0 m
defined by the design
Ÿ Ÿ
4 2,2 m 4/2,4 4/3,6
Ÿ Ÿ
5/4,5 5/6,1
5 1,7 m
Ÿ Ÿ
6/5,5 6/7,5
6 1,3 m
7 1,0 m
8 0,8 m
9 0,6 m
Table 2.8.3: Example of the support types matrix for invert arch (ÖNORM B 2203-1)
Excavation round
SUPPORT NUMBER
NUMBER
1 2 3 4
1 No limit 1/1
2 36,0 m 2/2
3 24,0 m 3/2
5 6,6 m 5/4
6 4,4 m
7 2,2 m
PE Roads of Serbia 15
Underground Works Serbian Road Construction Specifications
Table 2.8.4: Evaluation of support elements and auxiliary measures (ÖNORM B 2203-1)
Support element (for 1 m of tunnel) Unit Quantity Factor Partial no. Notes
Self-threading
m 1,7
injection bore bolt
Pre-stressed rock
m 2,5
bolts
Anchor plate
2
without pre- pc 1,7
stressing
Ribbed bars in
m 0,9
mortar
Self-drilling
m 1,3
injection piles
Injection piles /
m 1,6
holders
Injection >10 kg
Injection per m of anchor, kg 0,1
pile, pilot
External side 3
m² 2,0
without the arch
Temporary invert 3
m² 0,8
arch
Additional
3,4
reinforcement, m² 2,0
excavation face
16 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
Support element (for 1 m of tunnel) Unit Quantity Factor Partial no. Notes
Invert arch,
5
temporary invert m³ 12,0
arch
5
Face m³ 14,0
Deformatio Without
7
n elements deformation m 3,5
elements
With deformation 7
m 5,0
elements
Steel
Steel laggings m² 5,5
laggings
Phase 8
Phase excavation pc 22,0
excavation
Excavation
Excavation of the
of the 9
calotte toe - m 50,0
calotte toe -
widening
widening
Sum
NOTE:
1. Number of existing anchors in each excavation round. Weighting factors have been taken
into consideration for installation, shortening and loading during the excavation phase.
2. Number of anchor plates, installed at the face in question.
3. Theoretical quantities, not taking into consideration the exceeding in the longitudinal and
transversal direction.
4. Layout surface, covered with reinforcement - reinforcement at the joints calotte / bench and
bench / invert arch is not estimated.
5. Theoretical quantities, not taking into consideration the super section and the fender.
6. Filling of planned wedges (adjacent to driven steel laggings, etc.) or filling of accepted
wedges over the excavation in the rock side of the boundary plane A.
7. Linear metre of the deformation slot.
8. Phase excavation area refers only to the area where the excavation phase is immediately
and adequately supported after the excavation.
9. For both calotte toes, per linear metre of the tunnel
10. The length of the temporary invert arch of the calotte, during the bench excavation round in
question, regardless of the potential phase excavations.
PE Roads of Serbia 17
Underground Works Serbian Road Construction Specifications
Table 2.8.5: Area where the second organising number applies (support number)
Calotte Bench
No limit ± 0,35
No limit 0,45
4,0 m ± 0,35
3,0 m ± 0,45
3,0 m 0,70
2,2 m ± 0,60
1,7 m ± 0,80
2,0 m 1,20
1,3 m ± 1,00
0,8 m ± 1,60
0,6 m ± 2,10
HK Height of calotte
HS Height of bench
BL Boundary line, outer lining surface
HK, HS i BL Stipulated by contract
18 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
Pursuant to the standard ÖNORM B2203-1, In the situation where two cells (support
support type is defined by calculating the types) overlap in the matrix, the upper value
supporting number (second organising value) of the lower support type, i.e. lower value of
and taking into consideration the first the upper support type is taken as an
organising value (length of the excavation average value of the overlapping of these two
round/ round length). cells (see the example below).
As part of the lump sum, the Contractor has Calculation of the excavation price and of the
to include the risk of deviation from the lower rate of progress applies to the entire area of
limit of the excavation round, as well as the the individual support type.
position of the support number in the matrix
box. The Contractor is responsible for choosing
the excavation method, calculating the
While computing the support number, proposed time for completion and calculating
support elements as defined by the support a unique excavation price for each individual
type itself are taken into consideration, as support type, in a manner that ensures the
well as the support elements for the minimum of excavation and fulfilment of the
additional support measures. geotechnical requirements.
For example:
Support type: 7/11,79 7/13,51
Lower limit: 10,49 12,21
Upper limit: 13,09 14,81
Overlapping: 12,21 – 13,09
Overlapping midrange: 12,65
Valid lower limit: 10,49 12,65
Valid upper limit: 12,65 14,81
PE Roads of Serbia 19
Underground Works Serbian Road Construction Specifications
of the support types and elements, or Extrapolation of the offered unique price has
subsequently in an office. to be calculated in the following manner:
([ BA )−1]∗0 , 6
The quantities in the rating area and payment
Line 1a (depending on the deformation F=1+
tolerance set by the Engineer) are fixed
quantities.
UP new =UP old∗F
For potential changes of the thickness of the
inner lining, the rating area remains the V old
same. V new =
F
The valuation of the bench is performed
regardless of whether the bench is excavated A - 2. characteristic value of the
in sections or as a whole. The excavation offered matrix box
round and the support type for the invert arch
have to be determined before they are B - 2. characteristic value of the
constructed. newly set matrix box
UP new - extrapolated unique price
In a special section of the technical report,
the contractor is obligated to determine (the UP old - unique price for the tendered
offer) the progress speed, i.e. the advance support type
rate. These specific values represent an
integral part of the contract.
V new - extrapolated contracted
excavation speed
Niches and cross passages have to be V old - contracted excavation speed
constructed subsequently. for the tendered support type
Temporary backfills for the invert arch must Extrapolation when two or three support
serve as an adequate protection of the types are located next to each other in the
shotcrete lining. The cost of the time taken horizontal row of the matrix:
for the backfilling and cleaning of the residual
backfilling material is no extra charge. These Extrapolation has to be performed as shown
works, the time consumed and the expenses in example B2 in the standard ÖNORM
are taken into consideration while calculating B2203-1.
the rate of progress.
The example of extrapolation for two support
2.8.2.5.4 Calculating prices for non- types in the horizontal row of the matrix:
tendered types of support
Example:
n simple cases where the support system
deviates from the support types specified
Support types:
during the tender procedure, together with
the respective tolerance in the matrix box, the
5/4,5 5/6,1
standard ÖNORM 2203/1 prescribes the
systematic determination of new unique
Offered unique prices:
prices for excavation and the contracted
progress speed, i.e. the advance rate.
41,-- 52,-- [€/m3]
Pursuant to standard ÖNORM B2203-1, not
Offered unique speed:
more than one tender support type may be
extrapolated, to the left or to the right
2,0 1,7 [m/day]
respectively.
Second organising number (support number)
Extrapolation when there is only one support
for the construction of several support
type in the horizontal matrix row:
elements amounts to 8.1.
If the tender documentation foresees only
The next greater second organising number
one support type in the horizontal row of the
(support unit) amounts to:
matrix, the following procedure has to be
followed:
6,1 + 2 * 0,8 = 7,7.
20 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
For the support type 5 / 7.7 the price is: Quadratic polynomial is used as an
approximation function.
52,-- + ( 52 – 41 ) = 63,-- [€/m3]
Extrapolation curvature for the unique price
For the support type 5 / 7.7 the speed is: of the new support type is as follows for the
given example:
1,7 - ( 2,0 – 1,7 ) = 1,40 [m/dan].
2
UP new =1,1719∗B −5,5469∗B+ 42 ,23
The example of extrapolation for three
Extrapolation curvature for the unique speed
support types in the horizontal row of the
of the new support type is as follows for the
matrix:
given example:
Support types: 2
V new =−0,0195∗B +0,0195∗B+2,3076
5/4,5 5/6,1 5/7,7
B– support number of the new support type
Offered unique prices: For the support type 5 / 9.3 the price is: 92.00 [€/m3].
41,-- 52,-- 69,-- [€/m3] For the support type 5 / 9.3 the speed is: 0.80
[m/day].
Offered unique speed:
If the tender documentation foresees more
2,0 1,7 1,1 [m/day] than three support types in one horizontal
row of the matrix, three tendered adjacent
Second organising number (support number) support types have to be taken into
for the construction of several support consideration while determining the new
elements amounts to 9.1. support type.
PE Roads of Serbia 21
Underground Works Serbian Road Construction Specifications
22 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
conditions, safety measures, temporary and system has to be planned and has to work in
final drainage arrangement including the final accordance with local legislation.
landscaping.
All suggestions have to be delivered to the The ventilation system has to be planned to
Engineer in a timely manner, before the take into account the length of the tunnel, the
beginning of the construction phase or at a applied excavation method and the number
previously agreed time. of workers working in the tunnel.
Concentrations of poisonous gases, smoke
and dust particles, as measured at the
2.8.3.2 Execution construction site, must not exceed the
allowable concentrations (MPC).
2.8.3.2.1 Equipment
For tunnels with the potential for the
All mechanical equipment used for
occurrence of dangerous gases (for example,
underground excavations and transport have
methane), ventilation has to be designed and
to be adequate for the works included in the
installed in a manner that will ensure the
tender documents and have to correspond to
adequate reduction of the concentration of
the safety regulations valid in the Republic of
dangerous gases (CO2, CO, NO, NO2, etc.).
Serbia. It also has to correspond to the
The concentration of gases is measured by
requirements set forth in the construction
portable or stationary measuring instruments.
time programme and has to be approved by
the Engineer.
Generally speaking, the ventilation system
has to be designed in such a way to provide
The underground mechanical plant and the
a inflow of fresh air to the furthest excavation
equipment have to be powered by electricity,
heading, and to provide outflow of all harmful
compressed air or diesel engines. Diesel
gases. The distance between the end of the
engines have to be equipped with filters for
ventilation duct or hose pipe and the
the treatment of exhaust gases. Petrol or
excavation face must not exceed 30 m. The
paraffin mixtures must not be used as fuel
thrust of the ventilation fans has to be
during the construction of the tunnel.
sufficient to dilute the concentration of
explosive gases to below 0.5 % and
Rock-drilling with water flushing is not
simultaneously ensure a velocity of air
allowed in rock formations sensitive to water,
stream greater than or equal to 0.5 m/sec.
unless otherwise instructed by the Engineer.
2.8.3.2.4 Definition of the excavation profile
2.8.3.2.2 Lighting and power during the
construction phase The excavation profile as indicated in the
drawings (characteristic tunnel cross profile )
The Contractor is obligated to provide the
refers to the theoretical excavation profile
adequate protection and maintenance of
defined as Line 2 – Um.
electric power lines so as to ensure safe
working conditions. In cases when safe
Depending on the quality of rock mass, an
working conditions are not ensured, the
appropriate enlargement of the theoretical
Engineer may require that the electrical
excavation profile has to be made in order to
devices be disconnected or replaced.
provide enough space for radial deformations
and construction tolerances.
The Contractor is obligated to provide a
back-up diesel generator for each heading.
The excavation Line 1a - line (see figure
The capacity of the generator has to be
2.8.2) is designed for compensation of radial
sufficient to provide uninterrupted power to
deformation Um for various support types.
the lighting devices and the pumps used for
Deformations which correspond to the
water supply.
deformation tolerances Um (td) have been
given for each support type. Values given on
The Contractor is obligated to install and
the corresponding drawings or in the tender
maintain the minimum illumination of 100 W
documents for expected deformations Um
per 10 m of tunnel, or higher if required.
may be adjusted so as to take into
2.8.3.2.3 Ventilation during construction consideration the actual deformations in
accordance with the experience gained
The Contractor is in charge of the ventilation during the excavations. Adjustments have to
during the construction phase. The ventilation be made by the Designer, whereas the
Engineer has to approve them.
PE Roads of Serbia 23
Underground Works Serbian Road Construction Specifications
Line A represents the minimum excavation to stabilise the area. The Designer and the
profile. Generally speaking, rock mass must Engineer have to be informed immediately.
not protrude inside this line during The Contractor and the Designer or Engineer
excavations. It is allowed only locally, for have to consult and agree on the means of a
protruding edges and corners of sound rock, solution. A detailed solution plan has to be
within the tolerance of two thirds of the drafted by the Contractor and approved by
nominal shotcrete thickness. the Engineer. Remedial works have to be
performed before the excavation continues,
The Contractor is obligated to construct the unless otherwise ordered by the Engineer.
profile as defined by Line A. It is achieved
through careful control of the drilling and After it has been determined that an
through the application of various elements of overbreak has occurred as a consequence of
smooth blasting or other special blasting physical conditions beyond the control of the
techniques. Contractor, and that the overbreak was not
caused by inadequate working methods or
In order to maintain the excavation profile as carelessness, the volume of the void formed
defined by Line A, the Contractor must by the overbreak has to be measured. The
adhere to the construction tolerance Up (tc) Engineer has to approve and cover all the
for excavation and support installation. costs of materials required for the repair of
Construction tolerance Up (tc) also has to the overbreak.
include survey inaccuracies, as shown in
figure2.8.2. 2.8.3.2.6 Excavation requirements
24 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
The Contractor has to carry out systematic The Contractor has to provide a
inspections of the tunnel side walls and the sedimentation tank or other equipment for
roof so as to detect any potential cracks or decontamination, in accordance with the
other signs of instability in the tunnel. The requirements of the Engineer, which has to
evaluation of the number of cracks and the be used before the water is released into the
size of the cracks has to be performed based environment.
on the results of geotechnical measuring and
in cooperation with the Designer. The Contractor is obligated to remove the silt,
sediment or gravel that is a result of the
Blasting may commence only after all safety excavation works, in accordance with the
measures have been implemented and requirements of the Engineer.
personnel and machinery have been
protected. At the portals, the Contractor is obliged to
make, maintain and manage the structures
Drilling, blasting, excavating and shotcreting and devices required for the treatment of the
have to be performed using methods and contaminated waste water that is being
equipment which prevent the creation of dust, drained from the tunnel during construction.
smoke, gases, fog and mist to a large extent. These structures and devices have to consist
of two sedimentation tanks, an oil separator,
2.8.3.2.8 Continuous working a neutralisation device and the required
control station. The neutralisation device has
In order to provide safety and protection of to be designed and managed in such a way
the works, excavation of the tunnel has to be that the pH value of the treated water is
performed without interruption, unless the constantly kept in the range between 6.5 and
Engineer approves otherwise. Should the 8.5 before it can be released into the
nature of the works allow it, interruption of environment.
work is allowed over weekends and holidays,
on the condition that the works are secured Materials and execution
and that safe conditions are ensured.
Longitudinal drainage: Draining of the tunnel
Interruptions are allowed only after all during the construction phase has to be
support elements have been installed as achieved by means of the drainage channel
required for the support type at a given dug at the bottom of the calotte i.e. benching.
location. The walls of the drainage channel have to be
covered with shotcrete. The areas with a
Moreover, the heading and the surrounding greater inflow of water have to be drained by
area have to be covered with a 3-5 cm thick means of perforated or unplasticised PVC
layer of shotcrete. This does not apply in the pipes with notches, 150 to 250 mm in
PE Roads of Serbia 25
Underground Works Serbian Road Construction Specifications
diameter, depending on the quantity of water 2.8.3.2.10 Traffic at the construction site on
that has to be drained. the finished excavation grade
level
When works are performed in rocks that are
sensitive to water, the Contractor has to pay The excavation surface which corresponds to
special attention to emerging, collecting and the grade level of the final subgrade
draining of the water from the rock mass and formation and which is ready for the
of the technological water that was used for construction of the carriageway, has to be
construction of the tunnel. protected from wearing or deterioration that
may occur due to the transportation of rocks
In the situation where the tunnel is or other types of transport, by creating a
constructed downwards, the Contractor must backfilling layer consisting of the materials
construct chambers for pumping of water at excavated in the tunnel or other materials
an appropriate distance from each other. with adequate properties, with a minimum
Water has to be pumped out of the tunnel by thickness of 0.5 m.
means of suitable steel or PVC pipes.
The Contractor has to prevent the detention
Radial drainage: For concentrated inflow of of water in the tunnel. Traffic movement over
water, draining holes have to be drilled in the the residual water at the construction site is
soil or in the shotcrete. These holes have to not permitted.
be equipped with perforated steel or
unplasticised PVC pipes, 1.5 to 2“ in All materials of poorer quality than permitted
diameter. The space between the pipe and have to be removed prior to the installation of
the mouth of the hole has to be filled with the carriageway and have to be replaced by
quick-setting mortar. Quick-setting mortar is a adequate material in accordance with the
material that enables setting and hardening instructions and requests of the Engineer.
within minutes and is used for temporary
consolidation and filling. One end of the pipe Material used for the protection of the
is connected to a rubber hose for draining the carriageway must not be removed before the
water to a temporary longitudinal drainage works on the construction of the carriageway
point, to the chamber for pumping water or to commence.
a longitudinal channel at the bottom of the
calotte or bench in the tunnel. 2.8.3.2.11 Traffic at the construction site
over the invert arch
Circulatory drainage: In wet areas, water
from the tunnel walls is collected by means of Traffic over the unprotected construction of
corrugated, plasticised PVC pipes attached the invert arch is forbidden, both if it is made
to the rock by means of quick-setting cement of cement or shotcrete and if it is temporary
mortar or cement shotcrete, and which are or permanent in character.
subsequently connected to the chamber for
pumping or the longitudinal channel at the These construction units or assembly have to
bottom of the calotte or the bench in the be protected against damage or destruction
tunnel. by means of a backfill layer made of
adequate excavated or other material, with a
Wet areas that subsequently appear on the thickness of 0.5 m. Backfill must not consist
shotcrete lining have to be drilled and treated of rock pieces larger than 150 mm.
as previously described.
2.8.3.3 Dimensions of the excavation
In tunnels which are constructed on water
permeable soil or heavily cracked rocks, the The works specified in detail in this chapter
systematic installation of circulatory drainage are measured in the following manner:
has to be conducted with the approval of the
Engineer, with the minimal diameter of 4 cm, Excavation of tunnels and laybys in all rock
so as to prevent the occurrence of water behaviour types have to be measured in
pressure behind the shotcrete lining. cubic metres (m3) along "Line 2", as shown in
The Contractor has to ensure that the the figure 2.8.2. The length of each round is
chambers for pumping are cleaned regularly calculated along the tunnel axis. Dimensions
and that the drainage system is maintained in are determined for partial excavations of
a manner which enables the controlled cross profiles as shown in the designs. In
drainage of all waters during the construction cases when there is a need to construct a
phase. temporary arch in the calotte, the dimensions
26 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
of the bench have to be reduced pipe roof, are paid for separately, under the
proportionally. following conditions, regardless of the
quantities more or less required:
Excavation of the cross passages in all - for the item "excavation of the saw
support types is measured in cubic metres tooth profile below the pipe roof" /
(m3) along "Line 2", in the manner shown in installed pipe roof pipe (e = 40 cm),
the previous line. - for the item "shotcrete filler" / installed
pipe roof pipe (e = 40 cm),
Excavation of the niches is measured in
cubic metres (m3) along "Line 2"”. Furthermore, a timeframe has to be
submitted for the construction of the pipe roof
The increase of the excavation profile due to (together with the grouting and other works).
the permitted construction tolerances (tc) and Additional excavation works necessary for
unavoidable overbreak inside Line A are not the construction of temporary foundations in
measured for payment (see figure 2.8.2). the calotte are measured by linear metres of
the foundation (m').
Excessive overbreaks outside Line A,
occurring due to unfavourable geological Additional work and the materials necessary
conditions, are measured at the locations for the careful execution of work in rock types
where they occurred, in actual quantities, that are sensitive to water (swelling of the
under the condition that the overbreak rock mass) are not measured additionally
exceeds 2 m3 per linear metre of the tunnel. and are not paid for.
Overbreak up to 2 m3 per linear metre is not
measured and not paid for. PriIn the case of excavation in a downward
direction, the control of water of up to 5 l/sec,
Additional excavation works due to the which involves adequate drainage,
widening of the profile in areas where the redirection flow and removal of the water, is
crown is reinforced with pipe roof is paid as a the obligation of the Contractor and thus is
separate item. A special matrix is used for not calculated. The occasional control of
the excavation and support of the calotte water quantities that exceed 5 l/sec is
underneath the pipe roof. These payment calculated separately, based on the time
conditions also apply for the support, i.e. spent pumping out the water. The water
support type below the pipe roof. This means being used for drilling, washing, setting and
that rating areas shall apply, such as other works is not measured and not paid for.
"payment lines" 1a and 1b, which remain
unaltered. PriIn the case of excavation in an upward
direction, occasional control of overall water
It has to be pointed out that the increased that occurs at the tunnel face, which involves
consumption of support elements, due to the adequate drainage, redirection and removal
variable geometry of the primary tunnel lining of the water, is the obligation of the
(pipe inclination approx. 5.2°, used length of Contractor and thus is not measured and not
the pipe roof 10.0 m , which represents the paid for.
length of the saw tooth profile) is not taken
into consideration for determining the support Distractions and interruptions of downward
unit. Larger quantities are compensated by excavations, i.e. upward excavations,
unique prices. The contractor has to design resulting from the inflow of water, are
and calculate the variable geometry of the calculated as additional items if the water
shotcrete in respect of the execution method quantity exceeds 10 l/sec. This measurement
he uses. does not include the quantity of water used
for drilling, washing, setting and other works.
The increased quantities required for the The amount of inflow is determined
filling of the wedge below the pipe roof are (measured) 20 meters behind the excavation
not included in the matrix, since the filling of face.
the wedge is not performed in the immediate
progress area. This also applies in the The Contractor is responsible for the
situation where the contractor fills the wedge ventilation of the tunnel during the
20 m behind the excavation face due to construction phase. This ventilation is
working reasons. calculated separately, i.e. it may be included
in the time-dependent costs.
Increased quantities, as well as the shotcrete
required for the filling of the wedge below the
PE Roads of Serbia 27
Underground Works Serbian Road Construction Specifications
The Contractor is in charge of the lighting of Excavation of the tunnel for different support
the tunnel and the supply of electric energy types is paid as per unit price per cubic meter
during the construction phase. These costs (m3).
are calculated separately, i.e. they may be Difficulties due to water inflow that exceeds
included in the time-dependent costs. 10 l/s are paid per unit price per cubic metre
of excavated material for the entire duration
Primary support of the rock mass, which of the excessive inflow.
includes the cement shotcrete, reinforcement Temporary control of the inflow of water that
mesh, steel segments, anchors, protection of exceeds 5 l/s in downward excavations is
the excavation face by means of cement paid per unit price for one hour of pumping.
shotcrete and holders, is calculated The unit price for the temporary control of
separately (see chapter 7 of this water inflow has to include all the works,
specification). costs of equipment and materials (e.g. pipes,
chambers for pumping of water, etc.)
Transportation of the excavated material from required for the execution of works. Pumping
the tunnel portal or the temporary dump site equipment is calculated separately and may
next to the tunnel portal to the permanent be included in time-dependent costs.
dump site or embankment is measured by Interruptions of works lasting for more than 6
cubic metre of the initial rock mass hours, which occurred due to heavy inflow of
(fragmentation factor is not taken into water, overbreak or other unforeseen
consideration). circumstances, are paid per unit price for one
hour of interruption. Payment is made only in
The Contractor has to include in the price all cases when the workers and the equipment
potential interruptions that may occur due to in the tunnel cannot be redistributed to other
the coordination of works with other locations or works.
construction sites (e.g. due to traffic) and Interruptions of works lasting for more than 2
must not calculate them separately. hours, which occurred due to high
concentrations of gas which exceed the
Interruptions shorter than 2 hours caused by allowable concentrations, are paid per unit
the inflow of water, overbreak or other price for one hour of interruption. Payment is
unforeseen events are not calculated. made only in those cases when the workers
and the equipment in the tunnel cannot be
Interruptions shorter than 2 hours caused by redistributed to other locations or works.
high concentrations of explosive gases (e.g.
methane) are not calculated. The unit price for the excavation also
includes the excavations above the Line 2
(figure 2.8.2). Increase of the excavation
2.8.3.4 Payment profile (super section) due to permitted
construction tolerances Up (tc).
The unit price for the excavation works has to
include the costs for all works, equipment The unit price for excavation has to include
and materials required for excavation within all the works, costs of equipment and
the determined boundaries, the removal of materials required for the control and
the primary support (e.g. temporary invert reduction of the concentration of gases
arch, arch made of shotcrete, rock bolts), during the excavation phase, as well as the
required adjustment to the excavation pre-drilling required for early detection of
equipment, loading, transport and dumping of explosive gases (methane). The equipment is
the material excavated from the face to the calculated separately and may be included in
portal or embankment in front of the portal, the time-dependent costs.
i.e. to a temporary dump site located up to
300 m from the portal, temporary control of The offered unit price for the excavation has
water in upward excavations, difficulties to be independent of the method actually
caused by inflow of water up to 10 l/s, used for excavation (drilling and blasting
difficulties caused by geotechnical measuring methods or by means of mechanical
and geological mapping, interruptions due to devices).
the installation of the support elements and
development and adjustment of the drilling The unit price for the transportation of
programme used for blasting purposes, as excavated material to the embankment or the
well as all potential additional measured, dump located 300 m from the tunnel portal
interruptions and problems listed in the has to include all the works and equipment
previous chapter 2.8.3.3.: required for the loading, transportation and
28 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
unloading of material. The dump site has to for separately. Equipment is separately
be designed in such a way to allow for the calculated and may be included in the one-off
uninterrupted runoff of water. Loading and costs.
unloading of the material at the temporary
storage has to be included in the transport Final excavation for construction of the body
unit price. of the road has to be included in the unit
price for excavation and is not measured and
The unit price for excavation also has to paid for separately.
apply to the local widening of the profile for
temporary portals that need to be constructed The unit price for excavation has to include
in order to increase the thickness of the the interruptions caused by simultaneous
concrete lining in the cut & cover drafting of the geological-technical
constructions). documentation.
The unit price for excavation has to include The unit price for excavation has to include
all the works, costs of equipment and all the work on filling and backfilling
materials required for treatment and recharge (protection of the support in the invert arch
of all contaminated waters in the tunnel area, with minimal thickness of. 0.5 m).
before they are released, which is not paid
Figure 2.8.2: Calculation lines: excavation and support elements - layout prior to deformation
PE Roads of Serbia 29
Underground Works Serbian Road Construction Specifications
After deformation
Figure 2.8.3: Calculation lines: concrete and excess concrete - layout per deformations
2.8.4 CONTROL OF THE PROFILE AND mounted on each side of the tunnel and onto
PERMITTED DEVIATIONS which the tunnel lining is placed.
30 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
After the installation of the supports is The final examination of the free profile upon
finished and after the surface has been the completion of the re-profiling and surface
prepared as specified in this specification, as preparations, has to be performed in the
well as after a deformation, in accordance presence of the Supervising Engineer.
with the previous line in this article, the final
free profile for the inner lining has to be
adjusted to the minimum thickness of the 2.8.4.2 Permitted construction
inner lining, as shown in the drawings. deviations
Control of the profile has to be conducted by 2.8.4.2.1 Permitted deviations for the initial
constant utilisation of the profile vehicle lining
equipped with a pattern, or otherwise by
The reduction of the theoretical thickness of
applying modern geodetic techniques on at
the inner concrete lining is not allowed,
least every 2.0 m.
unless approved by the Engineer. In order to
meet this requirement, the support elements,
Any deviation from the theoretical free profile
such as shotcrete, anchor heads, steel ribs,
for the inner lining has to be adjusted by the
etc. must not penetrate the theoretical inner
application of an additional layer of shotcrete
concrete lining, as shown in the drawings.
or with the installation of thicker inner
concrete lining, if the free profile is too big, or
In the invert arch and foundation beam area,
by reshaping of the tunnel support sections
parts of rocks must not penetrate the
which penetrate into the free profile. The
theoretical excavation line.
Contractor is responsible for the execution of
these works without the right to additional 2.8.4.2.2 Permitted deviations from the
payment. excavation level of the invert arch
The Contractor has to present the If the tunnel is constructed without the
Supervising Engineer with suggestions for concrete invert arch, the Contractor has to
the execution of remedial works. excavate the lower invert arch level with the
accuracy of +0 to -100 mm, relative to the
No reshaping of the tunnel support is allowed theoretical excavation line of the invert arch.
unless approved by the Supervising
Engineer. If after the cleaning of the silt, loose material,
etc. the lower excavation level is more than
Geotechnical measuring prior to, during and 100 mm below the designed theoretical
after the implementation of adequate excavation line, the Contractor is obligated to
measures has to be performed in accordance
PE Roads of Serbia 31
Underground Works Serbian Road Construction Specifications
backfill these surfaces up to the designed, L, width of the free profile envelope B and
theoretical level using the material from the the radius R of the tunnel alignment. The
lower bearing layer or in accordance with the necessary "permitted deviation of curvature
instructions and approvals obtained from the C" may be calculated by means of the
Supervising Engineer. following formula:
√(
If the tunnel is being constructed with a
2.8.4.2.3 Permitted deviations of the inner Deviation of the inner surface of the concrete lining
concrete lining from the theoretical cross profile must not
exceed 100 mm (in the radial direction)
Permitted geodetic deviations towards the inner side. The inclination of the
walkway has a permitted deviation of the
The tunnel axis of the completed cross profile inner surface which is limited to 50 mm
may deviate from the calculated road centre towards the inner side, so as to maintain the
line (alignment) not more than 30 mm in the minimal dimensions of the cable duct.
direction. Permitted deviation for the
inclination is limited to 10 mm. Moreover, as is the same with any other permitted
deviation, the designed theoretical thickness
Permitted formwork deviations of the inner concrete lining has to be
maintained, as well as the appropriate free
Permitted formwork deviations, including the road cross-profile and walkway.
deviations referring to the construction of the
formwork, irregularities during the installation Other permitted deviations
and deformation of the formwork during
concrete works, must not exceed 60 mm inNiches and similar constructions have to be
the radial direction. constructed with a permitted deviation of
50 mm compared to the designed location.
Curvatures impact Permitted deviations for the sizes of the
niches are limited to 10 mm.
Having in mind that the tunnel formwork is straight, a
curved tunnel is actually polygonal in shape.
Prefabricated elements and cable ducts have to be
Therefore, deviation of the theoretical shape
constructed with a permitted deviation of
has to occur with the maximum at the centre
10 mm compared to the theoretical position.
of the concrete block. This permitted
deviation depends on the length of the block
32 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
PE Roads of Serbia 33
Underground Works Serbian Road Construction Specifications
valid safety regulations. Furthermore, the compared with the base shotcrete (without
capacity of the equipment has to be sufficient accelerating admixtures) at the age of 7 and
to meet the production requirements in terms 28 days must not exceed 10%, regardless of
of the construction programme. the actual strength.
The equipment has to be properly maintained Only wet mix shotcrete is allowed.
and spare parts have to be available so as to Regardless, however, a dry mix plant has to
ensure that the equipment required for be kept on site in the situation of the eventual
support installation is available at all times, failure of the wet plant, provided that it is
regardless of the location of the underground approved by the Supervising Engineer.
excavations.
2.8.5.2.2 Materials
The uninterrupted supply of materials to all
working areas that require support installation Cement
has to be ensured at all times. It should be
recognised that for excavations in poor Cement used for the preparation of shotcrete
quality rock this pre-requisite is mainly has to correspond to SRPS B.C1.011, 013,
related to the safety of the tunnel 014 Standards.
construction.
Cement used together with the additive for
For each tunnel heading, the Contractor is non-alkali acceleration of setting has to be
obligated to provide the material and Portland cement PC 450 and has to
equipment necessary for a quick and efficient correspond to the following requirements
response in emergency situations, such as which refer to compressive strength, all in
unexpected instability of the rock mass, accordance with the Austrian standard
heavy water inflow, etc., which cannot be ÖNORM B3327-1:
handled with the regular procedures of tunnel
support installation. Age at the day of Min. compressive
testing: strength:
The Contractor is obligated to keep onsite or
have immediately available at least a two- 9 N/mm2
week supply of any of the support elements Day
(5 % facture)
required according to the rock mass
classifications, as indicated in the drawings 40 N/mm2
and foreseen by the work programme. 28 days
(5 % facture)
34 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
Coarse aggregates must not contain large accordance with the requirements set forth in
quantities of long rocks. chapter 2.8.5.2.6. of this Specification. Any
addition to this dosage rate must not exceed
A quantity of fine aggregate with particle size 1% of the cement content in the weight of the
under 0.1 mm must not exceed 2% of the designed mix. The dosage rate may be
overall mixture. reduced in cases of downhand and horizontal
spraying positions. An automatic device has
Maximal aggregate size must not exceed 11 to be used for the adding of the setting
mm. accelerator mixture. The appropriate dosage
has to be determined through laboratory
Granulometric composition has to be testing.
between lines A11 and C11, preferably near
line B11, as shown in the drawing 2.8.4. Additives
The use of frozen aggregate is not allowed. With the consent of the Supervising
Minimum temperature of the aggregate is Engineer, additives for the improvement of
plus 5° C. characteristics, workability, etc. may be
added.
During rainy and cold periods, aggregate has
to be stored in a covered warehouse for at Additives which are to be used need to be
least 48 hours before usage, so as to reduce included in the testing described in chapter
the water content. 2.8.5.2.6 of these specifications.
Cement content
PE Roads of Serbia 35
Underground Works Serbian Road Construction Specifications
after application will indicate that the cement Measuring has to be done by weight. During
to water ratio is adequate. batching, all aggregates have to be dry or
sufficiently drained to have a stable moisture
Wet procedure:: content which must not exceed 7 %.
Onsite testing has to be carried out so as to
determine and establish a suitable water to Mixing of cement and aggregate has to be
cement ratio. performed mechanically with a mixer. The
use of shotcrete is not recommended if it
Binding and strength development cannot be placed within 90 minutes from the
time of mixing. The time span has to be as
Accelerating admixtures or special "cement- short as possible, especially during seasons
binders" have to be used so as to meet the characterised by high temperatures and high
requirements for the setting and strength humidity.
development of shotcrete applied onsite.
Mixing time must not be shorter than 3
In order to determine an adequate dosage minutes.
rate of acceleration admixtures, suitability
tests have to be carried out. A system of delivery notes has to be
introduced to be able to record the date and
The compressive strength of shotcrete onsite time of mixing, number of the design mix,
(taken from the tunnel lining or panels quantity, delivery point, time of delivery and
sprayed in the tunnel) has to develop the completion of application. Delivery notes
progressively to the final strength, in have to be available to the Supervising
accordance with the minimal requirements Engineer who has to approve them.
set forth in the text below. Uniaxial
comprehensive tests have to be carried out in For the dry procedure, liquid or powdered
accordance with the provisions set forth in setting accelerator is added to the dry
chapter2.8.5.2.6. mixture. The powdered accelerator shall be
proportioned and added through a
Strength development, due to suitability mechanical device (dispenser) just before the
testing, has to exceed the specified onsite dry mix enters the shotcrete machine. Liquid
strength by a factor of 1/0,85 (=1,18). accelerator is introduced by means of a
special dosing pump and is added to the dry
The strength of 28 day old shotcrete has to mixture at or near the nozzle. The dosing
be at least 25 N/mm². Shotcrete strength pump and the hoses of the nozzle have to be
development has to meet the following in functional condition at all times.
requirements:
- 0,1 – 0,2 MPa after 2 minutes (not During period of cold weather, the setting
more than 0,2 MPa) properties of shotcrete have to be maintained
- 0,2 – 0,5 MPa after 6 minutes by heating of the water or aggregate or both,
- approx1,0 MPa after 1 hour depending on the temperature. Relevant
- approx2,0 MPa after 2 hour standards have to be applied.
- 2,0 – 5,0 MPa after 6 hours.
During periods of hot weather, the water
- When it comes to tunnelling under content of the aggregates used in the dry
buildings or shallow cover, the strength procedure has to be above 4% so as to avoid
development of young shotcrete has to cement loss at the rotor of the shotcrete
reach 12 N/mm² after 24 hours. machine.
Truck mixers which are to be used for the See also Section - Work with cement
transportation of shotcrete into the tunnel concrete - SPECIAL TECHNICAL
have to be equipped with approved exhaust CONDITIONS.
filters.
Only liquid types of setting accelerators are
Dry procedure for the preparation of used for the wet procedure for the
shotcrete preparation of shotcrete; these mixtures are
added at or near the nozzle. The output of
Cement and aggregates have to be batched the accelerator pump must be controlled and
in the specified and designed proportions.
36 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
has to be proportional to the output of the the proper rounding of notches and corners.
concrete pump. The nozzle has to enable the At projections of sound rock, the actual
preparation of a homogeneous mixture of wet shotcrete thickness may be locally reduced to
mix with the additives for the acceleration of two thirds of the specified thickness. This
setting. applies only to behaviour type BT 1 (See
Serbian Road Design Manual 11.2 Earth
Special cement binder Works, Table 11.2.4: Categories of Rock
Mass Behaviour Types).
Basically, there are two ways to apply
shotcrete with a special cement binder: Waste shotcrete has to be removed
- using dry aggregates with water content immediately after finishing the application of
less than 0.8%; aggregates may be mixed the shotcrete. Waste shotcrete has to be
with cement binder immediately prior to removed in particular at the horizontal
application. shotcrete connections due to separate
excavation sequences and at all cold joints, if
- Using wet aggregates with water content necessary, using pneumatic hammers, prior
less than 4 %; aggregates and cement to the application of shotcrete.
binder have to be mixed immediately prior
to application. Under no circumstances can waste shotcrete
be reused. Waste shotcrete has to be
2.8.5.2.5 Applying shotcrete regularly removed from the construction.
The maximum thickness of shotcrete applied In order to avoid excess shotcrete load on
at once must not exceed 15 cm. If it is the lining, especially in heavy squeezing
necessary to increase the thickness, rock, deformation slots have to be placed in
additional layer/layers must not be applied the shotcrete lining. Generally, the slots have
until the previous layer develops sufficient to have an opening width of 20 to 40 cm and
strength to support the additional layers. The have to be boarded radially. The actual
application of additional layers has to be position of the slot depends on the
completed over the course of three days. geotechnical conditions.
Steel ribs, roof ties, reinforcement mesh and 2.8.5.2.6 Shotcrete testing
other types of reinforcement have to be
embedded into shotcrete as shown in the Suitability tests and the quality control of
drawings. On the inner side of the tunnel shotcrete have to be performed in
lining, reinforcement mesh and reinforcing accordance with Austrian "Sprayed Concrete
bars have to be covered with at least 2 cm of Guideline", unless otherwise prescribed in
shotcrete or as shown in the drawings. this section.
If more than one layer of reinforcement is The type and number of suitability tests for
being used, the second layer must not be mix design are listed in table 2.8.6.
placed before the first layer is placed and
covered with shotcrete. The type, number and frequency of tests
necessary for quality control during
If shotcrete is applied to a sound rock, construction are listed in table 2.8.7.
shotcrete has to follow the rock surface with
PE Roads of Serbia 37
Underground Works Serbian Road Construction Specifications
Suitability tests
Bolt screws are shot into the concrete and
The compatibility of the cement and the the depth of penetration is determined. Then
mixtures for the acceleration of setting have the bolt screws are removed and the pull-out
to be tested in the laboratory with the force is measured. The ratio of the pull-out
checking of setting times and whether the force to the penetration depth is the
addition of the accelerator leads to excessive parameter used for determining the
reduction in the long term compressive compressive strength. A HILTI DX 450 L bolt-
strength of the shotcrete. setting unit with green cartridges is used to
drive the bolt screws into the concrete. The
On site tests have to be performed so as to pull-out force is determined by means of a
determine setting and strength development, pull-out device (for example, HILTI Tester 4).
as well as to determine the required dosage Testing has to be carried out in accordance
of additives used for accelerating the of with the Austrian "Sprayed Concrete
setting of shotcrete. Guideline”.
For each type of setting accelerator that has Measuring range 16 to 56 MPa
previously been determined as being suitable
through laboratory testing, a trial mixture has HILTI bolt screws, type M6-8-52 D12 (overall
to be applied on the test panels (3 pieces length 60 mm) are shot into the concrete and
500x500x200 mm per trail mixture). These the depth of penetration is determined. Then
mixtures have to be cured under site the bolt screws are removed and the pull-out
conditions and have to be subjected to tests. force is measured. The ratio of the pull-out
At least three different dosages of each type force to the penetration depth is the
of setting accelerators have to be tested as parameter used for determining the
described. The range of accelerator dosages compressive strength. A HILTI DX 450 L bolt-
has to vary between 2% and 7% of the setting unit, set to position 2, with yellow
cement weight. cartridges is used to drive the bolt screws
into the concrete. The pull-out force is
The ambient temperature during the test has determined by means of a pull-out device (for
to correspond to actual conditions in the example, HILTI or ETIRIP). Testing has to be
tunnel. carried out in accordance with the Austrian
"Sprayed Concrete Guideline“.
38 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
mm and height of 120 mm, at the age of 28 - submit proposals for the approval of
days. the Supervising Engineer before
the remedial works commence.
2.8.5.2.7 Quality control
If the required 28-day-strength of the
To ensure the required quality of shotcrete shotcrete is not achieved, the Supervising
during construction, it is necessary to test the Engineer may require that the theoretical
aggregate gradation, cement, additives (for thickness of the shotcrete ds is increased by
example, fly ash), additives for acceleration the value d1, calculated using the following
of setting, strength development of "young" formula:
shotcrete and shotcrete strength at 7 and 28
[ ]
days, as shown in table 2.8.7.
F
d 1= −1 d s
Compressive strength failures M
This chapter presents a list of all the actions F – required 28-day-strength in N/mm²
which need to be undertaken in situations M – actual measured strength of the
where the strength requirements specified in shotcrete lining in N/mm²
chapter 2.8.5. of this specification are not d1 – additional thickness of shotcrete to be
met. sprayed, in cm
ds – theoretical thickness of shotcrete lining in
Failure of pull-out test at 24 hours, or cores cm
on 3 day tests:
- notify the Supervising Engineer, In some cases, the Supervising Engineer
- immediate examination of the tunnel may require for the failed shotcrete to be
lining in the area in question, removed and the rock support to be re-
- immediate examination of the installed in accordance with the specified
elements used for the making, type of rock mass.
transport and application of shotcrete,
- organise constant supervision, It should be noted that the Supervising
- prepare for further tests that have to Engineer may require additional
last for three days, strengthening measures to be taken at any
- take new test panels as soon as time after the failure of the 3 day cores.
possible and conduct a penetrometer
test, pull-out test and compression test Failure of the compressive strength as
in core samples as specified above. described above is the responsibility of the
Contractor. The required strengthening or
Failure of cores on 7 day tests: reinforcement of the installed rock support
- notify the Supervising Engineer and due to failed quality control tests will not be
the Designer, measured for payment.
- install a measurement section,
- organize monitoring in accordance with
the specification (section 10 of this 2.8.5.3 Micro-reinforced shotcrete
specification), reinforced with steel or polymer
- should the results of the monitoring fibres
indicate instability of a certain section,
additional rock support has to be General
installed,
- if the interpretation of deformation
measurements is such that additional
support is not required, further tests
shall be carried out at 28 days. Steel or polymer fibres may be used for the
production of fibre reinforced shotcrete. The
Failure of cores on 28 day tests: resistance and the flexural strength of
- notify the Supervising Engineer and shotcrete are increased after fibres are
the Designer, added into the shotcrete, compared to the
- take the cores from the tunnel lining, properties of the shotcrete that has not been
- determine the area in question reinforced with fibres.
- test the cores and if failure occurs:
- prepare a proposal for the
strengthening of a certain area, in
cooperation with the Designer,
PE Roads of Serbia 39
Underground Works Serbian Road Construction Specifications
Material
Application
40 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
Installation
Flexural strength being tested after 7 days
must not be less than 5MPa. In accordance
with SRPS EN 14488-3 three bending tests
have to be carried out on the shotcrete Reinforcement mesh has to be installed so
samples (beams) with the dimensions of 100 that it follows as closely as possible the
mm x 100 mm x 400 mm, with the span of irregularities of the excavation surface or the
300 mm or 150 mm x 150 mm x 600 mm with previous layers of shotcrete. It has to be
the span of 450 mm, with the load positioned firmly fixed to prevent vibration and change of
on three locations. The load points have to position during the spraying of the shotcrete.
be 100 i.e. 150 mm apart. Testing by means Reinforcement mesh has to be installed in
of artificially caused deformations has to be the longest practical length. The overlap of
carried out by the bending of the samples reinforcement mesh installed into the
(bending rate 0.1 mm/min), where the ratio shotcrete lining has to be at least twice the
load/bending has to be simultaneously pitch distance in circumferential and one
recorded. For this purpose, it is more pitch distance in longitudinal direction.
appropriate to use lateral fixing at the sample
axis. Test samples are subjected to a load
until the bending of the beam reaches 1/150
of the span (2mm or 3 mm). The first crack
on the beam with 300 mm span may occur
The installation of the reinforcement mesh
only after deflection of 0.03 mm to 0.05 mm.
has to be such to ensure concrete coverage
with the minimal thickness of 3.0 cm.
Material Material
Installation
Depending on the approval of the Reinforcing steel bars have to be securely
Supervising Engineer, the reinforcement attached to the previously applied shotcrete
layer or the reinforcement mesh.
PE Roads of Serbia 41
Underground Works Serbian Road Construction Specifications
42 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
quality of the weld. Slag has to be removed visible slag permitted to a limited
after every welding session. The most remains extent, but not continuous
favourable welding position has to be chosen
for each individual case. minor depressions
craters
permitted
Manual flame cutting is used for the cutting of
steel profiles. Sawing is also permitted. permitted, but not on large
lack of fusion
areas and not continuously
Further preparation of joints and welds has to
be done by grinding. individual minor local
cracks
cracks permitted
Parts to be welded have to be placed so that
excessive
the joints are easily accessible and visible to
asymmetry of side ratio < 1:0.6.
the operator. welds
PE Roads of Serbia 43
Underground Works Serbian Road Construction Specifications
the works and for the prevention of Supporting holders have to be done as
overbreak, which is always connected to the shown in the designs or as instructed by the
erection of steel ribs. The length of steel Supervising Engineer.
pipes or rods has to be at least 1 m longer
than the anticipated length of the excavation Mortar has to be filled into the predrilled
round. holes from the bottom to the top.
2.8.5.6.1 Injected holder pipes Dowels have to be inserted into the predrilled
holes from the face of the drive towards the
Material unexcavated ground.
Installation
44 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
The rock bolts have to be installed according One end of the rod has to be fitted with a
to the lengths and rock bolt patterns shown in suitable nut which is to receive an anchor
the drawings for each relevant standard rock bolt plate and a fixing nut.
support system, unless otherwise determined
by the representatives of the Contractor and As a safety measure, all types of rock bolts
the Supervising Engineer based on the have to be used with rock bolt plates, size
classification of the existing rock mass. 150 x 150 mm and thickness of 8 mm, unless
otherwise instructed by the DESIGNER and
Definitions approved by the Supervising Engineer. The
shape of the rock bolt has to allow a uniform
SN-bolts are made of ribbed steel bar. They seat, even if the bolt is not installed exactly
are bonded to the surrounding rock by means perpendicular to the surface below.
of mortar. The hole is filled with cement
mortar before the insertion of the bolt. The Washers and nuts have to enable a secure
abbreviation SN derives from the mine "Store transfer of the anchor force to the anchor
Norfors" where these bolts were first applied. plate.
SN- bolts and PG-bolts Anchor plates are used for the transfer of
anchor force over the head of the rock bolt to
Bolts shall have a minimum diameter of 28 the shotcrete, steel rib or rock surface.
mm for steel grade RA 400/500; B 500 A.
PE Roads of Serbia 45
Underground Works Serbian Road Construction Specifications
The equipment recommended by the be installed within 3 hours after the drilling
manufacturer of the rock bolts has to be used and the preparation of the borehole.
for injecting water into the rock bolts.
Prior to the installation of the rock bolt, the
Joints for bolts entire borehole has to be filled with cement
mortar. Filling is performed by inserting a
Joints have to be made of the same material grout hose to the full depth of the hole and
as the rock bolts or of even higher quality withdrawing the hose while the grout is
material. The joint diameter has to enable pumped in.
grouting of the whole bolt length from the
deepest point of the drill hole. The nozzle has to be kept buried in the grout
while the hose is being drawn out so that air
is displaced as the hole fills with grout. The
bolt is then pushed into the hole.
46 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
PE Roads of Serbia 47
Underground Works Serbian Road Construction Specifications
Fp
700 tolF
The Contractor is obligated to keep records
600
on the details of bolt installation during
driving, including that of cement mortar 500
400
48 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
or more shorter units (L2) which are activated Special attention must be paid to the proper
due to certain deformations. In this case, the placement of the elements on the lining. The
bearing capacity of the element is gradually functionality of the lining must not be affected
increased. by the assembly, transport and installation.
Execution
PE Roads of Serbia 49
Underground Works Serbian Road Construction Specifications
Spacing between the steel pipes in the crown The injection mass has to consist of Portland
of the excavation profile must comply with the cement, water and admixtures, if required.
distance specified in the drawings, but must The cement must not contain (by weight)
be adjusted to the prevailing geological more than 0.02% of chlorides or 0.10 % of
conditions of the tunnel face. sulphides. The admixtures must not damage
the properties of the bars or the injection
After drilling, steel pipes have to be cleaned mass. The water to cement ratio must be
by means of compressed air, prior to low kept as low as possible. It must not exceed
pressure grouting. 0.45. After 3 hours after mixing, the permitted
bleeding of the injection mass must not
exceed 0.5 % of the volume or not more than
2.8.5.10 Geotechnical bar anchor 1 % when measured at 20 C in a covered
glass or metal cylinder 100 mm in diameter
General
and with a injection mass t depth of
approximately 100 mm.
This part of the specification applies to the
supply and installation of prestressed bar
At prestressing, the compressive strength of
anchors required for, and used as additional
the injection mass must be at least 20
support.
N/mm².
All works have to be carried out in
Protective pipes
accordance with SIA 191 (1996) standard.
The free length of the bars has to be encased
in a smooth HDPE pipe. The HDPE pipe has
to be homogeneous and free of voids. The
use of recycled material is not allowed. The
pipe wall has to be at least 3 mm thick.
Anchor head
Figure 2.8.7: Bar anchors
The strength of the anchor head has to be at
least equal to the strength of the bars.
Materials
System requirements
Anchors must not contain materials that are
mutually incompatible or incompatible with Protection against corrosion
the surrounding environment.
The anchor system has to be protected
Prestressed bars against corrosion in accordance with SIA 191
(1996).
Prestressed anchors consist of prestressed
steel bars in accordance with ÖNORM B Protection against corrosion includes all the
4258. The distance between the bars and necessary parts, such as: the anchor head,
plastic pipes has to be sufficient to enable packer, free anchor length and bond length of
faultless embedding in the cement or mortar the bar and the distant end of the anchor.
50 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
PE Roads of Serbia 51
Underground Works Serbian Road Construction Specifications
Injecting of the free anchor length has to be Anchors must not contain materials that are
done after the prestressing of the anchor. mutually incompatible or incompatible with
the surrounding environment.
Procedures for the testing of anchors
Prestressing tendons
Anchor testing procedures have to be
performed in accordance with SIA 191 (1996) Prestressing tendons have to consist of
standards. prestressing steel strands (bars) in
accordance with prEN 10138-3. The distance
Suitability tests between individual wires has to be sufficient
to enable faultless embedding in cement or
Suitability tests are carried out on anchors mortar or in the permanent plastic corrosion
constructed under the same conditions protection material. The wires have to be
applied to the working anchors. These tests made of steel with high tensile strength.
indicate the results which may be obtained by
the subsequent testing of working anchors, The mechanical properties and technical
i.e. by conducting a routine acceptance test. characteristics have to comply with the
Considerable and significant changes to the standard prEN 10138-3, as follows:
conditions of the working anchors e.g. - seven-wire strand, tensile strength
geological conditions, require the suitability 1570/1770,
tests to be conducted. - nominal wire diameter 15.2 and 16,0
mm.
In the course of the anchor acceptance test, Injection mass has to consist of Portland
each anchor has to be stressed up to the cement, water and admixtures, if required.
relevant test load. In cohesive soils, the The cement must not contain (by weight)
creep values also have to be determined. more than 0.02% of chlorides or 0.10 % of
sulphides. The admixtures must not damage
Testing programme: the properties of the bars or the injection
mass . The water to cement ratio must be
A cyclic loading and unloading procedure has kept as low as possible. It must not exceed
to be carried out so that the initial load is 0.45. After 3 hours after mixing, the permitted
increased in each successive round for each bleeding of the injection mass must not
load step, until a specified maximum load is exceed 0.5 % of the volume or not more than
reached. At each increase of the load, the 1 % when measured at 20 C in a covered
displacement of the bars at the anchor head glass or metal cylinder 100 mm in diameter
relative to a fixed point in the environment and with a injection mass depth of
has to be observed, under a constant load approximately 100 mm.
corresponding to the set schedule.
At prestressing, the compressive strength of
the injection mass must be at least 20
2.8.5.11 Cable anchors N/mm².
General
Protective pipes
This part of Section 3 applies to the supply
The free length of the bars has to be encased
and installation of prestressed cable anchors
in a smooth HDPE pipe. The HDPE pipe has
required for and used as additional support
to be homogeneous and free of voids. The
for the bored piles in the open cut sections.
use of recycled material is not allowed. The
pipe wall has to be at least 3 mm thick.
All works have to be carried out in
accordance with SIA 191 (1996) standard.
The bond length of the bars has to be
encased in a corrugated pipe with a minimum
wall thickness of 1 mm
Materials
Anchor head
General
The strength of the anchor head has to be at
least equal to the strength of the bars.
52 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
PE Roads of Serbia 53
Underground Works Serbian Road Construction Specifications
54 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
PE Roads of Serbia 55
Underground Works Serbian Road Construction Specifications
56 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
Notes:
1) The requirements and specifications for suitability tests for shotcrete refer to the application in
the tunnels and on the slopes
2) Suitability tests have to be carried out by an authorised laboratory
Test items Properties Testing method sample Age at Test Frequency Test
testing of sampling type
location and testing
PE Roads of Serbia 57
Underground Works Serbian Road Construction Specifications
Test items Properties Testing method sample Age at Test Frequency Test
testing of sampling type
location and testing
58 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
For drainage purposes, SPECIAL “Grouting of layers“: This term refers to the
TECHNICAL CONDITIONS apply, unless pressurised injection of material into the
otherwise prescribed by this section. layers of rock so as to consolidate cracked
rocks or to fill the openings and cavities in the
2.8.6.1.1 General rocks surrounding the tunnel. Grouting of
layers does not include injections for loose
In accordance with the "Geological and soil.
geotechnical report", in tunnel sections the
Contractor is obligated to probe ahead of the "Consolidation grouting": This term refers to
face with a length of 20 to 30 m pre-drilling so the grouting of loose material by means of
as to prove or investigate the ground ahead, bentonite, cementitious or chemical grouting.
as well as to check whether gas and water
sources are present. Probe testing has to be
repeated and overlapped so that probe 2.8.6.2.2 Documentation
testing is always at least 10 m ahead of the
tunnel face. The Contractor is obligated to prepare a
detailed grouting specification, since the
The number of probe tests, their position and grouting work is diverse and there is a wide
angles are determined based on the type of range of methods and techniques that may
ground and the testing data available. Radial be used for improving the ground to match
probe testing may also be necessary. the actual conditions. The grouting
specifications have to be submitted to the
At locations where excessive ground water Supervising Engineer for approval, unless
flow is expected or present, pre-drilling ahead otherwise agreed with or instructed by the
of the tunnel face is proposed so as to Supervising Engineer.
reduce the hydrostatic pressure at the tunnel
face. The Contractor is obliged to provide the
Supervising Engineer with the details of the
2.8.6.1.2 Documentation proposed grouting procedures, including the
details of grouting equipment, location, depth
All details related to probe testing have to be and orientation of the grout holes, grout
determined and confirmed by the Supervising methods, grout composition, grouting
Engineer. pressures and time scaled programme for
each sequence of the grouting operation. The
If unexpected conditions appear during the depth and means of grouting have to be such
excavation of the tunnel, such as to allow for the holes to be positioned exactly
underground water, the suspicious colour or along the zones that need to be grouted.
smell of water, floor heave, voids or gas,
careful observation and recording of the 2.8.6.2.3 Necessity of ground treatment
condition ahead of the tunnel face is drilling
obligatory. The Supervising Engineer has to
be fully informed. After the consultations of the Supervising
Engineer and the Contractor, the necessity
2.8.6.1.3 Execution for ground treatment, in addition to the
ground treatment indicated in the drawings,
The Contractor shall be held responsible for shall be based on soil investigations, probe
the validity of the data obtained by pre- testing, the amount of water at the face, or
drilling, especially from the perspective of any other indications that the ground which is
additional costs which may occur due to to be excavated is soft, fissured or heavily
incorrect and inadequate data obtained by water laden, as well as on the data contained
pre-drilling. in the contract.
PE Roads of Serbia 59
Underground Works Serbian Road Construction Specifications
2.8.6.2.4 Grout bore holes and ground After the grouting is finished, the grouted
treatment drilling area has to be tested by a procedure agreed
upon with the Supervising Engineer.
Grout holes for primary and secondary
grouting have to be drilled at a certain 2.8.6.4.2 Drilling
distance and according to the sequence in
the area that needs to be grouted and which Grout holes have to be drilled either with
requires injection mass to be injected under percussion type or rotary type drilling
pressure, all in accordance with the approval equipment.
of the Supervising Engineer. Gauges have to
be installed adjacent to the point of injection The diameter of the bottom of the grouting
and have to be used for measuring the hole must not be less than 35 mm. If drilling
pressure of the grout. The design pressure of is performed with percussion type drilling
the grouting proposed by the Contractor and equipment, the diameter of the drilling bit
approved by the Supervisor must not be must be at least 8 mm larger than the
exceeded without the previous consent of the diameter of the joints used for the drill rods.
Supervising Engineer.
Unless otherwise ordered by the Supervising
Engineer, only dry drilling may be performed.
2.8.6.3 Material All drill holes have to be thoroughly cleaned
immediately after drilling, by means of
The grout may consist of the following: compressed air. After cleaning, downward
- chemical grout, holes have to be kept closed until the
- cement mortar grout (cement/sand), commencement of the grouting operation.
- cement grout made of clay or
bentonite. 2.8.6.4.3 Mixing of grout
Ordinary Portland cement is used. All grout mixes have to be prepared in high
speed, high shearing action mixers so as to
The sand being used for grouting has to be produce a grout of uniform homogeneous
pure, mineral sand, of uniform quality and consistency.
has to originate from an approved source.
If the mixed grout is stored prior to pumping
Water has to be clean, without traces of oil, for a short period of time, it has to be stored
acid, base, organic or any other harmful in an agitation tank made for that purpose.
substances.
If clay or bentonite additives are used,
The use of additives for improving the special agitation tanks need to be provided
performance of the grouting is permitted. for the preparation and mixing procedure.
60 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
PE Roads of Serbia 61
Underground Works Serbian Road Construction Specifications
62 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
PE Roads of Serbia 63
Underground Works Serbian Road Construction Specifications
64 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
Auxiliary materials
Surfaces to be fitted with waterproofing have
Fixing materials, reinforcement for expansion to be cleaned, smooth and free of all waste
joints, sealing flanges are produced and materials.
corners and intersections are prepared in
accordance with the instructions obtained Prior to waterproofing, the following treatment
from the manufacturer of the membrane. of surfaces has to be performed:
- For the fixing of the protective felt and
2.8.7.1.3 Execution the waterproofing membrane, a
minimum layer of 3 - 5 cm of shotcrete
Preparation of the surface has to be applied onto the rock.
PE Roads of Serbia 65
Underground Works Serbian Road Construction Specifications
Prior to the application of waterproofing, all Special attention needs to be paid to ensure
surfaces that need to be waterproofed have that the waterproofing membrane is not
to be inspected and approved by the damaged during and after installation. All
Supervising Engineer. damage that occurs need to be repaired and
examined before the final concrete lining is
The application has to be performed in applied.
accordance with the written instructions of
the manufacturer. Essentially, the procedure 2.8.7.1.4 Quality control of execution
is as follows:
Testing of seams
Preparation
Special preparations are required for the All seams have to be tested, while the
application of waterproofing at the Contractor is obligated to keep a record on
transitions and intersections of the tunnel the testing performed and to deliver the
face, as well as for projections passing records to the Supervising Engineer.
through the membrane. These
preparations have to be carried out in Testing of seams using compressed air
accordance with the manufacturer's
recommendations. The tightness of the seams between the
adjacent sheets of waterproofing membrane
- Fixing of felt must be tested. This test has to be performed
Protective felt has to be attached to the by pumping compressed air into the test
shotcrete surface using suitable fixings channel created from a double welded joint.
specified by the manufacturer. Depending The initial pressure test has to be 2 bars
on the location, from 2 to 4 fixing during a trial period of 5 minutes or 1.5 bars
elements have to be used per square during a trial period of 10 minutes. Seams
metre. Felt has to be loosely fixed so as to are deemed waterproof if the loss of air
avoid overstressing during casting. pressure does not exceed 20 % in both
Adjacent sections of felt need to overlap cases.
by approximately 10 cm and be joined by
point welding or a similarly adequate Testing of seams using vacuum equipment
procedure. Along the bottom of the tunnel
side walls, the felt has to be long enough Vacuum equipment may be used for the
testing of a membrane area of a limited size,
such as special configurations of joints or
66 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
local repairs with patches. Such equipment The porous concrete has to consist of
consists of a vacuum bell which is emptied by ordinary Portland cement and natural
pumping after being firmly placed above the aggregate with a grain size of 32 mm. The
testing area so as to detect cavities in the ratio of aggregate to cement has to be 8:1 by
membrane. volume or 10:1 by mass.
PE Roads of Serbia 67
Underground Works Serbian Road Construction Specifications
68 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
PE Roads of Serbia 69
Underground Works Serbian Road Construction Specifications
2.8.8 CASTING AND REINFORCEMENT between the in-situ concrete lining and the
shotcrete or the membrane lining
(waterproofing membrane). The contact
2.8.8.1 General injecting has to be carried out systematically
in the roof section of the tunnel after the
This section contains specifications for the concrete lining hardens. Provisions for the
construction of the final tunnel lining, the fixing of the pipes for contact grouting have to
foundation beams, the concrete invert arch be anticipated in the roof arch formwork. The
and prefabricated concrete components, as position of the injection holes has to be
well as for the concrete works on the opened approved by the Supervising Engineer.
excavation with the afterwards tunnel tube
covering (cut-and-cover), for the concrete The coating of the concrete surface of the
arch and support structures. The structures inner lining is required so as to protect the
of the excavated tunnel are predominantly concrete and allow for easier cleaning.
not reinforced, but they may also be
reinforced locally, as designed and approved A reinforced concrete arch built in-situ forms
by the Supervising Engineer, while the the roof of the mixed tunnel/cut-and-cover
sections of the cut-and-cover tunnel sections, method. The concrete arch transfers the
the concrete arch and supporting structures forces created by the backfill, into the lateral
are generally reinforced. load bearing rock mass. After the concrete
arch is protected, the tunnel may be
2.8.8.1.1 Description
constructed using the conventional methods.
Section SPECIAL TECHNICAL
2.8.8.1.2 Documentation that needs to be
CONDITIONS, unless otherwise prescribed
delivered
in this section.
Working drawings have to be submitted
The final tunnel lining, a concrete lining which depict the camber of formwork
installed onsite, increases the overall safety required as compensation for the deflection
factor of the tunnel lining system, provides a caused by the application of concrete.
uniform interior surface and improves the
water tightness of the tunnel lining. A smooth The Contractor is obliged to provide the
internal surface is required to facilitate Supervising Engineer with detailed workshop
airflow, for aesthetic reasons and for drawings of the formwork.
maintenance and lighting reasons.
The Contractor shall be obligated to submit
The foundation beams form the abutments for the approval of the Supervising Engineer
for the final tunnel lining. Cable ducts are the following: separate workshop drawings
mainly placed on longitudinal concrete for the formwork of the tunnel cross profile,
beams. pedestrian cross passage, niches, concrete
arch and cut-and-cover.
The invert arch forms the rounded end of the
tunnel lining (tunnel pipe) where poor Reports on the testing of concrete which is to
geological conditions prevail. be used have to be delivered in accordance
with the section of the SPECIAL TECHNICAL
The formwork for the foundation beams, CONDITIONS.
invert arch and roof arch are necessary tools
for the construction of the final tunnel lining. The Contractor shall be obligated to provide
The formwork has to be designed and made the Supervising Engineer with a list of
of steel in such a manner that the shape, references of the manufacturers prior to the
dimensions and surface finish of the concrete production of the prefabricated concrete
are achieved, as specified. elements.
Prefabricated concrete elements form the The Contractor is obliged to provide the
lateral boundaries of the road surface (kerbs) Supervising Engineer with the methodology,
and are also used in the construction of cable as well as the description of facilities and
duct slabs. materials for contact injecting, prior to the
commencement of works on the inner
Contact injecting represents the injection of concrete lining.
material under pressure so as to fill the voids
70 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
The Contractor is obliged to provide the vibrators for the compacting of concrete, to
Supervising Engineer with the test results permit the inspection of concrete during
and the samples of the material for the placement and the inspection of the
coating of the concrete surfaces. hardened concrete surface, prior to discharge
or removal of the formwork. The size of the
2.8.8.1.3 Conditions for the execution of opening has to be at least 600 square mm.
works Openings intended for the pouring of
concrete have to be provisioned at such
The inner concrete lining in the tunnel must heights that prevent the segregation of the
not be applied until the rate of displacement concrete. Joints in the forms have to be
at any position on the tunnel periphery and sufficiently tight to prevent the leakage of
perpendicular to the periphery is less than 4 grout and water from the concrete.
mm per month, unless otherwise ordered by
the Supervising Engineer. The forms have to be kept in good condition
so that the accuracy of shape, strength,
The inner concrete lining must not be placed rigidity, water tightness and smoothness of
before the Supervising Engineer accepts and the surface are guaranteed at all times. The
consents to the re-profiling results. forms have to be clean, corrosion-free and in
good condition.
The inner concrete lining in the tunnel must
not be placed until the installed waterproofing The upper sector of the lining formwork has
system has been accepted by the to be provisioned with elements for the
Supervising Engineer. mounting of external vibrators at regular
intervals, so as to provide uniform
The installation of the prefabricated concrete compaction of the arched soffit.
components cannot commence prior to
obtaining consent from the Supervising The steel form must be equipped with
Engineer. suitable elements which allow for the
construction of the groove on the outside rim
The concrete surface cannot be coated until of the secondary lining segment. This results
the Supervising Engineer approves the in a uniform appearance of the secondary
surface of the inner concrete lining. lining and of the area where the tunnel is on
a curve.
2.8.8.2 Material 2.8.8.2.2 Concrete
Materials have to comply with the Section SPECIAL TECHNICAL
requirements set forth in SPECIAL CONDITIONS, unless otherwise prescribed
TECHNICAL CONDITIONS, unless in this section.
otherwise prescribed in this section.
The concrete grade for the tunnel lining,
2.8.8.2.1 Formwork
foundation, invert arch, concrete arch and
Refer to - section SPECIAL TECHNICAL cut-and-cover works has to be at the
CONDITIONS. minimum C 25/30.
The shape of the concrete arch has to be The maximum aggregate size has to comply
modelled with a steel formwork. with those set forth in SPECIAL TECHNICAL
CONDITIONS.
The formwork has to be rigid enough to
maintain the forms in the correct positions, The strength of the mixture has to be such to
shape and profile, so that the final concrete allow the placement of the concrete by
construction is within the limit of tolerances. pumping.
The formwork for the tunnel lining has to be Plasticizers may be used in the concrete mix
made of steel and has to be adequate for to improve flow and compaction. Detailed
subsequent re-use. data regarding such additives have to be
delivered to the Supervising Engineer for
The formwork for the tunnel lining has to approval prior to their application.
have openings along each side wall and at
the crown. The openings have to be
designed in such a way to permit the use of
PE Roads of Serbia 71
Underground Works Serbian Road Construction Specifications
Cement has to comply with current The adhesion value being tested by cutting a
standards. The grout has to be a uniform grid of 5 mm x 5 mm (in accordance with
mixture of adequate fluid consistency to RSV 8.29.4) has to be at least 85 %.
ensure that the pressurised grout can flow
into all sections of cavities.
2.8.8.3 Casting
The grout mix has to have low or no
bleedability and low shrinkage properties. Casting has to be performed in accordance
The grout mix has to have the lowest with the provisions set forth in SPECIAL
possible permeability after it sets. TECHNICAL CONDITIONS, unless
otherwise prescribed in this section.
2.8.8.2.5 Reinforcement
2.8.8.3.1 Preparation of formwork prior to
For the inner concrete lining, steel concrete works
reinforcement is necessary in heavily
stressed areas, such as cut-and-cover tunnel SPECIAL TECHNICAL CONDITIONS, unless
sections, sections under houses and shallow otherwise prescribed in this section.
cover, portal areas, niches, junctions of
tunnels and pedestrian cross passages, The internal surface of the formwork has to
depending on the local ground conditions and be coated with approved oil that does not
as shown in the design drawings. leave stains, in order to prevent the adhesion
Furthermore, the inner concrete lining may of concrete.
be reinforced in areas of heavy installations
inside the tunnel, for example where Release agents have to be applied strictly in
ventilation fans are fixed. accordance with the manufacturer's
instructions and must not come in contact
Reinforcement is required for the concrete with the reinforcement.
arch, as well as for the prefabricated
concrete elements. The composition of the release agent has to
be such that it does not interfere with future
Materials for reinforcement mesh surface treatments.
72 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
PE Roads of Serbia 73
Underground Works Serbian Road Construction Specifications
2.8.8.3.5 Removal of formwork The sealing agent must not interfere with the
bonding of any subsequent surface
Section SPECIAL TECHNICAL treatment.
CONDITIONS, unless otherwise prescribed
in this section. Curing may be omitted if measurements
show that the curing process is no longer
The Supervising Engineer has to be informed affecting the moisture and shrinkage of the
in advance regarding the date the Contractor concrete.
intends to remove the formwork.
The Contractor is responsible for avoiding or
The Contractor shall be responsible for the minimising the occurrence of cracks due to
time in which the formwork is removed. shrinking and thus has to execute the works
very carefully and to apply the methods and
The formwork has to be designed in such a techniques as prescribed. In reinforced
way to enable its easy removal, without concrete linings, the of shrinkage cavities is
resorting to hammering or levelling against limited to 0.3 mm. Wide cracks have to be
the surface of the concrete, and without filled with resin or mortar. Shrinkage cracks in
damaging the concrete. non-reinforced lining, whose width exceeds
1.0 mm have to be filled with mortar or resin,
The Contractor is obligated to remedy any or processed in accordance with the
damage that has occurred during the removal instructions obtained from the Supervising
of the formwork. Engineer.
The removal of the formwork must not 2.8.8.3.7 Remedial treatment of surfaces
commence until the concrete attains
sufficient strength to withstand the most Any remedial treatments of surfaces have to
unfavourable load conditions which could be agreed upon with the Supervising
cause damage to the construction. The Engineer, and executed without any delay
74 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
after the inspection of the surfaces, tests and to deliver them to the Supervising
subsequent to the removal of the formwork. Engineer for approval, when requested.
Any concrete whose surface has been If pre-prepared dry injection mass produced
treated prior to the inspection performed by by an accepted manufacturer is being used,
the Supervising Engineer is subject to this mix has to be made with water/solids
rejection. ratios recommended by the manufacturer. All
injection mixes have to be prepared using
2.8.8.3.8 Prefabricated concrete elements high speed mixers.
After injecting is finished, the Contractor has The installation of the reinforcement has to
to cut off the surplus lengths of the pipes. be such to ensure a concrete cover of a
minimum 4.0 cm.
The Contractor is obligated to provide the
Supervising Engineer with the records The Contractor has to take particular care not
referring to the areas being injected, injection to damage the waterproofing membrane
pressures, consumption of grout and details during the installation of the reinforcement.
about the mix, as potentially required by the
2.8.8.4.2 Reinforcing steel bars
Supervising Engineer.
The Supervising Engineer may require tests Reinforcing steel bars have to be attached to
to be carried out to confirm that the injection the previously installed reinforcement mesh.
mix and its constituent materials are in Overlapping has to be performed in
accordance with the specifications. The accordance with the relevant drawings.
Contractor is obligated to carry out these
PE Roads of Serbia 75
Underground Works Serbian Road Construction Specifications
The quality and quality control of the coating Interruptions due to the installation of the
material and works have to comply with the protection of the waterproofing membrane
provisions of the Austrian directive RVS during the installation of the reinforcement
8.29.4. are not measured separately and thus have
to be included in the relevant unit prices.
2.8.8.6 Measuring The curing of concrete (for example, refilling
of cracks) is not measured for payment
Works listed in this section are measured as
purposes, and thus has to be included in the
follows:
relevant unit price.
The inner concrete lining in the tunnel is
measured in cubic metres, including the
Prefabricated concrete components are
theoretical thickness of the inner lining (di)
measured in metres of length.
inside "Line 3", as shown on figure 2.8.9. The
quantities for the inner concrete lining outside
The preparation and coating of the concrete
of "Line 4" are not measured, except for the
surface is measured in square metres along
filling of the excessive overbreak due to
the inner surface of the lining. Cleaning of the
unfavourable geological conditions.
surface has to be included in the unit price.
In cases when the average value of the
actual deformation in a specific section is 2.8.8.7 Payment
smaller than the agreed deformation
tolerance, the measurement for the additional Unit prices for different calculation items have
inner concrete is done in cubic metres, to include the labour, equipment and
provided that the difference "c" is bigger than materials required for completion of works,
10 cm. The quantity of additional concrete including sampling, testing and quality
has to be calculated between "Line 3" and control. Formwork and scaffolding have to be
"Line 4". The actual average deformations included in the unit prices of the relevant
have to be derived from geological calculation items.
measurements.
Should aggressive components appear in the
Filling of an excessive overbreak with inner leachate during the excavation of the tunnel,
concrete has to be measured in-situ as per the inner concrete lining at these sections
the actual quantities, provided that the has to be made of concrete which is resistant
requested quantity of concrete does not to sulphates. Labour, equipment and
exceed 2 cubic metres (in accordance with materials have to be included in an additional
figure2.8.9). payment for sulphate-resistant concrete.
76 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
materials required for the completion of The unit price of coating has to include the
works, including the reinforcement, sealing of labour, equipment and materials required for
joints and the transport to the construction the completion of works.
site.
Explanation:
di … thickness of the inner lining
da … thickness of the levelling shotcrete
including the thickness of the
waterproofing membrane
ds … thickness of the shotcrete
tc … construction tolerance
b … unavoidable overbreak
c … deformation tolerance
td … actual average deformation
Figure 2.8.9: Lines for measuring and calculating the inner concrete lining
Figure 2.8.10: Lines for measuring and calculating the filling of the overbreak with inner concrete
lining
Explanation:
di … thickness of the inner lining
da … thickness of the levelling shotcrete including
the thickness of the waterproofing
membrane
ds … thickness of the shotcrete
PE Roads of Serbia 77
Underground Works Serbian Road Construction Specifications
td … deformation tolerance
78 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
2.8.9.3 Execution
PE Roads of Serbia 79
Underground Works Serbian Road Construction Specifications
The tunnel tube must be protected from the Worker and technical staff present in the
effects of at least 4-hour fire, whereby it may course of these works must wear protective
resist the temperature of 12000C in duration masks.
of one hour.
2.8.1.4. Compliance Control
2.8.1.2. Material
Chemical mixture must be tested before the
This coat must be resistant to aggressive Serbian institutions testing compliance with
gases that might appear in the tunnel. all characteristics and quality standards, as
indicated in the following tables.
Material must not emit any toxic or harmful
gases, and must not pose any threats to the Kerns must be used for testing, when the
health before, in the course of after its mass hardens to ensure compliance with all
application. characteristics and quality standards as
indicated in the following tables.
The chemical mixture of this coat must be
environmentally friendly in its solid state. Obligatory quality evidence in line with:
Prior to its use, the Supervising Engineer ГТ-98036-1a tunnel fire test
must approve it.
Thickness control, by inserting a 1.5mm
2.8.1.3. Execution diameter steel needle every 100m2 of the
coated layer immediately after application,
This protection is achieved by applying a and no later than 1 hour after the machine
special mass in one or more layers according has stopped operating, which performs the
to the manufacturer's instructions. plastering of the fire mortar.
80 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
2.8.2. TUNNEL REHABILITATION These works shall be measured and shall not
WORKS be paid.
Upon the completion of works and To completely remove all impurity from the
installations in the facility, the Contractor is existing tunnel lining, it must be cleaned with
obliged to remove at its own expense all the steel brush. In such a process, all dust
temporary facilities together with all tools, and particles generated when cleaning are
inventory and scaffolding, to clean the site, to washed away with the pressurized water and
bring all excavations to original condition. All pressurized-air to remove all impurity from
debris should be removed from the lining and damaged cracks and joints and
construction site and transported to a prepare them for further treatment.
designated site, approved by the Authority.
2.8.2.2.2. Cleaning of joints and cracks
2.8.2.1.1. Temporary electrical installations This item of works shall be performed in the
section strip joints, cracks and joints of the
Lighting reflectors must allow safe execution retaining walls that are severely damaged
of works. If necessary, light can be dimmed under the influence of water and ice or are
so as to focus on areas within the filled in with harmful and inadequate material.
construction site and avoid irritation. The The number of these cracks, joints and points
tunnel lighting must cover its entire length is specified by the Supervising Engineer, in
and must not be less than required for safe situ, after having examined deformation
operation and access, at least 100 watts status of the tunnel lining.
every 10 m of tunnel length.
Cleaning shall be performed manually, with
Alternative energy source and system in the careful work so as to remove all material that
emergency must exist so as to ensure the has fallen into these areas (corroded
execution of necessary interventions and concrete, residual timber formwork,
safe evacuation in the event of a primary penetrated mountain material, dust and
power outage. An appropriate number of impurities). Cleaning depth shall be 5-6cm,
hand lamps must also be available at key i.e., the depth that is accessible for manual
locations in the tunnel. work. The area surrounding the crack in
lining shall be stripped off so as to remove all
2.8.2.1.2. Drainage in the tunnel in the corroded concrete (approximately 30cm)
course of construction from both sides. The section strip joints and
cracks are then washed with pressurized air
The Contractor shall deliver, place, and water (this item of works is described
commission and maintain sufficient number within the section 1.2 Preparatory works).
of pumps and pipes to control and drain the
water from any part of the underground Material that falls off in the course of the
works. Water retention will not be allowed. works executed regarding this item of works
must be removed from the tunnel and
The tunnel shall be drained in the course of transported to a designated landfilled.
the execution of works as required by the
Contractor and in accordance with the
design.
PE Roads of Serbia 81
Underground Works Serbian Road Construction Specifications
Areas where these repair mortars are applied Waterproofing silicone strips are used for
should be previously prepared, clean without additional securing of cracks. This stripe
any dust or impurities. even better strengthens the crack and
overbridges greater elongations by up to 3
The decision on the cracks that should not be times, so that in the case of a smaller crack
specifically treated, rather levelled with the spread, waterproofing shall not be damaged.
repair mortars shall be made by the
Supervising Body at the construction site.
82 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
Then the other roughness on the concrete 2.8.2.4.2. Contour bond injection of grout
lining shall be treated with repair mortar for behind tunnel lining
the repair of old concrete.
Description
Quality Control
Contour bond grouting of grout behind tunnel
Selection of the type of material to be used, lining shall be executed, if necessary, in the
and the way of control in the course of the weakened tunnel zones upon the decision of
works shall be made by the Supervising the Supervising Body.
Body and the Designed, and the material
must be certified by the competent In the case of insufficient light profile or if it is
authorities. Compressive strength and necessary to strip off the most of the
adhesive strength must be tested at least damaged lining part, thereby posing a threat
once a day. to the remaining lining bearing capacity, the
continuous injection of the soil directly by the
The decision on the correctness of the tunnel lining is envisaged to withstand the
executed works shall be made by the pressure of the surrounding soil, until the
Supervising Body at the construction site. rehabilitation works of the inner part of the
tunnel are completed.
2.8.2.4. Injecting
Before the application, compactness,
adhesion and plasticity shall be tested.
2.8.2.4.1. Bond injection of section strips
and greater cracks by whole Depending on the geological structure, the
drilling and instalment of injection Supervisory Body shall specify the quality
packers conditions that this grout must meet and the
proof of the quality of the contact mass
Description according to the requirements of the
following standards:
Such an injection system is suitable for
repairing places where moisture and water - SRPS U.E3.O15 Injectable grout.
leakage occur. Moisture places shall be Technical conditions.
occasionally drained, and then permanently - SRPS U.M8.O22 Injecting. Testing of
injected, after waterproofing is installed and grout compressive strength.
hardened. - SRPS U.M8.O23 Injecting. Testing
and separation of water and change in
When the waterproofing membrane is the grout volume.
hardened, resin injection shall be injected - SRPS U.M8.O24 Injecting. Testing of
which shall completely close the crack and grout flow rate.
prevent further penetration of moisture.
An obligatory addition to such a grout Betolit,
Such a resin injection works particularly well which provides waterproofing to this mixture.
in humid and wet environments, and it foams
in contact with water and fills all cracks, In addition to the role of creating a complete
thereby forming a permanently impermeable, surface circumferential connection of the
highly flexible sealant. A lasting sealing effect existing concrete lining and the surrounding
is achieved. soil, this grout shall connect the surrounding
soil and the existing concrete lining in a
This resin is injected like common resin, and transverse and longitudinal direction, thus
there is a possibility that in cases of active creating the conditions for redistributing
water penetration, a faster reaction can be some of the pressure of relieving ground arch
achieved by adding an accelerator. from this lining to this grout.
Quality Control
The decision on the need to execute these
Selection of the type of material to be works, the way of their execution and
installed, for all the above-mentioned items of material to be applied shall be made by the
works, must be approved by the Supervising Supervising Body at the construction site.
Body and the Designer, and materials must
be certified by the competent authorities. Quality Control
PE Roads of Serbia 83
Underground Works Serbian Road Construction Specifications
Quality Control
2.8.2.5. Elastomer-sprayed waterproofing
Adhesive force, tensile strength and coating
New technology materials, certified by the thickness shall be controlled at every 100m2.
authorised institutes of the EU Member
States shall be used for tunnel structure Poorly executed work must be repeated.
waterproofing, after being approved by the
Supervising Body. 2.8.2.6. OTHER WORKS
Materials
2.8.2.6.1. Painting the walls of the tunnel to
These materials must be certified by the a height of 2.5 m, (from the top
competent authorities in the Republic of edge of the official, pedestrian
Serbia. path)
Selection of the type of material to be The walls of the tunnel shall be painted with
installed, for all the above-mentioned items of a colour that is resistant to various
works, must be approved by the Supervising atmospheric effects and exhaust gases of
Body and the Designer, and material must be motor vehicles and industrial salts thrown
certified by the competent authorities. over the winter period.
84 PE Roads of Serbia
Serbian Road Construction Specifications Underground Works
The second finishing coat shall be white. It if the need for new points is identified in the
shall prevent water penetration, eliminate remediation process.
chlorides and increase the resistance of
concrete to thawing and freezing cycles and Measurements shall be made by surveying
to salt. instruments in the global coordinate system.
PE Roads of Serbia 85