1 BESI H BEAM 200 1794 KG 2 PIPA CS SCH 10 47.16 KG 3 SEWA CRANE 2 HARI 4 PEMINDAHAN PIPERACK 1 LS 5 Penggalian tanah 11.48 m³ 6 Pengurukan tanah 11.48 m³ 7 Pembesian 190 kg 8 Pengecoran k300 4 m³ 9 Angkur bolt 20x60 18 buah 10 Bagesting 3.5 m² Mobilisasi dan Demobilisasi 1 ls House skeeping 1 ls TOTAL DAN NEW PIPERACK Material Upah Jumlah Rp 35,000.00 Rp 10,000.00 Rp 80,730,000.00 Rp 16,000.00 Rp 8,000.00 Rp 1,131,840.00 Rp - Rp 12,000,000.00 Rp 24,000,000.00 Rp 12,000,000.00 Rp 12,000,000.00 Rp - Rp 170,000.00 Rp 1,951,600.00 Rp 100,000.00 Rp 1,148,000.00 Rp 20,000.00 Rp 10,000.00 Rp 5,700,000.00 Rp 1,450,000.00 Rp 200,000.00 Rp 6,600,000.00 Rp 130,000.00 Rp 60,000.00 Rp 3,420,000.00 Rp 250,000.00 Rp 100,000.00 Rp 1,225,000.00 Rp - Rp 2,000,000.00 Rp 2,000,000.00 Rp - Rp 1,000,000.00 Rp 1,000,000.00 Rp 140,906,440.00