Professional Documents
Culture Documents
4.2 MLH - Technical Specifications - Phase 2A-1
4.2 MLH - Technical Specifications - Phase 2A-1
MILTON, ONTARIO
SPECIFICATIONS
DIVISION 1 - GENERAL
01005 General Requirements ............................................................................................................... 21
01340 Submittals .................................................................................................................................. 13
01500 Temporary Facilities ................................................................................................................... 04
01545 Safety Requirements .................................................................................................................. 10
01546 Flagging and Track Protection ................................................................................................... 07
01550 Track Closures ...........................................................................................................................03
01560 Environmental Protection ........................................................................................................... 26
01600 Material and Equipment ............................................................................................................. 02
01610 Setting Out and Measurement ................................................................................................... 02
01620 Quality Control and Assurance .................................................................................................. 03
01800 Project Closeout ......................................................................................................................... 02
DIVISION 2 - SITEWORK
02000 Mobilization and Demobilization................................................................................................. 03
02140 Dewatering .................................................................................................................................. 08
02141 Construction Access Road ......................................................................................................... 03
02143 CN Track Approach Ramp ......................................................................................................... 03
02144 Site Entrance .............................................................................................................................. 03
02150 Temporary Flow Diversion ......................................................................................................... 08
02160 High Flow Contingency Plan ...................................................................................................... 06
02200 Signal and Fibre Optic Cables ................................................................................................... 13
02201 Construction Monitoring ............................................................................................................. 12
02202 Noise and Vibration Monitoring & Control ................................................................................. 09
02203 Conditions Surveys ..................................................................................................................... 06
02225 Site Demolition & Removals ....................................................................................................... 04
02231 Clearing & Grubbing ................................................................................................................... 05
02272 Erosion Control – General .......................................................................................................... 05
02276 Retained Soil Systems, Wall-Slope ........................................................................................... 31
02283 Noise Wall System ..................................................................................................................... 10
02311 Site Grading ................................................................................................................................ 16
02312 Winter Work ................................................................................................................................ 06
02315 Excavating, Trenching & Backfilling ........................................................................................... 13
02316 Structural Excavations ................................................................................................................ 06
02340 Geogrid and Geotextiles ............................................................................................................. 04
02350 Traffic Control ............................................................................................................................. 07
02362 Dust & Mud Control .................................................................................................................... 04
02368 Temporary Railway Shoring ....................................................................................................... 07
02372 Rip Rap ....................................................................................................................................... 06
02383 Steel H-Piles ............................................................................................................................... 08
02384 Concrete Caissons…………………………………………………………………………………. 04
02620 Subdrainage................................................................................................................................ 04
02630 Culverts & Storm Sewers ........................................................................................................... 06
CN – DESIGN & INDEX FOR
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 4
MI. 36.79 TO 41.00 HALTON SUB
DIVISION 5 – METALS
05120 Structural Steel ........................................................................................................................... 08
05121 Metal Railings for Structures ...................................................................................................... 02
DIVISION 7 – MISCELLANEOUS
07100 Waterproofing Bridge Decks ...................................................................................................... 06
07109 Bearings ...................................................................................................................................... 04
07112 High-Performance Waterproofing. ............................................................................................. 09
07113 Ballast Mat System ..................................................................................................................... 06
CN STANDARD DOCUMENTS
CN 3817-B Bid Bond .................................................................................................................. 01
CN – DESIGN & INDEX FOR
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 4
MI. 36.79 TO 41.00 HALTON SUB
REFERENCE DOCUMENTS
PROJECT OVERVIEW
.1 Track grading and drainage for the construction of the pocket track.
.2 Track grading and drainage for the mainline between South of Britannia
Road and Derry Road.
.3 Lower Base Line Road grade separation, including rail over road bridge.
.4 Track grading and drainage for the mainline in the vicinity of the Lower
Base Line new bridge (both sides of the bridge)
.5 Britannia access road, including the private overpass bridge (road over
rail).
c SITE VISIT
a) The Contractor must have visited the site before submitting a Tender in order to be
thoroughly acquainted with all local conditions under which the Tenderer will be called
upon to carry out the work coming under this Contract.
b) A mandatory site meeting is scheduled at the following time and location to discuss this
Contract and view the site. This will be the only opportunity for Tenderers to enter CN
CN – DESIGN & INSTRUCTIONS TO BIDDERS ANNEX “C”
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2 SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 10
MI. 36.79 TO 41.00 HALTON SUB
property. The Contractor and their employees, while on CN property, will be required
to wear safety hard hats, safety glasses, orange reflective apparel and safety boots
in accordance with Company regulations. Attendance is limited to one person per
invited contractor.
Location: 61 James Snow Parkway, Unit 202, Milton, ON, L9E 0H1
ana.carlotto@cn.ca
e) The site may also be viewed from public roads and road crossings in the area.
Contractors are prohibited from entering CN property for purposes of viewing the
site.
The Contractor is expected to commence the Work within two (2) weeks of the Notice
to proceed with the work.
a) For the purposes of developing the construction schedule, the Contractor shall develop
the construction schedule to complete the entire project work within the allocated
timeframe. The Contractor shall consider all restricted activity periods indicated in the
Contract drawing in developing the construction schedule. The contractor shall submit
the construction schedule together with the bid document, considering the completion
date for the entire work under the Phase 2A contract by September 30, 2025. The
Contractor shall deploy multiple crews (as much as required) to undertake the contract
work concurrently and complete the major works in accordance with the following
milestones and notes:
1. Milestone 1: Complete the entire work for the pocket track bed and other
associated works by August 01, 2024.
2. Milestone 2: Complete the Lower Base Line bridge construction, including the
wing walls, to be ready to receive the new tracks by October 30, 2024.
3. Milestone 3: Complete the entire track bed, drainage, and utilities on both sides of
the new Lower Base Line Bridge by November 15, 2024.
• Coordinate two (2) months in advance with CN Track and Signal crews to
construct the track on top of the bridge and remove the existing track
diversion through the Lower Base Line.
4. Milestone 4: Complete the entire track bed, drainage, and utilities work between
South of Britannia Road and Derry Road by June 30, 2025.
5. Milestone 5: Complete the entire Lower Base Line grade separation and open it to
the public by May 31, 2025.
• The Lower Base Line grade separation must be open to the public on May
31, 2025, and the date is firm and non-negotiable.
6. Milestone 6: Complete the entire work for Britannia access road, including the
bridge and other associated works, by July 01, 2025.
b) The contractor shall deploy the following minimum number of multiple crews to
undertake the contract work concurrently. The contractor has no right to claim delays
in case the following minimum number of working crews is not provided.
CN – DESIGN & INSTRUCTIONS TO BIDDERS ANNEX “C”
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2 SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 10
MI. 36.79 TO 41.00 HALTON SUB
No. Description of Work Minimum number of working Crews
The contractor shall review the milestones date and provide a sufficient number of
working crews to meet the entire project completion date.
c) The Contractor must submit, with the Proposal, a detailed schedule or diagram
(in pdf format) showing the dates by which all activities will be commenced and
finished, bearing in mind that the completion date must not be altered. The Contractor
must indicate, in the schedule, expected progress in increments of not more than one
week.
d) Based on the Contractor proposed schedule, Contract must submit with the Proposal a
contract spend estimate by year of construction, i.e., 2024 and 2025.
i) Confine all work activities between 07:00 and 17:00. When night work or
work outside of the period is required, notice must be provided to the
Engineer with a minimum of seven (7 days’ notice).
ii) Working shift is not to exceed 10 hours per day for activities on-site where
flagging is required. Flagging will not be provided for more than 10 hours
per day on site. The working shift will include the daily job briefing and
mobilization/demobilization from the work location(s). Daily downtime
calculation does not include the daily job briefing and
mobilization/demobilization.
ii) Request for additional work hours and work on Saturday, Sunday, or
Holidays must be approved by the Engineer. The contractor shall not be
entitled to extra payment for working hours beyond 10 hours per day and
for working hours during weekends, public holidays, and night shifts to
meet or expedite the construction schedule.
iii) The contractor shall consider that all culverts shall be installed during track
closures required to complete the work during the night shift and over the
weekends.
CN – DESIGN & INSTRUCTIONS TO BIDDERS ANNEX “C”
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2 SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 10
MI. 36.79 TO 41.00 HALTON SUB
iv) The contractor shall consider that sections of the track grading along the
existing mainline will be completed during track closures. The work shall be
undertaken during the night shift and over the weekends.
v) The Contractor must submit, in writing, the proposed hours of work that will
constitute the working day to maximize productivity. The proposed hour of
work must take into account the daily rail traffic, as provided in the General
Staging Notes and/or observed by the Contractor.
vi) The Contractor shall take into consideration downtime to permit the
passage of trains on the adjacent tracks. Downtime calculations do not
include the daily job briefings and mobilization/demobilization. The
Contractor shall have no claims for additional payment for delays.
TENDER CONDITIONS
Tenderer must confirm their intention to submit a proposal no later than 4:00 pm E.D.T.,
September 20, 2023, through Ariba or by email to ana.carlotto@cn.ca
3 BID DEPOSIT
It must be a condition of all Tenders that there be deposited with each Tender, a Bid Bond
in form and to the amount as follows:
a) Bid Bond
The Bid Bond must be in favour of the Canadian National Railway Company in the
amount of ten percent (10%) of the estimated total amount of the Tender, issued
by a Guarantee or Indemnity Company, approved by the Railway, and having an
office in Canada, preferably in the Province in which the work will be performed
and in form and terms satisfactory to the Railway.
b) Upon the opening of Tenders, all Bid Bonds will be immediately taken in charge by
the CN Contract Officer, who must retain them in safekeeping until advised by the
Engineer as to their retention or return.
c) Tenders shall be open for acceptance for a period of 60 days after the Tender
closing date.
e) The Bid Deposit of the successful Tenderer shall be returned to them after they
have furnished the Railway with the security hereinafter referred to.
CN – DESIGN & INSTRUCTIONS TO BIDDERS ANNEX “C”
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2 SEPTEMBER 2023
GRADING & DRAINAGE PAGE 6 OF 10
MI. 36.79 TO 41.00 HALTON SUB
4 CONSENT OF SURETY
It shall be a condition of all Tenderers that there be deposited with each Tender a letter
from a recognized surety company, licensed to operate in the Province of Ontario, stating
that, if the Tenderer is successful, the surety company will issue the following in Canadian
National Railway Company’s name, and in form acceptable to the Railway:
a) A Performance Bond for fifty percent (50%) of the estimated Contract price.
b) A Labour and Material Payment Bond for fifty percent (50%) of the estimated
Contract price (excluding H.S.T.).
5 CONTRACT SECURITY
d) The acceptable form of a Labour and Materials Payment Bond shall be Document
Number CCDC 222 of the Canadian Construction Documents Committee
(C.C.D.C.). Any variation from this form may result in rejection:
f) If such security has not been received by the Railway within eight (8) days from
Notification of Acceptance the Railway must have the right to retain the amount of the
Bid Deposit as liquidated damages and to rescind the award.
g) Upon the satisfactory completion of the Contract and the passing of the final estimate,
such security will be returned to the successful Tenderer.
6 FORMAL AGREEMENT
a) The successful Contractor will be required to enter into a formal agreement with the
Railway on its Standard Contract Form No. CN-3819, a copy of which is attached with
these documents.
7 EMPLOYMENT
8 TENDER FORMS
a) Tenders must be submitted on the forms supplied by the Canadian National Railway
Company for this purpose and no Tender or amendment of Tender will be considered
unless submitted on the said forms prior to the time of closing.
b) The enclosed "Instructions to Bidders" must not be detached from the "Form of
Tender" as it constitutes a part of the Contract.
c) The Railway requires that all pages in the Form of Tender be completed in their
entirety prior to Tender closing. Late submissions of tendering information will not be
considered or accepted.
9 SUBSTITUTIONS
Tenderer must submit, on the attached Form of Tender, a complete list of proposed
substitutions together with cost differences. The Tenderer must complete the Form of
Tender by pricing the item listed, not a substitution. The substitution and the associated
cost difference(s) can only be noted under the Substitutions section.
10 TRADES
a) Tenderer must submit, on the attached Form of Tender, a complete list of trades to be
executed together with Contractor's own forces, as well as a completed list of Sub-
Contractors to be employed.
11 SOURCE OF MATERIALS
Tenderer must submit, on the attached Form of Tender, a complete list of sources of
materials he/she intends to supply.
12 TENDER EVALUATION
a) CN reserves the right to accept the Bid that it deems in its discretion most
advantageous. The Bid having the lowest cost to CN or any Bid shall not necessarily
be accepted. CN may take into account the following evaluation criteria (not
necessarily in order of importance):
b) CN is not obliged to inform the Bidders of the relative weight to be given to any
particular evaluation criteria, to open the Bids publicly, or to provide reasons to any
Bidder with respect to any use of the CN’s discretion.
c) CN and the Engineer may make such investigations as they deem necessary to
evaluate the ability of any Bidder and its named subcontractors to perform the Work,
and CN may utilize the results of such investigation in awarding the Contract.
f) CN reserves the right, in its discretion, to seek further information from, or clarification
of, any Bid submitted by any Bidder in respect of any of the terms and conditions of the
Contract Documents. CN is entitled to utilize the information or clarifications received
in awarding the Contract.
h) The Bidder acknowledges and agrees that it shall have no claim against, or entitlement
to damages from, CN or the Engineer by reason of the CN’s rejection of its Bid or all
Bids.
13 FAXMITTALS
14 TENDER CLOSING
b) Time for receiving Tenders will close at 3:00 PM, E.D.T., October 30, 2023 and no
Tender or amendment of Tender will be accepted or considered if received by the
Railway after that hour.
15 ADDENDA
i) Tenderers must state on the Tender Form in the space provided the numbers of
all Addenda received and included for by them in the preparation of the tender.
a) The Tenderer shall include in their Tender submission an attestation issued by the
Workers' Compensation Board indicating the Contractor's Safety Performance
Rating/Record and all "lost time injuries" during the last five years.
CN – DESIGN & INSTRUCTIONS TO BIDDERS ANNEX “C”
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2 SEPTEMBER 2023
GRADING & DRAINAGE PAGE 10 OF 10
MI. 36.79 TO 41.00 HALTON SUB
17 FINANCIAL STATEMENTS
a) The Tenderer shall include in their Tender submission financial statements for the
past three (3) fiscal years, prepared in accordance with generally accepted
accounting principles of the jurisdiction in which the Proponent is located, and
audited by an independent certified public accountant; or a statement from the
Proponent regarding how financial information may be reviewed by CN.
19 ENQUIRIES
a) Any enquiries concerning the Tender Documents must be submitted no later than
September 29, 2023.
The undersigned hereby offers and agrees to furnish all and every kind of supervision, labour, tools, equipment,
machinery, service and materials that may be required and to execute and complete in a satisfactory and
workmanlike manner all the work in accordance with Plans and Specifications attached hereto and exhibited and
such further details as may be furnished from time to time during the progress of the work.
We have examined the Plans, Specifications, Instructions to Bidders, the Site and the existing conditions and
have ascertained all necessary particulars with regard to the work and upon acceptance of this Tender, we
are prepared to enter into a contract in the form exhibited with the said Specification, for the performance of
the work for the Lump Sum and/or Unit Prices shown below.
SCHEDULE OF PRICES
Proponents can submit the schedule of prices in a locked format such as .pdf and in addition please
submit schedule of prices in the excel format provided in Ariba.
The listed Lump Sum and/or Unit Prices in the Schedule of Prices must include all taxes imposed by
competent taxing authorities, including business taxes properly payable by the Contractor. Harmonized Sales
Tax is not included in the above Lump Sum and/or Unit Prices and is to be shown as a separate item.
Unit Price Quantities shown in the Schedule of Prices are estimated only. All payments will be made on the
basis of "As Constructed" quantities.
Lump Sum items will be only eligible for payment only if the material/service is delivered/provided by
Contractor and approved by CN.
The Railway Company reserves the right to delete from the contract any items listed on the Form of Tender.
The tender submitted is based on the plans and specifications. Below, we propose substitutions with cost
differences for your consideration. Bidders are not required to propose any substitutions.
MATERIAL SOURCES
The Tenderer must state below the locations from where he/she intends to obtain all the materials he is to
supply.
Materials Source
Granular Materials
Concrete
Concrete Reinforcement
Drainage Structures
Culverts
Sewer Pipes
NOTE: Acceptance of this tender does not constitute approval of the above material sources.
CN – DESIGN & FORM OF TENDER FOR ANNEX "B"
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 13
MI. 36.79 TO 41.00 HALTON SUB
LIST OF EQUIPMENT
The undersigned, submit a list of equipment will be employed if the Tender is accepted.
We acknowledge the above equipment will meet zero-emission requirements as specified in Section 01005,
Clause 1.22.5 of the specifications. It is agreed that there will be no substitution of, or any addition of,
equipment without the prior written approval of the Railway.
CN – DESIGN & FORM OF TENDER FOR ANNEX "B"
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 13
MI. 36.79 TO 41.00 HALTON SUB
LIST OF PROJECTS
The undersigned, submit a list of similar project undertaken in the past 5 years.
The undersigned, submit a list of Sub-Contractors whose services will be employed if the Tender is accepted.
We acknowledge we have investigated the above sub-contractors and confirm they are reliable and
competent to carry out the work satisfactorily. It is agreed that there will be no substitution of, or any addition
of, sub-contractors without the prior written approval of the Railway.
The undersigned, submit herewith a list of the trades to be executed by our own forces.
Scope
CN – DESIGN & FORM OF TENDER FOR ANNEX "B"
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 6 OF 13
MI. 36.79 TO 41.00 HALTON SUB
MOBILIZATION/DEMOBILIZATION
Please describe all items included in your pricing under Mobilization and Demobilization lines.
CN – DESIGN & FORM OF TENDER FOR ANNEX "B"
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 7 OF 13
MI. 36.79 TO 41.00 HALTON SUB
UNIT RATES
Please attach to your proposal your unit rates for Labour and Equipment applied to this RFP scope.
CN – DESIGN & FORM OF TENDER FOR ANNEX "B"
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 8 OF 13
MI. 36.79 TO 41.00 HALTON SUB
RESOURCE HISTOGRAM
Please provide a resource histogram planned with roles/trades is to be included along the project
schedule/timeline.
CN – DESIGN & FORM OF TENDER FOR ANNEX "B"
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 9 OF 13
MI. 36.79 TO 41.00 HALTON SUB
SCHEDULE
Please submit your schedule, work sequencing & staging plan binding to the Proposed Milestones dates in
the Instructions to Bidders:
CN – DESIGN & FORM OF TENDER FOR ANNEX "B"
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 10 OF 13
MI. 36.79 TO 41.00 HALTON SUB
CONTRUCTION METHODOLOGY/WORK PLAN
Please submit a description of the highlights of your construction methodology for this work. The method
statement shall detail the methodology used to develop the contract schedule to meet the scope milestones
considering CN Safety Policies and Standards. Please include your methodology and proposal inclusions
to comply with CN Environmental Plan tied to this scope.
CN – DESIGN & FORM OF TENDER FOR ANNEX "B"
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 11 OF 13
MI. 36.79 TO 41.00 HALTON SUB
INDIGENOUS PROCUREMENT
Canadian National Railway Company is committed to developing respectful, sustainable and mutually
beneficial relationship with Indigenous communities while ensuring service to our customers. Does your
firm have any initiative or level of effort in engaging and incorporating Indigenous participation as part of
your provided services?
If yes, please provide a brief description. Also, please provide the following information:
POLICY/COMMITMENT:
Is the bidder an Indigenous-owned
business or does the bidder have
Indigenous engagement
commitments to this scope or
policies in place (i.e., ownership*,
hiring opportunities, subcontracting
opportunities, Indigenous
community engagement, etc.)? If
yes, please describe.
TARGET:
Does the bidder have targets or
goals pertaining to Indigenous
engagement? If yes, please
describe.
PERFORMANCE:
Does the bidder track and report
any KPIs related to Indigenous
engagement (e.g., % Indigenous
employees, % spend with
Indigenous business, etc.)? If yes,
please describe.
CN – DESIGN & FORM OF TENDER FOR ANNEX "B"
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 12 OF 13
MI. 36.79 TO 41.00 HALTON SUB
SITE VISIT / MEETING
The undersigned will execute, under authority of Form CN-8653-B, at prices to be established under the
provisions of Clauses 14 to 17 inclusive of Contract Form CN-3819, any and all other items of work required
by the Division Engineer of the Railway Company.
REGISTERED
COMPANY NAME
SIGNATURE
WITNESS PRESIDENT/OWNER
SECRETARY OF
WITNESS COMPANY
ADDRESS
CITY/PROVINCE
POSTAL CODE
PHONE NO.
FAX NO.
SIGNED DAY OF 2023
BANK NAME
ADDRESS
PHONE NO.
HST REGISTRATION NO.
INSERT NUMBERS OF ADDENDA INCLUDED WITH THIS
TENDER
NOTE: If the Contractor is an incorporated Company, the Tender must be signed by the President (or other
Officer duly authorized to sign) and the Secretary of the Company.
If the Contractor is not a Corporate body, the Tender must be signed by each individual member of the Firm
and their address given.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
1.2 INTERPRETATION
.1 This Contract covers the supply of all labor, material, and equipment required to
carry out the construction of the Milton Logistics Hub – Phase 2A Mile 36.79 to
Mile 41.00 Halton Sub, located in Milton in the Province of Ontario:
.1 Track grading and drainage for the construction of the pocket track.
.2 Track grading and drainage for the mainline between South of Britannia
Road and Derry Road.
.3 Lower Base Line Road grade separation, including rail over road bridge.
CN – DESIGN & GENERAL REQUIREMENTS SECTION 01005
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2 SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 21
MI. 36.79 TO 41.00 HALTON SUB
.4 Track grading and drainage for the mainline in the vicinity of the Lower
Base Line new bridge (both sides of the bridge)
.5 Britannia access road, including the private overpass bridge (road over
rail).
.13 Supply and placement of rip rap and other environmental requirements;
.17 All incidental construction requirements necessary to carry out the Work
indicated in the Contract Documents including, but not limited to,
provision of facilities, purpose-made equipment, and environmental
control measures, and licenses and permits procured by the Railway;
.18 Supply of all surveying resources required to set and maintain lines and
levels and to measure quantities; quality control and assurance required
to assure compliance with specifications and all other Work;
.20 All other work as called for on the Contract Drawings and/or described in
the Specifications.
.3 Only the latest issue of these Codes, Standards and Specifications shall be
followed:
.7 Submittals 01340;
.4 ASTM Standards:
.1 The Engineer may furnish drawings in electronic format, in Adobe Acrobat (PDF)
format, via a project website or via email. These drawings shall have same
meaning and intent as if they were included with plans referred to in Clause 3 of
these Supplementary General Conditions.
.2 The Engineer may furnish additional drawings to assist proper execution of work.
These drawings will be issued for clarification only. Such drawings shall have
same meaning and intent as if they were included with plans referred to in
Clause 3 of these Supplementary General Conditions.
.1 Payment for the work will be made on the basis of the various Unit and Lump
Sum Prices as submitted on the Form of Tender. Quantities for payment under
Unit Price items will be determined by the Engineer, based on measurement
methods specified subject to actual quantities completed on site. Lump Sum
items will be only eligible for payment if the material/ service is delivered/provided
by Contractor and approved by CN.
.2 Unless otherwise stated in this Section, the Unit and Lump Sum Prices above
referred to shall include all labour, scaffolding, tools, implements, machinery,
service and materials constructed in place, and shall include all overhead, profit
and supervision and the entire cost of all permits, certificates, Provincial Labour
Taxes, Workplace Safety and Insurance, Public Liability and Property Damage,
Surety Bond, Royalties, and any and all other costs of a like nature to which the
work is liable.
.3 Harmonized Sales Tax is not to be included in the Unit and Lump Sum Prices.
This tax is to be shown as a separate item on the Form of Tender.
.4 If it is found that any portion of the work specified or shown on the drawings can
be omitted, the Engineer reserves the right to omit such portions of the work as
he may see fit. Deductions shall be made from the Contract price for any work
omitted at the Unit Price stated in the Contractor's Tender.
.5 The Contractor shall take into consideration all of the precautions, conditions and
limitations of every kind which may affect the work or their operations, and they
must allow for same in the various Unit and Lump Sum Prices submitted.
CN – DESIGN & GENERAL REQUIREMENTS SECTION 01005
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2 SEPTEMBER 2023
GRADING & DRAINAGE PAGE 6 OF 21
MI. 36.79 TO 41.00 HALTON SUB
.2 The manner in which the total number of units of measurement for the various
items of work and/or material will be established for payment is clearly defined in
the various sections of this Section.
.1 All work that may be called for in the Specifications and not shown on the Plans
or shown on the Plans and not called for in the Specifications, shall be executed
by the Contractor as if described in both. Should any work or material be required
which is not denoted in the Specifications or Plans, either directly or indirectly,
but is nevertheless necessary for the proper carrying out of the intent thereof, the
Contractor is to understand the same to be implied and required and shall
perform all such work and furnish all such materials as fully as if they were
particularly delineated or described.
.2 If the Contractor, in the course of the work, finds any discrepancy between the
Plans and the physical conditions of the locality, or any errors or omissions in the
Plans, it shall be their duty to immediately inform the Engineer in writing, and the
Engineer shall promptly verify the same. Any work done after such discovery,
until authorized, will be done at the Contractor's risk.
.3 Specifications shall take precedence over the Contract Drawings. Figures on the
Drawings shall take precedence over scaled measurements; details shall take
precedence over Contract Drawings made to a smaller scale.
.4 The Contractor shall make written application to the Engineer for further detail
drawings required. Such application must be received by the Railway at least 14
days before they will be required by the Contractor.
.5 The decisions of the Engineer shall govern the interpretation of Drawings and the
Specifications throughout the execution of the work and he shall be the sole
judge of the work, material and plant, whether temporary or permanent, both as
to quality and quantity. The Engineer’s decision on questions of dispute with
regard to work, material and plant, shall be final.
.1 Contract Drawings;
.2 Specifications;
CN – DESIGN & GENERAL REQUIREMENTS SECTION 01005
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2 SEPTEMBER 2023
GRADING & DRAINAGE PAGE 7 OF 21
MI. 36.79 TO 41.00 HALTON SUB
.3 Addenda;
.5 Change orders;
.12 All other documents called for in various sections of the Specifications.
.3 CN’s standard payment terms are sixty (60) days from the date on the invoice.
Invoices shall be issued after the Engineer's approval of the progress payment
certificate.CN’s payments will be made via EFT (Electronic Funds Transfer).
Details of the payment are provided to the Contractor by email.
.1 A fixed Lump Sum amount has been attributed to this contract for the successful
performance of environmental compliance as determined by the Engineer and
CN Environmental Monitor.
.2 Once the Contractor has completely mobilized to the Site, a maximum aggregate
amount as indicated in the Form of Tender shall be attributed conditional to FULL
compliance to the environmental clauses identified in the Tender.
.3 If the Contractor does not willfully comply with these requirements or the direction
of the CN Environmental Monitor in a reasonable time period (as determined by
the Engineer and CN Environmental Monitor) during that given month, then the
full amount for that given month will be canceled from the aggregate amount of
the Form of Tender.
CN – DESIGN & GENERAL REQUIREMENTS SECTION 01005
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2 SEPTEMBER 2023
GRADING & DRAINAGE PAGE 8 OF 21
MI. 36.79 TO 41.00 HALTON SUB
.5 The aggregate amount shown in the Form of Tender shall remain fixed for this
contract and in case of extension of the contract, no additional remuneration will
be awarded.
.6 Incentive Payments are an incentive for Contractor compliance and are not
allocated to fund any portion of the work to be completed to get or remain in
compliance.
.1 A fixed Lump Sum amount has been attributed to this contract for the successful
performance of safety compliance as determined by the Engineer.
.2 Once the Contractor has completely mobilized to the Site, a maximum aggregate
amount as indicated in the Form of Tender shall be attributed conditional to FULL
compliance to the safety clauses identified in the Tender.
.3 If the Contractor does not willfully comply with these requirements or the direction
of the Engineer in a reasonable time period (as determined by the Engineer)
during that given week then the full amount for that given week will be cancelled
from the aggregate amount of the Form of Tender.
.5 The aggregate amount shown in the Form of Tender shall remain fixed for this
contract and in case of an extension of contract, no additional remuneration will
be awarded.
.6 Incentive Payments are an incentive for Contractor compliance and are not
allocated to fund any portion of the work to be completed to get or remain in
compliance.
.1 The right is reserved to make reasonable changes in the design of the work or to
omit any such part as the Engineer may see fit. In the case of work or material,
which is added to, or deducted from the work herein specified, a fair and
reasonable valuation of same must be added to or deducted from the Contract as
the case may require.
.2 The Contractor must refer to Clause No. 14 (1) and (2) of the "General
Conditions" of Contract Form No. 3819-B with reference to payment for extra
work.
CN – DESIGN & GENERAL REQUIREMENTS SECTION 01005
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2 SEPTEMBER 2023
GRADING & DRAINAGE PAGE 9 OF 21
MI. 36.79 TO 41.00 HALTON SUB
.3 All Price Fixing and Change Orders must be submitted with detailed material
lists, labour costs and receipted invoices.
.4 For Extra Work not customarily performed by the Contractor’s own personnel, or
for Extra Work so designated by the Engineer, the Contractor shall obtain
quotations from a minimum of three (3) subcontractors:
.2 The Engineer may designate specific persons from whom or entities from
which the Contractor shall obtain bids;
.3 The Contractor shall not be required to contract with anyone whom the
Contractor has reasonable objection;
.5 The Contractor shall be entitled to recover only demonstrable direct costs for
extra work, plus mark-up per Contract Form 3819.
.6 For labour and operators, such cost is deemed to be a maximum, wages plus
40% labour burden. The Contractor shall provide proof of labour costs upon
request.
.7 For equipment, standby time caused by CN delays only will be paid at 50% of the
hourly rate included in the Form of Tender or OPSS 127 for that type of
equipment.
.8 Indirect costs, including, but not limited to, as-built drawings, project
management, site superintendence, temporary facilities, office support,
surveying, bonding and insurance shall be covered in general contract and / or
specified mark-up and shall not be allowed in valuation of extra work.
.9 The Contractor shall submit an Extra Work Order to the Engineer for approval
prior to such work.
CN – DESIGN & GENERAL REQUIREMENTS SECTION 01005
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2 SEPTEMBER 2023
GRADING & DRAINAGE PAGE 10 OF 21
MI. 36.79 TO 41.00 HALTON SUB
.1 Clearly identify all submittals and correspondence submitted to the Engineer with
the project title as it appears on the Railway's drawing title block including
Subdivision and mileage.
.1 Before the award of the Contract, any Tenderer may be required to show to the
satisfaction of the Engineer that he has, or can obtain the necessary and proper
equipment, tools, facilities and means, and that he has the experience, ability
and financial resources to perform the work within the time specified and in a
satisfactory or workmanlike manner.
1.16 EMPLOYMENT
.1 The Contractor shall comply with all existing Laws and Regulations as prescribed
by the Canada Labour Code and/or the Minister of Labour and the Government
of Canada.
.1 The Railway, before the award of the Contract, will obtain the requisite
permission of authorities, landowners and tenants for:
.2 Before entering on or disturbing any land or property for the purposes of the
works or commencing any part of the works, the Contractor shall:
.1 Ascertain from the Engineer and Environmental Monitor what permits are
being sought by the railway and what permits have been obtained by the
Railway and the terms under which these permits have been obtained;
and
.4 The Contractor shall strictly adhere to the terms of the permissions obtained as
above for the carrying out of the works and provide the Railway with
documentation of said permission and the terms thereof.
.5 Without limiting the Contractor's obligations under the subsection, the Contractor
shall, in particular, serve notices in respect of their operations on all other
authorities concerned in the provision of utility or communication services whose
water, gas, sewer, electricity or other service lines and installations may be
affected by the Contractor's operation.
.1 The Contractor shall obtain and pay for all necessary non-environmental permits,
licenses, inspections and certificates required for the execution of the work, the
cost of which is to be included in the tender. The Contractor shall deliver all the
required documents to the Railway at no additional cost.
1.19 COOPERATION
.1 The Contractor shall cooperate with all other Contractors, Railway Forces, Utility
companies and Road Authorities carrying out work in the area, allowing free
access to their works at all times, so that all the work to be performed under this
Contract shall be completed not later than the date named in "Instructions to
Bidders - Annex C".
.3 In the event that all utilities requiring relocation have not been relocated prior to
the time when the “Contractor” commences “Work”, he will be required to co-
operate with the utility owner and “Work” around the utilities such that the existing
services are protected until such time as they can be removed from the line of
construction. No claims for extra payment will be allowed for this requirement.
.1 The Contractor shall visit the site before submitting their Tender in order to
thoroughly acquaint themself with all local conditions under which he will be
called upon to carry out the work coming under this Contract. The Contractor
CN – DESIGN & GENERAL REQUIREMENTS SECTION 01005
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2 SEPTEMBER 2023
GRADING & DRAINAGE PAGE 12 OF 21
MI. 36.79 TO 41.00 HALTON SUB
shall not visit the site unescorted. A mandatory site visit is scheduled to occur as
called for in the “Instructions to Bidders” - Annex C of these documents. All those
present at the site visit must wear 6” tall safety boots, hard hats, safety glasses
with side shields, appropriate face masks, and reflectorized vests.
.1 Study all Contract Drawings, in particular the Contract Drawings showing the
general layout, and utility plants, so as to become familiar with the conditions
under which the Contract will have to be carried out.
.2 The Contractor must limit construction activities to CN property as per the extents
indicated in Contract Documents. The Contractor shall install fencing at the
design locations as shown on the Contract Drawings.
.4 The Contractor must undertake all work in such a way and sequence outlined in
the Contract Drawings and permits and approvals so that all work covered under
the Contract will be completed by the date named in “Instructions to Bidders” –
Annex “C”.
.2 All work along and within the entire length of the site shall be subject to the
following restrictions, and as directed by the Engineer:
.1 Confine all work activities to between 07:00 and 17:00. When night work
or work outside of the period is required, notice must be provided to the
Engineer within a minimum of one (1) month notice;
.2 Working shift is not to exceed ten (10) hours per day for activities on-site
where flagging is required. Flagging will not be provided for more than ten
(10) hours per day on site. The working shift will include the daily job
briefing and mobilization/demobilization from the work location(s). Daily
downtime calculation does not include the daily job briefing and
mobilization/demobilization; and
CN – DESIGN & GENERAL REQUIREMENTS SECTION 01005
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2 SEPTEMBER 2023
GRADING & DRAINAGE PAGE 13 OF 21
MI. 36.79 TO 41.00 HALTON SUB
.1 The Contractor shall ensure that its actions during all phases of construction are
considered in a careful and precautionary manner, promote sustainable
development, are informed by the best information and knowledge including
community and Indigenous knowledge, available at the time the Contractor takes
action, are based on methods and models that are recognized by standard-
setting bodies, are undertaken by qualified individuals, have applied the best
available economically and technically feasible technologies to achieve
continuous improvement and meet all engineering requirements for safe railway
and facility operation.
.2 As far as it is consistent with the nature of the work and the results to be attained,
the Contractor shall develop the order and methods of prosecuting the work so
that it is consistent with the approvals and permits in place provided safety is not
compromised.
.3 All equipment must have quieter 'shushing' backup alarms instead of the
louder beeping alarm.
.6 Should the Engineer be of the opinion and so state in writing to the Contractor
that the force of men or the quantity of plant supplied for the performance of the
work is not sufficient, or that the character of said plant is not suitable, or that the
methods employed are not such as will ensure that the work will be completed
within the time specified in the Contract, the Contractor shall, at their own
expense, forthwith increase the number of workers employed upon the work
and/or shall make the required additions or revisions to their plant, and shall
employ work methods satisfactory to the Engineer.
.7 The Contractor shall prosecute the work with all skill and diligence and their
delegated representative having jurisdiction shall cooperate with all trades and
the Engineer in every legitimate way to conduct their respective business in an
effective, successful and harmonious manner so as to complete the work in
accordance with the Contract. If the Contractor fails, in the opinion of the
Engineer, to carry on the work with sufficient diligence and skill, or their
delegated representative having jurisdiction, fails to cooperate with all trades and
the Engineer as aforementioned, to ensure completion in accordance with the
Contract, the Engineer may take whatever steps he considers necessary under
Clauses 22 and 23 of Contract Form No. 3819 attached.
.2 Arrange with the Engineer for the area required for storage of equipment and
material, and the erection of offices and sheds.
.3 The location and layout on the site of the Contractor's office and plant areas,
storage yards, access and transport routes, shall be as detailed in the drawings
and is subject to the direction and approval of the Engineer who will, insofar as it
is in their opinion reasonable to do so, meet the Contractor's wishes in these
respects.
.4 Confine the storage of materials and the operation of workmen to limits indicated
by law, ordinances, permits or direction of the Engineer and in accordance with
Section 01560 Environmental Protection.
CN – DESIGN & GENERAL REQUIREMENTS SECTION 01005
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2 SEPTEMBER 2023
GRADING & DRAINAGE PAGE 15 OF 21
MI. 36.79 TO 41.00 HALTON SUB
.6 No material or equipment shall be stored closer than five (5) meters from nearest
rail of any operated track.
.7 Cooperate with the Railway, road authorities, utility companies and all other
agencies required to work in that area.
.8 Onsite roads will be defined, delineated and enforced to a 30 km/h speed limit.
.9 Refueling areas will be identified and will not be closer to 30 meters from the
nearest water body, watercourse or floodplain areas.
.10 Hazardous materials for use on site will be stored in areas delineated and
managed as per the MSDS sheets.
.2 The Contractor shall be responsible for the true and proper laying out of the
works and for the correctness of the position, levels, dimensions and alignment
of all parts of the works, and for the provision of all necessary instruments and
labour in connection therewith. If, at any time during the progress of the works
any error shall appear or arise in the position, levels, dimensions or alignment of
any part of the works, the Contractor shall, at their own expense, rectify such
errors to the satisfaction of the Engineer, unless such error is based on incorrect
data supplied by the Engineer.
.3 The checking of the setting out of any line or level by the Engineer shall not in
any way relieve the Contractor of their responsibility for the correctness thereof,
and the Contractor shall carefully protect and preserve all bench marks, stakes
and other items used in setting out of the works.
.1 The Contractor must take into consideration, when submitting their Tender, the
location of any existing utility plant.
.2 Public utilities will be relocated in the working area by others before and during
the work and the Contractor is expected to cooperate to ensure delays are kept
to a minimum.
CN – DESIGN & GENERAL REQUIREMENTS SECTION 01005
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2 SEPTEMBER 2023
GRADING & DRAINAGE PAGE 16 OF 21
MI. 36.79 TO 41.00 HALTON SUB
.3 The Railway will not entertain claims for any inconvenience or delay to the
Contractor caused by the relocating of said utilities.
.6 The Contractor is directed to carefully examine the location of the work and to
make special enquiry of the companies owning, controlling, or operating any
utilities, pipes, conduits, or other structures and to determine their own
satisfaction the character, size, length and position of such utilities, pipes,
conduits, or other structures. The Contractor shall not make any claims against
the Railway for damages or extra work caused by them relying upon such
records, reports, or information, either as a whole or in part, furnished by any
Civic Government Department or Commission, Utility Company or individual.
.7 The Contractor shall contact the various Utility companies in order to determine
the actual location of all buried live service lines, prior to commencement of their
operation. The Contractor shall also ensure at that time that all buried service
lines, falling within the work area, are dead, and have been abandoned by the
Utility companies involved, and the Contractor shall be responsible for removing
of same within the limits of their excavation.
.8 The Contractor will be responsible for locating and protecting all buried utility
services and will be held liable for any damage to same. Where trenching under
existing water mains, gas mains, and hydro and telephone or cable conduits, the
Contractor will be required to support these mains or conduits in accordance with
the requirements of the Enbridge Gas Company, Hydro One, Rogers, Bell
Canada or the Public Utilities Commission.
.9 In the event that any underground utility must be relocated, the Contractor will be
required to co-operate with the Utility Companies and will be expected to alter
their construction schedule as necessary, to permit relocation of utilities. No extra
payment or extension of completion time will be allowed for these requirements.
.2 The Engineer or CN’s Environmental Monitor may decide that adverse weather
conditions do not permit certain portions of the work to be completed within the
CN – DESIGN & GENERAL REQUIREMENTS SECTION 01005
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2 SEPTEMBER 2023
GRADING & DRAINAGE PAGE 17 OF 21
MI. 36.79 TO 41.00 HALTON SUB
true meaning and intent of the Specifications and the Contract Drawings, and he
may order the Contractor to discontinue work on these portions of the work:
.1 The Contractor shall stop and not continue work on these portions until he
has received permission from the Engineer to proceed;
.2 If the Engineer stops the work or any portion thereof for any period, the
Contractor shall be granted an extension of time equal to that period; and
1.28 EMERGENCIES
.1 In the event of any part of the work being in danger from any cause whatsoever,
or if the work cannot be completed by the specified time, the Engineer shall have
the right to call upon the Contractor for continuance of work without interruption.
.1 Contractual Clause:
.1 It is understood and agreed that this policy extends to cover the
liability of (name of contracting company) assumed under contract
with the Canadian National Railway Company, for (description of
project).
.1 The Contractor is referred to Clause 36, Sub (c) of Contract Form No. 3819
attached.
.2 Fire Precautions shall be taken in accordance with Clause 11, of Contract Form
No. 3819 attached.
.3 The Certificate of Insurance shall be filed with the Railway before the Contractor
commences the work under this Contract.
.1 The Contractor shall refer to Clauses 34 and 35, of Contract Form No. 3819 with
reference to superintendence and negligence.
1.32 DAMAGES
.1 The Contractor shall refer to Clause 12 of Contract Form No. 3819 with reference
to damages to persons or property.
1.33 PATENTS
.1 The Contractor shall refer to Clause 5, of Contract Form No. 3819 with reference
to patents.
.1 The Contractor shall be registered with the Workplace Safety and Insurance
Board in the Province of Ontario. Upon the award of the Contract, the Contractor
shall provide evidence of such registration.
.1 The Contractor shall provide and maintain readily accessible at the works all first
aid equipment and installations required by the Occupational Health and Safety
Act, and all safety and lifesaving equipment appropriate to the nature of the
works.
.1 Hold weekly project meetings at times and locations approved by the Engineer.
1.37 DIARY
.1 The Contractor, for each category of work, shall supply the Engineer at the end
of each week, a summary of daily information by hours tabulated as follows:
.1 Personnel by classification;
.1 All fossils, coins, articles of value or antiquity and structures and other remains or
things of geological or archaeological interest discovered on the site shall follow
the Archaeological and Cultural Resources Plan. The Contractor shall take all
reasonable precautions and any precautions required by the Engineer to prevent
their workers or other persons from removing or damaging any such article or
thing and shall immediately upon discovery thereof notify the Engineer and
Environmental Monitor in accordance with the Archaeological and Cultural
Resources Plan.
.1 As soon as the necessity for Contractor's equipment has passed, the Contractor
shall promptly remove such equipment and surplus material from the structure
and site to the satisfaction of the Engineer.
.1 The Contractor shall at all times keep the site in a neat and tidy condition.
Precautions shall be taken to prevent debris, including mud and dust, from
drifting from the site. Upon completion of the work, the Contractor shall clean up
the site to the satisfaction of the Engineer.
.2 The cost of debris control and final site cleanup shall be borne by the Contractor.
Should the Contractor fail to control debris and clean up the site to the
satisfaction of the Engineer, the Railway may undertake the same and the cost
thereof shall be deducted from any money due or that may come due to the
Contractor under this Contract.
.3 The contractor shall provide street sweeping for all adjacent roads that are used
by the construction vehicles.
.1 The Contractor will be held absolutely responsible for the care of the work and
whatever appertains thereto from the commencement of same to its final
completion and acceptance.
.2 All work performed under this Contract, unless otherwise specified, shall be
guaranteed by the Contractor for a period of two (2) years from the date of final
acceptance of work by the Railway. The Contractor shall, immediately on receipt
of notice in writing from the Railway, and at their own expense, make good all
defects of whatever nature that may develop during that period.
.3 In the event of the Contractor refusing or neglecting to do so, the Railway may
employ some other person or persons to make good any such defects, loss or
damage, and the expense of employing such person or persons to make good
CN – DESIGN & GENERAL REQUIREMENTS SECTION 01005
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2 SEPTEMBER 2023
GRADING & DRAINAGE PAGE 21 OF 21
MI. 36.79 TO 41.00 HALTON SUB
any such defects, loss or damage, shall be charged to and paid for by the
Contractor.
.2 The primary function of the field representative is to act as a liaison between the
Contractor and the Engineer to facilitate the prosecution of the work required
under the Contract. The presence of the field representative does not relieve the
Contractor of its primary responsibility to perform and complete the work required
under the Contract in a safe and workmanlike manner and in compliance with all
specifications but should the field representative become aware of material or
work that is not in conformity with the requirements of the Contract, he/she shall
have the authority to reject such work.
.3 In the event of any dispute between the contractor and field representatives with
respect to the prosecution of work under the Contract, the representative's
decision or rejection shall stand until the questions at issue can be referred to
and decided by the Engineer.
.5 The field representative shall not perform any duty or management on behalf of
the Contractor.
.1 Payment at the Contract bid price shall include all labour, equipment, and
material to perform the work specified herein.
1.46 INSPECTION
.1 All work and material must be at all times open to the inspection, acceptance or
rejection of the Engineer, their duly authorized representative or Federal
Compliance Officers. The Contractor must give the Engineer reasonable notice
of starting any new work.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
1.1 GENERAL
.1 Submit to the Engineer, for review, design drawings, shop drawings, product data
and samples specified.
.2 Submit shop drawings, product data, and samples as required, pdf submissions
are acceptable.
.3 Clearly identify all shop drawings, product data, and samples with the project title
as it appears on the Railway's drawing title block including subdivision and
mileage.
.4 All shop drawings, product data, and samples shall be reviewed, and comments
shall be provided, stamped, and signed by the Contractor prior to submission to
the Railway.
.5 All such drawings, product data, and samples must be reviewed by the Engineer
before the work involved is started.
.6 Until submission is reviewed, work involving relevant products may not proceed.
.7 Work carried out prior to having shop drawings reviewed shall be at the
Contractor's own risk, and liable for rejection at no cost to the Railway.
.8 The review of shop drawings will not relieve the Contractor of any responsibility
should errors occur in them, and further, the review by the Engineer of any
design drawings or shop drawings submitted by the Contractor shall not form, or
be construed as forming, the basis of a claim for any extra, unless such claim is
specifically made by the Contractor at the time of submission of such drawings
for review and has been agreed to in writing by the Engineer.
.2 Identify details by reference to the sheet and detail numbers shown on the
Contract Drawings.
.3 The Contractor shall complete and submit the following reports/plans and plan
updates within two (2) weeks of the project award date
1 Environmental Two (2) weeks The Contractor shall provide to CN a copy of the
Policy upon project Contractor’s Environmental Policy, that will be
award. consistent with the requirements outlined in the
Environmental Protection Plan.
Management
Plan A redacted plan from Phase 1 is provided with the
document attached to the Contract as outlined in the
Cover Index. This plan will be updated by the
Contractor for Phase 2A.
2 Erosion and 30 days prior Prior to the commencement of any Work that might
Sediment to start of cause erosion and/or sedimentation, the Contractor
Control Plan construction must receive approval from the Engineer for any
proposed revisions to the Erosion and Sediment Control
Plan - General. The proposed revisions shall be outlined
in an Erosion and Sediment Control Implementation
Plan as outlined in 02272- Erosion Control. The Plan
shall include site specific details of when, where and
how the specific erosion control measures will be used.
Changes to the Plan will be consistent with the
requirements outlined in 02272 – Erosion Control and
the Environmental Protection Plan.
specific gravity of
aggregates with the report
from Testing Agency
71 Product Data 14 days prior to the 02825 – Fencing and Road
commencement of the work Signage
72 Shop Drawings for 14 days prior to the 02825 – Fencing and Road
Fencing , gates and road commencement of the work Signage
signages
73 As-Builts Drawings for At the completion of the Work 02825 – Fencing and Road
Fencing and before final inspection Signage
74 Shop Drawings for Steel 14 days prior to the 02844 - Steel Beam Guide
Beam Guide Rail commencement of the work Rail
75 Manufacturer’s Test Data 14 days prior to 02844 - Steel Beam Guide
and Certification commencement of the work Rail
76 Topsoil, Seed and Mulch 14 days prior to the 02912 - Topsoil and Finish
Test Reports commencement of the work Grading
77 Top Soil and Finish 14 days prior to the 02912 - Topsoil and Finish
Grading - Topographical commencement of the work Grading
Survey – Pre-construction
78 Top Soil and Finish After completion of the work 02912 - Topsoil and Finish
Grading - Topographical Grading
Survey – Post-
construction
79 Notification of plant A minimum 10 working days 02970 - Tree and Shrub
material supply sources prior to projected delivery to the Planting
site
80 All packing slips for Within 48 hours of the delivery 02970 - Tree and Shrub
delivery of plant material Planting
81 Warranty - Live stakes Upon Completion of work 02972 - Livestakes
82 Mill Test Certificates for 21 days prior to 03200 - Concrete
Reinforcing Steel Bars, commencement of the work Reinforcement
Stainless Steel
Reinforcing Bars, Steel
Welded Wire
Reinforcement, Splice
Bars and Stainless Steel
Splice Bars
83 Welding Details 21 days prior to 03200 - Concrete
commencement of the work Reinforcement
84 Mechanical Connections 21 days prior to 03200 - Concrete
Details commencement of the work Reinforcement
85 Shop Drawings and 21 days prior to 03200 - Concrete
Schedules commencement of the work Reinforcement
86 As-Builts Drawings for the At completion of the Work 03200 - Concrete
Concrete Reinforcement Reinforcement
87 Deck Joint Assembly 21 days prior to 03203 - Concrete
Shop Drawings commencement of the work Accessories
CN – DESIGN & SUBMITTALS SECTION 01340
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 13 OF 13
MI. 36.79 TO 41.00 HALTON SUB
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
1.1 ACCESS
.1 The Contractor shall be limited to using access to the site as shown on the
drawings or as directed. Provide and maintain adequate access to the project
site.
.2 Roads constructed between any points in the working area for the convenience
of the Contractor, for the conveyance of material or otherwise, shall be at the
Contractor's own expense and risk.
.4 The Contractor shall comply with all Municipal and Provincial Regulations,
Ordinances, Bylaws, etc., pertaining to the usage of Municipal and Provincial
roads, and shall protect the Railway against any and all claims arising out of their
non-compliance with the above Ordinances, Regulations, and Bylaws.
.5 Prior to using any Municipal and/or Provincial roads, the Contractor must provide
the Engineer with documentation that he/she has advised the Municipal and/or
Provincial Authorities of their haul route and has received authority to use the
roads on their haul route for purposes of transporting fill material.
.7 The Contractor shall construct adequate access roads for the conveyance of
equipment, material, disposal, etc. that they deem necessary for their operations.
On completion of the work, CN and private property shall be restored to their
original condition as approved by CN and private landowners.
.8 The Contractor is not permitted to enter into an agreement with local landowners
for any additional access to property that they deem necessary for their
operations.
.9 On completion of the work, provide a signed clearance from the landowner that
the areas used have been cleaned up to the landowner’s satisfaction. A copy of
the clearance must be provided to CN prior to final payment.
.10 In cases of dispute between the Contractor and the landowner, it will be expected
that the Contractor shall reach a favorable settlement with the landowner.
CN – DESIGN & TEMPORARY FACILITIES SECTION 01500
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 4
MI. 36.79 TO 41.00 HALTON SUB
.11 If the Contractor cannot reach a settlement with the landowner, then CN shall
arbitrate an agreement binding on the Contractor to the satisfaction of and at no
cost to CN.
.12 Secure the site with fencing and gates to prevent public access to the site.
Maintain access to all driveways in the vicinity of construction.
.1 The Contractor shall provide for the use of their employees, the necessary
sheltered, heated facilities. This Site Office shall be included in the Infrastructure
Management Plan as outlined in 01340 Submittals.
.1 The Contractor shall provide, for the sole use of the Engineer, a weatherproof
temporary modular field office which shall be at least 7.3m x 18.3m with five
compartments (four offices and one meeting room) and furnished with the
following:
.4 1 plan rack;
.10 Indoor washroom facility including toilet and sink, c/w separate water and
wastewater tanks to be regularly maintained by the Contractor.
.11 4 X 4 pickup truck with four seats for the use of CN’s site representatives
on site within the construction limits. The vehicle shall be parked on-site
daily for the use of CN’s site representative.
.2 All furniture and equipment supplied shall be in a new or near new condition,
acceptable to the Engineer.
.3 The office shall be supplied with adequate air conditioning, heat, light, weekly
cleaning, winter snow removal, and clearing/salting of stairs and walkways, care
and cost of which shall be borne by the Contractor.
CN – DESIGN & TEMPORARY FACILITIES SECTION 01500
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 4
MI. 36.79 TO 41.00 HALTON SUB
.4 Prior to any pre-construction meetings being attended by CN and prior to the
start of work, the office shall be set up on-site, at a location agreeable to the
Engineer, with all appropriate furniture in place. The office must be complete with
temporary power (if not fully hooked up). No work on-site will be authorized until
this is completed.
1.4 COMMUNICATIONS
.1 The Contractor shall install in the Engineer’s site office a colour printer/scanner /
fax machine capable of handling letters, legal and ledger-size paper. The
machine must be installed immediately after the work is commenced. The
Contractor shall pay all charges for the machine, including paper and toner
supply, except for long-distance charges incurred by the Engineer.
.3 The Contractor shall supply the Engineer with a two-way radio for their sole use
during the contract for communicating instructions to the Contractor and their
workforce. The foreman as well as the superintendent shall also be equipped
with a two-way radio so that the Engineer can be in communication with them at
all times.
.1 Provide adequate weathertight sheds with raised floors, for storage of materials,
tools, and equipment that are subject to damage by weather.
.3 All sanitary facilities for the workforce shall be in accordance with governing
regulations and ordinances.
.4 Provide a separate sanitary facility within the Engineer’s office for the sole use of
Railway representatives.
CN – DESIGN & TEMPORARY FACILITIES SECTION 01500
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 4
MI. 36.79 TO 41.00 HALTON SUB
.5 Post notices and take such precautions as required by local health authorities,
especially regarding COVID-19. Keep the area and premises in a sanitary
condition.
.1 The Contractor must make all arrangements with the local Utility company for the
supply and installation of temporary light and power required in carrying out the
Contract, and pay all costs involved in connection therewith:
.2 The generator must be a quiet type with a noise level at the rated output
not exceeding 60 dBA. The noise level at ¼ of the rated output must be
less than 55 dBA; and
.3 The Generator shall be CSA approved and shall bear CSA labels.
.2 The Contractor must make all arrangements and pay for all water required for
construction and drinking purposes, and supply and install all necessary piping
and connections.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
.2 In the event of a conflict between any provisions of the above authorities, the
most stringent provision will apply.
.3 Reflective apparel must be properly fastened and closed around the body
to minimize the possibility of catching on equipment and causing injury.
.1 A fixed Lump Sum amount has been attributed to this contract for the
performance of safety compliance as determined by the Engineer.
.2 Once the Contractor has completely mobilized to the Site, a maximum aggregate
amount as indicated in the Form of Tender shall be attributed conditional to FULL
compliance to the safety clauses identified in the Tender.
CN – DESIGN & SAFETY REQUIREMENTS SECTION 01545
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 10
MI. 36.79 TO 41.00 HALTON SUB
.3 If the Contractor does not fully comply with the requirements or the direction of
the Engineer in a reasonable time period (as determined by the Engineer) during
the given week then the full amount for that given week will be cancelled from the
aggregate amount of the Form of Tender.
.5 The aggregate amount shown in the Form of Tender shall remain fixed for this
contract and in case of extension of contract no additional remuneration will be
awarded.
.6 Incentive payments are an incentive for Contractor compliance and are not
allocated to fund any portion of the work to be completed to get or remain in
compliance.
.1 At the work site, provide and maintain readily accessible first aid equipment and
installations required by the Workers’ Compensation Act, and all safety and
lifesaving equipment appropriate to the nature of the works.
.1 The Contractor shall comply with CN Annex “D” – “Safety Guidelines for
Contractors”, Clauses 4.2.1 and 4.2.2 before they begin any construction activity
on the site. Authority to commence construction will be authorized only after this
is completed.
.2 The Contractor shall designate a full time safety officer responsible for enforcing
the safety program at the site for the duration of the work and shall indicate to CN
in writing the name of that person as well as their alternate.
.3 The Contractor shall ensure that all employees and all persons admitted to the
work site attend a daily briefing session as outlined in CN Appendix “D” – “Safety
CN – DESIGN & SAFETY REQUIREMENTS SECTION 01545
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 10
MI. 36.79 TO 41.00 HALTON SUB
Guidelines for Contractors”, Clause 4.2.3 and 4.2.4, and that they comply with
the safety program and all applicable laws, regulations and codes.
.5 The Contractor shall ensure that all contractors and sub-contractors working on
CN property, arrange to have their companies and their employees who will be
entering upon CN property registered as to having eRailsafe Canada registration,
background check, training and testing available at www.erailsafecanada.com,
maintain an up-to-date list of all such trained employees on site and ensure all
employees carry the identification card provided in a readily available location for
presentation when requested. The Contractor shall pay all costs ($120.00 US
one time company set up and $105.00 US per person) associated with having all
participants have the background check and take the web-based training and
registration. Authority to commence construction will be authorized only after this
is completed:
.1 ALL truck drivers, material supply drivers, visitors and service providers
who will be accessing the Limits of Construction more than once shall
complete the on-line “Contractor Orientation for Railroads” course found
at www.contractororientation.com prior to entering the Limits of
Construction. The Contractor shall pay all costs ($15 USD per person)
associated with having all participants take the web-based training and
registration. Upon request by CN or its designated representative, the
Contractor shall supply a list of qualified personnel to CN confirming its
compliance with the above; and
.2 Truck drivers, material supply drivers, visitors and service providers who
shall enter the Limits of Construction only once and shall utilize the
temporary track crossing, or traverse the Limits of Construction, but do
not have Contractor Safety Orientation qualification, shall be escorted by
the General Contractor while on the Limits of Construction.
.7 The Contractor shall provide the location and meeting room for Start-up Meetings
along with any audio and video equipment required by CN.
.8 Ensure that all workers on the site be qualified to perform the work in a safe
manner.
CN – DESIGN & SAFETY REQUIREMENTS SECTION 01545
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 10
MI. 36.79 TO 41.00 HALTON SUB
.9 Carry out frequent work site inspections to ensure compliance with the required
safety measures.
.10 Conduct weekly Safety Meetings and provide minutes of those meetings to the
Engineer.
.11 Send the notice of job start and completion, as required by the MOL and / or
WSIB.
.1 Contractor’s Obligations:
.2 Employee qualifications;
.5 Employees who are not on the above list and whose proof of
qualifications are not provided will not be allowed on CN property;
.7 Contractors must ensure that their employees are briefed and are
provided current copies of CN’s standards and policies including
the most recent updates.
CN – DESIGN & SAFETY REQUIREMENTS SECTION 01545
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 10
MI. 36.79 TO 41.00 HALTON SUB
.3 In order to allow new employees access to a CN work site, the following
process must be followed:
.1 This does not preclude other training requirements specific to the position
such as crane, welder, machine operation or other trade skills as the job
may require; and
.2 The Contractor shall post this plan in a conspicuous place and ensure that all
persons having access to the job site are trained on implementation of the plan
prior to having access to the site.
.1 Emergency phone numbers for police, fire, ambulance, hospital and utility
companies;
.7 All material safety data sheets for materials used on site; and
.4 The Construction Emergency Response Plan shall also include spill response
procedures as outlined in the EPP and 01560 Environmental Protection, related
to training, handling and safe storage and disposal of materials that may be
harmful to employees, the public and the environment.
.2 The Contractor shall notify the Engineer of changes to the list, in writing,
and provide relevant Material Safety Data Sheets; and
.1 Provide flag persons to protect vehicular and pedestrian traffic during the
operations, at any time when workers or equipment could endanger such traffic,
all to the complete satisfaction of the Engineer and any other authority having
jurisdiction at this location.
.2 Accept responsibility for any damage to vehicles and damage and injury to
pedestrians’ occupants of vehicles resulting from the operations or the operating
of equipment by others. Provide adequate protection to the satisfaction of the
Engineer.
.4 Supply, erect and maintain the traffic control measures (signs, cones,
delineators, barriers) when construction operations may affect vehicular or
pedestrian traffic.
.1 The Contractor shall not be permitted to cross the track(s) with vehicles or
equipment, except on a CN approved temporary construction crossing.
.2 If crossing the tracks is deemed necessary by the Engineer, the Contractor shall
obtain a License for Temporary Crossing from CN and would only be permitted to
use the crossing when a CN flagman is onsite and a crossing safety plan is
agreed to by CN and the Contractor. CN would be responsible for building the
temporary crossing. All costs associated with the construction and removal of the
crossing shall be the responsibility of the Contractor:
.1 Have a level gradient on either side for a distance of 8m from nearest rail.
or not less than the maximum length of vehicle using it;
.1 Supply and install gates and stop signs at 12 feet from the gauge side of
rail on each side of the tracks;
.4 Supply, place and compact granular material or clear stone (as directed
by CN) within the 8 foot space between the mainline tracks (for 2 or more
tracks). Granular material/clear stone shall be placed on top of filter fabric
in order to prevent ballast contamination;
.6 Maintain the crossing surface and keep the flangeways clear at all times.
.6 The Contractor shall be responsible to provide and install any required protection
of CN’s and Bell Canada (360 Networks) underground cables at the approaches
CN – DESIGN & SAFETY REQUIREMENTS SECTION 01545
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 9 OF 10
MI. 36.79 TO 41.00 HALTON SUB
to the crossing, as directed and supervised by CN and Bell Canada. Refer to
Section 02200 Signal & Optic Cables for specific requirements for work near and
protection of cables.
.7 Use of the crossing shall be done only in the presence of a CN flag person. The
crossing gates shall be secured, with a CN lock, at the end of each working day.
.8 Steel tracked equipment shall not come into contact with the rails at any time
when traversing the crossing, as this could result in a malfunction of CN’s train
signal system. The Contractor shall supply and place rubber matting/wood planks
to protect the rails during the use of the crossing by steel-tracked equipment.
.9 The Contractor shall make all attempts to ensure that the track ballast remains
free of contamination from the deposit of mud, soil,s and other fines from
construction operations. The presence of fines in the track ballast traps water,
which results in poor track surface and necessary train speed reductions, which
will not be tolerated by CN. Should ballast contamination be evident upon
removal of the temporary track crossing, the Contractor shall be responsible for
all costs for CN to repair the track structure.
.10 Upon notice from CN, the Contractor, at their cost, may be required to remove
and reinstall the temporary crossing to allow CN track maintenance.
.11 On completion of the work, the Contractor shall restore the track to its original
condition, all to the satisfaction of the Engineer.
.1 The Occupational Health and Safety Act (OHSA) imposes a duty on CN to inform
the Contractor of any Designated Substances present at the Work Site, where it
is reasonable for CN to have known about the substance.
.2 The following are currently Designated Substances. These are subject to special
regulations under OHSA:
.1 Asbestos;
.2 Lead;
.3 Ethylene oxide;
.4 Mercury;
.7 Benzene;
.8 Arsenic;
CN – DESIGN & SAFETY REQUIREMENTS SECTION 01545
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 10 OF 10
MI. 36.79 TO 41.00 HALTON SUB
.9 Coke oven emissions;
.11 Isocyanates.
.3 The Contractor shall take appropriate health and safety precautions to protect
human health and the environment, including recommending additional
investigations or sampling if deemed appropriate. Such recommendations are
subject to acceptance by CN.
.4 Asbestos:
.2 The Contractor shall cease Work in the area and barricade the area to
prevent entry until such time as CN confirms the presence or absence of
asbestos; and
.5 Mould:
.2 The Contractor shall cease Work in the area and barricade the area to
prevent entry until such time as CN confirms the presence or absence of
mould; and
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
1.1 GENERAL
.2 The Contractor shall note that the presence of CN Personnel on site is for the
protection of the Railway’s operations and interests.
1.2 DEFINITIONS
.1 Working Area: A portion of track within the limits of exclusive track occupancy
(working limits) in which movement authority of trains and other equipment is
restricted by the Protecting Foreman. Working limits are established using Mile
posts and will be expressed in whole miles and must be established by 16:00 the
previous day as agreed to between the Protecting Foreman and Contractor.
.3 Flag Person or Employee in Charge (EIC): The CN employee responsible for the
safety, instruction, performance and protection of all employees under their
supervision, when the nature or size of the work is such that the 42 Foreman
cannot personally observe, advise and supervise all persons engaged in the
work.
.1 The 42 Foreman must receive written confirmation from the Rail Traffic Controller
that the appropriate orders stating time and work limits have been given to all
trains that may enter the limits. Until such confirmation is received, flags may not
be placed, and no work is able to take place on site.
.5 Separated work groups are required when flagman cannot visually observe or
maintain effective communication. When Separated Work Groups are required
(no more than four individual groups are permitted under one 42 Foreman
control), each group shall have assigned a Flag Person.
.8 The Contractor shall expect to be sharing Rule 42 limits and flagging protection
with CN work groups.
.9 Each separated work group shall have a responsible person equipped with
portable two-way radio(s) to communicate with the CN Flag Person. The
Contractor’s responsible person will be charged with ensuring that the separated
work group and all associated trucks/deliveries comply with the track-clearing
requirements described in this section.
.10 Portable two-way radios shall be furnished by the Contractor and shall be
Kenwood TK3302 or approved equivalent. The Contractor shall provide each CN
Flag Person with a portable two-way radio for communication with the
responsible person(s). The Contractor must ensure that all two-way portable
radios communicate on the same frequency and that adequate supply of
batteries are on hand to ensure no interruption in communications.
.11 The Contractor shall be responsible for staffing the project with gate keepers and
truck/delivery escorts at all access points to the CN ROW. Each gate keeper and
truck/delivery escort must be equipped with a portable two-way radio capable of
communication with the CN Flag Person.
CN – DESIGN & FLAGGING AND TRACK PROTECTION SECTION 01546
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 7
MI. 36.79 TO 41.00 HALTON SUB
1.4 TRACK CLEARING PROCEDURE
.1 Trains approaching a red flag will contact the 42 Foreman, to request instructions
for entering and passing through the working limits protected by the Rule 42.
.2 Before permitting the train to enter the working limits, the 42 Foreman will:
.1 Advise all Flagmen of the separated work groups (again, no more than
four) that a train will be passing through the working limits;
.4 Equipment which is stopped must remain stopped until the full train has
passed the entire Rule 42 limits and authority from the Flag Person to
resume work has been received:
.1 Buckets for excavators or other equipment that has a boom must
remain on the ground in parallel position to the nearest track and
at distance at least 19 ft from the nearest rail until the entire train
has passed the entire Rule 42 limits and advised by Flag Person;
and
.2 To eliminate the possibility of unexpected movements after a train
has been cleared through the Rule 42 limits, all equipment and
trucks must be turned off/ locked out, or the operator/driver must
exit the piece of equipment/truck.
.5 Before canceling the authority of before the time limits have expired on a
Rule 42, the Foreman will contact the Flagmen of separated work groups
and receive confirmation that all work has been stopped and all
employees and machines are clear of the track;
.6 If comfortable with the rail traffic and work conditions, the 42 Foreman
may also act as a Flagman, solely at their discretion;
.7 This Track Clearing Procedure applies whether the train is passing on the
adjacent track or other track; and
.8 As the work progresses and the Engineer gains familiarity and confidence
in the Contractor’s safety and train clearing performance, written
provisions may be made modifying this requirement by allowing some
equipment that cannot foul an adjacent track, to continue working or
traveling.
CN – DESIGN & FLAGGING AND TRACK PROTECTION SECTION 01546
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 7
MI. 36.79 TO 41.00 HALTON SUB
.3 The Contractor is advised that non-work related radio communications will not be
tolerated, as it may interfere with the train clearing communications.
.1 Note that the works shall be carried out adjacent to the Railway's operating
tracks. CN Flag Persons must be present at all times when work progresses
within the CN ROW. The presence of CN Flag Persons in no way relieves the
Contractor from liability for damage or disruption to CN property, infrastructure or
rail traffic caused by their operations.
.2 All work executed by the Contractor shall not interfere with the continued, safe
movement of rail traffic. Any object waved violently by anyone on or near the
tracks is a signal for trains to stop. The Contractor shall be liable for all costs,
direct and indirect, incurred by CN as a result of damage, disruption or
inconvenience to CN’s operations, property or infrastructure, caused by the
Contractor’s operations.
.3 The Railway will provide a maximum of four (4) Flag Persons, at no cost to
the Contractor, up to the Contract Completion date specified in Annex “C”. After
this date, or if the Contractor requires additional Flag Persons for their
operations, these extra Flag Persons will be provided, if available, at a rate of
$205/hour, minimum 8 hours on site and 2 hours travel/set up per Flag Person
per day, maximum 12 hours per person, per day, the cost of which will be
automatically deducted from the amounts due the Contractor in progress
payments.
.4 The Contractor will be responsible for ensuring that construction operations are
carried out without interfering with the continued safe movement of rail traffic.
The Contractor will be liable for the cost of train delays and for the cost of repairs
to any rail, ties, ballast and signal appliances required as a result of damage
caused by their operation.
.5 Give the Engineer at least five (5) working days’ notice of the hours within which
work is to be carried out in order that protection may be provided. Time wasted
unnecessarily by the Railway personnel due to the Contractor will be charged
against the Contractor.
.6 Ensure that a responsible person is present at all times to whom the Railway
personnel will issue orders regarding work near the tracks. Comply immediately
with such orders and instructions.
.7 The Contractor shall take into consideration downtime to permit the passage of
trains on the adjacent tracks during construction of all work under this Contract.
Downtime calculations do not include the daily job briefings and
mobilization/demobilization. The Contractor shall have no claims for additional
payment for delays.
.8 The Contractor shall expect that 25 to 30 trains may be operated during any 24-
hour period; and
CN – DESIGN & FLAGGING AND TRACK PROTECTION SECTION 01546
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 7
MI. 36.79 TO 41.00 HALTON SUB
.10 Red colour shall not be used for safety helmets, safety vests or survey markers
on the CN ROW in order to avoid conflict with CN Operational Practice. Other
highly visible colours such as orange are acceptable.
.12 Metal measuring tapes or other metal appliances are not to come into contact
with the rail of any track. Walking or stepping on a rail, switch, interlocking
machinery or connection is prohibited.
.13 The CN Flag Person may be required to leave the job site at any time, without
notice, to provide emergency services at other locations. In this event, the
Contractor shall cease all work within the ROW and immediately exit CN property
prior to the CN Flag Person leaving the site. The Contractor shall not enter onto
CN’s property until such time a Flag Person is present.
.1 At all locations where there is a possibility of trees, rock or other debris falling on
the tracks, provide track protection such as timber mats or an approved
equivalent in order to prevent possible damage to rail, ties and ballast.
.3 The Contractor shall be liable for all costs, direct and indirect, incurred by CN due
to the settlement of track(s) or any other problems related to CN’s operations,
property or infrastructure, that occur as result of the Contractor’s operations, for a
period of two (2) years from the date of completion of the work.
.4 The Contractor shall be responsible for all costs associated with delays or
inconvenience to the Contractor’s operations as a result of:
.1 CN’s requirements;
.1 In order to ensure the continued safe movement of rail traffic, certain restrictions
shall be imposed on the construction operations. Without in any way limiting the
generality of the foregoing statement, the following are some of the limitations or
restrictions that shall be imposed.
.2 Confine all work activities to daylight and evening hours, except where noted
otherwise, or as directed by the Engineer, and the following restrictions:
.1 Confine all work activities to between 07:00 and 17:00. When night work
or work outside of the period is required, notice must be provided to the
Engineer with a minimum of one (1) month notice;
.2 Working shift is not to exceed 10 hours per day for activities on site were
flagging is required. Flagging will not be provided for more than 10 hours
per day on site. The working shift will include the daily job briefing and
mobilization/demobilization from the work location(s). Daily downtime
calculation does not include the daily job briefing and
mobilization/demobilization; and
.3 All men and equipment must stop working at the direction of the CN Flag person
and remain stopped until the entire train has passed through the Rule 42 limits.
.1 Observe all necessary precautions and provide, erect, and maintain suitable
signs, barricades, and lights to protect all persons from injury and all vehicles
from damage during the progress of the work, all to the approval of the Engineer
or any authority having jurisdiction at this location.
.3 Install temporary gates, approved by the Engineer, to prevent use of the access
points by unauthorized personnel and keep gates locked, with Contractor’s lock
and lock provided by the Engineer, when access points are not in use.
CN – DESIGN & FLAGGING AND TRACK PROTECTION SECTION 01546
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 7 OF 7
MI. 36.79 TO 41.00 HALTON SUB
.4 Site access points shall only be used by equipment when flagging protection has
been provided by Railway personnel and the Contractor shall provide a full-time
gate keeper at each access point while being used.
.6 On notification that a train is approaching, the gate keeper shall block off the
access point and not allow any further entrance to the site and report to the
Contractor’s Responsible Person that the access point is closed, and must
remain closed until notified that it is safe to re-open the gate.
.7 It shall be the Contractor’s responsibility to ensure that all gates are closed and
locked at the end of each shift.
.2 Payment for the Work of this Section shall be deemed incidental to and included
in the various lump sum and unit prices included in the Form of Tender.
GENERAL CONDITIONS
The General Conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
.1 Except for the work to be executed under scheduled track closures, all other work
executed by the Contractor shall be carried out without interfering with the
continued safe movement of rail traffic. The Contractor shall be liable for the cost
of train delays and for the cost of repairs to the track required as a result of
damage caused by their operation.
.2 CN cannot guarantee that the scheduled start or finish times of the track closures
can be provided due to train schedules; the Contractor shall have no claims for
additional payments for delays or standby time.
.3 The Contractor shall note that track closures may be scheduled on holidays,
weekends, and during the night. Confirmation of the dates and times of the track
closures by CN will be supplied to the Contractor one (1) week prior to the work
but may be subject to cancellation or re-scheduling by the Railway at any time
prior to the track closure.
.4 For night work activities, the Contractor shall supply and maintain adequate
temporary lighting and associated generators in the Contract area such that all the
work in these areas can be carried out safely manner. Generators used shall be
the quietest available. At no time shall lights be directed towards the railway tracks.
No separate payment will be made for temporary lighting.
.5 At least twenty-four (24) hours prior to the scheduled track closures, the Contractor
shall have all resources and equipment in place to carry out the work for that
particular closure. If, in the opinion of the Engineer, any of the above is
unsatisfactory, the Engineer will cancel and reschedule the temporary track
closure, and the Contractor will pay all costs associated with the cancellation and
rescheduling.
.6 The Contractor shall note that, from time to time, CN or other work in the area may
impact on the scheduled closures and may cause cancellation of the closure or
reduction of the hours allowed. The Contractor shall have no claims for additional
payment for delays.
.1 The Contractor shall provide at least one (1) month written notice to CN prior to
the works requiring Track Closures.
CN – DESIGN & TRACK CLOSURES SECTION 01550
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2 SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 3
MI. 38.72 TO MI. 41.00 HALTON SUB
.2 The Contractor shall provide a detailed Work Plan Method complete with an
hour-by-hour schedule for each location to include the following information:
.3 Materials to be used
.5 Back up equipment
.1 Installation of new culvert sections under the existing main track at the
following locations:
.1 Mile 37.00
.2 Mile 37.20
.3 Mile 37.63
.4 Mile 37.98
.4 The Contractor is referred to Clause 3.1 Liquidated Damages of this Section with
regards to overrunning and any additional track closures required to complete the
works.
.5 All work requiring track closures will be allowed between the following times: from
approximately 22:00 to 06:00 only.
.6 The Contractor will have up to eight (8) hours to complete the work, including one
(1) hour at the beginning and one (1) hour at the end for CN to facilitate track work,
and all work must be completed by the end of the track closure.
.1 It is agreed by the parties to the contract that in case all the work called for under
each track closure is not finished or completed within the allotted time specified,
a loss or damage will be sustained by the Railway. Since it is and will be
impracticable and extremely difficult to ascertain and determine the actual loss or
damage which the Railway will suffer in the event of and by reason of such delay,
the parties hereto agree that the Contractor will pay to the Railway the following:
.2 These liquidated damages will be automatically deducted from the amounts due
to the Contractor in the progress payments.
.3 It is also agreed that this amount is an estimate of the actual loss or damage to
the Railways which will accrue during the period in excess of the prescribed track
closure termination and that this is without prejudice to CN's other recourse
relative to failing to complete the work and returning the tracks back into service.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
The Milton Logistics Hub Project is situated within the treaty lands and traditional territory of the
Mississaugas of the Credit First Nation (also referred to below as the “Treaty Holder”). The Six
Nations of the Grand River and the Huron Wendat First Nation also have interest in the area (all
three Aboriginal groups collectively referred to hereinafter as the “Identified Nations”). CN is
committed to ensuring and facilitating meaningful economic opportunities and participation in
the Project by these Nations, as a means of reconciliation and in recognition of the location of
the Project within these lands. Lead contractors should embrace and have specific plans to
fulfill CN’s commitment to such meaningful participation.
Consistent with our commitments, CN expects lead contractors to engage directly with the
Mississaugas of the Credit First Nation, as the Treaty Holders, to discuss opportunities for
meaningful economic involvement in the Project as described below. This is not meant to
exclude participation from either the Huron-Wendat or the Six Nations of the Grand River.
Lead contractors are required to demonstrate in their submissions how they will incorporate
meaningful Indigenous participation in the following areas:
Lead contractors are also required to demonstrate in their submissions how they will
meaningfully engage with the Identified Nations.
In order to advance your efforts clearly in the RFP submissions, we have provided the contact
information so you are able to reach out directly to the MCFN to discuss how
they can participate in your submission.
Huron-Wendat:
Maxime Picard
Manager economic development and major projects
maxime.picard@cnhw.qc.ca
1-418-843-3767
Robinn Vanstone
Lands and Resources, Six Nations of the Grand River
rvanstone@sixnations.ca
Work: 519-753-0665 ext. 5433
Cell: 226-388-0284
1.1 GLOSSARY
.12 “Environmental Site Inspector” has the meaning given in Sections 1.5.2
and 1.5.3;
.13 “Final List of Approval Conditions (January 21, 2021), form the Decision
Statement issued under Section 54 of the Canadian Environmental
Assessment Act, 2012 (January 21, 2021) issued to Canadian National
Railway Company for the Milton Logistic Hub Project by the Impact
Assessment Agency of Canada;
.14 “Fisheries Act” means Fisheries Act (R.S.C., 1985, c. F-14), as amended
from time to time;
.15 “Impact Assessment Act” means the Impact Assessment Act (S.C. 2019,
c. 28, s. 1), as amended from time to time;
.16 “Impact Assessment Agency of Canada” leads all impact assessments for
major Federal projects under the Impact Assessment Act;
.19 “Migratory Birds Convention Act (1994)” means the Migratory Birds
Convention Act, 1994 (S.C. 1994, c. 22), as amended from time to time;
.20 “Monthly Compliance Report” has the meaning given in Section 1.5.4;
.21 “No-go zone or area” means Protected Sensitive Natural Area and
Temporarily Protected Area as identified on Contract Drawings;
.22 “Clean Equipment Protocol for Industry” means the Ontario Invasive
Plant Council’s Clean Equipment Protocol for Industry (June 2016);
.23 “Ontario Regulation 406/19, as amended” means the O. Reg. 406/19: On-
Site and Excess Soil Management filed December 4, 2019 under
Environmental Protection Act, R.S.O. 1990, c. E.19;
.29 “Species at Risk Act (Canada)”, means the Species at Risk Act, S.C.
2002, c. 29, as amended from time to time;
.33 “Waste Audit and Reduction Program and Source Separation Program”
has the meanings given in Ontario Regulations 102/94 and 103/94, made
under the Environmental Protection Act (Ontario).
.1 The Contractor shall comply with any applicable laws, rules or regulation of any
public authority, orders of a Court of competent jurisdiction and CN directive with
respect to the contracted Work. The Contractor shall also indemnify and hold
harmless CN or CN’s designated Environmental Monitor from all damages and
liabilities assessed against CN as a result of Contractor non-compliance therewith.
.2 The Contractor shall ensure and warrant that all employees possess and maintain
in effect all licenses, permits, authorizations, insurance and any other documents
that the acts and/or regulations pertaining to environmental protection require it to
have for the performance and the duration of contracted Work.
.3 The Contractor shall be solely responsible for the cost of all Work carried out to
correct any environmental contamination or non - compliance caused by the
Contractor, their subcontractors or employees on CN property. If the Contractor
CN – DESIGN & ENVIRONMENTAL PROTECTION SECTION 01560
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 26
MI. 36.79 TO 41.00 HALTON SUB
fails to correct any environmental contamination resulting from the contracted Work,
CN may perform such work by its employees or agent. CN may charge the
Contractor for all cost incurred by CN in correcting such environmental
contamination, plus thirty percent (30%) for overhead, and the Contractor shall pay
CN’s invoice or invoices for such cost under the same terms and condition as would
otherwise apply in the contracted Works for Contractor invoices to CN. In the event
such remedial work is carried out by any public authority, the cost shall be borne by
the Contractor.
.1 The Contractor shall be fully familiar with and comply with all applicable laws.
.3 The Contractor shall ensure that its actions during all phases of construction are
considered in a careful and precautionary manner, promote sustainable
development, are informed by the best information and knowledge including
community and Indigenous knowledge, available at the time the Proponent takes
action, are based on methods and models that are recognized by standard-setting
bodies, are undertaken by qualified individuals, have applied the best available
economically and technically feasible technologies to achieve continuous
improvement and meet all engineering requirements for safe railway and facility
operation.
.5 The Contractor shall review and be fully familiar with the documents attached to the
Contract as outlined in the Cover Index. Final documents will be provided to the
successful bidder. The Contractor shall comply with the requirements included in
the attached documents:
.1 A fixed Lump Sum amount has been attributed to this contract for the successful
performance of environmental compliance as determined by the Engineer and CN
Environmental Monitor.
.2 Once the Contractor has completely mobilized to the Site, a maximum aggregate
amount as indicated in the Form of Tender shall be attributed conditional to FULL
compliance to the Clauses of this Section.
.3 If the Contractor does not willfully comply with these requirements or the direction of
the CN Environmental Monitor in a reasonable time period (as determined by the
Engineer and CN Environmental Monitor) during the given month, then the full
amount for that given month will be cancelled from the aggregate amount of the
Form of Tender.
.5 The aggregate amount shown in the Form of Tender shall remain fixed for this
contract and in case of extension of contract no additional remuneration will be
awarded.
CN – DESIGN & ENVIRONMENTAL PROTECTION SECTION 01560
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 8 OF 26
MI. 36.79 TO 41.00 HALTON SUB
.6 Incentive payments are an incentive for Contractor compliance and are not
allocated to fund any portion of the work to be completed to get or remain in
compliance.
.1 The Contractor shall review and adhere to all of the requirements outlined in the
Environmental Protection Plan, Updated Consolidated Table of Mitigation Measures
and Proponent Commitments and Final List of Approval Conditions and other
documents outlined in Section 1.3.
.3 The responsibilities of the Environmental Site Inspector shall include daily start-up
meetings to coordinate project construction activities, including:
.4 The Contractor shall document, on a monthly basis, compliance with the Final List
of Approval Conditions and the Updated Consolidated Table of Mitigation Measures
and Proponent Commitments in accordance with 01340 - Submittals. The Monthly
Compliance Report shall document:
.6 The Contractor shall keep on-site a list of hazardous materials, toxic products, Work
procedures and contaminants used in the Work and clearly display at the Site the
lists and Material Safety Data Sheets (MSDS) and provide to the CN Environmental
Monitor.
.7 Prior to any on-site activities, the Contractor and any sub-contractors shall attend
an Environmental Orientation, to be developed by the Engineer and the CN
Environmental Monitor. The Contractor will be responsible for ensuring all personnel
on the Site are informed on the contents of the Plans outlined in 1.3.5 and the
Environmental Orientation program. The Contractor must ensure that all new
employees and/or subcontractors receive the Environmental Orientation training
prior to them conducting any activity on site.
CN – DESIGN & ENVIRONMENTAL PROTECTION SECTION 01560
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 10 OF 26
MI. 36.79 TO 41.00 HALTON SUB
.8 Environmental Orientation will include but not be limited to Site Specific Training for:
Black Ash (expected to become a protected Species at Risk during the contract period)
.3 The Engineer and/or CN’s Environmental Monitor will notify the Contractor of any
complaints received. It is the responsibility of the Contractor to rectify or develop a
CN – DESIGN & ENVIRONMENTAL PROTECTION SECTION 01560
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 11 OF 26
MI. 36.79 TO 41.00 HALTON SUB
plan with the Engineer and/or CN’s Environmental Monitor to rectify the complaint
within 24 hours of receiving the complaint.
.2 The Contractor shall implement and maintain stabilized construction access and
roadways to reduce tracking of construction sediment (mud and dirt) onto public
roads by construction equipment. A sweeper needs to be kept onsite to routinely
clean public roads, as necessary.
.4 The Contractor shall take all reasonable measures to prevent accidents and
malfunctions that may result in adverse environmental effects and mitigate any
adverse environmental effect from accidents and malfunctions that does occur.
.5 The contractor shall comply with and maintain the Accident & Malfunction
Response Plan during all phases of the construction. The Contractor shall submit
any updates to the Accident & Malfunction Response Plan to the CN
Environmental Monitor and the Engineer in accordance with 01340-Submittals.
.6 The Contractor shall not use salt for de-icing or traction control purposes during
construction. Except for the use of sand, any other non-salt de-icing methods for
traction control must be approved to the satisfaction of the Engineer and CN’s
Environmental Monitor. If salts such as calcium chloride are deemed necessary,
the Contractor must develop a Salt Management Plan to the satisfaction of the
Engineer and CN’s Environmental Monitor. Once approved internally, the
document will be circulated by CN to regulatory agencies before approval is
permitted for use of the material on the site. This process will take a minimum of
4 weeks.
.1 The Contractor shall be solely responsible and liable for, without being limited to, all
testing documentation, clean up, reporting, repairs, removal, damages and
associated costs, and any other actions arising from any spill or incident that results
in release of a contaminant.
.2 The Contractor, within 15 days of project award, shall provide the Engineer with an
updated Accident & Malfunction Response Plan based on the version from Phase 1.
This Phase 1 version will be provided by CN to the Contractor upon project award.
CN – DESIGN & ENVIRONMENTAL PROTECTION SECTION 01560
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 12 OF 26
MI. 36.79 TO 41.00 HALTON SUB
.3 The Contractor shall ensure all staff are trained on the Accident & Malfunction
Response Plan through an employee education and orientation program. Copies of
training records shall also be provided to the Engineer.
.4 All supervisory personnel will be trained in and aware of the requirements of the
WHMIS program. All machine operators will be provided with and trained in the use
of emergency spill kits.
.6 The Contractor shall store bulk quantities of combustible and flammable materials in
designated containment areas at least six meters away from the property limits.
.7 Machinery should arrive onsite in clean and good working conditions and be free of
fluid leaks.
.8 The Contractor shall conduct and record daily inspections on all equipment for
review by CN’s Environmental Monitor and the Engineer. Issues arising from the
inspection will be resolved immediately.
.9 The Contractor will not be permitted to perform any major equipment repair onsite.
Minor repairs (e.g., hydraulic hose repair) will be permitted onsite within the
approved temporary workspace.
.10 Oil changes, lubricating and fueling of mobile construction equipment will only be
completed at designated, contained locations approved by CN’s Environmental
Monitor.
.11 Fuel tanks stored on the property for equipment fueling purposes must be double
walled tanks, appropriately labeled and protected with vehicle impact barriers.
Designated fueling locations must be located 30 metres from the top of bank of the
closest waterbody, at least six meters away from the property limits and at a
contained location approved by the Engineer and CN’s Environmental Monitor. The
Contractor shall use ultra-low Sulphur fuel.
.12 Spent oils, lubricants and filters will be collected in covered bins located onsite and
disposed of at licensed disposal facilities.
.13 All fuel and service vehicles will carry a minimum of 25 kilograms (kg) of suitable
absorbent and spill contingency materials.
.14 The Contractor will have strategically placed, readily accessible, spill response
equipment, in addition to those listed in 1.8.13. as a minimum and to be replaced as
used:
CN – DESIGN & ENVIRONMENTAL PROTECTION SECTION 01560
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 13 OF 26
MI. 36.79 TO 41.00 HALTON SUB
6 Orange Poly 50
Construction Fencing metres
or similar required for
Tree Protection
Fencing
.15 The Contractor shall treat wastewater and wash waters to Protection of Aquatic Life
(PAL) criteria (between pH 6.5 and 9.0) and the turbidity will be less than 25 NTU
above background when it is discharged.
.16 All spills shall immediately be reported to the Engineer and CN’s Environmental
Monitor. The Engineer will report the spill to the regulatory authorities in accordance
with the Accident & Malfunction Response Plan.
.17 In the event of a spill, the Contractor shall carry out the steps outlined in the
Accident & Malfunction Response Plan (at a minimum).
1.9 FIRES
.1 A Fire Response Action Plan will be prepared by the Contractor as part of the
Accident & Malfunction Response Plan. Requirements of this plan are outlined in
the template for the Accident & Malfunction Response Plan and Environmental
Protection Plan.
CN – DESIGN & ENVIRONMENTAL PROTECTION SECTION 01560
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 14 OF 26
MI. 36.79 TO 41.00 HALTON SUB
.2 In advance of construction on the Site, the Contractor shall identify a Fire Boss. The
Fire Boss shall be trained in the use of on-site fire-fighting equipment.
.4 Smoking shall not be permitted on the Site except in specifically designated areas.
.1 The Contractor shall collect domestic wastewater daily and store in closed
containers until disposed of at an approved waste disposal site.
.2 The Contractor shall collect food waste daily and store in closed animal proof
containers until disposed of at an approved waste disposal site.
.3 All other waste materials will be collected separately and recycled, where
appropriate. Any materials surplus for recycling will be disposed of at an appropriate
and approved waste disposal site.
.4 The Contractor shall not bury or burn rubbish, waste, debris or any form of material
on the Site.
.5 Chemical or portable toilets will be provided on the Site and maintained on a regular
basis by the Contractor.
.7 The Contractor shall not dispose of chemicals, liquid waste, volatile materials, etc.,
on the ground surface, in excavations, into waterways, surface drainage features,
sanitary or storm sewers.
.8 The Contractor will protect concrete pours from rainfall with an impermeable cover
for a minimum of 48 hours, or until the concrete cures, in order to prevent high pH
run-off.
.9 The Contractor shall designate a concrete washout area on site and provide details
in the Erosion and Sediment Control Implementation Plan. The Contractor shall
implement measures during construction to prevent wet concrete or cement-laden
water, including high pH run-off occurring during concrete work, from entering any
wetland or waterbody.
.10 The Contractor shall collect and treat all wastewaters and wash waters, if produced,
taking into account the Council of Canadian Ministers of the Environment’s
Canadian Water Quality Guidelines for the PAL.
.1 The Contractor shall review the Soil Management Plan prepared for the Project and
incorporate all pertinent details, background information, recommendations,
mitigation and monitoring measures presented therein. The implementation of the
Soil Management Plan shall be overseen by the Contractor’s Qualified Person (as
defined by O. Reg. 153/04, as amended) and all records of soil management
activities shall be consolidated in a monthly report prepared by the Contractor’s
Qualified Person and provided to the Consultant. All records shall also be made
available for review by the Engineer or CN’s Environmental Monitor.
.2 The Soil Management Plan will be followed to prevent admixing, compaction, rutting
and soil loss.
.3 The Contractor shall handle and store soils during construction in a manner that
protects soil quality for re-use. Potentially contaminated soils that are observed
during construction will be sent for analysis to characterize and determine suitability
for re-use on the Site.
.4 Contaminated soils not suitable for re-use on the Site shall be managed in
accordance with all applicable law, industry standards and best management
practices, including but not limited to:
.5 Soil piles of any type must be stored with slopes 70 degrees or less from May 15 to
August 3. If not permittable, the Contractor shall implement exclusion techniques
such as tarping of slopes to prevent bird nesting, wildlife use, mobilization of dust,
etc.
.6 Topsoil will be stripped and stockpiled in accordance with the Grading Plan and Soil
Management Plan for all permanent and temporary construction areas. Topsoil piles
shall be marked with appropriate signage to prevent accidental admixing. Topsoil
shall not be imported to or exported from the Site.
.7 Subsoil will be stored separately from topsoil with a minimum of 1 metre separation
of the piles. Topsoil from the natural areas (i.e., Indian Creek) will be separated from
other topsoil so that it may be used for restoration.
CN – DESIGN & ENVIRONMENTAL PROTECTION SECTION 01560
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 16 OF 26
MI. 36.79 TO 41.00 HALTON SUB
.8 Silt fencing shall be installed around soil stockpiles in accordance with the Erosion
and Sediment Control Plan and Soil Management Plan and at the instruction of
CN’s Environmental Monitor. The Contractor is responsible for correcting any
identified deficiencies within 24 hours, following an inspection.
.9 The Contractor will be responsible for the re-use of soils on site as no off-site soil
transportation or disposal is planned. The Contractor is expected to make all
reasonable efforts to find suitable locations within the Construction Limits to dispose
of excess soil. However, in the event that excess soils cannot be re-used or
stockpiled on site and/or if contaminated soils are encountered that cannot be re-
used or disposed of on site, off-site transportation and disposal may be considered.
Any off-site transportation and disposal of soils from within the Construction Limits
must be approved by the QP, Engineer and CN’s Environmental Monitor prior to
commencing any off-site soil management activity. Off-site transportation and
disposal of contaminated or excess soils would be subject to provincial and local
legislation. Compliance with applicable legislation and regulation, including
obtaining all necessary permits, approvals, certificates, or other authorizations,
including payment of any associated fees, will be the responsibility of the Contractor
for any and all off-site soil management activity outside the Construction Limits.
.11 The Contractor must notify the Engineer and CN Environmental Monitor of any
suspected hazardous materials including contaminated soil, defined below, in
excavation.
.12 The Contractor must notify the Engineer and CN Environmental Monitor of any
suspected hazardous materials in excavation within 24 hours.
1.12 DEWATERING
.3 The Contractor shall comply with the Erosion and Sediment Control Plan and notify
CN’s Environmental Monitor of any changes resulting from site conditions.
.5 The Contractor must not pump water containing suspended materials into
waterways, stormwater management ponds, sewers or drainage systems, with the
exception of areas outlined in 02140 - Dewatering.
.7 The Contractor will establish an appropriate dewatering system that will dissipate
the energy and reduce the sediment content of discharging water for the purpose of
limiting potential erosion effects.
.8 The Contractor must make provisions to contain any oil or chemical spill that may
occur on the Site as outlined in the Accident & Malfunction Response Plan.
Vegetation clearing April 1 to August 31 Areas under active farming may be excluded from the
(nesting birds / migratory vegetation clearing timing restriction, pending verification
bird habitat) by the CN Environmental Monitor.
CN’s Environmental Monitor shall confirm the vegetation
clearing timing window with relevant authorities of any
given year.
Removal of vegetation/trees during the restricted period
should only occur under very limited circumstances. A
qualified biologist hired by the Engineer shall be retained
to conduct a wildlife sweep to document the absence of
migratory birds and/or nests at those sites (including
both vegetation and structures) at the time of clearing. If
the area is cleared by the qualified biologist, vegetation
removal should occur within 24 hours of the completion
of the avian survey; otherwise an additional survey will
be required.
Vegetation Clearing (bat April 1 to August 31 Vegetation and tree clearing shall be restricted by the
species at risk) Contractor during the active bat roosting season.
Use of flood lighting April 1 to May 31; August The Contractor shall restrict the use of flood lighting
15 to October 31 during the migratory bird breeding window.
CN – DESIGN & ENVIRONMENTAL PROTECTION SECTION 01560
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 18 OF 26
MI. 36.79 TO 41.00 HALTON SUB
Activity Restricted Activity Contractor Requirements
Period (No Work) *
Earth moving in proximity May 12 to August 22 Avoid grading or heavy earth moving from May 1st to
to the Heritage Barn June 30th within 100m to the south of the Barn Swallow
colony in the existing barn (as identified in Contract
Drawings).
Construction works April 1 to September 30 The Contractor shall install wildlife exclusion fencing as
outlined in the Contract Drawings in advance of the start
of construction and prior to September 30.
Prior to September 30, CN’s Environmental Monitor must
provide confirmation to the Contractor that snake
surveys/relocation has occurred. Snake
surveys/relocation must occur prior to construction, but
can be targeted in areas where construction activity is
anticipated to start. This is to be coordinated with the
Contractor.
Mainline work north of Mid-March to mid-April No work along the mainline in this area unless the CN
Britannia Road to Louis Environmental Monitor has confirmed that the Western
St. Laurent Blvd. (Western Chorus frogs have left their upland / overwintering
Chorus Frog) habitat and exclusionary fencing has been installed as
outlined in the Contract Drawings before proceeding with
any work in this area. The exclusionary fencing will be
installed during Phase 1 of the project but will be
maintained during Phase 2 construction. Contractor must
verify with the Environmental Monitor prior to work in this
area.
.2 Any exceptions to the above timing window restrictions shall be identified by the
Contractor and communicated to the Engineer and CN Environmental Monitor with
sufficient time to allow CN to consult with applicable regulatory agencies to confirm
acceptance. Exceptions will not be granted without prior approval of CN following
confirmation from the applicable regulatory agency.
.1 Before entering on or disturbing any land or property for the purposes of the works
or commencing any part of the works, the Contractor shall verify with the Engineer
that all permits have been obtained and the terms under which these permits have
been obtained.
.2 The Contractor shall delineate the Limit of Construction as identified on the Contract
Drawings to demarcate the areas within which all construction activities will occur.
Absolutely no Work shall occur outside of the Limits of Construction.
.3 The Contractor must limit vegetation disturbance, tree removal and all aspects of
construction activity to the Site as indicated in Contract Drawings.
.7 Silt fencing and/or tree protection fencing shall be installed prior to grubbing and
excavation where appropriate to protect existing vegetation, and no closer than the
dripline. Taller tree protection fencing (i.e., hoarding around trees) shall be installed
in these areas to protect tree limbs from equipment in adjacent areas. Root/tree
pruning is required as a tree protection/preservation measure and should be
conducted by a Certified Arborist or under the supervision of a Certified Arborist
employed by the Contractor.
.8 The Contractor shall not place temporary worksites within the boundaries of
wetlands, unless pre-approved by CN’s Environmental Monitor and in accordance
with the Limits of Construction identified on the construction drawings.
.10 If barn swallow or bank swallow nests are encountered during the removal of a
culvert, the Contractor shall notify the Engineer and CN’s Environmental Monitor
who will implement a ‘no-go’ zone that shall be adhered to by the Contractor. Once
the nest is empty, CN’s Environmental Monitor will notify the Contractor that the
area is clear for construction.
.1 The Contractor shall follow the requirements outlined in the Wildlife Management
Plan.
.2 The Contractor must limit vegetation disturbance and tree removal to CN property
as per extents indicated in Contract Documents. The Contractor shall install wildlife
exclusion fencing in sensitive areas adjacent to active construction areas in
accordance with the Tender Package Drawings.
.4 The Contractor shall inspect all wildlife exclusion fence at least daily and before and
after rainfall events (10 mm / 24 hours) and significant snow melts. Cleanout shall
be completed when sediment accumulation reaches approximately 30%. The
CN – DESIGN & ENVIRONMENTAL PROTECTION SECTION 01560
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 20 OF 26
MI. 36.79 TO 41.00 HALTON SUB
Contractor is responsible for correcting any identified deficiencies within one
working day, following an inspection. The Contractor shall report to CN’s
Environmental Monitor any major repairs within 24 hours and document in the
Monthly Compliance Report.
.6 The Contractor shall install and maintain signs to notify drivers of the risk of turtle
collisions along any temporary and permanent road, taking into account Ontario's
Best Management Practices for Mitigating the Effects of Roads on Amphibians and
Reptile Species at Risk in Ontario when installing the signs.
.7 The Contractor shall carry out the Works in a manner that protects migratory birds
and avoid harming, killing or disturbing migratory birds or destroying, disturbing or
taking their nests or eggs and shall account for Environment and Climate Change
Canada’s Avoidance Guidelines to reduce risk to migratory birds. The Contractor
shall also be in compliance with the Migratory Birds Convention Act (1994), the
Migratory Birds Regulations and with the Species at Risk Act.
.8 Grading and heavy earth movement shall be avoided by the Contractor from May
12 to August 22 within 100 metres of the existing barn (barn swallow colony)
outlined in the Contract Drawings. The barn shall be fenced to prevent
encroachment by equipment or personnel during construction - no access to the
barn by Contractor is permitted.
.9 If wildlife is discovered on the Site, the Contractor shall report the siting to CN’s
Environmental Monitor. Appropriate mitigation to protect and/or relocate the
species will be developed by the CN’s Environmental Monitor for implementation.
.10 Sighting of species of management concern or species at risk as outlined during the
Environmental Orientation Training will be reported to CN’s Environmental Monitor
and the sighting will be recorded in daily reports. Specific protection measures will
be implemented by the Contractor at the direction of CN’s Environmental Monitor.
.11 The Contractor shall not harass, harm or kill any wildlife encountered during
construction.
.12 The Contractor shall not block or prohibit wildlife access to culverts. Passage for
wildlife or fish through culverts must be maintained throughout construction.
.13 All construction equipment and vehicles shall give right-of-way to wildlife, allowing
wildlife to pass and proceed to a safe distance prior to construction
equipment/vehicles commencing construction activities.
.14 In the event wildlife is injured or killed during construction activities, the Contractor
shall immediately cease Work activities in the immediate vicinity and notify CN’s
Environmental Monitor.
CN – DESIGN & ENVIRONMENTAL PROTECTION SECTION 01560
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 21 OF 26
MI. 36.79 TO 41.00 HALTON SUB
.15 No hunting or fishing is permitted on-site or surrounding areas. Recreational use of
all-terrain vehicles or snowmobiles is also prohibited on the Site.
.16 If the Contractor encounters any Beaver dams while on site, CN’s Environmental
Monitor shall be notified and a means for removal/relocation shall be developed by
the Contractor.
.17 No additional compensation shall be made for work delays as a result of encounters
with wildlife.
.1 The Contractor shall carry out construction activities near water following DFO
Measures to Avoid Causing Harm to Fish and Fish Habitat and in accordance with
the DFO Authorization.
.2 The Contractor will provide an updated schedule identifying when in-water work is
proposed in accordance with 01340 - Submittals. All in-water work will be scheduled
with CN’s Environmental Monitor in advance to accommodate coordination with fish
rescue activities if necessary.
.3 Before the commencement of in-water activity, the Contractor shall ensure that all
necessary equipment and materials are available and are on-site, including
contingency (back-up/extra) equipment and materials.
.5 Specific fish in-water timing windows, as well as Snapping Turtle and Western
Chorus Frog timing windows, shall be followed as applicable as outlined in Section
1.13.
.6 The Contractor shall isolate in-stream culvert installations, if required, from fish-
bearing waters in accordance with the Contract Drawings and associated plans.
.1 The Contractor shall restrict grubbing, stripping and grading on approach slopes to
watercourses and water bodies to the amount required to allow safe passage of
equipment and completion of the Work.
.2 The Contractor shall control operations to prevent the entry of deleterious materials
into watercourses.
.4 The Contractor shall remove any felled trees, debris or soil inadvertently deposited
below the high watermark of a watercourse within 1 working day.
.5 For low risk activities, erosion and sediment control measures shall be inspected on
a weekly basis as well as prior to and following heavy precipitation events (i.e.
10mm in 24 hours) and significant snow melts to ensure the measures are
CN – DESIGN & ENVIRONMENTAL PROTECTION SECTION 01560
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 22 OF 26
MI. 36.79 TO 41.00 HALTON SUB
functioning properly, maintained and upgraded as required. If erosion and sediment
control measures are not functioning properly, the Contractor shall make repairs
immediately. Low risk activities include those occurring away from sensitive natural
areas as identified. High risk activities shall be monitored daily. High risk activities
include those that occur in close proximity to sensitive natural areas, in-or near
water works, concrete works, dewatering, vegetation clearing and grubbing, and
those where should erosion and sediment control measures fail, there is likely
impact to sensitive natural areas. Cleanout shall be completed when sediment
accumulation reaches approximately 30%. The Contractor is responsible for
correcting any identified deficiencies within one working day, following an
inspection. The Contractor shall report to CN’s Environmental Monitor any major
repairs within 24 hours and document in the Monthly Compliance Report.
.1 The Contractor must prevent dust nuisance resulting from their operations. The
Contractor is to prepare an Air Quality Best Management Practice Plan.
.2 The Air Quality Best Management Practice Plan for construction air emissions
control shall be drawn up by the Contractor and submitted to the Engineer for
approval in accordance with 01340 – Submittals and 02362 – Dust and Mud
Control. This Plan shall identify the procedures to be implemented by the Contractor
to reduce the potential generation of dust (specifically PM10) and other fugitive air
emissions during construction, with the least potential for adverse environmental
effects. This Plan will include a description of the measures to be implemented by
the Contractor to reduce the potential for offsite migration of construction dust,
which shall include a combination of visual observations and on-site dust monitoring
where action levels of daily dust generation will trigger localized dust suppression or
surface wetting, and reaching threshold values will necessitate cessation of
activities up to and possibly including a construction activity pause until such time
that the surface or meteorological conditions change to reduce offsite dust
migration.
.3 The Contractor shall implement a no idling policy for all construction equipment and
vehicle emissions during construction. The policy will be reviewed and approved by
the Engineer prior to construction.
.4 The cost of all such preventative measures will be borne by the Contractor.
.5 The Contractor will have a CO2 tank with regulator, hose and diffuser available on-
site during concrete work to neutralize pH levels as needed.
.8 The Contractor will be responsible for ensuring all dirt and mud that is tracked onto
the roadways from vehicles entering or leaving the Site is regularly cleaned from the
roadways. The Contractor must, upon request from the Engineer, CN’s
Environmental Monitor, CN complaint process or their consultant, immediately
proceed with clean-up operation at their expense using street sweepers or similar
equipment, or if in the opinion of the Engineer, the Contractor has not removed or
cannot sufficiently remove the mud from the road, the Engineer will proceed with the
necessary clean up with all costs being charged to the Contractor.
.1 The Contractor shall follow the noise control requirements outlined in 02202- Noise
Control.
.2 The Contractor shall prepare a Noise Reduction Plan as outlined in 02202 – Noise
Control in accordance with 01340 – Submittals. Construction activities shall
generally occur between the hours of 7:00 am and 10:00 pm with the following
exceptions:
.1 Activities associated with the pouring of workpads (i.e., concrete
plant operation and continuous pour requirements)
.2 Isolated night-time activities associated with Lower Base Line
.3 In circumstances where work is not technically feasible before
10:00 pm
.4 Other limited activities subject to approval by the Engineer.
.4 On-site speed limits will be enforced, and vehicle traffic will be restricted to routes
outlined in the Construction Traffic Management Plan to reduce the intensity of
travel noise.
.6 CN will develop a Communication Protocol for the receiving of complaints from the
public. The Contractor shall implement any corrective action deemed appropriate,
based on direction from the Engineer, as outlined in Section 1.6.2.
CN – DESIGN & ENVIRONMENTAL PROTECTION SECTION 01560
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 24 OF 26
MI. 36.79 TO 41.00 HALTON SUB
1.20 VIBRATION CONTROL MEASURES (CULTURAL HERITAGE RESOURCES)
1.21 LIGHTING
.4 Requiring for all motor vehicles to use low-beam headlights within the
Site.
.3 CN will develop a Communication Protocol for the receiving of complaints from the
public. The Contractor shall implement any corrective action deemed appropriate,
based on direction from the Engineer, as outlined in Section 1.6.2.
CN – DESIGN & ENVIRONMENTAL PROTECTION SECTION 01560
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 25 OF 26
MI. 36.79 TO 41.00 HALTON SUB
1.22 EROSION AND SEDIMENT CONTROL PLAN
.1 The Contractor shall install, inspect, and maintain erosion and sediment control
measures as per the Erosion and Sediment Control Plan (General) outlined in the
Contract Drawings.
.2 Prior to the commencement of any Work that might cause erosion and/or
sedimentation, the Contractor must receive approval from the Engineer for any
proposed revisions to the Erosion and Sediment Control Plan - General. The
proposed revisions shall be outlined in an Erosion and Sediment Control
Implementation Plan as outlined in 02271- Erosion Control and 01340 - Submittals.
The Plan shall include site specific details of when, where and how the specific
erosion control measures will be used. Changes to the Plan will be consistent with
the requirements outlined in 02271 – Erosion Control and the Environmental
Protection Plan.
.3 The Contractor shall install, inspect, and maintain erosion and sediment control
measures as per the Erosion and Sediment Control Plan – General. This will
include appropriate locations adjacent to all watercourses and/or water bodies, or
as directed by CN’s Environmental Monitor. The Contractor will be responsible for
correcting any identified deficiencies within one working day, following an
inspection.
.4 The Contractor shall subscribe to a meteorological alert service, ensuring that there
is advance warning of flood-producing severe rainfall events (those producing more
than 10mm of rainfall precipitation in a 24-hour period). The warning area is to be
focused on the Indian Creek Watershed (and its tributaries).
.1 The Contractor shall coordinate and comply with CN's Environmental Monitor during
all site grading and ground disturbance activities in accordance with the
Archaeological and Cultural Resources Protection Plan.
.4 The contractor shall attend the Environmental Orientation which will include cultural
and indigenous awareness training for all employees working on the site in
CN – DESIGN & ENVIRONMENTAL PROTECTION SECTION 01560
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 26 OF 26
MI. 36.79 TO 41.00 HALTON SUB
recognition of the indigenous traditional lands and archaeological artifacts and
cultural heritage structures found and existing at this site.
1.24 RESTORATION
.2 The Contractor shall ensure any special environmental concerns identified by CN’s
Environmental Monitor are addressed before site restoration.
.5 The Contractor shall use native Ontario species and non-invasive grass species
and nurse crops for restoration in areas not covered by regulatory permit conditions.
.1 Exclusionary fencing per the Contract Drawings, shall be installed by the Contractor.
.2 Temporary Fencing shall consist of Heavy Duty Silt Fence and be installed and
maintained in good repair under supervision of CN’s Environmental Monitor.
Exclusion fencing installed during Phase 1 will also be maintained. Permanent
fence installation for operation shall be in accordance with the Contract Drawings.
.3 The timing of exclusionary fence installation should align with the timing windows
outlined in Section 1.13. CN’s Environmental Monitor will indicate to the Contractor
when fence installation can occur.
.4 The location of the fencing shall be coordinated and determined with CN’s
Environmental Monitor prior to anticipated installation timing.
1.26 PAYMENT
.1 Payment for the work of this Section shall be deemed incidental to Item A3
submitted in the Form of Tender, and no separate payment will be made.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
.1 The Contractor shall handle all material at their own expense, including the
loading and unloading of Railway cars, and shall unload all material from cars
promptly on their arrival or will be liable to the regular demurrage charges at the
destination provided for in the current car service regulations.
.2 All equipment, plant, and materials used on the job site by the Contractor if
shipped via the Railway, are to be at the Contractor's expense under full tariff
rates currently enforced.
.3 The Contractor shall include in their tender the entire cost of transportation,
handling, and placing of all materials and all overhead, office, insurance, and
supervision costs connected therewith.
.2 The Contractor must furnish, for approval, a complete list of all materials the
Contractor proposes to use on the work, and any purchase of material that they
may make before this approval is given must be at their own risk.
1.3 OVERHAUL
1.4 TESTS
.1 All inspection tests, etc., outlined in the various specifications covering the
different materials entering into this work, will be carried out and rigidly enforced
by the Railway.
.2 Other materials of similar and equal quality may be substituted, but in such
cases, only with the written consent of the Engineer.
.3 Application for the substitution of materials will not be considered by the Engineer
until after the Contract has been awarded.
.4 Application for the substitution of material shall be made in writing, setting forth
clearly the description and function of the article for which substitution is desired
and the difference in cost, if any.
.5 The acceptance of any substitution does not relieve the Contractor of liability
should the article substituted not fully perform the function claimed for it.
.6 Where required, samples of materials provided for use in the work shall be
submitted to the Engineer, in duplicate, for their approval before being used.
.7 The sample shall be retained by the Engineer in their office and referred to as
standards.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
.1 The Contractor shall be responsible for the true and proper laying out of the
works and for the correctness of the position, levels, dimensions, and alignment
of all parts of the works, and for the provision of all necessary instruments and
labour in connection therewith. In case at any time during the progress of the
works any error shall appear or arise in the position, levels, dimensions or
alignment of any part of the works, the Contractor shall, at their own expense,
rectify such errors to the satisfaction of the Engineer, unless such error is based
on incorrect data supplied by the Engineer.
.2 The Engineer will provide a minimum of two benchmarks and three horizontal
control monuments to assist the Contractor in the laying out of the work. The
Contractor shall satisfy themself with the suitability and accuracy of these points
prior to the commencement of the Work.
.3 After the Contractor has verified the accuracy of the control points established by
the Engineer, the Contractor shall set and maintain horizontal or vertical controls
necessary for complete and accurate layout and construction of the work
including, but not necessarily limited to station stakes, centerline stakes, offset,
grade stakes, stakes for pipelines, subdrains, batter boards, control points for
footings as well as all other.
.4 The Contractor shall furnish all assistance and co-operation, to the Engineer’s
survey crew as necessary for them to provide these points.
.5 The checking of the setting out of any line or level by the Engineer shall not in
any way relieve the Contractor of their responsibility for the correctness thereof,
and the Contractor shall carefully protect and preserve all bench marks, control
points, stakes, legal monuments and other items used in setting out of the works.
1.2 MEASUREMENT
.1 The Contractor will carry out all measuring and surveying necessary to confirm
the quantity of Work performed for payment of each item in the Contract, and any
other items subsequently appended to the Contract.
.2 The Contractor shall supply the Engineer with sets of original and final cross-
sections, in digital format acceptable to the Engineer, after all stages of
construction, for calculation purposes.
CN – DESIGN & SETTING OUT AND MEASUREMENT SECTION 01610
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 2
MI. 36.79 TO 41.00 HALTON SUB
.3 If for any reason the Contractor is unable to provide data acceptable to the
Engineer, as listed above, quantity calculations will be based on design volumes
or plan quantities.
1.3 PAYMENT
.1 Payment for the work of the Section shall be deemed incidental to the various
prices submitted in the Form of Tender, and no separate payment will be made.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
Lift (m)
Item OMC SPMDD Test Type
depth
Earth Cut
Disturbed areas & Sub-
± 2% 95% Proof-roll
grade
Earth Fill & Borrow
Standard Proctor & OMC
Each material type or borrow
Soil Test Analysis &
source
Characterization
Sub-grade Proof-roll
Top 0 – 2 m 0.20 ± 2% 98% ± 2% Compaction, 25m grid
Bottom 2 – 10 m 0.30 ± 2% 95% Proof-roll each lift
Granular Materials
Prior to Ordering 2 samples, sieve, Proctor
Production 1 sample per 5,000t
Placing 0.15 ± 2% 98% Compaction, 25m grid, per lift
Drainage Structures,
Trench Base & Backfill,
Foundation Base,
Retaining Walls & Backfill,
Pipe Bedding & Backfill
Base (Foundation) Verify load bearing capacity
Bedding 0.15 ± 2% 98% ± 2% Compaction, every 5m, per lift
Backfill 0.30 ± 2% 98% ± 2% Compaction, every 5m, per lift
Concrete
Mix Design Verify meets specification
Daily or per 38 m3 or element 2 tests for air content
Daily or per 38 m3 or element 2 tests for slump
Daily or per 38 m3 or element set of 4 cylinders
Mechanical
To be addressed in each of All ITPs to be submitted to the
the Inspection and Testing Engineer for review and
Plans (ITP) as follows: acceptance)
CN – DESIGN & QUALITY CONTROL AND ASSURANCE SECTION 01620
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 3
MI. 36.79 TO 41.00 HALTON SUB
Non-Destructive Testing
(NDE)
Welding
Coating (Pipeline and
Bends)
Corrosion and Protection
Hydrostatic Testing
Pipe Bending
Horizontal Directional Drilling
(HDD)
ITP Checklist
CN Track settlement
monitoring
.3 The Contractor shall conduct all required tests and provide copies of all results,
including re-test of failed areas, to the Engineer on a daily basis.
.4 Where tests or inspections by the Contractor’s testing laboratory reveal work not
in accordance with the contract requirements, the Contractor shall pay costs for
additional tests or inspections required by the Engineer to verify the acceptability
of corrected work.
.5 The Engineer may carry out their own Quality Assurance activities. The Quality
Assurance effort undertaken by the Engineer will not relieve the Contractor in any
way with respect to the accuracy
.6 The Contractor shall give the Engineer a minimum of 24 hours’ notice for testing
to be permitted.
.7 Where tests or inspections are called for prematurely or the testing laboratory is
delayed by the Contractor, the Contractor shall pay all additional costs incurred.
.6 Pay costs for uncovering and making good work that is covered before
required inspection or testing is completed and approved by the Engineer.
CN – DESIGN & QUALITY CONTROL AND ASSURANCE SECTION 01620
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 3
MI. 36.79 TO 41.00 HALTON SUB
.9 The Engineer shall not be responsible for any delays to the Contractor’s
operations where the Contractor fails to give sufficient advance notice to the
Engineer to carry out the required inspection, sampling and testing.
.10 As the work progresses and as the Engineer and Contractor gain familiarity and
confidence in the quality control regime, the Engineer may permit the Contractor
to proceed with less testing than specified, but this will in no way relieve the
Contractor from any responsibilities with respect to quality or warranties for the
Works.
1.2 PAYMENT
.1 Payment for the work of this Section shall be deemed incidental to the various
prices submitted in the Form of Tender, and no separate payment will be made.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
.1 Tables;
.4 2 Binders and 2 Hard Drives containing the above and shall include the
following as a minimum (workplans, submittals, reports, testing, letters,
final surveys, MTRs, Weld Matrix, NDE reports, etc). The Contractor
shall provide a Table of Contents indicating the list of items for review
and acceptance 3 weeks prior to project closeout.
.5 At the completion of the project and prior to the final inspection, submit "as-
constructed" drawings to the Engineer.
.1 A joint inspection will be carried out between the Engineer and Contractor prior
to the Engineer accepting any portion of the works.
CN – DESIGN & PROJECT CLOSEOUT SECTION 01800
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 2
MI. 36.79 TO 41.00 HALTON SUB
.2 Deficiencies shall be noted during this inspection and any such deficiencies
must be corrected within five (5) working days and before final acceptance for
use by the Engineer.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
.6 All costs related with maintaining access to the site for the duration of the
construction.
.7 All costs related to establishing construction offices for the Engineer, Contractor
and all subcontractors.
.9 Security on site to guard the materials, tools, equipment, offices, vehicles, and
fencing, as necessary, etc.
.10 The supply and transportation to the site of construction equipment, cranes, and
workforce as required for the performance of the Work.
.11 Upon completion of the work, restoration of the site in accordance with the Final
Restoration and Enhancement Plans, all to the approval of the Engineer and CN
Environmental Monitor.
.12 Payment for permits including Road Occupancy Permits from the applicable
municipalities.
.13 All cost associated with supplying bonds and insurance coverage.
.15 All costs associated with the implementation of the Section 01340 Submittals,
Section 01500 Temporary Facilities, Section 01545 Safety Requirements,
Section 01546 Flagging and Track Protection, Section 01560 Environmental
Protection, Section 01570 Traffic Control, Section 01600 Materials and
Equipment, Section 01610 Setting Out and Measurement, Section 01620 Quality
Control and Assurance, Section 01800 Project Closeout and Railway
Requirements as included within these tender documents.
.16 All other costs, including administrative costs, which are not directly associated
with the execution of items specified in the Form of Tender.
.1 Not applicable.
PART 2 - PRODUCTS
.1 Not applicable.
CN – DESIGN & MOBILIZATION AND DEMOBILIZATION SECTION 02000
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 3
MI. 36.79 TO 41.00 HALTON SUB
PART 3 - EXECUTION
3.2 GENERAL
.1 Liaise with Engineer and all other applicable stakeholders in a timely manner to
ensure that a safe quality product is delivered within the timeframe specified
herein.
4.1 MEASUREMENT
4.2 PAYMENT
.1 The Contractor will be paid 60% of the Contract Bid Price for Mobilization and
Demobilization item upon completion of the mobilization operation. The
remainder of the Contract Bid Price for this item will be paid when the Contractor
demobilizes from the site and restores the site to a condition acceptable to the
Engineer.
.2 The Lump Sum price A1 for "Mobilization and Demobilization" items in the Form
of Tender shall not exceed ten (10%) percent of the Total Estimated Contract
Item Price.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
2. This Section pertains to the removal of groundwater and surface water from all
construction operations, including all types of foundations.
3. This Section specifies the requirements to complete a water well survey and to
identify the location of the wells prior to the Works commencing.
1.3 REFERENCES
.1 Ontario Water Resources Act, R.S.O. 1990, Regulations 387/04 and 903.
CN – DESIGN & DEWATERING SECTION 02140
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 8
MI. 36.79 TO 41.00 HALTON SUB
.2 Environmental Protection Act, R.S.O. 1990, Regulation 63/16Ontario Provincial
Standard Specification:
.1 The Contractor is responsible for conducting its own quality assurance program
to ensure that all dewatering for the Project meets the requirements of this
Section and Section 01620 Quality Control and Assurance.
.3 The Contractor shall ensure that Professional Geoscientist (PGO) checks and
seals the design calculations and drawings of the dewatering system; and
.4 The Contractor shall ensure that the Professional Geoscientist (PGO) inspects
the installation of the system and certifies that the installation and operation are
in accordance with the design.
.5 The Contractor shall ensure that, as part of its scope under Section 01620
Quality Control and Assurance, Contractor performs:
.2 Material testing in the laboratory and prepare test reports and submittals
for dewatering work as required.
1.5 SUBMITTALS
.1 Contractor shall submit the following submittals for review in accordance with the
requirements of Section 01340 Submittals prior to commencing the Work:
1.6 PERMITS
.1 The Contractor shall review with the CN Environmental Monitor if permits and
approvals are required. Should they be required, the Contractor shall obtain the
appropriate permits and approvals to discharge where dewatering occurs. The
Groundwater Dewatering Implementation Plan shall identify the Contractor’s
selected treatment systems, discharge systems and discharge location(s) for
each discharge location within the Limits of Construction.
.2 The Contractor’s Professional Geoscientist (PGO) shall review the site conditions
and boreholes information provided in the Geotechnical Reports and additional
supplemental geotechnical investigation reports, the proposed method of
construction by the Contractor to verify the amount of the water taking.
.3 The Contractor shall submit detailed means and methods required to undertake
the dewatering (and disposal of the pumped water) to the Engineer. The
Contractor shall obtain all necessary permits and approvals in accordance with
Contract Documents.
.2 The Contractor shall ensure that a copy of the Fisheries and Oceans Canada
(“DFO”) request for review documentation for each watercourse and all DFO
Determination Letters, including response letters/emails are kept on Site while
any works at or near water crossings are in progress in accordance with the
requirements of Section 01560 Environmental Protection. The Contractor shall
ensure that the detailed mitigation within the letter shall be followed for all in-
water Works.
.5 The Contractor shall provide erosion and sedimentation controls and protection
of environmentally sensitive areas downstream.
.4 Ensure that by-pass pumps are properly sized to manage expected flows
and can pump a 5-year return storm event. The Contractor shall ensure
that all by-pass pumps have a fish screen that meets DFO’s freshwater
intake end-of-pipe fish screen guideline to prevent entrainment or
impingement of fish. Project Co shall ensure that there are extra pumps
onsite and in position in the event of pump malfunction;
.5 Ensure that the raw concrete poured at the culvert inlets/outlets is always
securely isolated from the stream flows until the concrete has set. In
addition, Contractor shall ensure that the isolated containment area is of
sufficient size to hold all of the concrete used during this Project in the
event of a leak; and
.6 Contractor shall ensure that applicable permits for relocating fish are
obtained and provide a copy of the fish salvage results and any other
environmental monitoring reports to DFO or local Environmental Agency
office at the completion of the Project.
.10 The Contractor shall not stockpile fill materials within a minimum of 30m to the
watercourse.
CN – DESIGN & DEWATERING SECTION 02140
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 8
MI. 36.79 TO 41.00 HALTON SUB
.11 The Contractor shall remove all excess materials to disposal sites outside of site,
including earth, stones, boulders, topsoil and organic materials.
.2 The Contractor shall ensure that all dewatering is completed in accordance with
the O.Reg. 387/04: Water Taking and Transfer and shall be responsible for any
Environmental Activity and Sector Registry requirements and/or Permits to Take
Water. The Contractor shall ensure that the water is pumped into a filter bag or
sedimentation pond or diffused onto vegetative areas a minimum of 30m from the
watercourse. The Contractor shall ensure that the water is not pumped directly
into the watercourse:
.1 For isolation areas that require pumping to maintain work-in the dry
conditions, The Contractor shall ensure that contingency planning (all
requirements including extra pumps and fuel) is in place;
.2 The Contractor shall ensure that all pumps have a fish screen that meets
DFO’s Freshwater Intake End-of-Pipe Fish Screen guideline to prevent
entrainment or impingement of fish. The Contractor shall ensure that
there are extra pumps onsite and in position in the event of pump
malfunction; and
.3 The Contractor shall ensure that during dewatering activities, fish salvage
is undertaken by Environmental Specialist within the isolated areas prior
to any in-water works and dewatering activities in accordance with section
01560. The Contractor shall ensure that any fish located within the Site
are removed and relocated to appropriate habitat downstream of the Site.
.1 The Contractor shall provide Erosion and Sediment Control in accordance with
Section 01560 Environmental Protection and Section 02270 Erosion Control
General.
.2 Geotechnical:
.3 Water Wells: The Contractor shall complete a water well survey and identify the
location of any wells within the Limits of Construction prior to the commencement
of Work.
PART 2 - PRODUCTS
2.1 EQUIPMENT
.3 The Contractor shall ensure that all of the equipment including standby power
equipment, is operated in accordance with requirements of Section 01560
Environmental Protection in order to minimize noise impact on adjacent
properties.
.4 The Contractor shall ensure that the dewatering system is in good working order
and regularly maintained in accordance with manufacturer requirements.
PART 3 - EXECUTION
.1 Excavation work shall not commence prior to the installation of all erosion and
sedimentation control measures in accordance with Section 02270 Erosion
Control General.
.2 The Contractor shall operate the dewatering system continuously 24 hours a day,
7 days a week until installation and backfill is completed.
.3 Provide and maintain perimeter and diversion ditches to prevent surface water
from entering any excavation.
.5 Measure and record the volume of water removed by the system(s) on a daily
basis.
.8 The Engineer and/or CN’s Environmental Monitor will notify the Contractor of any
complaints received. It is the responsibility of the Contractor to rectify or develop
CN – DESIGN & DEWATERING SECTION 02140
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 7 OF 8
MI. 36.79 TO 41.00 HALTON SUB
a plan with the Engineer and/or CN’s Environmental Monitor to rectify the
complaint within 24 hours of receiving the complaint.
.10 The Contractor shall be responsible for controlling and disposing of all water in
accordance with the Final Dewatering Plan and any necessary permits obtained
by CN.
.11 The dewatering system shall control groundwater using filtered sumps within the
excavated areas as outlined in the Final Dewatering Plan. Dewatering effluent
shall be diverted to an appropriate approved location. At the discharge point, an
energy dissipation and erosion control measure must be established (i.e., no
direct discharge to a waterbody or wetland is permitted). If deemed necessary, a
treatment and filtration system shall be installed at the downstream end of the
weir tank to treat the dewatering effluent in order to comply with Provincial Water
Quality Objectives.
.12 During dewatering, the pumping rate should be monitored and recorded by the
Contractor based on pump size/rating curves with field measurements of flow
rate be taken on a daily basis. The digital flowmeter shall be calibrated as per the
manufacturers recommendation and installed on the outflow of the weir tank to
monitor the instantaneous and cumulative rate of dewatering effluent discharge.
.13 The Contractor shall complete the following on a daily basis during dewatering:
.14 Construction of culverts and retaining walls must be carried out in dry conditions.
.15 The Contractor must provide temporary drainage and pumping as necessary to
keep excavations and the Site free from water. The outfall from pumping
operations must be directed away from creeks onto approved splash pads,
retention areas, or stormwater management ponds.
.16 Dewatering effluent shall not be discharged directly into a waterbody or wetland.
.17 The Contractor shall not discharge water containing suspended materials into
waterways, sewers, or drainage systems.
.18 The Contractor must control the disposal or runoff of water containing suspended
materials or other harmful substances in accordance with PAL requirements.
CN – DESIGN & DEWATERING SECTION 02140
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 8 OF 8
MI. 36.79 TO 41.00 HALTON SUB
.19 The Contractor must make provisions to contain any oil or chemical spill that may
occur on the Site as outlined in the Construction Emergency Response Plan.
.20 Prior to discontinuing operation and removal of the dewatering system, the
Contractor shall obtain written approval from the Engineer.
4.1 MEASUREMENT
4.2 PAYMENT
.1 Payment for the Work of this Section shall be included in the unit prices included
in the Form of Tender. Payment will be full compensation for design, all
materials, labour, use of equipment, tools and incidentals necessary to complete
the Work of this Section.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the requirements of design, supply and install and removal
of construction access road for the Works.
.1 The Contractor shall conduct their own quality assurance program to ensure
Access Road construction meets the requirements of the specifications, as per
Section 01620 Quality Control and Assurance of this Section.
1.4 SUBMITTALS
.1 Not applicable.
.1 Not applicable.
CN – DESIGN & CONSTRUCTION ACCESS ROAD SECTION 02141
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING AND DRAINAGE PAGE 2 OF 3
MI. 36.79 TO 41.00 HALTON SUB
1.6 ENVIRONMENTAL REQUIREMENTS
PART 2 - EXECUTION
2.1 GENERAL
.1 The Contractor shall design and install the temporary access road in accordance
with the proposed alignment as shown in the Contract Drawings.
.2 The Contractor shall install erosion control measures prior to commencing the
construction of the access road.
.3 The Contractor shall remove the topsoil along the proposed access road and
supply and install a minimum of 300 mm of granular B Type II as road base.
.4 The Contractor shall improve the existing construction access by widening the
access to a minimum of 6 m wide with 300 mm of Granular B Type II road base.
.5 The Contractor shall ensure positive drainage along the access road and install
the necessary culverts and pipes to avoid blocking the drainage along the access
and entrances.
.6 The Contractor shall comply with the requirement of Section 02350 Traffic
Control regarding the traffic control.
.7 The Contractor shall include wooden matts at the staging areas as needed in
order to complete the work and store materials and equipment.
.8 The existing utilities/ pipeline shall be identified in the field using the hydro-vac
truck or by hand digging, and the silt fence will be placed 3 m from the utilities.
.9 The Contractor is not allowed to perform any work beyond the silt fence area
except during the connection work.
.1 Install Heavy Duty Silt Fence barriers to control erosion and siltation as well as to
delineate the working areas, setback areas, and environmentally sensitive areas
as identified on the Contract Drawings and as directed by the Engineer.
.2 Install Orange Construction Fence between staging areas to identify the limit of
construction shown in the Contract Drawings and as required by the Engineer.
.3 Ensure that all grades, turns, and curves of the Access Road meet the
requirement for all equipment transportation vehicles for the project.
3.1 MEASUREMENT
3.2 PAYMENT
.1 Payment for the Work of this Section shall be included in the unit prices in the
Form of Tender. Payment will be full compensation for all materials, labour,
culvert pipes, use of equipment, tools and incidentals necessary to complete the
Work of this Section.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the approach ramp requirements for the temporary track
crossing works.
.1 The Contractor shall be responsible for conducting their own quality assurance
program to ensure Access Road construction meet the requirements of the
specifications, as per Section 01620 Quality Control and Assurance of this
Section.
1.4 SUBMITTALS
.1 Not applicable.
.1 Not applicable.
CN – DESIGN & CN TRACK APPROACH RAMP SECTION 02143
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING AND DRAINAGE PAGE 2 OF 3
MI. 36.79 TO 41.00 HALTON SUB
1.6 ENVIRONMENTAL REQUIREMENTS
PART 2 - EXECUTION
.2 The Contractor shall not be permitted to cross the track(s) with vehicles or
equipment except on a CN-approved temporary construction crossing.
.4 Granular materials on the ramp shall extend up and level with the
crossing planks and be wrapped with Terrafix to avoid contamination; and
.1 Supply and install gates and stop signs at 12 feet from the gauge side of
rail on each side of the tracks;
3.1 MEASUREMENT
.1 Measurement for the approach ramp shall be made by each as measured in the
field.
3.2 PAYMENT
.1 Payment for the Work of this Section shall be included in the unit prices in the
Form of Tender. Payment will be full compensation for all materials, labour,
culvert pipes, use of equipment, tools and incidentals necessary to complete the
Work of this Section.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the site entrance requirements for the Works.
.1 The Contractor shall be responsible for conducting their own quality assurance
program to ensure Site Entrance construction meet the requirements of the
specifications, as per Section 01620 Quality Control and Assurance and of this
Section.
1.4 SUBMITTALS
.1 Not applicable.
CN – DESIGN & SITE ENTRANCE SECTION 02144
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING AND DRAINAGE PAGE 2 OF 3
MI. 36.79 TO 41.00 HALTON SUB
1.5 DELIVERY, STORAGE & HANDLING
.1 Not applicable.
PART 2 - EXECUTION
2.1 GENERAL
.1 Install all erosion and siltation control devices prior to the commencement of
clearing, grubbing and grading works.
.2 Equipment and vehicles are not allowed to park on City Road/Streets during
construction except at mobilization and delivery of materials.
.3 Traffic control measures are to be in place, including flag persons for all
movement of vehicles to and from the job site.
.4 All Traffic Control measures are to follow MTO Book 7 and City of Milton/Halton
Region Standards.
.5 No work will be permitted on site until all such erosion and siltation control
devices are properly installed.
.7 After heavy rainfall and high winds, the contractor shall inspect and correct all
items under erosion control.
.1 Install Heavy Duty Silt Fence barriers to control erosion and siltation as well as to
delineate the pipeline setback areas, environmentally sensitive areas as
identified on the Contract Drawings and as directed by the Engineer.
.2 Ensure that Site Entrance width meets the requirement for all equipment
transportation vehicles entering the project site. Extend the entrance width as
needed.
.3 The Contractor shall install and remove mud mats at all construction access:
• The Contractor shall ensure that positive drainage is provided at the mud
mat locations; and
• The Contractor shall remove the mud matt upon completion of the Work,
and clean drains, and existing culvert of debris and unwanted granular
materials from road construction.
.4 Ensure that Site Entrance is properly sloped and graded to meet the requirement
for all equipment and transportation vehicles for the project. Protect the existing
culvert and both sides of the ditches with a silt fence and silt sox.
.5 Maintain dust and mud control measures during the full project construction
period.
.6 Remove and restore the site entrance upon completion of the Work.
.1 The Contractor shall ensure that site restoration is carried out upon completion of
Works in accordance with Section 02315 Excavating, Trenching and Backfilling.
3.1 MEASUREMENT
.1 No measurement shall be made for the work of this Section. Payment shall be
included in the unit price in the form of tender under new and existing
Construction Accesses.
3.2 PAYMENT
.1 Payment for the Work of this Section shall be included in the unit price in the
Form of Tender under new and existing Construction Accesses. Payment will be
full compensation for all materials, labour, use of equipment, tools and
incidentals necessary to complete the Work of this Section.
GENERAL CONDITIONS
The General Conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the requirements for the design, supply, and install
temporary flow diversion for the culvert’s construction and extension on the Site,
including temporary flow diversion requirements for the construction of culverts
and instream work.
.2 The work under this Section includes the design, supply, installation, operation,
maintenance, and removal of temporary flow diversion systems at each site and
for each phase to isolate a working area for the extension of existing transverse
culverts and other works and permit the Contractor to complete this work in the
dry while maintaining watercourse flows during the Work.
1.3 REFERENCES
.3 The Contractor shall, at all times, ensure the safety of the construction Site and
the protection of all workers on Site.
.5 The Contractor shall ensure that the Hydrogeologist inspects the installation of
the system and certifies that the installation and operation are in accordance with
the design.
.6 The Contractor shall ensure that, as part of its scope under Section 01620
Quality Control and Assurance, Contractor performs:
.2 Material testing in the laboratory and prepare test reports and submittals
for temporary flow diversion Works.
CN – DESIGN & TEMPORARY FLOW DIVERSION SECTION 02150
CONSTRUCTION MILTON LOGISTICS HUB -PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 8
MI. 36.79 TO 41.00 HALTON SUB
1.5 SUBMITTALS
.1 Contractor shall submit the following submittals for review in accordance with the
requirements of this Section and Section 01340 Submittals prior to commencing
the Work:
.4 Reports: Procedures that fully describe the sequence and timing of the
work, the associated waterbody and fish habitat protection measures, and
the related contingency measures associated with each phase of the
temporary flow diversion system.
.1 Refer to the Geotechnical and Data Report (GDR) for the Project.
.1 The Contractor shall design the temporary flow diversion at each location
considering the flows and corresponding water surface elevations required for
the work. The contractor acknowledges that the actual headwater elevations
could be significantly higher in the presence of flow constrictions and should be
confirmed by the Contractor’s Hydrogeologist.
Table 2: Culvert inlet normal headwater with Temporary Flow Diversion System
Return Period
Number 2 Year 5 Year 10 Year
Bypass Pipe
Site of
Size/Material Flow Elevation Flow Elevation Flow Elevation
barrels
(m3/s) (m) (m3/s) (m) (m3/s) (m)
Mile 37.00
450 mm /
(59+544.25) 1 0.09 196.32 0.12 196.39 0.13 196.42
CSP
(Culvert 13)
Mile 37.20
525 mm /
(59+869.25 1 0.14 195.39 0.18 195.46 0.20 195.49
CSP
(Culvert 12)
Mile 37.63
375 mm /
(60+567.18 1 0.04 192.84 0.05 192.87 0.06 192.91
CSP
(Culvert 11)
Mile 38.02
moved to
750 mm /
37.98 1 0.28 189.87 0.36 189.95 0.41 190.00
CSP
(61+125)
(Culverts 10)
Mile 38.31
600 mm /
(61+756) 1 0.16 186.72 0.20 186.78 0.23 186.82
CSP
(Culvert 9)
Mile 38.52
375 mm /
(61+993) 1 0.04 185.74 0.06 185.74 0.07 185.77
CSP
(Culvert 8)
PART 2 - PRODUCTS
2.1 EQUIPMENT
.1 The Contractor shall be responsible for providing all materials, tools, equipment,
labor and services necessary to complete the work.
CN – DESIGN & TEMPORARY FLOW DIVERSION SECTION 02150
CONSTRUCTION MILTON LOGISTICS HUB -PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 6 OF 8
MI. 36.79 TO 41.00 HALTON SUB
.2 Provide a complete temporary cofferdam solution that best suits specific
conditions at each site requiring temporary flow diversion.
PART 3 - EXECUTION
.2 The Contractor shall ensure that work on the temporary flow diversion system
does not commence before installing all other erosion and sedimentation control
measures.
.3 The Contractor shall ensure that all work undertaken is in accordance with the
timing constraints specified in Section 01560 Environmental Protection.
.4 The Contractor shall build a temporary flow diversion system in accordance with
reviewed Comprehensive Temporary Flow Diversion Plan and drawings. The
contractor shall advise the Engineer of any changes made to accommodate field
conditions. The Contractor shall resubmit Comprehensive Temporary Flow
Diversion Plan and drawings as necessary to reflect the field conditions for
review and approval.
.5 The Contractor shall maintain and monitor the temporary flow diversion system
for impacts to items, including settlement and groundwater usage. The
Contractor shall advise the Engineer and CN’s Environmental Monitor
immediately of any impacts.
.6 The Contractor shall demonstrate that the temporary flow diversion system is
functioning in accordance with design requirements and Contract Documents.
.7 The Contractor shall inspect the operation of the temporary flow diversion system
at a minimum frequency of 24 hours, whenever the temporary flow diversion
systems are in place, including weekends and holidays.
.8 The Contractor shall maintain the temporary flow diversion system until it is
required and obtain written approval from the Hydrogeologist prior to the removal
of the temporary flow diversion system.
.1 The Contractor shall submit for review the qualifications of the Hydrogeologist,
installer, operator and Independent Laboratory and Sampling and Testing
Company in accordance with Contract Documents.
CN – DESIGN & TEMPORARY FLOW DIVERSION SECTION 02150
CONSTRUCTION MILTON LOGISTICS HUB -PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 7 OF 8
MI. 36.79 TO 41.00 HALTON SUB
.2 Design drawings for Comprehensive Temporary Flow Diversion Plan(s):
.2 The Contractor shall ensure that the following information is shown on the
Contract Drawings:
.2 The design flow return period on which the design is based; and
.3 The Contractor shall ensure that the Comprehensive Temporary Flow Diversion
Plan(s) contains the procedures that fully describe the sequencing and timing of
the work, the associated waterbody and fish habitat protection measures, and the
related contingency measures associated with each phase of the temporary flow
diversion system.
3.3 PREPARATION
.2 The Contractor shall coordinate the installation and operation of the temporary
flow diversion system with other contractors, where applicable. The Contractor
shall coordinate with other contractors regarding access to the Site for
installation, operation and maintenance of Works as required and in accordance
with Contract Documents.
3.4 INSTALLATION
.1 The Contractor shall install temporary flow diversion systems in accordance with
reviewed Comprehensive Temporary Flow Diversion Plan(s).
3.5 OPERATION
.2 The Contractor shall maintain continuous operation of the installation at all times
during the work.
.3 The Contractor shall ensure compliance with the Section 02160 High Flow
Contingency Plan (General) in order to maintain a safe working area for workers
and equipment, as well as prevent potential impact upstream of working sites.
3.6 RESTORATION
.1 The Contractor shall remove all equipment and materials that are in the right-of-
way upon completion of the Works and shall ensure that all areas disturbed as
part of this work are restored to their preconstruction conditions in accordance
with the Restoration and Enhancement Plans and Contract Documents.
.2 The Contractor shall ensure that all work is completed in accordance with the
Contract Documents.
4.1 MEASUREMENT
4.2 PAYMENT
.1 Payment for the Work of this Section shall be included in the appropriate item in
the Form of Tender, including but not limited to the design, supply, installation
and removal of the dewatering system, temporary flow diversion, flood
emergency response plan and erosion and sediment control plan as necessary
to complete the Work of this Section.
GENERAL CONDITIONS
The General Conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 GENERAL
.1 This Section specifies the requirements of high flow contingencies for the flow
diversion for construction of the new culverts and existing culverts extension
throughout the entire project Limits of Construction, including the special
procedures for Culvert at Mile 37.00, Mile 37.20, Mile 37.63, Mile 38.02, Mile
38.31, and Mile 38.52.
1.3 REFERENCES
.5 The Contractor shall ensure that, as part of its scope under Section 01620
Quality Control and Assurance, Contractor performs:
Material testing in the laboratory and prepare test reports and submittals
for temporary flow diversion Works.
1.5 SUBMITTALS
.1 The Contractor shall submit the following submittals for review and approval in
accordance with this Section and Section 01340 Submittals:
CN – DESIGN & HIGH FLOW CONTINGENCY PLAN SECTION 02160
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 6
MI. 36.79 TO 41.00 HALTON SUB
High Flow Contingency Plan; and
.1 The Contractor shall provide Erosion and Sediment Control (ESC) drawings in
accordance with Section 01560 Environmental Protection and Section 02272
Erosion Control:
2.1 GENERAL
Table 2 extracted from the Temporary Flow Diversion Section 02150 Temporary
Flow Diversion presents. Culverts would require a CSP bypass pipe to ensure
working dry zones for each return period:
CN – DESIGN & HIGH FLOW CONTINGENCY PLAN SECTION 02160
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 6
MI. 36.79 TO 41.00 HALTON SUB
Table 2: Culvert inlet normal headwater with Temporary Flow Diversion System
Return Period
Number 2 Year 5 Year 10 Year
Bypass Pipe
Site of
Size/Material Flow Elevation Flow Elevation Flow Elevation
barrels
(m3/s) (m) (m3/s) (m) (m3/s) (m)
Mile 37.00
450 mm /
(59+544.25) 1 0.09 196.32 0.12 196.39 0.13 196.42
CSP
(Culvert 13)
Mile 37.20
525 mm /
(59+869.25 1 0.14 195.39 0.18 195.46 0.20 195.49
CSP
(Culvert 12)
Mile 37.63
375 mm /
(60+567.18 1 0.04 192.84 0.05 192.87 0.06 192.91
CSP
(Culvert 11)
Mile 38.02
moved to
750 mm /
37.98 1 0.28 189.87 0.36 189.95 0.41 190.00
CSP
(61+125)
(Culverts 10)
Mile 38.31
600 mm /
(61+756) 1 0.16 186.72 0.20 186.78 0.23 186.82
CSP
(Culvert 9)
Mile 38.52
375 mm /
(61+993) 1 0.04 185.74 0.06 185.74 0.07 185.77
CSP
(Culvert 8)
As shown, the 10-year return period flow is safely accommodated at all culverts
under partial blockage of the culvert openings. The protected working zone is
then expected to be wetted.
.1 Contractor shall provide a plan of working areas within the 2-year flood elevation
limits at a given location, based upon the planned restrictions to full stream flow
by cofferdam arrangements. The plan shall provide equipment types that may
work in those limits.
.2 The same plan shall show working areas above the regulated flood limits.
CN – DESIGN & HIGH FLOW CONTINGENCY PLAN SECTION 02160
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 6
MI. 36.79 TO 41.00 HALTON SUB
2.4 HIGH FLOW CONTINGENCY PLAN
.1 The Contractor shall provide a High Flow Contingency Plan that provides the
following basic information:
Triggers:
Priorities:
.1 Personnel evacuation;
Assembly Areas:
2.5 EQUIPMENT
.1 The Contractor shall be responsible for providing all materials, tools, equipment,
labour and services necessary to complete the work.
2.6 RESTORATION
.1 Contractor shall ensure that all equipment and materials are removed from the
Limits of Construction upon completion of the Work and that all areas disturbed
as part of the Work are restored to their preconstruction conditions in accordance
with the Contract Documents.
.2 Contractor shall ensure that the Work is completed in accordance with the
environmental and operational constraints specified in the Contract Documents.
.3 Contractor shall restore the area in accordance with the requirements of Section
02315 Excavating, Trenching and Backfilling.
CN – DESIGN & HIGH FLOW CONTINGENCY PLAN SECTION 02160
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 6 OF 6
MI. 36.79 TO 41.00 HALTON SUB
PART 3 - MEASUREMENT AND PAYMENT
3.1 MEASUREMENT
3.2 PAYMENT
.1 Payment for the Work of this Section shall be deemed included in the applicable
item in the Form of Tender, including but not limited to design, supply, install and
removal of dewatering system, temporary flow diversion, flood emergency
response plan and erosion and sediment control plan as necessary to complete
the Work of this Section.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the requirements for the existing signal and fiber optic
cable and the new conduits for the future signal and fiber optic cable for the
Work.
.1 Supply and install permanent signal conduits HDPE SDR 11 and pull boxes for
CN S&C shown on the Contract Drawings.
.3 Supply and install new hot dip galvanized steel casing pipe with min. 7.1 mm
thickness (schedule 40) for the location shown on the Contract Drawings.
.4 Supply and install new hot dip galvanized steel casing pipe with min. 12.8 mm
thickness (schedule 40) for the location shown on the Contract Drawings.
.5 The work of this Section consists of the location and protection of all signal and
fibre optic cables in the areas of the works as outlined on the Contract Drawings.
.6 Railway and third-party signal and fibre optic cables in the area will be relocated
by others prior to and during construction. Cables that remain in place shall be
protected by the Contractor.
.7 Remove inactive Utilities and cable. Protect existing active Utilities and cables.
.8 Supply all labour, material and equipment required to locate and protect all CN
and all other fibre optic cables in the area of the works, all to the satisfaction of
the Engineer and/or CN Signals and Communications maintainer.
CN – DESIGN & SIGNAL AND FIBRE OPTIC CABLES SECTION 02200
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 13
MI. 36.79 TO 41.00 HALTON SUB
.9 The Contractor shall use a vacuum truck to locate, verify and identify conflicts for
all existing Utilities within and along the Rail Corridor, and all Utilities and
municipal service connections located in municipal roads that are included in the
Site.
.10 The Contractor shall use a vacuum truck to locate and verify all existing
infrastructure including existing Utilities, cables, pull boxes, and handholes within
the Site along the entire Rail Corridor, and shall consider the following:
.11 The Contractor shall coordinate with all Utility Companies of the existing Utilities
to remove, protect, and relocate existing Utilities and install all new underground
Utilities for the Works.
.1 The Contractor is responsible for conducting its own quality assurance program
to ensure that the work for underground utilities, meets the requirements of this
Section and Section 01620 Quality Assurance.
.2 The Contractor shall perform all the testing as part of its scope under Section
01620 Quality Control and Assurance, and in accordance with the requirements
of this Section.
1.6 SUBMITTALS
.1 The Contractor shall submit the following submittals for review in accordance
with the requirements of Section 01340 Submittals:
.2 Product data for all types of conduits, handwells and pull boxes; includes
but not limited to:
.1 Material
.2 Density
.3 Water Absorption
.5 Melt Flow
.6 Brittleness Temperature
.7 Tensile at Yield
.8 Elongation at Break
.6 Work Plan Methodology for Casing (or Conduit) Installation by Open Cut;
.7 Inspection and Test Reports submittal for all tests and inspections
performed by the Contractor appointed inspection and testing company in
accordance with this Section, including testing results to support proof
that conduits are clear, properly connected one piece to the next,
waterproof and capable of being filled with wires as required; and
.8 As-Built Drawings for the Works performed by the Contractor within the
Limits of Construction.
CN – DESIGN & SIGNAL AND FIBRE OPTIC CABLES SECTION 02200
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 13
MI. 36.79 TO 41.00 HALTON SUB
.9 The Contractor shall submit a confirmation from the supplier to confirm
that all HDPE products (Conduits and pull boxes) are designed to support
Copper E90 railway loading.
PART 2 - PRODUCTS
.2 Tracer wire, #14 AWG RWU90 green insulated copper conductor cable is
attached to the conduits for tracing, complete with terminal boxes,
markers and tracer wire connections;
.1 1-32mm Blue;
.2 1-32mm Red;
.3 1-32mm Brown; and
.4 1-32mm Green.
CN – DESIGN & SIGNAL AND FIBRE OPTIC CABLES SECTION 02200
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 6 OF 13
MI. 36.79 TO 41.00 HALTON SUB
.1 168.4 mm Dia. Schedule 40, 7.1 mm thick hot dipped galvanized steel
pipe and 550 mm Dia. Schedule 40, 12.8 mm thick hot dipped galvanized
steel pipe for power and communication conduit casing are installed in
the location indicated on the Contract Drawings;
.1 Pull box sizes and depth per the information provided in the Contract
Drawings.
.5 Fish Rope:
3.1 GENERAL
.1 The Contractor shall perform on Site inspections to determine the exact routing
of all new conduits and accommodate any modifications that may require Site
adjustment during the construction phases. The Contractor shall notify the
Engineer of any such changes before incorporating into the design or
construction.
.2 The locations of the pull boxes provided on the Contract Drawings are
approximate. The Contractor shall adjust the location based on the Site
conditions.
.3 The Contractor shall obtain written approval from the Engineer before splicing
any conduits. In the event that approval is granted, butt fusion welding shall be
used to splice conduits.
.5 The Contractor shall clean and reinstate the areas affected by the works and
reinstate the original elevation and conditions before installation.
.1 The Contractor shall coordinate with the Engineer for any installation of power
and signal railway signal cables.
.2 Pull boxes are located no closer than 3 m from the centerline of the track;
.4 The top of the pull boxes is sealed, level, and even with the surrounding
finish grade. The Contractor shall avoid placing the pull boxes under the
ballast;
CN – DESIGN & SIGNAL AND FIBRE OPTIC CABLES SECTION 02200
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 8 OF 13
MI. 36.79 TO 41.00 HALTON SUB
.5 Flexible ducts are routed through the bottom of the pull boxes and capped
300 mm above the bottom. Conduits shall be placed in the designated
boxes;
.6 The grading around the pull boxes is adjusted to the elevation shown on
the Drawings or reinstated to the original conditions; and
.7 Lid for the pull boxes is supplied with the name of the utility in the box:
.1 Signals; and
.2 Power.
.2 The Contractor shall ensure that for all casings installed across existing tracks
using directional drilling or any other location by directional drilling, The
Contractor shall submit for review, a Work Plan Methodology for Conduits by
Directional Drilling indicating the Contractor’s methodology including:
.2 A procedure for avoiding and detecting drill contact with obstructions. This
procedure shall include a description of the emergency recovery
procedure if unintended contact with obstruction occurs;
.3 The Contractor shall submit Work Plan Methodology for Casing (or Conduit)
Installation by Open Cut submittal for review providing a detailed construction
methodology including a Construction Settlement Monitoring Plan (CSMP), in
accordance with the Contract Documents prior to commencing work. For the
installation of conduits at the road, the Contractor shall ensure that Work Plan
Methodology for Casing (or Conduit) Installation by Open Cut shall also include:
.4 The Contractor shall ensure that all casing pipes are either capped or all ends
are plugged and terminated as follows:
.3 Sealing compound shall be injected between the casing pipe and the
HDPE conduits.
.1 The Contractor shall control the excavation process for open cut utility trench on
daily basis. The trench must be backfilled at the end of the work shift to avoid any
hazard to rail operations and maintenance crews.
.2 The Contractor shall ensure that excavation does not interfere with the normal
45-degree splay of bearing from either the bottom of the base slabs or the edge
of tie footings and bearing structures.
CN – DESIGN & SIGNAL AND FIBRE OPTIC CABLES SECTION 02200
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 10 OF 13
MI. 36.79 TO 41.00 HALTON SUB
.3 If an unknown utility is found, the Contractor shall stop the activity immediately
and contact the utility locator to identify the Utility Company. The Contractor shall
coordinate with the Engineer and the Utility Company regarding the relocation
and protection of the utility.
.4 If an existing utility is damaged, the Contractor shall immediately stop the work
and notify the Engineer and the Utility Company. The Contractor shall replace or
reinstate the damaged utility to the original conditions.
.1 The Contractor shall install the conduits upon completion of the subgrade layer
as indicated on the Contract Drawings, by open cut direct buried or directional
drilling methods.
.2 The Contractor shall install the conduits in the hot dipped galvanized steel pipe in
the locations as shown on the Contract Drawings.
.3 The Contractor shall interrupt existing duct banks and provide pull boxes and
new duct banks as necessary.
.4 The Contractor shall make directional changes in conduits runs exceeding a total
of 10 degrees, either vertically or horizontally, by long smooth bends that have a
minimum radius of curvature of 25 feet.
.5 The Contractor shall cap the conduits at both ends immediately after the proofing
process. The Contractor shall ensure that the conduits are ready for future use.
The Contractor shall fill all conduits entering pull boxes or housings with a sealing
compound after installing the cables.
.6 The Contractor shall provide, compact and cover sand bedding in accordance
with Section 02315 Excavation, Trenching and Backfilling and OPSS.PROV
1001. Prior to the commencement of bedding, pipe laying and backfilling, the
Contractor shall ensure that the trench is free of debris and sharp rocks.
.7 Prior to backfilling the trench, the Contractor shall ensure that the conduits are
lying flat, and are not intertwined with one another, to allow for future
unobstructed installation of cables.
.8 The Contractor shall mark routing of ducts with cable marker tape placed along
the centerline of the trench, approximately 500 mm below finished grade.
.9 The Contractor shall provide the installed conduits and ensure that all conduits
are free of water, debris, breakage and distortion. The Contractor shall submit a
proving certificate for each section of the conduits, witnessed and signed by its
inspection and testing company.
CN – DESIGN & SIGNAL AND FIBRE OPTIC CABLES SECTION 02200
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 11 OF 13
MI. 36.79 TO 41.00 HALTON SUB
.10 The Contractor shall carry out restoration of the Site upon completion of the Work
in accordance with Section 02315 Excavation, Trenching and Backfilling and the
requirements of the authorities having jurisdiction.
.11 Modern signals and communications cables are conveyors of high technology
information. Disruption of this service is costly to repair and most importantly,
causes severe loss of revenue and inconvenience to CN, and their customers. In
addition, the cables carry high voltages that could cause serious injury or fatality.
Therefore, it is important that Contractors use extreme caution when working in
the vicinity of any signals and communications cable:
.12 Take every conceivable precaution to ensure that the cables are not damaged.
.13 Supply and maintain the required protection of all signals and communications
cables within the working limits, including overhead cables.
.14 For all underground cables, adhere to the following specific procedures:
.1 Do not operate any heavy equipment nor excavate mechanically within 1 meter
(3 feet) of the cable until arrangements for protecting the cable have been made
with the Engineer.
.2 Prior to commencing any excavation work or any work near and around the fibre
optic or signal cables, the Contractor shall provide the railway flagman a copy of
a current locate sheet, no more than 30 days old, for their records and
information.
.3 Prior to commencing any excavation work or any work near and around the fibre
optic or signal cables, the Contractor shall receive authorization daily from the
Engineer and confirm that the Engineer has notified CN's Network Management
Centre at (800) 661-3687.
CN – DESIGN & SIGNAL AND FIBRE OPTIC CABLES SECTION 02200
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 12 OF 13
MI. 36.79 TO 41.00 HALTON SUB
.4 Prior to excavation, all cables must be exposed by approved hydra-vac service
over the entire area of the works, at intervals approved by the Engineer and/or
CN Signals and Communications maintainer Generally, cables will require
locating as directed and where new facilities cross existing cables.
.5 Record and mark location and depth of cables on a working copy of plans. Place
a marker, to protrude not more than 100 mm (4”) above original ground, in the
hole indicating location and depth of cables and immediately backfill holes with
approved material. No open holes will be allowed at the end of the work shift.
.6 The Contractor may also be required to expose cables not in the immediate area
of excavation, in order to provide positive identification of the cables. The
Engineer and
.1 All excavations required within 1 meter (3 feet) of the cable shall be done
carefully, with hand digging or approved hydra-vac service only, and in the
presence of the Engineer and/or CN Signals and Communications maintainer.
.2 When it is necessary to cross over the cable with heavy equipment or during
blasting operations, the Contractor shall protect the cable with 1 meter (3 feet) of
cover or greater depth, as dictated by ground conditions and determined by the
Engineer. Material used for cover shall be approved fill and separated from the
ballast shoulder by means of a heavy filter fabric. The Railway roadbed shall be
restored to its original elevations on completion of the works:
3.9 DAMAGE
.2 The Contractor shall be held liable for any costs for repairs and loss of revenue
resulting from any disruption to the cable system caused by their operation.
4.1 GENERAL
.1 Measurement and payment for all work of this section shall be in accordance with
the Schedule of Prices listed in the Form of Tender and shall include all labor,
equipment, surveying, and material required to perform the work specified herein.
CN – DESIGN & SIGNAL AND FIBRE OPTIC CABLES SECTION 02200
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 13 OF 13
MI. 36.79 TO 41.00 HALTON SUB
4.2 HYDRA-VAC TRUCKS
4.3 CONDUITS
4.5 PAYMENT
.1 Payment for the Work of this Section shall be included in the unit prices included
in the Form of Tender. Payment will be full compensation for all materials, labour,
use of equipment, tools and incidentals necessary to complete the Work of this
Section.
.2 Supply of water for hydra-vac trucks, disposal of excavated materials and backfill
for holes for the Work shall be considered incidental to the work, and no separate
payment will be made for these items, except for items under Provisional Items
as approved by the Engineer.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specifications.
PART 1 - GENERAL
1.1 GENERAL
.1 This Section specifies the requirements for Construction monitoring for the Work.
.2 The Contractor shall undertake Construction monitoring for the Work activities
that are carried out in close proximity to the existing railway track, all type of
structures, embankments, as well as all types of underground structures
(including existing sewers, watermains, gas main, fiber optics works and other
buried and all types of surface features).
.3 The Contractor acknowledges that its operations may pose a risk to existing
adjacent and nearby infrastructure due to vibration, soil displacement,
dewatering, and settlement. The Contractor shall perform all work using methods
that minimize all possible risks to the surface and buried structures, services and
features.
.5 The Contractor will be required to make restitution to the Railway for all costs
required for repairs to the railway tracks if as a result of their operations, it is
determined that the elevation or alignment of the railway tracks has changed.
.20 HDD Drilling, Pullback Oil Pipeline Relocation Project Section 15240
1.5 SUBMITTALS
.1 The Contractor shall submit the following submittals for review in accordance
with this Section and Section 01340 Submittals:
.2 During Construction, the Contractor shall monitor all operations for the following:
.3 The Contractor shall take all possible reasonable steps through its Construction
means and methods to ensure that:
.7 The Contractor shall carry out all the monitoring in accordance with the
requirements stated in this Section that identifies the following:
.3 The monitoring frequency and duration for each instrument and reading;
.8 The Engineer will review the Contractor’s monitoring program in accordance with
Section 01340 Submittals, requirements and provide recommendations, including
CN – DESIGN & CONSTRUCTION MONITORING SECTION 02201
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 12
MI. 36.79 TO 41.00 HALTON SUB
suggestions to improve the system so that the monitoring program can be altered
to enable the Contractor to modify its Construction operations prior to any
structure or facility, railway track, and grading or railway equipment being
damaged or otherwise compromised.
.9 The Contractor shall submit to the Engineer a progress monitoring report within
three Business Days upon the Engineer’s request. The report shall include
proactive actions required for any Construction impact mitigation. The Contractor
shall submit a post Construction survey report and post Construction track
monitoring report to the Engineer prior to Substantial Completion of the Project.
PART 2 - PRODUCTS
2.1 GENERAL
.1 The Contractor shall supply and install all necessary monitoring instrumentation
required to complete the Works and satisfy the requirements of the Contract
Documents including vertical displacement measuring points (i.e., settlement
rods), settlement and lateral movement pins, crack monitoring gauges, and other
required equipment.
2.2 LOCATIONS
.2 With regards to settlement and lateral movement for structures, the Contractor
shall, as a minimum, install one point on the structure of each property fronting
Construction and shall monitor daily for both horizontal and vertical
displacements before, during and after Construction:
.2 Contractor shall not use driven nails, pins, or marks made on the
structure for measurement of displacements as these devices or
markings can result in equivocal measurements or be dislodged from
their initiation location; and
.3 The Contractor shall indicate the location for the railway track and grading,
retaining wall, shoring and other piles in the track proximity in the Geotechnical
Instrumentation Monitoring Plan.
CN – DESIGN & CONSTRUCTION MONITORING SECTION 02201
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 6 OF 12
MI. 36.79 TO 41.00 HALTON SUB
PART 3 - EXECUTION AND REPORTING
3.1 GENERAL
.3 The Contractor shall submit monitoring reports (that include reference to the
Shop Drawings with numbered monitoring targets, pins and points) that show the
readings in tabular and graphical formats for all monitoring activities performed
during the previous week. Upon completion of the monitoring program, the
Contractor shall ensure that a final report is submitted that demonstrates the
results and interpretation of the readings. The Contractor shall ensure that these
reports are included in the Geotechnical Instrumentation Monitoring Plan and
submitted in accordance with Section 01340 Submittals and Section 01620
Quality Control and Assurance.
.4 The Contractor shall take all possible reasonable steps to ensure that ground
movements associated with any Construction activity adjacent to or otherwise
affecting adjacent structures, services, railway track and grading or railway
equipment are minimized and subsequently reflected in the monitoring reports.
.6 The Contractor shall undertake regular monitoring of the horizontal and vertical
alignment of the railway track and grading.
.7 ‘Alert levels’ with actions to be taken, are required. The alert levels shall
be as indicated in Table 1:
.1 Allowable Limits: The Contractor will review the available data and
provide comments on any potential ground movement concerns
and implications to railway operations. The ground movement
monitoring reports shall be forwarded to CN or CN representative
within 24 hours of readings;
.1 At any location where the Engineer deems that the Contractor’s work methods
may destabilize the existing track bed, the Contractor is required to undertake
ground and track movement monitoring and install a track protection system and
monitoring system. Both angular movements and vertical settlement shall be
monitored by the Contractor.
.2 For the purposes of design, the nearest point at which excavation can be
undertaken, is as follows:
.3 All excavations must comply with the Occupational Health and Safety Act.
.3 Either angular movement or settlement of the ground behind the track protection
that exceeds the establishment limits shall be reported to the Engineer
immediately.
.4 The following method of monitoring for horizontal and vertical settlement and
reporting limits shall be implemented:
.2 The Contractor shall be required to take survey shots of the elevation and
location of these monitoring rods prior to start of construction and on a
daily basis and shall send the monitoring reports (tracking X, Y, and Z
direction movements) to the Engineer via facsimile or e-mail, within 24
hours;
.1 Monitoring Guidelines: The monitoring requirements are for one (1) utility
crossing. For more than one (1) utility crossing, the monitoring requirements are
subject to change (i.e. monitoring points shall monitor all utility installations).
.2 Contractor shall ensure that over-excavation does not occur and the
liner/casing is installed tight to the excavation;
CN – DESIGN & CONSTRUCTION MONITORING SECTION 02201
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 11 OF 12
MI. 36.79 TO 41.00 HALTON SUB
.3 Report theoretical vs. actual volumes of spoils removed on per meter and
total bases;
.4 Contractor shall ensure that the excavation is fully supported until the
liner/pipe installation is complete;
.5 Ensure that the bulkhead is installed at the end of every work shift or
during any prolonged stoppage of work; and
.6 Ensure that voids are fully grouted to refusal immediately after the
completion of liner/pipe installation.
.1 Progress of the contractor and pipe installation and what work was
completed on that day;
.1 Station;
.4 Difference in Elevation.
.1 The Contractor shall not backfill or remove instruments until they are no longer
required, including until Substantial Completion, if it is required.
CN – DESIGN & CONSTRUCTION MONITORING SECTION 02201
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 12 OF 12
MI. 36.79 TO 41.00 HALTON SUB
.2 The Contractor shall backfill borehole casings for removed instruments with
cement grout up to the underside of surface restoration.
.3 The Contractor shall backfill surface excavations with unshrinkable fill when
within roadways or sidewalks and with selected fill when outside of such areas up
to the underside of surface restoration. The Contractor shall remove steel
casings, if any, to a minimum depth of 1500 mm below the ground surface.
.1 The Contractor shall not disclose any Construction data to third parties and shall
not publish data without prior approval and written consent of the Engineer.
4.1 MEASUREMENT
4.2 PAYMENT
.1 Payment for Work of this Section shall be included in the unit-priced item
included in the Form of Tender for construction monitoring. Payment will be for
full compensation for all materials, labour, use of equipment, tools, submittals,
monitoring reports, reinstatement of the monitoring system, removals of the
monitoring system and incidentals for the Work.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the noise and vibration monitoring and control
requirements for the Works.
.3 The Contractor shall supply all labour, Products, equipment, tools, supervision,
and services necessary for noise and vibration monitoring and control work and
reading vibration instruments specified in this Section.
.4 The Contractor shall supply monitoring data to the Engineer and shall ensure that
all data is considered acceptable and accurate for the purposes of assessing the
noise and vibration levels for the Project. The Contractor acknowledges that the
Engineer will rely on this data for the interpretation of noise and vibration levels
from construction activities for the Project. The Contractor shall submit
monitoring data in weekly reports. In addition, the Contractor shall make
available daily data as and when requested by the Engineer.
.3 The Contractor shall refer to the Technical Data Report for Noise Effects
Assessment included in Background Information (Stantec 2015).
CN – DESIGN & NOISE AND VIBRATION SECTION 02202
CONSTRUCTION MONITORING AND CONTROL SEPTEMBER 2023
MILTON LOGISTICS HUB – PHASE 2A PAGE 2 OF 9
GRADING & DRAINAGE
MI. 36.79 TO 41.00 HALTON SUB
.4 The Contractor shall refer to the Geotechnical Investigation Report for the Project
included in Background Information.
1.4 DEFINITIONS
.5 “The Frequency of Vibration” means the rate of oscillation that occurs in one
second, measured in hertz (Hz), where 1Hz equals one cycle per second.
.1 The Contractor is responsible for conducting its own quality assurance program
to ensure all the work related to noise and vibration monitoring meet the
requirements of this Section and Section 01620 Quality Control and Assurance.
1.6 SUBMITTALS
.1 The Contractor shall ensure all submittals comply with Section 01340 Submittals
and Section 01560 Environmental Requirements.
.5 Submit Weekly Noise and Vibration Monitoring Summary Report that also
includes notifications of vibration limit, including the following:
.2 The Contractor shall route haulage and dump trucks on main roads where
possible;
.3 The Contractor shall use vehicles and equipment with efficient muffling
devices;
.4 The Contractor shall minimize drop heights of materials and use positive
noise attenuation for all construction zones where repetitive metal to
metal contact may generate excessive noise, i.e. muck cars, tipping
chains, dump trucks and excavators; and
.1 The Contractor shall conduct noise and vibration monitoring including baseline
measurements near sensitive receptors, in accordance with Section 01560
Environmental Requirements.
CN – DESIGN & NOISE AND VIBRATION SECTION 02202
CONSTRUCTION MONITORING AND CONTROL SEPTEMBER 2023
MILTON LOGISTICS HUB – PHASE 2A PAGE 5 OF 9
GRADING & DRAINAGE
MI. 36.79 TO 41.00 HALTON SUB
PART 2 - EQUIPMENT
.2 The Contractor shall be responsible for maintaining power to the noise and
vibration monitoring equipment. It is assumed that these will be battery operated.
If an alternative power source will be used, such as solar or direct grid
connection, the Contractor shall provide details in accordance with Section
01340 Submittals for review.
.3 The Contractor shall submit a list of noise and vibration monitoring equipment,
including name, model, manufacturer, and serial number to the Engineer or the
Engineer Representative for review as part of its Construction Noise and
Vibration Management Plan, in accordance with Section 01340 Submittals.
.4 The Engineer reserves the right to request any manufacturer documentation for
the noise and vibration monitoring equipment.
.4 Monitoring equipment shall be calibrated within one week prior to its initial use
and once per month thereafter
PART 3 - EXECUTION
.1 The Contractor shall coordinate with the Engineer to secure the easement
required for installation of the monitors at the private properties.
.2 The Contractor shall conduct baseline noise and vibration readings as specified
in Section 01560 Environmental Requirements and shall submit a detailed report
of baseline noise and vibration monitoring results to the Engineer in accordance
with Section 01340 Submittals.
.5 When requested by the Engineer, the Contractor shall facilitate access to the
Contractor-installed equipment to all the Engineers to obtain independent
readings.
.7 The microphone of the noise monitor(s) shall be placed between 1.5 and 4.5
meters above the local ground level
.8 The frequency weighting of the sound level meter shall be set to “A” using a “fast”
response.
.9 Vibration monitoring shall be conducted for structures that are within the Zone of
Influence of construction activities where the predicted vibration levels exceed
the limits set in Section 3.2.
.1 The Contractor shall ensure that the noise and vibration level limits comply with
requirements under Section 01560 Environmental Requirements.
.1 The Contractor shall not disclose any instrumentation data to third parties and
shall not publish data without prior approval and written consent of the Engineer.
.1 The Contractor shall ensure that the Construction Noise and Vibration
Performance Limits are not exceeded. The Contractor acknowledges that
activities may be suspended in the affected area with the exception of those
actions necessary to avoid exceeding Construction Noise and Vibration
Performance Limits or to make the work and affected properties safe and secure.
CN – DESIGN & NOISE AND VIBRATION SECTION 02202
CONSTRUCTION MONITORING AND CONTROL SEPTEMBER 2023
MILTON LOGISTICS HUB – PHASE 2A PAGE 7 OF 9
GRADING & DRAINAGE
MI. 36.79 TO 41.00 HALTON SUB
.2 If a Construction Vibration Peak Particle Velocity Limit is reached, the Contractor
shall:
.1 Notify the Engineer within one hour of any levels that exceed the Alert
Level;
.3 Identify the source causing the excessive noise or vibration, e.g. specific
Construction equipment or activity, or extraneous source un-related to
construction;
.1 The Contractor shall ensure that additional noise and vibration monitors are kept
at the Site such that field monitors can be replaced within 24 hours in the event
of equipment failure.
.2 The Contractor shall ensure that all noise and vibration monitoring is a
continuous operation. In the event of an equipment failure (for any reason), the
Contractor shall complete the following:
.1 The vibration technician shall check the equipment within eight hours of a
failure and conduct an equipment review. The vibration technician shall
prepare an Equipment Failure Report and submit it to the Engineer
regarding the nature of the failure and the action steps necessary to
repair the equipment. The Equipment Failure Report shall be sent to the
Engineer no later than 24 hours after equipment failure;
PART 4 - REPORTING
4.1 GENERAL
.5 The Contractor shall ensure that the Final Noise and Vibration
Monitoring Summary Report does not refer to the other reports
and acknowledges that this report shall be considered a
standalone report to document all noise and vibration monitoring
completed for the Project.
CN – DESIGN & NOISE AND VIBRATION SECTION 02202
CONSTRUCTION MONITORING AND CONTROL SEPTEMBER 2023
MILTON LOGISTICS HUB – PHASE 2A PAGE 9 OF 9
GRADING & DRAINAGE
MI. 36.79 TO 41.00 HALTON SUB
PART 5 - MEASUREMENT AND PAYMENT
5.1 MEASUREMENT
5.2 PAYMENT
.1 The Lump Sum Prices submitted in the Form of Tender shall include all labour,
materials and equipment required to complete the work and submit the reports.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specifications.
PART 1 - GENERAL
1.1 SCOPE
.3 The Contractor acknowledges that its operations may pose a risk to existing
adjacent and nearby infrastructure due to vibration, soil displacement,
dewatering, and settlement. The Contractor shall perform all Works using
methods which minimize all possible risks to the surface and buried structures,
services and features. The Contractor shall have in place a fully documented
program of planned inspections and consequent actions will be undertaken by
the Contractor to ensure that this requirement is met.
.4 The Contractor shall undertake conditions surveys prior to proceeding with the
construction work that shall be carried out adjacent to the existing railway track
and grading, structures (all types, including industrial, commercial and
residential), embankments, as well as all types of underground structures
(including existing sewers, watermains, gas main, fiber optics works, buried and
surface features) and all road right of way assets (including sidewalks, curbs,
cycling facilities, road surfaces and medians).
.5 The Contractor shall undertake post-condition surveys for locations (for which
pre-condition surveys was performed) after the Works is complete.
.1 The Contractor is responsible for conducting its own quality assurance program
to ensure conditions surveys, meet the requirements of this Section and Section
01620 Quality Control and Assurance.
.2 The Contractor shall retain the services of Pre and Post Conditions Survey
Company, in accordance with the requirements of Section 01620 Quality Control
and Assurance, responsible for conducting their own pre-condition and post-
condition survey of all existing structures, buildings and other services which
have any possibility of being affected by the Contractor’s activities.
.3 Contractor shall ensure that all the Pre-Condition Survey Reports and Post-
Condition Survey Reports are signed and stamped by a professional engineer
licensed to practice in the province of Ontario.
CN – DESIGN & CONDITIONS SURVEYS SECTION 02203
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 6
MI. 36.79 TO 41.00 HALTON SUB
1.5 SUBMITTALS
.1 The Contractor shall submit the following submittals for review in accordance
with this Section, Section 01340 Submittals and Section 01620 Quality Control
and Assurance:
.1 Derry Road:
.2 Britannia Road:
.1 Prior to the commencement of any construction on the Site, the Contractor shall
perform pre-condition surveys of all existing roads, railway tracks, buildings,
structures and grading, railway equipment and other services, as well as City of
Milton road right of way assets which may be affected by the Works.
.2 The Contractor shall acquire written permission from the property owners of the
Lands on which surveys will be completed prior to undertaking pre-condition and
post-condition surveys.
CN – DESIGN & CONDITIONS SURVEYS SECTION 02203
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 6
MI. 36.79 TO 41.00 HALTON SUB
.3 The Contractor shall ensure that the pre-condition survey shall include the
locations and conditions of adjacent properties, buildings, underground
structures, utility services and structures that may be affected by the Works,
including all areas of permanent or temporary work, all areas of temporary
structures and shoring and all residences abutting the Rail Corridor.
PART 2 - PRODUCTS
2.1 GENERAL
.1 The Contractor shall supply and install all necessary monitoring instrumentation
required to complete the Works and satisfy the requirements of the Contract
Documents including vertical displacement measuring points (i.e., settlement
rods), settlement and lateral movement pins, crack monitoring gauges, and other
required equipment.
2.2 LOCATIONS
3.1 GENERAL
.1 Derry Road:
.2 Britannia Road:
.2 The pre-condition survey shall include but not be limited to pavement structures,
sidewalks, utilities, and drainage that shall be impacted by the contractor
vehicles, trucks and equipment.
.5 Pre-Condition Survey Report: The Contractor shall ensure that the Pre-Condition
Survey Report includes the following:
.1 The owners and occupiers of Lands that fall within the zone of influence
of the construction activities as noted above. These owners and
occupiers are to be advised of the survey by public notice (i.e. pamphlet,
newspaper) provided by the Contractor. The Contractor shall coordinate
with and have the notice reviewed by. The Contractor shall ensure that
the Engineer and the affected community are informed well in advance of
the zone of influence;
.7 The Contractor shall ensure that all of the pre-condition and post condition
surveys and inspections, photographs, notes, and videotapes form a clearly
documented record of the benchmark conditions existing on the Site prior to the
commencement of construction operations.
4.1 MEASUREMENT
4.2 PAYMENT
.1 The Lump Sum Prices submitted in the Form of Tender shall include all labour,
materials and equipment required to complete the work.
GENERAL CONDITIONS
The General Conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the requirements for site demolition, salvage and removal,
wholly or in part of those materials and structures as designated within the Limits
of Construction for the Work.
1.3 REFERENCES
.1 The Contractor is responsible for conducting its own quality assurance program
to ensure all materials, equipment and removals, meet the requirements of this
Section and Section 01620 Quality Control and Assurance.
CN – DESIGN & SITE DEMOLITION & REMOVALS SECTION 02225
CONSTRUCTION MILTON LOGISTICS HUB -PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 4
MI. 36.79 TO 41.00 HALTON SUB
1.5 SUBMITTALS
.1 The Contractor shall provide submittals for review in accordance with the
requirements of this Section and Section 01340 Submittals.
.1 Protect existing items designated to remain and items designated for salvage. In
the event of damage to such items, immediately replace or make repairs with the
approval of the Engineer and at no cost to CN.
.1 Removal and disposal of existing fences of all types, including footings and
gates.
.4 Removal and disposal of part of existing culvert and headwall, cleaning existing
culvert, grout remaining portion of the culvert.
.8 Removal and disposal of existing power and light poles including light pole
foundations.
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.1 PREPARATION
.1 Inspect site with Engineer and verify extent and location of items designated for
removal and items to remain.
.2 Locate and protect utilities. Preserve active utilities traversing site in operating
condition.
.3 Contractor shall notify and obtain approvals from all agencies as required prior to
commencing site demolition and removals.
.4 Identify the Limits of Construction on the Contract Drawing and remain within the
limits.
3.2 REMOVAL
.1 Remove items as indicated in the Contract Drawings and as required for the
work.
.3 Utility Poles to be fully removed including the footing. Cutting off at ground level
is prohibited:
.1 Cables, if present, to be cut off and tied back to existing poles at ends of
work area.
.1 The Contractor shall ensure that all Site removals and waste material are
removed from the Site and disposed in accordance with Section 01560
Environmental Protection.
.2 Dispose of materials not designated for salvage or re-use in work off site.
3.4 SALVAGE
.1 The Contractor shall ensure that salvaged materials are delivered and stored
properly within the site at the locations provided by CN Rail. The Contractor shall
provide list of materials stored in the yard prior to delivery.
.1 Upon completion of site demolition and removals, restore areas and existing
works outside areas of demolition to match condition of adjacent undisturbed
CN – DESIGN & SITE DEMOLITION & REMOVALS SECTION 02225
CONSTRUCTION MILTON LOGISTICS HUB -PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 4
MI. 36.79 TO 41.00 HALTON SUB
4.1 MEASUREMENT
.1 Measurement and payment for work of this Section shall be in accordance with
OPSS.PROV 510 for the particular item as listed in the Schedule of Prices.
.2 All other demolition and removals will be incidental to the work of construction
and the costs thereof shall be included in other contract rates.
4.2 PAYMENT
.1 Payment for the Work of this Section shall be included in the unit prices included
in Form of Tender. Payment will be full compensation for all materials, labour,
use of equipment, tools and incidentals necessary to complete the Work of this
Section.
*** END OF SECTION ***
CN – DESIGN & CLEARING AND GRUBBING SECTION 02231
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 1 OF 5
MI. 36.79 TO 41.00 HALTON SUB
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the Clearing and Grubbing requirements for the Work. The
Contractor shall remove and dispose of trees and vegetation of any types and
sizes within the Limits of Construction of the Project.
.2 The Contractor shall undertake Clearing and Grubbing for all the Lands identified
as construction access and laydown areas within to facilitate the construction of
the Project.
.4 The Contractor shall undertake pruning of shared or boundary trees, scrub, and
shrubs of any diameter at breast height that conflict with Construction activities.
1.3 REFERENCES
.3 Province of Ontario – Fish and Wildlife Conservation Act, 1997, S.O. 1997, c. 41.
1.4 DEFINITIONS
.1 ‘Clearing’ consists of cutting off trees and brush vegetative growth and disposing
of felled trees, previously felled/fallen trees and stumps, and surface debris. This
surface debris may include fence-posts and wire, tires, barrels, metal objects
such as shopping carts, pieces of concrete and asphalt, wood and other building
materials, asphalt shingles, landscaping debris, etc.
.1 Not applicable
1.6 SUBMITTALS
.1 Not applicable
1.8 PROTECTION
PART 2 - PRODUCTS
.1 Not applicable
CN – DESIGN & CLEARING AND GRUBBING SECTION 02231
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 5
MI. 36.79 TO 41.00 HALTON SUB
PART 3 - EXECUTION
.2 Removal of vegetation/trees during the restricted period should only occur under
very limited circumstances. A qualified biologist hired by the Contractor shall be
retained to conduct a wildlife sweep to document the absence of migratory birds
and/or nests at those sites (including both vegetation and structures) at the time
of clearing. If the area is cleared by the qualified biologist, vegetation removal
should occur within 24 hours of the completion of the avian survey; otherwise, an
additional survey will be required.
.6 The Engineer shall not be responsible for any delays to the Contractor’s
operations where the Contractor fails to give sufficient advance notice to the
Engineer to carry out the required inspection.
3.2 PREPARATION
.1 Inspect the site and verify with Engineer items designated to remain.
.2 Locate and protect utility lines. Preserve active utilities traversing the site in
operating condition.
.4 Clearly mark out limits of all areas to be grubbed for approval of the Engineer.
.5 Clearing and grubbing operations shall not commence until areas have been
inspected and approved by the Engineer.
3.3 CLEARING
.4 Cut off branches and cut down trees overhanging the area as directed by
Engineer.
.5 Cut off and remove unsound branches on trees designated to remain as directed
by Contractor Certified Arborist.
3.4 GRUBBING
.1 Grub out stumps and roots to not less than 200 mm below ground surface.
.2 Grub out visible rock fragments and boulders, greater than 300 mm in greatest
dimension but less than 0.25 m3.
.1 Remove and dispose of all grubbed material off site, including all items listed in
Part 3.3 above. The Contractor may choose to chip and mulch the cleared and
grubbed material to the satisfaction of the Engineer and resulting mulch may be
left on site.
.1 Stockpile sufficient wood debris material to meet the requirements of the various
environmental features required by the Contract Drawings and Specifications.
.2 Topsoil will be stripped and stockpiled in accordance with the Grading Plan
Drawings and Soil Management Plan for all permanent and temporary
construction areas. Topsoil piles shall be marked with appropriate signage to
prevent accidental admixing. Topsoil shall not be imported to or exported from
the Site.
.5 Remove and dispose of any material not required for these works off site.
4.1 MEASUREMENT
.2 Measurements for work of this section shall be in hectares (ha) cleared based on
plan quantities for areas as shown on the Drawings.
.4 Individual trees that require removal may not be shown on the Contract
Drawings, the Contractor shall be responsible for removal as if shown on the
Contract Drawings. The removal of such trees shall be considered incidental to
clearing and no separate payment will be made.
4.2 PAYMENT
.1 Payment for the Work of this Section shall be included in the unit prices included
in the Form of Tender. Payment will be full compensation for all materials, labour,
Certified Arborist, use of equipment, tools and incidentals necessary to complete
the Work of this Section.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the erosion and sediment control requirements for the for
the temporary and permanent Work.
1.3 REFERENCES
.5 OPSD 219.211 – Temporary Rock Flow Check Dam Flat Bottom Ditch.
.1 The Contractor shall be responsible for conducting their own quality assurance
program to ensure that all erosion and sediment control for the Project meet the
requirements of this Section and Section 01620 Quality Control and Assurance.
1.5 SUBMITTALS
.1 The Contractor shall submit the following submittals in accordance with this
Section and Section 01340 Submittals:
.1 Not applicable.
PART 2 - PRODUCTS
2.1 MATERIALS
.4 Rock Flow Check Dam, Flat Bottom Ditch or Channel – OPSD 219.2110;
.7 Plywood; and
PART 3 - EXECUTION
3.1 GENERAL
.1 The Contractor shall comply with the Erosion and Sediment Control Plans
provided in the Contract Drawings and shall provide detailed site-specific
methods and drawings as part of a Surface Water Management Implementation
Plan (SWMIP). The Contractor shall submit the SWMIP to the Engineer and CN’s
Environmental Monitor in accordance with the schedule outlined in Section
01340 Submittals. The SWMIP shall include but not be limited to:
.1 Project/Site Information;
.3 Environmental Permits;
.6 Inspection Logs.
.2 The Contractor shall adhere to the timing windows outlined Section 01560
Environmental Protection and shown on the Contract Drawings.
.3 Install all erosion and siltation control devices and tree fencing prior to
commencement of clearing, grubbing and grading works, as outlined in the
Erosion and Sediment Control Plan and to the satisfaction of CN’s Environmental
Monitor. The Contractor shall notify CN’s Environmental Monitor of any proposed
changes to erosion and siltation control devices or installation resulting from site
conditions and shall be included in the inspection logs.
CN – DESIGN & EROSION CONTROL - GENERAL SECTION 02272
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 5
MI. 36.79 TO 41.00 HALTON SUB
.4 No work will be permitted on site until all such erosion and siltation control
devices are properly installed and verified by CN’s Environmental Monitor.
.5 The Contractor must limit vegetation disturbance and tree removal to the Limits
of Construction as per extents indicated in Contract Documents. The Contractor
shall install exclusion fencing in sensitive areas adjacent to active construction
areas in accordance with the Contract Drawings.
.6 Stockpiles onsite shall have silt fencing installed a minimum of 1m distance from
the toe of the stockpile.
.2 Maintain all erosion and siltation control devices to the satisfaction of CN’s
Environmental Monitor.
.3 The Contractor shall inspect all erosion and sediment control measures on a
weekly basis and before and after rainfall events (10 mm/24 hours) and
significant snow melts to ensure proper functioning, re-establish if damaged,
cleanout (when sediment accumulation reaches approximately 30%), and
provide a repair or restoration plan outline The Contractor is responsible for
correcting any identified deficiencies within one working day, following an
inspection. The Contractor shall report to CN’s Environmental Monitor any major
repairs within 24 hours and document in the inspection logs of the SWPPP and
the Monthly Compliance Report as outlined in Section 01340 Submittals.
.4 As part of the High Flow Contingency Plan detailed in Section 02160 High Flow
Contingency Plan, the Contractor shall subscribe to a meteorological alert
service, ensuring that there is advance warning of flood-producing severe rainfall
events; those producing more than 10 mm of rainfall precipitation in a 24-hour
period. Warning area to be focused on the Indian Creek Watershed (and its
tributaries).
.1 Install tree protection barriers at the Limits of Construction under the direction of
a Certified Arborist as outlined in Section 01560 Environmental Protection and as
directed by CN’s Environmental Monitor.
.2 Tree protection barriers must be maintained at 1.2 m high and consist of orange
plastic web snow fencing on a wood frame made of 2x4 boards. Where
CN – DESIGN & EROSION CONTROL - GENERAL SECTION 02272
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 5
MI. 36.79 TO 41.00 HALTON SUB
excavation or fill material is to be temporarily placed near a tree protection
barrier, plywood must be used to ensure no material extend beyond the Limits of
Construction.
4.1 MEASUREMENT
.1 Measurement for silt fence or fibre roll shall be by linear meter of properly
installed silt fence as measured in the field.
.2 Measurement for Rock Flow Check Dam shall be by each properly installed flow
check as measured in the field.
4.2 PAYMENT
.1 Payment for the Work of this Section shall be included in the unit prices included
in the Form of Tender. Payment will be full compensation for all materials, labour,
use of equipment, tools and incidentals necessary to complete the Work of this
Section.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of this
Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section 02276 specifies the requirements for the design and construction of
retained soil systems (RSS) walls and steep slopes, and the material requirements
for fabrication and delivery of RSS precast concrete elements, including panels for
facing elements, finishing caps, corner elements and other element types.
.6 Forms:
.1 PH-CC-701, Request to Proceed;
.2 PH-CC-702, Notice to Proceed; and
.3 PH-CC-822, Certificate of Conformance.
CN – DESIGN & RETAINED SOIL SYSTEMS, WALL/SLOPE SECTION 02276
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 29
MI. 36.79 TO 41.00 HALTON SUB
.2 Ontario Provincial Standard Specifications (OPSS):
.1 Acceptance
.1 The acceptance of elements shall be according to the requirements of
this Section 02276, including satisfactory completion of all repairs, if
applicable. Elements not meeting the requirements of the Contract
Documents shall be deemed unacceptable and shall not be included
in the Work.
.2 Acceptance of compressive strength, air void system parameters,
rapid chloride permeability, salt scaling resistance and concrete cover
of wet cast concrete shall be on a lot basis.
CN – DESIGN & RETAINED SOIL SYSTEMS, WALL/SLOPE SECTION 02276
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 29
MI. 36.79 TO 41.00 HALTON SUB
.3 Acceptance of compressive strength, rapid chloride permeability, salt
scaling resistance and concrete cover of dry cast concrete shall be on
a lot basis.
.4 Elements whose surfaces have not been kept in a continuously wet
condition shall be rejected and replaced.
.5 The lot size shall represent all precast elements from one structure,
from a single RSS supplier, with a maximum lot size of 500 m2 of
vertical face of the RSS. The lot size shall be confirmed by the
Engineer and remain consistent for the duration of the Contract.
.6 Unacceptable lots shall be rejected and replaced.
.7 Concrete Temperature
.1 Elements that meet the temperature requirements of this Section
02276 during production and the curing period are considered
acceptable. Elements that do not meet one or more of the
temperature requirements of this Section 02276 are considered
unacceptable and shall be rejected and replaced.
.8 Concrete Cover
.1 The Engineer shall carry out a covermeter survey on the concrete
elements prior to installation. Measurements shall be carried out on
multiple concrete elements randomly selected by the Engineer, at
CN – DESIGN & RETAINED SOIL SYSTEMS, WALL/SLOPE SECTION 02276
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 7 OF 29
MI. 36.79 TO 41.00 HALTON SUB
multiple locations on the elements. A total of thirty (30) measurements
per lot shall be carried out.
.2 Acceptance of concrete cover over steel reinforcement shall be based
on the percentage of satisfactory measurements. The concrete cover
over reinforcing steel shall be within -5/+15 mm of the specified
concrete cover. When 10.0% or more of the total number of
measurements per lot is outside the specified limits, the lot shall be
unacceptable.
.3 Unacceptable lots shall be rejected and replaced.
.4 The Engineer shall provide the results of the covermeter survey to the
Contractor.
Bugholes
Low Cover
Cracks
.1 The Engineer shall inspect the work to determine if the completed RSS has
any deficiencies identified in the below tables. If RSS contains any of the
deficiencies listed in the tables below, the RSS shall be deemed rejectable.
Medium N/A ≤ 50
Notes:
CN – DESIGN & RETAINED SOIL SYSTEMS, WALL/SLOPE SECTION 02276
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 11 OF 29
MI. 36.79 TO 41.00 HALTON SUB
RSS Deficiencies
.1 The Owner shall accept the RSS at the end of the RSS warranty period if
none of the deficiencies listed in the tables in Clause 1.4.2.1 of this Section
02276 are found during the warranty inspections. The RSS shall not be
accepted until all deficiencies have been repaired by corrective work.
.4 Warranty Inspections
.1 Throughout the warranty period the Owner will carry out warranty
inspections of the RSS for deficiencies in accordance with the tables in
Clause 1.4.2.1 of this Section 02276. The Owner will notify the Contractor as
to the date and time of the inspection(s) and the Contractor may, at their
discretion, be present during the inspection(s).
.2 Within two (2) weeks following a warranty inspection, the Owner will notify
the Contractor in writing of all deficiencies that require corrective work.
1.5 SUBMITTALS
.1 Shop Drawings
.2 The RSS superintendent shall always have a copy of the Shop Drawings on
site during the construction of the RSS.
.2 RSS Superintendent
.3 Manufacturer’s Representative
.2 The Engineer shall be notified in writing 48 hours prior to each site visit by
the manufacturer’s representative. The advance notice shall include the
dates and locations the manufacturer’s representative will be on site.
.4 Inspection Reports
.3 Where the design height of the RSS is greater than 5.0 m, the inspection
report shall document inspections at the constructed height of the RSS at
5.0 m, 10.0 m, and 15.0 m, as applicable, up to and including the design
height.
.1 The concrete mix design shall be submitted according to the Mix Design
clause in Section 03312 Concrete Work.
.1 The certificate verifying compliance of the precast plant with the certification
requirements of the Canadian Standards Association (CSA) or the Canadian
Precast Concrete Quality Assurance Certification Program (CPCQA) shall
be submitted to the Engineer with the concrete mix design Form A
submission.
.4 The elements shall not be delivered to the site until the Engineer has
received the Manufacturer’s Certificate of Conformance, the precast report
and issued MTO Form PH-CC-702, Notice to Proceed.
PART 2 - PRODUCTS
2.1 DESIGN
.1 General
CN – DESIGN & RETAINED SOIL SYSTEMS, WALL/SLOPE SECTION 02276
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 15 OF 29
MI. 36.79 TO 41.00 HALTON SUB
.1 The RSS shall be designed according to the approved product drawings,
CSA S6, MTO Structural Manual, and the Contract Documents.
.2 The geometric requirements of the RSS, such as lines and grades of the
facing elements and typical cross sections, shall be as specified in the
Contract Documents.
.2 RSS Selection
.1 An RSS shall be selected from the MTO’s DSM that meets the application,
performance and appearance requirements for that RSS, as specified in the
Contract Documents.
.2 An RSS shall be selected from the MTO’s DSM designated as either ‘A’
(Accepted) or ‘DE’ (Demonstration). RSS designated as ‘DE’ status requires
inspection, instrumentation and monitoring of the constructed RSS, and the
reporting of the findings to the MTO by the manufacturer as specified in the
Qualification Criteria for RSS.
.3 When there is more than one RSS included in the same tender item number
for payment, all RSS for the tender item shall be selected from the same
MTO’s DSM including type and colour of facing elements.
.3 Obstruction
.1 Design details of the RSS shall be provided for all obstructions as specified
in the Contract Documents. Where an obstruction exists but is not located to
sufficient accuracy for the design of the RSS, the obstruction shall be
located in the field to sufficient accuracy as required to design the RSS.
.2 The Owner warrants the data in the foundation investigation report, except
that interpretations of the data and opinions expressed in the foundation
investigation report are not warranted.
2.2 MATERIALS
.1 General
CN – DESIGN & RETAINED SOIL SYSTEMS, WALL/SLOPE SECTION 02276
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 16 OF 29
MI. 36.79 TO 41.00 HALTON SUB
.1 All materials for the selected RSS shall be according to the approved
product drawings for that RSS.
.1 The RSS precast concrete elements, including panels for facing elements,
finishing caps, corner elements and other element types shall be as
specified in the Contract Documents.
.3 Burlap
.4 Concrete
.5 Concrete Sealers
.6 Formwork
.7 Hardware
.11 Water
.1 Water used for curing, fog misting, steam curing of concrete, including
presoaking of material for moist curing, shall be according to OPSS.PROV
1302.
.1 General
.1 Equipment made of aluminum material shall not come in contact with the
plastic concrete.
.2 Consolidating Equipment
.3 Contact Thermometers
2.4 PRODUCTION
.1 General
CN – DESIGN & RETAINED SOIL SYSTEMS, WALL/SLOPE SECTION 02276
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 18 OF 29
MI. 36.79 TO 41.00 HALTON SUB
.1 The Engineer shall be notified in writing at least seven (7) business days
prior to commencement of fabrication.
.3 Steel Reinforcement
.4 Production of Concrete
.5 Placing of Concrete
.1 General
.1 The method of transporting, placing, and consolidating the concrete
shall be such as to prevent segregation.
.2 Concrete shall be deposited within 0.5 m of the top of the steel
reinforcement, and 1.5 m horizontally of its final position.
.3 Concrete shall be placed at a steady rate, such that a monolithic
concrete is obtained without the formation of cold joints or pour lines.
.6 Consolidation
.2 Vibration shall not be used to make the concrete flow or to spread the
concrete more than 1.5 m from the point of deposit.
.7 Concrete Finishing
.8 Curing
.1 General
.1 Concrete shall be moist cured for 4 days except for concrete
containing silica fume which shall be moist cured for 7 days. Curing in
cold weather conditions shall be according to the Cold Weather
Protection Period clause of this Section 02276.
.2 Moist Curing
.1 Moist curing of exposed surfaces shall commence immediately after
concrete finishing. For elements with exposed surfaces that have
architectural finish, moist curing shall be applied within 30 minutes of
concrete placement.
.2 Moist curing shall be sufficient to keep all surfaces of the element in a
continuously wet condition, with no dry areas, by applying one or a
combination of the following methods:
.1 Curing according to the Curing with Burlap and Water clause
in OPSS.PROV 909.
.2 Curing by means of continuous water application; e.g., mist.
.3 Curing according to the Steam Curing and Other Application of
Heat clause in OPSS.PROV 909.
.4 Curing by means of immersion in water.
.3 Records of moist curing shall be maintained and submitted according
to the Manufacturer’s Certificate of Conformance and Precast Report
clause of this Section 02276. The records shall provide evidence that
curing is being confirmed and is satisfactory. As a minimum, records
of moist curing shall include the identification of the person checking
the moist curing and the time that it was confirmed.
CN – DESIGN & RETAINED SOIL SYSTEMS, WALL/SLOPE SECTION 02276
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 20 OF 29
MI. 36.79 TO 41.00 HALTON SUB
.3 Cold Weather Protection Period
.1 If cold weather conditions are present at the end of curing period, the
elements shall be provided with protection from cold weather and
moisture loss for an additional 24 hours, prior to exposure to cold
weather conditions. Protection shall be extended beyond 24 hours if
required to meet the requirements according to the Control of
Temperature subsection of this Section 02276.
.9 Control of Temperature
.1 General
.1 All necessary actions shall be taken to maintain temperatures within
the specified limits. During the moist curing and protection periods,
the following temperature requirements shall be met:
.1 The concrete temperature shall not exceed 60 °C.
.2 The concrete temperature shall not fall below 10 °C before the
end of moist curing.
.10 Exposure
.1 During moist curing and cold weather protection periods, the element may
be exposed for a maximum total period of 1 hour per day for the purposes of
formwork removal, removal from the bed, filling of bug holes, inspection or
relocation within the plant, except for indoor precast concrete plants, where
the exposure period shall not exceed 2 hours per day.
.1 General
.1 Concrete surfaces shall not be treated with cement slurry or paste.
.2 Exposed Surfaces
.1 The appearance of the concrete, including repairs shall be uniform in
colour, pattern, and texture when viewed from a distance of 15 m.
.2 All projections, such as fins and bulges, and all blemishes, such as
stains and rust marks, shall be removed.
.3 Surface Tolerances
.1 Element surfaces when tested with a 3 m long straight edge placed
anywhere in any direction shall meet the following requirements:
.1 For formed surfaces there shall be no gap greater than 3 mm
between the bottom of the straight edge and the surface of the
concrete.
.2 For unformed surfaces on the back side of the element, there
shall be no gap greater than 6 mm between the bottom of the
straight edge and the surface of the concrete.
.1 Each concrete element shall be identified with a unique number and the date
of casting within 24 hours of stripping forms. The information marked on the
elements shall be marked on any surface of the element except the exposed
front face. Markings shall be stenciled, using indelible ink or paint.
.2 Any markings on a surface that would be visible after installation shall not be
permitted.
.14 Notification
CN – DESIGN & RETAINED SOIL SYSTEMS, WALL/SLOPE SECTION 02276
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 22 OF 29
MI. 36.79 TO 41.00 HALTON SUB
.1 A list of elements and their identification numbers shall be submitted to the
Engineer within 24 hours of the completion of a lot.
.1 Steel Reinforcement
.1 When requested by the Engineer, samples of steel reinforcement
shall be provided to the Owner according to Section 03200 Concrete
Reinforcement.
.3 The Engineer shall be notified in writing when the elements are ready for the
quality assurance concrete covermeter survey.
.1 All elements shall meet the dimensional tolerance requirements of CSA 23.4
unless otherwise specified in the Contract Documents. For dimensional
tolerances not specified, the maximum allowable dimensional variation shall
be 1:800 or ± 5 mm, whichever is greater.
.1 The Engineer shall be notified in writing three (3) business days prior to
delivery of the elements.
.4 Elements shall be loaded for shipping in such a manner that they can be
transported and unloaded at their destination without being damaged or
exposed to stresses for which they were not designed.
PART 3 - EXECUTION
.1 Skid steer, tired, and tracked vehicles shall not be permitted on any area where the
depth of backfill for RSS over installed reinforcing elements is less than 0.3 m.
Construction vehicles shall not be permitted to be in direct contact with installed
reinforcing elements at any time.
3.2 CONSTRUCTION
.1 General
.1 The RSS shall be constructed according to the Shop Drawings and this
Section 02276.
.2 RSS Superintendent
.1 The construction of the RSS shall be scheduled such that it is at all times
under the responsible charge of the RSS superintendent. The RSS
superintendent shall be advised on site by the RSS manufacturer’s
representative as to the required procedures for the construction of the RSS,
for the specified operations and time periods.
.3 Manufacturer’s Representative
.1 Backfill for RSS and reinforcement elements shall be placed within the lines
and grades shown on the Shop Drawings. All backfill for RSS shall be
compacted according to OPSS.PROV 501.
.2 Unless otherwise specified in the Contract Documents, backfill for RSS shall
not be placed against an adjacent concrete structure that is part of the work
until the concrete in that structure has obtained at least 70% of the
compressive strength specified in the Contract Documents.
.6 Performance Tolerances
.1 Performance tolerances for the RSS shall be according to the first table in
Clause 1.4.2.1 of this Section 02276.
.7 Certificates of Conformance
.8 Corrective Work
.1 General
.1 All deficiencies shall be repaired according to the repair procedures
for corrective work. All corrective work shall be done within the RSS
warranty period, unless prevented by seasonal shutdown, in which
case the corrective work shall be done prior to June 30 of the
following year.
.2 At least one week prior to commencement of any corrective work,
written notice of commencement of work shall be submitted to the
Engineer and the Owner.
CN – DESIGN & RETAINED SOIL SYSTEMS, WALL/SLOPE SECTION 02276
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 28 OF 29
MI. 36.79 TO 41.00 HALTON SUB
.3 Access to the corrective work shall be provided for inspection by the
Owner when requested.
.2 Repair Procedures
.1 Three copies of repair procedures for corrective work shall be
submitted to the Engineer 14 days prior to commencement of any
corrective work.
.2 The repair procedures shall include a description of the cause and
fully detail the corrective work required to correct the deficiencies
identified by the Owner.
.3 The repair procedures shall bear the seal and signature of an
engineer and be signed by the manufacturer’s representative.
.9 RSS Warranty
.1 The warranty period shall be 36 months from the date of the Contract
Completion Certificate.
.1 RSS, Wall/Slope, High Performance, Precast Fabrication, and RSS with Finishing
Cap, Wall/Slope, High Performance, Precast Fabrication
.1 RSS, Wall/Slope, High Performance, Precast Fabrication, and RSS with Finishing
Cap, Wall/Slope, High Performance, Precast Fabrication
.1 Payment at the Contract price for the RSS, wall/slope, high performance,
precast fabrication tender items and RSS with finishing cap, wall/slope, high
performance, precast fabrication tender items shall be full compensation for
all labour, equipment and materials to do the work.
.2 RSS, Wall/Slope, High Performance, Precast Delivery, and RSS with Finishing Cap,
Wall/Slope, High Performance, Precast Delivery
.1 Payment at the Contract price for the RSS, wall/slope, high performance,
precast delivery tender items and RSS with finishing cap, wall/slope, high
performance, precast delivery tender items shall be full compensation for all
labour, equipment and materials to do the work.
.3 RSS, Wall/Slope, High Performance, Installation, and RSS with Finishing Cap,
Wall/Slope, High Performance, Installation
.1 Payment at the Contract price for the RSS, wall/slope, high performance,
installation tender items and RSS with finishing cap, wall/slope, high
performance, installation tender items shall be full compensation for all
labour, equipment and materials to do the work.
.2 Payment for construction of the foundation for RSS shall be made under the
appropriate tender items in the Contract.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
.2 The Contractor shall consider the cost of all available architectural finishes in the
unit price for the noise wall system.
.3 Noise barrier heights shall be referenced from the top of the adjacent rail,
roadway surface, or finished grade elevation (as applicable) unless otherwise
indicated.
.4 Noise barriers shall be designed so that there shall be no sections less than 100
m in length with variable height. Where topographical changes precipitate shifts
in the datum of the noise wall – a minimum of five adjacent panels must be
maintained at each given top of barrier elevation within the 100 m parameter.
.5 Positive drainage shall be provided to eliminate ponding at the base of the noise
barriers.
.6 The noise barriers function safely and in a fully functional manner under the
expected ambient conditions set out in Table 1.1, and under any abrupt changes
in expected ambient conditions set out in Table 1.1.
1.3 REFERENCES
.1 ASTM C423, Standard Test Method for Sound Absorption and Sound
Absorption Coefficient by the Reverberation Room Method;
.4 ASTM D635, Standard Test Method for Rate of Burning and/or Extent
and Time of Burning of Self-Supporting Plastics in a Horizontal Position;
.10 ASTM D2843, Test Method for Density of Smoke from Burning or
Decomposition of Plastics;
.11 ASTM E84, Standard Test Method for Surface Burning Characteristics of
Building Materials;
.15 ASTM E795, Standard Practices for Mounting Test Specimens During
Sound Absorption Tests; and
.16 ASTM G155, Standard Practice for Operating Xenon Arc Light Apparatus
for Exposure of Non-Metallic Materials
CN – DESIGN & NOISE WALL SYSTEM SECTION 02283
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 10
MI. 36.79 TO 41.00 HALTON SUB
.4 CHBDC, Canadian Highway Bridge Design Code CAN/CSA S6
.1 Layout lines and establish elevations required for proper location and setting of
support posts, to suit site contours.
.2 The noise wall system may be built of a variety of materials provided that the
selected material achieves a minimum surface density of 20 kg/m2 or that the
Sound Transmission Class (STC) of the noise barrier panels shall be equal to or
greater than 32 as determined in accordance with ASTM E90 requirements.
.3 The cumulative weight loss of particles after 300 freeze/thaw cycles shall be less
than 1% as determined in accordance with ASTM C666 – Method A
requirements.
.4 The loss of mass due to scaling after 50 freeze/thaw cycles shall be less than 0.8
kg/m2 as determined in accordance with ASTM C672 requirements:
.1 The noise barrier panels shall not exhibit any deterioration in the form of
cracks, spalls or aggregate disintegration after 50 freeze/thaw cycles.
.5 The Flame Spread Index (FSI) of the noise barrier panels shall be less than 10
as determined in accordance with ASTM E84 requirements:
.1 Smoke Development (SD) of the noise barrier panels shall be less than
12 as determined in accordance with ASTM E84 requirements.
.6 The stain applied to the surface of noise barrier panels shall not exhibit any
apparent chalking, checking or blistering after 2,400 hours exposure in
accordance with ASTM G155 requirements, and shall comply with the following
requirement:
.1 The total difference in colour (ΔE*) of the stain shall not be greater than
3.0 as determined in accordance with ASTM G155 requirements.
CN – DESIGN & NOISE WALL SYSTEM SECTION 02283
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 10
MI. 36.79 TO 41.00 HALTON SUB
.7 Constructed such that there is sufficient structural support for the installation;
sound transmission value to comply with ASTM E90.
.10 Base plate connections: all noise walls installed on retaining walls shall be
connected to the concrete retaining wall cap. All elements of the connection,
including base plate and anchorages, shall be designed by the Contractor in
accordance with AREMA. The Contractor shall provide detailed design drawings
sealed and signed by a Professional Engineer licensed to practice in the
Province of Ontario.
.11 The contractor to provide design grades for noise wall sections indicates the
elevation of the top of the footings, panels profile, existing ground and existing
utilities through the wall. The information required to complete the grading
drawings along the noise wall shall be obtained as follows:
.1 Footings located within the designed grade: The Contractor to obtain the
information from the CAD design files provided by the Consultant;
.3 Location and elevation of the existing utilities can be obtained from the
locate of the existing utilities paid under item G2 in the Form of Tender:
and
.4 Payment for the listed works shall be deemed incidental to the unit price
for design, supply and installation of the noise wall system. No Separate
payment shall be made.
.1 Erection shall be performed by the barrier panel supplier or its licensee. Submit
proof of this qualification to the Consultant.
.2 Manufacturer shall oversee field installation and certify the installed work as
being in conformity with the Specifications.
CN – DESIGN & NOISE WALL SYSTEM SECTION 02283
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 6 OF 10
MI. 36.79 TO 41.00 HALTON SUB
1.7 SUBMITTALS
.1 Submit detailed design and erection drawings in accordance with Section 01340
Shop Drawings and Other Submittals, bearing the stamp of a Professional
Engineer licensed to practice in the Province of Ontario, at least eight (8) weeks
prior to construction, for approval, and shall include the following:
.2 The Work Methodology Plan for the construction of the noise wall system,
including procedures and equipment;
.3 Soil parameters and other subsurface data for the design of the noise wall
system;
.2 Safely store all materials and protect from damage prior to installation.
1.9 WARRANTY
.1 The noise barrier system shall resist rusting, warping, animal and insect nesting
and infestation. The noise barrier system shall not display any significant
deterioration, delaminating, disfigurement or failure for a minimum five (5) years
period from the date of Substantial Performance.
PART 2 - PRODUCTS
2.1 GENERAL
.1 The noise barrier supplier shall be included in the MTO Designated Sources for
Materials DSM #5.50.
.2 The Contractor shall select and use only one (1) system for the Project.
CN – DESIGN & NOISE WALL SYSTEM SECTION 02283
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 7 OF 10
MI. 36.79 TO 41.00 HALTON SUB
.3 Do not substitute for any component normally supplied by the supplier of the
proprietary wall system.
.4 Verify existing site conditions and ground elevations before preparing shop
drawings.
.5 Materials used shall withstand local weather conditions as noted below, for
example: any exposed steel shall be stainless or galvanized, etc.
.10 Sealant: If required, use GE Canada Silpruf 2000 Series silicone sealant or
approved equivalent.
.11 Anti-Graffiti coating for all instances of pre-cast concrete or wood fibre reinforced
concrete (absorptive side): Gemite Graffiti-Shield ST WB or approved equivalent.
.12 Galvanized primer: Zinc rich conforming to CAN/CGSB-1.181 for new galvanized
metal in compliance with CGSB 85-GP-16M. For galvanized fabrications touchup
to remain unpainted in finished work, use W.R. Meadows of Canada Ltd.
"Galvafroid" or Kerry Industries "Z.R.C." zinc rich coating or approved equivalent.
.1 Posts and footings shall be designed to withstand live, dead, lateral, wind,
seismic, handling, transportation, erection, imposed and other loads.
.2 Posts and footings shall conform to the dimensions shown on the approved Shop
Drawings submitted by the noise wall system manufacturer.
.3 Post footings shall be designed with reference to the soil parameters provided in
the Contract Documents and/or supplementary data acquired at the Contractor’s
expense, as described elsewhere in this specification. The depth, size and type
of footing shall be identified on the detailed design drawings submitted by the
noise wall system manufacturer.
CN – DESIGN & NOISE WALL SYSTEM SECTION 02283
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 8 OF 10
MI. 36.79 TO 41.00 HALTON SUB
.4 Determine footing depth in accordance with the Canadian Highway Bridge
Design Code 2006 based on the soil being compacted to 95% Proctor and per
borehole data provided in the Contract.
.5 The design of the footing shall ignore the horizontal resistance of the top 1000
mm of material in front of the footing.
PART 3 - EXECUTION
3.1 GENERAL
.1 Noise wall design and installation shall only initiate with written approval from the
Owner.
.4 Install panels which are visually uniform in appearance in terms of colour, pattern
and texture. Uniformity of appearance is subject to approval. Noise barrier panels
must visually match adjacent panels. Inspect during construction and after
installation at a distance of approximately 15 m from the structure and adjust as
required.
.5 The noise wall system shall be designed to provide smooth and ascetically
acceptable top of wall transitions, where footing grades vary from panel to panel.
.6 Examine the Site to determine local conditions under which the Work will be
undertaken.
.3 Remove from the site all surplus materials excavated for the placing of noise
barriers and footings.
3.3 FOOTINGS
.1 Footings in Earth:
.2 Footings in Rock:
.2 Backfill all excavations into rock with concrete. The excavation above the
top of rock may be formed into the required dimensions and the
remainder of the excavation backfilled with granular material.
3.4 POSTS
.1 Construct work to the line and grades shown with a tolerance of ±10 mm. Plumb
posts within a tolerance of ±6 mm in 3 m.
CN – DESIGN & NOISE WALL SYSTEM SECTION 02283
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 10 OF 10
MI. 36.79 TO 41.00 HALTON SUB
.2 Touch-up abraded galvanized surfaces with zinc-rich paint.
3.5 PANELS
.1 Install panels to the design grades prepared under item 1.5 (l) above. In
particular, note infill panel requirements to match changing slopes along grade,
transitions around culverts and retaining walls, etc. Infill panels to be provided as
required and shall be paid per square meter of installed panel under the same
noise wall system item listed in the Form of Tender (i.e., same unit price of the
noise wall per square meter).
.1 Shortened post spacing will be allowed to avoid placing posts on top of utilities
that interfere with the originally proposed barrier footing location.
.2 Obtain approvals from the utility owner for noise barrier installations within 3
meters of existing utilities.
.3 Work around underground utilities, and when construction operations are liable to
damage utilities, alter method of construction as directed by the Consultant or
utility companies in order to avoid any damage.
.4 The adjustment work (design and construction) and additional structural steel
required around the utilities shall be considered incidental and included in the
unit price of the noise wall's design, supply and installation.
4.1 MEASUREMENT
.1 Measurement for Noise Wall fence shall be by linear meters (m) of the installed
fence as measured in the field.
4.2 PAYMENT
Payment for the Work of this Section shall be included in the unit prices included
in Form of Tender. Payment will be full compensation for the design, supply, and
installation of the Noise Wall, including all materials, labour, use of equipment,
tools and incidentals necessary to complete the Work of this Section.
END OF SECTION
CN – DESIGN & SITE GRADING SECTION 02311
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 1 OF 16
MI.36.79 TO 41.00 HALTON SUB
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the site grading requirements for the works.
.2 The Contractor shall refer to the American Society of Testing and Materials
International (ASTM):
.3 The Contractor shall refer to the TSSA Guideline for Excavation in the Vicinity of
Utility Lines.
.4 The Contractor shall refer to the Geotechnical Reports for the Project attached to
the tender documents.
1.4 DEFINITIONS
.3 “Earth” means all soils except those defined as rock, and excludes stone
masonry, concrete, and manufactured materials;
.1 Rock shall not include glacial till or “hardpan” or layered rock in its
original location which can be ripped by a single rear-mounted
tooth on a D-8 crawler-type tractor rated at 265 drawbar H.P., or
equivalent.
.4 Used ballast;
.2 The Engineer may also carry out independent Quality Assurance tests as per
Section 01620 Quality Control and Assurance of these Specifications as
required.
1.6 SUBMITTALS
.1 The Contractor shall submit the following all submittals for review in accordance
with the requirements of this Section and Section 01340 Submittals at least four
weeks prior to commencing use:
.1 Prior to the use of material for Site use, the Contractor shall obtain
bulk soil test analysis (O. Reg. 153/04) and certification that all
material to be used on Site meets the requirements of Table 2
SCS for Agricultural or Other Property Use;
.6 The Contractor shall submit Inspection and Test Reports for all tests and
inspections performed by the Contractor-appointed inspection and testing
company in accordance with this Section and Section 01620 Quality
Contractor and Assurance;
.7 The Contractor shall supply As-Built survey information for Site Grading
for the completed grading;
.2 Date of disposition;
.10 Work plan to excavate through the shoulder of the existing mainline
tracks.
CN – DESIGN & SITE GRADING SECTION 02311
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 6 OF 16
MI.36.79 TO 41.00 HALTON SUB
.11 Work plan for working night shifts and throughout the weekends during
the track’s closure.
.1 Stockpile excavated materials separately and store until required. (e.g. topsoil,
earth fill).
PART 2 - PRODUCTS
2.1 MATERIALS
.3 Embankment material within 1.2 m of the bottom of the sub-ballast shall be non-
frost susceptible material with less than 30% passing by weight sieve No. 200.
.1 The Contractor shall examine the Geotechnical Reports prior to proceeding with
the Works.
.4 The Contractor shall ensure that all impacted soil is evaluated as solid non-
hazardous or hazardous waste and is sent off-site as non-hazardous or
hazardous waste to the appropriate landfill. The Contractor shall collect
composite soil samples assuming it as impacted and submit the samples to a
laboratory for Toxicity Characteristic Leachate Procedure (TCLP) for waste
evaluation – hazardous or non-hazardous prior to disposing of it off-site.
.5 The Contractor shall undertake regular soils analysis, as required, for excavated
soils or materials to be disposed of off-site to confirm the soil characteristics prior
to disposal in accordance with the Environmental Protection Act, R.S.O 1990, c.
E.19 (EPA) regulations. The Contractor shall account for and consider the
required stockpiling of soils and multiple handling of soils required in the process.
.6 The Contractor acknowledges that soil that requires to be disposed of off-site and
found to contain aesthetic impacts (cinders, slag, ballast, asphalt and/or brick
fragments or other debris) will require disposal as waste regardless of chemical
quality.
.1 The Contractor shall ensure that all grading work will be within the Limits of
Construction indicated in the Contract Drawings. No grading work shall be done
outside the Limits of Construction.
.2 The contractor shall consider the following for undertaking grading works within
6m of the existing live tracks:
.1 The grading work shall not impact on the stability of the existing track
embankment, subballast and ballast. The grading works shall be
undertaken in accordance with CN Rail guidelines for maximum allowable
temporary excavation along the mainline tracks under railway traffic; and
CN – DESIGN & SITE GRADING SECTION 02311
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 8 OF 16
MI.36.79 TO 41.00 HALTON SUB
.2 The grading work shall be undertaken when the adjacent tracks are not in
service or during night-time when there is no railway traffic on the tracks.
The contractor shall coordinate three months in advance with CN Rail and
obtain the approval prior to proceeding with the grading work along the
adjacent existing live tracks.
.1 The Contractor shall coordinate with CN S&C and obtain the locate for all
utilities and underground cables prior to proceeding the work;
.3 The Contractor shall confirm the locations of all buried Utilities prior to
proceeding with the Works;
.4 The Contractor shall protect all existing buried Utilities and structures as
required;
.5 The Contractor shall notify all owners having jurisdiction and shall
establish the location and state of use of all buried Utilities and structures
prior to commencing the excavation work. The Contractor shall ensure to
mark such locations to prevent disturbance during the Works;
.6 The Contractor shall maintain and protect from damage; water, sewer,
gas, electric, telephone and other Utilities and structures encountered.
The Contractor shall obtain permission from the Utility Companies before
moving or disturbing any Utilities or structures; and
.1 Do not handle topsoil while in wet or frozen condition or in any manner in which
soil structure is adversely affected as determined by the Engineer.
CN – DESIGN & SITE GRADING SECTION 02311
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 9 OF 16
MI.36.79 TO 41.00 HALTON SUB
.2 Commence topsoil stripping of areas as indicated after area has been cleared of
brush, weeds and grasses and removed from site.
.3 Topsoil will be stripped and stockpiled in accordance with the Grading Plan and
Soil Management Plan for all permanent and temporary construction areas.
Topsoil piles shall be marked with appropriate signage to prevent accidental
admixing. Topsoil shall not be imported to or exported from the Site.
.1 The Contractor shall ensure that the topsoil and soils containing organic or other
deleterious materials are stripped from the areas in accordance with the
Drawings prior to placement of fill materials. Following Stripping of the topsoil,
the Contractor shall ensure that the subgrade is compacted to 95% Standard
Proctor Maximum Dry Density (SPMDD) and then proof-rolled and inspected to
confirm the adequate conditions are present prior to commencing the fill
placement.
.2 The Contractor shall ensure that all soft zones are sub-excavated and replaced
with granular B type II material, in lifts that do not exceed 300mm in thickness,
compacted to 98% of SPMDD. The Contractor shall ensure that all repaired
areas are retested.
.3 The Contractor shall ensure that water inflows are controlled by drainage system
and subgrade is kept dry all the time.
The Contractor acknowledges that in case of rain, the subgrade may experience
more softening at the surface, in which case further sub-excavation may be
required in order to have the subgrade approved by the Contractor’s Independent
Geotechnical Engineer. The Contractor shall cover the subgrade immediately
with sub-ballast after each section of the subgrade is completed, in order to
mitigate the situation.
.4 The Contractor shall protect the exposed subgrade from frost penetration. If frost
penetrates the exposed subgrade due to the subgrade being left uncovered
overnight in freezing temperatures or for any other reasons, the frozen
CN – DESIGN & SITE GRADING SECTION 02311
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 10 OF 16
MI.36.79 TO 41.00 HALTON SUB
soil/material shall be sub-excavated, removed and replaced with granular B type
II in lifts not exceeding 300 mm in thickness, compacted to 95% of SPMDD.
.5 The Contractor shall inspect the subgrade to confirm stability. Any soft zones
shall be sub-excavated and replaced with granular B type II material to improve
the ground conditions. The Contractor shall be responsible for all sub-
excavations undertaken as a result of frozen conditions.
.6 Due to the sensitive soil condition, the Contractor shall not disturb the prepared
subgrade by movement of the construction equipment at any time. In the case
that the track bed is used for temporary construction access, a construction mat
shall be constructed; the Contractor shall increase the thickness of the sub-
ballast by two times the required thickness, subject to the approval by the
Contractor’s Independent Geotechnical Engineer. Once the construction traffic is
complete, the Contractor shall remove the additional sub-ballast material. The
Contractor shall be responsible for the supply, placement and removal of the
additional material required for all temporary construction access within the
Project limits. The cost for additional materials shall be borne by the Contractor.
.8 The Contractor shall use granular B type II to elevate the subgrade (after
Stripping) to the design elevation if fill from onsite cut is not available.
.9 The Contractor shall compact all stripped and disturbed areas to compaction
levels as indicated in Section 06120 Quality Control and Assurance.
.10 The Contractor shall key/bench existing slopes to ensure a proper bond between
the new materials and the existing surface as indicated:
.12 The Contractor shall remove and dispose of material not compacted to levels
detailed in this Section.
.13 Where compaction is not being obtained, the Contractor shall cease placing
material where adequate compaction has not been achieved and shall continue
to apply additional compaction to materials already in place until the desired
compaction result is achieved.
.14 The Contractor acknowledges that final acceptance of the materials will be made
after the materials are dumped, spread and compacted in place in accordance
with the allowable SPMDD:
.15 The Contractor shall not disturb soil within branch spread of trees or shrubs to
remain.
.16 The Contractor shall ensure that all the exposed soil during ditch regrading is
stabilized at the end of each workday.
.1 Stripping (topsoil) and cut material deemed acceptable for re-use may be
stockpiled in temporary locations as directed by the Engineer, with toes of
stockpiles no closer than 3 m from the existing track, complete with silt fence to
protect the track, existing fence and property line, with positive drainage
maintained at all times.
.3 Upon completion of embankments, the Contractor shall draw from the temporary
stockpiles and place material as topsoil.
.1 The Contractor shall review the Soil Management Plan prepared for the Project
and incorporate all pertinent details, background information, recommendations,
mitigation and monitoring measures presented therein.
.2 The Contractor shall handle and store soils during construction in a manner that
protects soil quality for re-use. Potentially contaminated soils that are observed
during construction will be sent for analysis to characterize and determine
suitability for re-use on the Site.
.3 Contaminated soils not suitable for re-use on the Site shall be managed in
accordance with all applicable law, industry standards and best management
practices, including but not limited to:
.4 The Contractor is responsible for the re-use of soils on site to the extent possible,
proper disposal of unsuitable materials is permitted where soil has been deemed
as not fit for onsite reuse (per applicable law), off of the Site. The Contractor shall
arrange for and pay for any additional testing required by the receiver site as a
condition of acceptance of the material. The Contractor shall submit to CN the
forms provided under OPSS.PROV. 180, signed by the receiver site.
.5 The Contractor shall re-use excess soil on the Site to the extent possible. Should
on-site re-use be determined to not be possible due applicable law, the
Contractor shall make all reasonable attempts to locate a suitable off-site
beneficial re-use receiver. Only as a last resort shall disposal of excess soil at
landfill be undertaken. Re-use at off-site beneficial re-use receivers shall be
communicated to CN and the Contractor shall verify and document that the
receiver is operating under appropriate by-laws, permits and regulations and that
the quality of material being re-used is suitable for their operation. Copies of all
agreements, bills of lading, weigh bills, analytical results shall be forwarded to the
CN and/or Contract Administrator.
.6 If requested by CN, the Contractor should work with the Engineer to ensure any
other concerns CN has with the excess soil movement are properly addressed.
CN – DESIGN & SITE GRADING SECTION 02311
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 13 OF 16
MI.36.79 TO 41.00 HALTON SUB
3.7 DEWATERING
.2 Protect open excavations against flooding and damage due to surface run off.
.2 The Contractor shall repair any damage to the completed subgrade prior to
placing the sub-ballast, to the satisfaction of the Contractor’s Geotechnical
Engineer and shall provide an Inspection and Test Report for review and
approval.
4.1 GENERAL
.1 Measurement and payment for work of this section shall be in accordance with
OPSS 206 and as listed in the Form of Tender. No additional payment will be
made for overhaul or secondary handling.
CN – DESIGN & SITE GRADING SECTION 02311
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 14 OF 16
MI.36.79 TO 41.00 HALTON SUB
.2 Keying/benching of fill into existing slopes shall be considered incidental to the
work and no additional payment will be made for this operation:
.3 The Contractor will not receive payment for any quantity of material placed
outside of the site tolerances specified.
.4 No premium costs will be paid if the Contractor chooses to stage their work in
such a way as to require double handling of material.
.5 The costs for embankment and track monitoring, as required for the Work will be
covered under the applicable item in the Form of Tender.
.1 Measurement for work of this item shall be by the cubic meter (m3) of volume
excavated based on cross-sections taken by the Contractor, prior to and after
stripping.
.2 The Contractor shall supply sets of original and final cross-sections to the
Engineer for calculation purposes.
.3 The Contractor shall supply the Engineer a detailed list, station by station, of
areas where cut was removed and properly disposed of as per OPSS 180.
.1 Measurement for work of this item shall be by the cubic meter (m3) of excavated
volume, compacted and placed as on-site design embankment, based on cross-
sections taken by the Contractor, prior to and after excavation and shall include
all keying into existing slopes.
.2 The Contractor shall supply sets of original and final cross-sections to the
Engineer for calculation purposes.
.3 The Contractor shall supply the Engineer a detailed list, station by station, of
areas where cut was removed and placed in fill.
CN – DESIGN & SITE GRADING SECTION 02311
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 15 OF 16
MI.36.79 TO 41.00 HALTON SUB
4.4 EARTH - FILL FROM ON-SITE CUT
.1 Measurement for work of this item shall be by the cubic meter (m3) of fill volume,
“compacted in placed” as on site design embankment, based on cross-sections
taken by the Contractor, prior to and after placement of fill, and shall include all
keying into existing slopes, compaction and trimming as specified herein.
.2 The Contractor shall supply sets of original and final cross-sections to the
Engineer for calculation purposes.
.3 The Contractor shall supply the Engineer a detailed list, station by station, of
areas where fill was placed from cut.
.1 Measurement for work of this item shall be by the cubic meter (m3) of fill volume,
“compacted in placed” as on site design embankment, based on cross-sections
taken by the Contractor, prior to and after placement of fill, and shall include all
keying into existing slopes, compaction and trimming as specified herein.
.2 The Contractor shall supply sets of original and final cross-sections to the
Engineer for calculation purposes.
.3 The Contractor shall supply the Engineer a detailed list, station by station, of
areas where fill was placed from borrow.
4.6 SUBEXCAVATION
4.7 PAYMENT
.1 Payment for the Work of this Section shall be included in the unit prices included
in Form of Tender. Payment will be full compensation for all materials, labour,
use of equipment, tools and incidentals including track monitoring requirements
necessary to complete the Work of this Section.
CN – DESIGN & SITE GRADING SECTION 02311
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 16 OF 16
MI.36.79 TO 41.00 HALTON SUB
Payment for night-time work and all equipment required to perform the work
during the night-time shall be included in the unit prices included in the Form of
tender. *** END OF SECTION ***
CN WINTER WORKS SECTION 02312
ENGINEERING MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 1 OF 6
MI. 36.79 TO 41.00 HALTON SUB
GENERAL CONDITIONS
The General Conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1
of this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
.1 The duration of the winter grading portion of the works will be defined as between
December 01 and March 31, regardless of weather conditions.
1.3 REFERENCES
.1 The Contractor shall refer to the following Ontario Provincial Standard Specification
(OPSS):
CN WINTER WORKS SECTION 02312
ENGINEERING MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 6
MI. 36.79 TO 41.00 HALTON SUB
1.4 DEFINITIONS
.1 The Contractor shall be responsible for conducting their own quality assurance program
to ensure all materials, compaction, etc., meet the requirements of this Section and
Section 01620 Quality Control and Assurance.
.2 The Engineer may also carry out independent Quality Assurance tests as per Section
01620 Quality Control and Assurance of these Specifications.
1.6 SUBMITTALS
.2 Contractor shall submit Salt Management Plan in accordance with the requirements of
this Section.
.2 The Contractor shall not use salt for de-icing or traction control purposes during
construction. Except for the use of sand, any other non-salt de-icing methods for traction
control must be approved to the satisfaction of the Engineer and CN’s Environmental
Monitor. If salts such as calcium chloride are deemed necessary, the Contractor must
develop a Salt Management Plan to the satisfaction of the Engineer and CN’s
Environmental Monitor. Once approved, the document will be circulated by the Engineer
to regulatory agencies before use of the material is permitted on the site. Consultation
with regulatory agencies may take up to 4 weeks.
CN WINTER WORKS SECTION 02312
ENGINEERING MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 6
MI. 36.79 TO 41.00 HALTON SUB
PART 2 - PRODUCTS
2.1 MATERIALS
.1 Suitable Common Material for earth embankments shall consist of material passing 100%
through a U.S. Standard 200mm sieve. Suitable Common Material shall be free of
organic or deleterious material.
.3 Embankment material within 0.3 meters of top of the sub-grade shall contain material
passing 100% through a U.S. standard 75 mm sieve.
PART 3 - EXECUTION
.1 Rough grade to levels, profiles, and contours allowing for surface treatment as indicated.
Excavate such that earth fill is segregated from unusable materials and can be
stockpiled on-site for subsequent use.
.2 Do not place material, which is frozen nor place material on frozen surfaces, unless
approved by the Engineer.
.3 During freezing conditions or forecast periods of freezing conditions, leave grade 0.3 m
high/low in order to protect subsequent grade from freezing.
CN WINTER WORKS SECTION 02312
ENGINEERING MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 6
MI. 36.79 TO 41.00 HALTON SUB
.4 Prior to placing additional material, remove snow and the top layer of frozen material all
to the satisfaction of the Engineer.
.5 Prepare an area sufficient for the placing operation for that day only. No areas of
unprotected grade will be allowed at the end of the day.
.6 For placement of borrow material, remove snow and a top layer of frozen material from
the borrow pit all to the satisfaction of and at no cost to the Engineer. Ensure that only
unfrozen material is used for fill placement.
.7 Remove any material that has become too wet and replace it with suitable unfrozen
compacted material, from an on-site cut or off-site borrow, as directed by the Engineer.
Material removed will be classified as “mud”. Payment for the removal of material shall
be measured and paid under the appropriate Tender Item for earthworks.
.8 Place fill maximum lifts and compact as described in Section 01620 Quality Control and
Assurance.
.9 Remove and dispose of material not thoroughly compacted at no cost to the Engineer.
.10 Where compaction is not being obtained, cease placing material and give additional
compaction to the material in place.
.11 Final acceptance of materials will be made after materials are dumped, spread, and
compacted in place:
.2 Engineer will not pay for the removal and disposal of any rejected material.
.1 Compact subgrade to 98% of SPMDD. Excavate all weak and soft spots as required and
replace them with a granular sub-base compacted uniformly to 98% of SPMDD.
.5 Ensure no frozen material is placed. Sub-ballast shall be taken from the stockpile area
and delivered to the site in an unfrozen condition.
.6 Place material only on clean unfrozen surface, free from snow or ice.
CN WINTER WORKS SECTION 02312
ENGINEERING MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 6
MI. 36.79 TO 41.00 HALTON SUB
.7 Prior to placing granular material, remove any snow or portion of high grade, compact as
specified and place granular material. Remove and prepare an area sufficient for the
placing operation for that day only. No areas of unprotected subgrade will be allowed at
the end of the day.
.8 Place granular materials using methods that do not lead to segregation or degradation.
.9 Place material to full width in uniform layers not exceeding 150 mm compacted
thickness.
.10 Shape each layer to smooth contour and compact to a specified density before the
succeeding layer is placed.
.11 Ensure that granular material is placed to full depth, as shown on the drawings, at the
end of the days operation, and do not leave any portion of the subgrade unprotected
from freezing.
.12 Remove and replace the portion of the layer in which material has become segregated
during spreading.
3.7 DEWATERING
.1 Maintain finished subgrade in condition conforming to this section until succeeding sub-
ballast course is constructed, or until granular sub-ballast is accepted by the Engineer.
.2 Repair any damage to completed subgrade prior to placing sub-ballast, all to the
satisfaction of the Engineer.
.1 Take cold weather precautions whenever the ambient temperature is, or is expected to
be, at or below 5°C.
.2 Have protective measures in place, or adjacent to the Work, and approved by the
Engineer before any concrete is mixed or ordered.
CN WINTER WORKS SECTION 02312
ENGINEERING MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 6 OF 6
MI. 36.79 TO 41.00 HALTON SUB
.3 Maintain concrete temperatures between 10°C. and 20°C. for a minimum of 3 days for
unloaded areas, and 6 days for areas receiving partial load. These durations may be
reduced by 33 percent with the use of high early strength cement.
.4 In methods employed to maintain the concrete temperature, provide suitable access and
removable inspection plates so that the temperature of the concrete may be measured
and recorded at any time. Locate inspection plates so as to provide representative areas
including corners and more exposed elements, and have their location approved by the
Engineer.
.5 Where the Work is enclosed, and heaters are used to provide heat:
.1 provide an access strip at least 1 m wide between the Work and the nearest
heater;
.5 maintain the humidity within the enclosure at or above 40 percent and install a
suitable measuring device, or employ wet curing terminated 12 hr. before the
termination of heating.
.6 Removal of forms, shores, and protection to conform to ACI 306, Tables 5.1.7 for the
structural concrete bearing load. Remove only after tests indicate sufficient concrete
strength and the release of the Engineer is obtained.
.7 At the termination of the protection period, do not drop the concrete temperature more
than 20°C. in the first 24 hr.
4.1 MEASUREMENT
4.2 PAYMENT
.1 Payment for the Work of this Section shall be included in the unit prices included in Form
of Tender. Payment will be full compensation for all materials, labour, use of equipment,
tools and incidentals necessary to complete the Work of this Section.
***END OF SECTION***
CN – DESIGN & EXCAVATING, TRENCHING AND BACKFILLING SECTION 02315
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 1 OF 13
MI. 36.79 TO 41.00 HALTON SUB
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
.2 The Contractor shall refer to the Canadian General Standards Board (CGSB):
.3 The Contractor shall refer to the following American Society of Testing and
Materials International (ASTM):
.3 ASTM D4318-17e1, Standard Test Method for Liquid Limit, Plastic Limit
and Plasticity Index of Soils.
.4 The Contractor shall refer to the Technical Standards & Safety Authority (TSSA)
Guideline for Excavation in the Vicinity of Utility Lines.
.5 The Contractor shall refer to the Geotechnical Reports attached to the tender
documents.
.6 The Contractor shall refer to the Soils Management Plan attached to the tender
documents.
CN – DESIGN & EXCAVATING, TRENCHING AND BACKFILLING SECTION 02315
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 13
MI. 36.79 TO 41.00 HALTON SUB
1.4 QUALITY ASSURANCE
.1 The Contractor is responsible for conducting its own quality assurance program
to ensure excavation, trenching, backfilling and compacting, meet the
requirements of this Section and Section 01620 Quality Control and Assurance.
.4 The Contractor shall ensure that the frequency of tests conform to OPSS.PROV
501.
.5 The Contractor shall ensure proper compaction techniques and adherence to the
required densities in accordance with Section 01620 Quality Control and
Assurance and Section 02311 Site Grading.
.6 The Contractor shall perform all testing of materials and compaction. The
Contractor shall arrange all required tests and shall provide copies of all results,
including re-test of failed areas for review. The Contractor shall be responsible
for the re-testing of materials as required to restore defective areas.
.7 The Engineer may carry out their own quality assurance activities. These
activities will not relieve the Contractor in any way with respect to the accuracy of
the quality of the Contractor’s work.
.8 The Contractor shall cooperate with and assist the Engineer during inspections
and tests.
1.5 SUBMITTALS
.1 The Contractor shall submit the following for review in accordance with the
requirements of Section 01340 Submittals and this Section:
.4 Inspection and Test Reports submittal, for all tests and inspections
performed by the Contractor’s inspection and testing company and its
Geotechnical Engineer in accordance with this Section.
.1 The contractor shall stockpile the extra material in the allocated berms locations
in the Contract Drawings. The contractor shall use all stockpile fill and topsoil
materials placed within CN Rail Milton property between south Lower Base Line
Road to Derry Road.
.2 The Contractor shall execute the delivery, storage and handling of granular
materials in accordance with Section 02701 Granular Materials.
.3 The Contractor shall ensure that all materials are handled and transported in a
manner and with equipment that will avoid segregation, intermixing degradation,
and contamination by any deleterious material.
.9 The Contractor shall remove rejected and excess material from the Site within 48
hours.
.10 The Contractor shall ensure that the management and disposal of excess
stockpile materials is in accordance with OPSS.PROV 180.
.11 The Contractor shall provide additional materials as required when stockpiled
materials take time to thaw or achieve their acceptable moisture content; and
shall ensure that additional materials that are un-segregated, not degraded, free
of contamination, frost and frozen material, and are at the correct moisture
content, ready for handling and placement.
.2 Earth means all soils except those defined as rock, and excludes stone
masonry, concrete, and manufactured materials;
.1 Rock shall not include glacial till or “hardpan” or layered rock in its
original location which, in the opinion of the Engineer, can be
ripped by a single rear-mounted tooth on a D-8 crawler-type
tractor rated at 265 drawbar H.P., or equivalent.
PART 2 - PRODUCTS
2.1 MATERIALS
.3 Sand Fill:
.1 Sand fill shall be natural, coarse sand having clean, hard, strong,
grains free from lumps, soft or flaking particles, shale, clay,
organic matter and other deleterious substances and shall be from
a source that is reviewed in accordance with Section 01340
Submittals; and
.1 The details for the proposed source of aggregates and imported fill. The
Contractor shall provide access for sampling and testing of quality of
material to the Engineer, if required;
.3 Geotechnical laboratory test results for samples of the specified fill and
aggregates to be supplied under this Section. The Contractor shall submit
with a proposed source of Borrow material, analytical chemistry analysis
of the representative samples of the fill that determine the concentrations
of the chemical parameters contained in Table 1 of the “Soil,
CN – DESIGN & EXCAVATING, TRENCHING AND BACKFILLING SECTION 02315
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 7 OF 13
MI. 36.79 TO 41.00 HALTON SUB
Groundwater and Sediment Standards for Use Under Part XV.I of the
Environmental Protection Act”.
.3 If the Contractor proposes a change in materials source during the Works, the
Contractor shall advise the Engineer two weeks in advance of proposed change
to allow for sampling and testing.
PART 3 - EXECUTION
.1 Examine site and geotechnical report to determine local conditions under which
the work will be undertaken.
.1 The Contractor shall remain within the Limits of Construction, as outlined in the
Contract Drawings.
.2 The Contractor shall consider that excavation for the new mainline will require to
encroach the shoulder of the existing live tracks for few sections. The contractor
shall consider excavating through the shoulder of the existing track shall be
undertaken during the night shift and tracks closure. The contractor shall submit
a request three months in advance to CN Rail to obtain the approval for track
closure prior proceeding the work. The contractor shall provide sufficient
manpower and equipment to complete the work within the limited period of the
tracks closure.
.4 Maintain and protect from damage, water, sewer, gas, electric, telephone
and other utilities and structures encountered. Obtain direction of the
Engineer before moving or otherwise disturbing utilities or structures; and
3.3 DEWATERING
.3 Protect open excavations against flooding and damage due to surface run off.
.6 Submit for the Engineer’s review details of proposed dewatering methods, such
as dikes or well points.
3.4 EXCAVATION
.3 Excavation must not interfere with normal 45° splay of bearing from bottom of
any footing or from the bottom of any tie of an in-service railroad track.
.4 Do not disturb soil within branch spread of trees or shrubs that are to remain. If
excavating through roots, excavate by hand and cut roots with sharp axe or saw.
CN – DESIGN & EXCAVATING, TRENCHING AND BACKFILLING SECTION 02315
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 9 OF 13
MI. 36.79 TO 41.00 HALTON SUB
.5 The contractor to refer to the typical sections in the Contract Drawings for the
excavation in the shoulder of the existing mainline tracks.
.10 Earth bottoms of excavations to be undisturbed soil, level, free from loose, soft or
organic matter.
.12 Remove unsuitable material from trench bottom to extent and depth as directed
by the Engineer.
.14 Hand trim make firm and remove loose material and debris from excavations.
Where material at bottom of excavation is disturbed, compact foundation soil to
density at least equal to undisturbed soil. Clean out rock seams and fill with
concrete mortar or grout to approval of the Engineer.
.2 Prior to removal of unsuitable soil from any CN property, the Contractor must
prepare an Excess Soils Management Plan to be submitted following Section
01340 Submittals.
.3 CN will obtain bulk soil test analysis on all material to be disposed of, as well as
waste characterization analysis, if required, and results will be provided to the
Contractor. If the Contractor believes further retesting and/or characterization
analysis is requiring, they will do so at their own cost.
CN – DESIGN & EXCAVATING, TRENCHING AND BACKFILLING SECTION 02315
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 10 OF 13
MI. 36.79 TO 41.00 HALTON SUB
.4 Based on the results, the Contractor shall propose disposal sites, following the
requirements of OPSS 180 and CN’s Guideline for Management of Excess Soil
(Off-Site Disposal/Deposit in Ontario).
.5 For each proposed disposal site, the Contractor shall provide to the Engineer for
review:
.6 Upon review and acceptance of the proposed disposal sites and accompanying
documentation:
.2 For disposal sites not registered as licensed waste disposal facilities (i.e.
industrial, commercial, residential, agricultural and similarly zoned
properties):
.7 The Engineer will not be responsible for any costs or delays associated with site
selection or approvals for soil disposal.
.9 Submit Soils Disposal Reports to the Engineer for all soil disposed of offsite at
non licensed waste disposal facilities; including:
.2 Date of disposition;
CN – DESIGN & EXCAVATING, TRENCHING AND BACKFILLING SECTION 02315
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 11 OF 13
MI. 36.79 TO 41.00 HALTON SUB
.3 Quantity (bill of lading); and
.4 A record of the exact location where the soil is deposited at the Receiving
Site (This can include maps, photos, and/or surveyed information).
.10 If requested by CN, the Contractor should work with the Engineer to ensure any
other concerns CN has with the excess soil movement are properly addressed.
.1 Place and compact granular bedding for all services, as shown on the drawings.
.3 Cover (surround) to be Granular “A’ or “B” Type II, as shown on the Drawings.
.4 Place and compact surround in layers not exceeding 200 mm to 98%, ±2%
SMPDD for sewers and culverts.
.5 Place and compact backfill to haunches of pipe before continuing with cover
backfill.
.1 The Contractor shall ensure that backfilling for trenching for drainage pipes and
around manholes, catch basins, and ditch inlets conform to OPSS.PROV 401,
except as modified by the following:
.1 The Contractor shall not proceed with backfilling until its Geotechnical
Engineer has inspected and accepted installation of bedding, covers and
condition of subgrade in accordance with the Contract Documents;
.2 The Contractor shall place all material using methods that do not lead to
segregation or degradation;
.3 The Contractor shall ensure that areas to be backfilled are free from
debris, snow, ice, water and frozen materials;
.4 The Contractor shall remove and replace portion of the layers in which
material has become segregated during placement;
.6 The Contractor shall ensure that its Geotechnical Engineer accepts each
compacted layer in accordance with the Contract Documents before
placing succeeding layers;
.7 The Contractor shall not backfill trenches until the piping, conduits and
cables therein have been inspected, tested, and accepted by inspection
authorities having jurisdiction;
.8 The Contractor shall shape each layer to a smooth contour and compact
to specified density before the next layer is placed;
.10 The Contractor shall compact backfill materials to the following minimum
densities for backfill:
.12 The Contractor shall ensure that all field compaction testing by
Geotechnical Engineer on other similar backfill areas forms the basis of a
direct comparison of individual in-situ density tests the target density; and
.13 The Contractor shall ensure that backfilling of pits and trenches for
underground Utilities within the Rail Corridor and/or inside the railway
loading influence zone is compacted to 98% SPMDD at 150 mm loose
lifts of granular material acceptable to the Geotechnical Engineer.
.1 The Contractor shall supply and utilize water for compaction in accordance with
OPSS.PROV 501.
.1 The Contractor shall install Insulation Boards, DOW Styrofoam Brand Highload
100 Extruded Polystyrene Insulation or approved equal/alternative on top of all
storm sewer placed at depth less than 1.2 m from finish grade in accordance with
Section 02630.
.3 In drainage trenches, the Contractor shall place insulation board to the size and
location as shown on the Contract Drawings, with the joints butt tight.
3.11 TOLERANCES
.2 The Contractor shall ensure that the finished subbase, base and backfill surfaces
are within 10mm of elevation as shown on the Contract Drawings.
3.12 RESTORATION
.1 Upon completion of work, remove waste materials and debris, trim slopes, and
correct defects as directed by the Engineer.
4.1 MEASUREMENT
4.2 PAYMENT
.1 Payment for the Work of this Section shall be deemed incidental to and included
in the various lump sum and unit prices included in the Form of Tender, including
but not limited to all excavation regardless of the depth, disposal of surplus and
unsuitable material off site, bedding and backfill, temporary lighting, working night
shift and over the weekends to complete the work necessary to complete the
Work of this Section.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of this
Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section 02316 specifies the requirements for excavating and backfilling for
structures, including dewatering.
.2 Quality assurance for granular aggregate materials for use in backfill to structures
shall be in accordance with OPSS.PROV 1010.
1.5 SUBMITTALS
.1 Preconstruction Survey
PART 2 - PRODUCTS
2.1 DESIGN
.1 Dewatering
2.2 MATERIALS
.1 Granular
.1 Granular material to be used for backfill, bedding and frost tapers shall be
according to OPSS.PROV 1010.
.2 The 19.0 mm clear stone to be used for wall drains shall be according to
OPSS.PROV 1004.
.2 Native Backfill
.1 Native and imported material shall be approved by the Engineer. All material
shall be free from frozen lumps, cinders, ashes, refuse, vegetable or organic
matter, rocks and boulders over 150 mm in any dimension, and other
deleterious material.
.3 Geotextile
3.2 CONSTRUCTION
.1 Removals
.1 All ice and snow shall be removed from all portions of the work area before
any excavation and backfill operations proceed. Frozen materials shall not be
incorporated into the work. Material shall not be placed over frozen ground,
ice or snow.
.4 Protection Systems
.1 Until backfilling has been completed and to permit the placing of concrete in
the dry, all work necessary to control the flow of water into the excavation and
to prevent disturbance of the founding material shall be carried out.
.2 The next operation after the completion of the excavation for the foundation
shall not proceed until a Notice to Proceed has been received from the
Engineer.
.3 Except as noted below, the quantity of excavation shall include only the
quantities below the designated payment surface within the neat lines
specified in the Contract Documents.
.2 Granular Backfill
.2 The quantity of granular backfill and granular bedding shall include only those
quantities measured below the subgrade and as measured within the
theoretical line and grades specified in the Contract Documents.
.3 Where the Contractor has excavated beyond the limits specified in the
Contract Documents, the conversion factor 2 t/m3 shall be used in
measurement of the excess volume when it is replaced with granular on a
tonnage basis.
.1 Payment at the Contract price for the Earth Excavation for Structure tender
item shall be full compensation for all labour, equipment and materials to do
the work.
.2 When the Engineer requests excavation for concrete working slabs, granular
working pads, or granular bedding, payment shall be at the Contract price for
the type of excavation required.
.2 When the Contract Documents do not include a separate item for granular
backfill to structure, the Contract price for the items directly associated with
the granular backfill to structure shall be full compensation for all labour,
equipment and materials required to do the work.
.4 Overexcavation
.1 No payment shall be made for overexcavation that has not been approved by
the Engineer or for backfill restoration of such overexcavation.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the geosynthetic soil stabilization requirements for the
Works.
1.3 REFERENCES
.1 The Contractor shall be responsible for conducting their own quality assurance
program to ensure that the geosynthetic soil stabilization meets the requirements
of this Section and Section 01620 Quality Control and Assurance.
1.5 SUBMITTALS
.1 The Contractor shall submit the following for review in accordance with Section
01340 Submittals and this Section, at least four weeks prior to commencing the
work:
.1 Geotextile labeling, shipment, and storage shall follow ASTM D 4873. Product
labels shall clearly show the manufacturer or supplier name, style name, and
roll number.
.2 Each geotextile roll shall be wrapped with a material that will protect the
geotextile from damage due to shipment, water, sunlight, and contaminants.
.3 During storage, elevate and cover geotextile rolls to protect them from the
following: site construction damage, precipitation, extended ultraviolet radiation
including sunlight, chemicals, flames including welding sparks, excess
temperatures, and any other environmental conditions that may damage the
physical property values of the geotextile.
CN – DESIGN & GEOGRID AND GEOTEXTILES SECTION 02340
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 4
MI. 36.79 TO 41.00 HALTON SUB
1.7 ENVIRONMENTAL REQUIREMENTS
PART 2 - PRODUCTS
2.1 MATERIALS
PART 3 - EXECUTION
.1 The Contractor shall excavate the subgrade to the line and grades as shown on
the Contract Drawings. The Contractor shall fill over-excavated areas with
compacted recycled concrete material in accordance with Sections 02311 Site
Grading and 02315 Excavation, Trenching and Backfilling. At a minimum, the
Contractor shall proof roll foundation soil to backfill the geosynthetic placement.
3.2 INSTALLATION
.4 Backfill material shall be placed in lifts and compacted as directed under project
specifications. Backfill shall be placed, spread and compacted in such a manner
as to minimize the development of wrinkles in and/or movement of the geotextile.
A minimum fill thickness of 150 mm (6in) is required prior to the operation of
tracked vehicles over the geotextile.
CN – DESIGN & GEOGRID AND GEOTEXTILES SECTION 02340
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 4
MI. 36.79 TO 41.00 HALTON SUB
.5 Turning of tracked vehicles should be kept to a minimum to prevent tracks from
displacing the fill and damaging the geotextile. Rubber-tired equipment may pass
over the geotextile reinforcement at low speeds, less than 16 km/hr (10 mph).
.6 Sudden braking and sharp turns shall be avoided. Any geotextile damaged
during installation shall be replaced by the Contractor at no additional cost to CN.
4.1 MEASUREMENT
.1 Measurement and payment for work of this Section will be based on field
measurement, in square meters (m2), of the product properly installed as directed
by the geotechnical engineer on site, with no allowance for waste, side overlap or
side splices.
4.2 PAYMENT
.1 Payment for the Work of this Section shall be included in the unit prices included
in the Form of Tender. Payment will be full compensation for all materials, labour,
use of equipment, tools and incidentals necessary to complete the Work of this
Section.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 GENERAL
.1 This Section specifies the traffic control requirements for the Works, including:
.7 All other traffic control measures are required to complete the Works.
.6 Load restrictions:
.1 The Contractor is responsible for conducting its own quality assurance program
to ensure that all traffic control for the Works meets the requirements of the
Specifications, in accordance with Section 01620 Quality Control and Assurance.
.2 The Contractor shall retain services of a Traffic Engineer in accordance with the
requirements of Section 01620 Quality Control and Assurance, for preparing
submittals and undertake any other work required in accordance with this
Section.
1.5 SUBMITTALS
.3 The Contractor shall verify that all load restrictions are accommodated
within their plans. The Contractor shall design traffic safety into work
zones and shall provide for safety, mobility, advanced warning and
positive guidance for traffic and pedestrian movement and
.2 The Contractor shall obtain all required road occupancy permits for the Project,
prior to the commencement of any work within its jurisdiction in accordance with
this Section and Section 01340 Submittals.
.1 The Contractor shall ensure that for each stage of construction, lane diversion or
alteration in the traffic control setup, a detailed Construction Traffic Management
Plan is provided for review before commencing the Works and shall maintain a
copy on Site during construction. The Construction Traffic Management Plan
shall:
.3 Identify curb line, sidewalks, property lines, and any Existing Third-Party
Infrastructure adjacent to the Site on the drawings;
.4 Indicate the vehicle movements entering and exiting the Site on the
drawings and identify the types of vehicles expected;
PART 2 - PRODUCTS
2.1 GENERAL
.1 The Contractor shall supply, place and maintain all barricades, warning signs,
delineators, temporary concrete barriers and flashing lights required for the
protection of the public and the Works, including warning signs of construction
operations maintained at both ends of the work zone, in accordance with the
Ontario Traffic Manual, Book 7 – Temporary Conditions.
.2 The Contractor shall ensure that all signs, flashers, barricades, temporary
concrete barriers, and delineators are cleaned and maintained throughout the
duration of the Project. The Contractor shall use either flexible drums (TC-54) or
construction markers (TC-52) with flashers for delineation in accordance with
Ontario Traffic Manual, Book 7 – Temporary Conditions. The Contractor
acknowledges that no other material will be accepted.
PART 3 - EXECUTION
.1 The Contractor shall not close any lanes of the road without written approval from
the Engineer. Before re-routing traffic, The Contractor shall erect suitable signs
and devices in accordance with instructions contained in the Ontario Traffic
Manual, Book 7 – Temporary Conditions.
.3 The Contractor shall prepare notices for any closures in accordance with CN’s
Communications Protocol. All public and municipal notification will be completed
by CN.
.5 The Contractor shall carry out snow and ice removal (including all de-icing
required to remove ice patches, freezing rain, and snow accumulation, etc.)
within the construction zone for the safe movement of vehicles and pedestrians:
CN – DESIGN & TRAFFIC CONTROL SECTION 02350
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 7
MI. 36.79 TO 41.00 HALTON SUB
.1 The Contractor shall ensure that all areas are in bare pavement condition
with painted lines visible and
.6 The Contractor shall coordinate the closure and signage within the limits of the
Project with CN, the Engineer and the Town of Milton.
.7 The Contractor shall coordinate the closure and signage within the limits of the
Project with the Engineer.
.8 The Contractor shall comply with the Town of Milton, municipal, firefighting,
ambulance service and Police Service regulations relating to notifications for
road or lane closures that may be used by emergency vehicles, within the limits
of the Project.
.2 The Contractor shall ensure that the Construction Traffic Management Plan is in
conformance with the procedure outlined in the pamphlet entitled “Correct
Methods for Traffic Control” issued by the Construction Safety Associations of
Ontario.
.3 The Contractor shall ensure that each traffic control person wears high visibility
safety apparel in accordance with the Ontario Traffic Manual – Book 7 –
Temporary Conditions.
.4 The Contractor shall provide, place in service, maintain and then remove all of
the traffic control devices required by the Ontario Traffic Manual, Book 7 -
Temporary Conditions for all temporary traffic control issues for both short and
long term durations. The Contractor shall ensure that all the required devices are
readily available on Site at all times to meet the requirements of this Section.
.5 The Contractor shall advise of the rough surface, raise maintenance covers, steel
plates and narrow lanes for motor vehicles, bicycles and pedestrians on all
approaches within areas of the Site.
.2 The Contractor shall ensure that all nylon vests are in accordance with OHSA
Reg 213/91 Section 67, 68, and 69.
.1 The Contractor shall ensure that all temporary construction and maintenance is
in accordance with the Town of Milton and reviewed Submittals of this Section.
.3 The Engineer reserves the right to retain a qualified contractor to complete any
repairs that have not been initiated by the Contractor within 24 hours of written
notification. All costs for such repairs shall be borne by the Contractor.
.4 The Contractor shall ensure that all new traffic signs are installed, and all new
markings are painted prior to the reopening of the road to traffic in accordance
with the Drawings.
.1 The Contractor shall schedule work so that there is no open excavation adjacent
to a lane carrying traffic overnight and on non-working days.
.1 The Contractor shall not store materials within 4m of the travelled portion of any
roadway.
.2 The Contractor shall not store equipment within 4m of the travelled portion of any
roadway.
.3 The Contractor shall remove any equipment or material which constitutes a traffic
hazard.
CN – DESIGN & TRAFFIC CONTROL SECTION 02350
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 7 OF 7
MI. 36.79 TO 41.00 HALTON SUB
3.7 DELIVERY AND TRUCKING
.1 The Contractor shall plan and schedule the routes of vehicles transporting all
materials to, from or within the Site so that vehicular movements are
accomplished with minimum interference and interruptions to traffic and in
accordance with the Construction Traffic Management Plan.
.2 The Contractor shall notify suppliers of materials and equipment of the above
requirements.
.3 The Contractor shall verify all restrictions as defined under Highway Traffic Act,
R.S.O. 1990, c. H.8.
3.8 SIGNAGE
.1 The Contractor shall install the signage in accordance to the signage drawings.
4.1 MEASUREMENT
4.2 PAYMENT
.1 The Lump Sum Prices submitted in the Form of Tender shall include all labour,
materials and equipment required to design, supply, place, maintain and remove
traffic control system, as called for in this Section.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the dust and mud control requirements for the works.
1.3 REFERENCES
.1 The Contractor shall be responsible for conducting their own quality assurance
program to ensure that the dust and mud control meets the requirements of this
Section and Section 01620 Quality Control and Assurance.
CN – DESIGN & DUST & MUD CONTROL SECTION 02362
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 4
MI. 36.79 TO 41.00 HALTON SUB
1.5 SUBMITTALS
.1 The Contractor shall submit Product Data for the non-chloride chemical dust
suppressant for review in accordance with the requirements of Section 01340
Submittals.
PART 2 - PRODUCTS
2.1 MATERIALS
.1 The Contractor shall use water as a dust suppressant. The Contractor may use a
non-chloride-based chemical dust suppressant where the application of water is
not suitable.
.2 The Contractor shall ensure that the water supplied conforms to OPSS.PROV
501 and OPSS.MUNI 506.
PART 3 - EXECUTION
.1 The Contractor must take such steps as may be required to prevent dust
nuisance resulting from they operations. The Contractor must implement an Air
Quality Best Management Practice Plan in accordance with the Environmental
Protection Plan and 01340 Submittals:
.2 The Contractor will be responsible for ensuring all dirt and mud that is tracked
onto the roadways from vehicles entering or leaving the Site is regularly cleaned
from the roadways. The Contractor must, upon request from the Engineer, CN’s
Environmental Monitor, CN complaint process or their consultant, immediately
proceed with clean-up operation at their expense using street sweepers or similar
equipment, or if in the opinion of the Engineer, the Contractor has not removed or
cannot sufficiently remove the mud from the road, the Engineer will proceed with
the necessary clean up with all costs being charged to the Contractor.
.3 The Contractor shall design, supply, install and remove mud mats at all
construction accesses:
.3 The Contractor shall ensure that the gravel pad is a minimum of 3.6
meters in width and can accommodate the widest anticipated vehicle
entering or exiting the Site;
.4 The Contractor shall ensure that the gravel pad is a minimum of 0.3
meters in depth and comprises a 50 mm to 150 mm diameter coarse
aggregate placed on top of woven geotextile filter fabric;
.8 The Contractor shall remove the mud mat upon completion of the Work;
and
.9 The Contractor shall provide a truck sweeper at all roads where the
construction accesses are located and shall ensure that the roads leading
to the working areas are clean at all times.
4.1 MEASUREMENT
4.2 PAYMENT
.1 Payment for Work of this Section shall be deemed incidental and included in the
various lump sum and unit priced included in the Form of Tender.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of this
Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section 02368 specifies the requirements for the construction, maintenance,
monitoring and removal of the Owner designed temporary railway shoring made
necessary by excavation, embankment construction, dewatering, or other work.
.1 Manual for Railway Engineering, Volume 2, Chapter 8, Part 28, Article 28.5.4
(2020), including all applicable references specified therein.
.1 General
.2 Inspection of Welds
.1 The Contractor shall be responsible for visual inspection of all welds. Any
required testing of welds shall be as specified by the Engineer.
.3 Monitoring
.1 General
.1 Monitoring shall be conducted by a Registered Ontario Land Surveyor
or an engineer in accordance with Section 02201 Construction
Monitoring.
.2 The minimum requirements for monitoring shall include the survey
measurements of scaled targets attached to the shoring wall at the
elevations specified. The scaled targets shall be placed at a maximum
spacing of 6 m with targets placed at the extreme ends and the
targets distributed between the outer limits. The survey targets shall
be monitored for horizontal displacement from the vertical at the
frequency specified.
.3 All test results, observations, and records, including the
preconstruction survey, taken during construction and operation of the
temporary railway shoring shall be available on the site for review by
the Engineer.
.4 If movement of the temporary railway shoring approaches the
allowable limit, the Engineer shall be notified immediately and suitable
measures shall be taken to ensure stability of the temporary railway
shoring and to ensure movement does not exceed the performance
level specified in the Contract Documents.
.2 The Contractor’s engineer shall inspect and verify that the materials have
been supplied and installed according to the Contract Documents. A
Certificate of Conformance shall be submitted to the Engineer upon
completion of the installation of the materials.
.3 The Contractor’s engineer shall inspect and verify that the temporary railway
shoring was installed, monitored, and subsequently removed according to the
Contract Documents. A Certificate of Conformance shall be submitted to the
Engineer upon completion of the removal of the temporary railway shoring.
1.5 SUBMITTALS
.1 Shop Drawings
.3 The Contractor shall have a copy of the Shop Drawings at the site during
temporary railway shoring installation.
.4 The following information and details shall be shown on the Shop Drawings:
.1 Plans, Elevations and Details
.1 Location of temporary railway shoring, including subdivision
and mileage limits.
.2 Plan and elevation of shoring showing the extent of the
temporary railway shoring.
.3 Details of the shoring system, including cross-sections.
.4 Details of internal bracing.
.2 Design Criteria
CN – DESIGN & TEMPORARY RAILWAY SHORING SECTION 02368
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 6
MI. 36.79 TO 41.00 HALTON SUB
.1 Pressure diagrams including values of horizontal and vertical
loads, dead load, and live load surcharge.
.2 Design assumptions and parameters.
.3 Anchor bond stresses.
.4 Pile design.
.5 Anchor system stressing schedule specifying working loads,
stressing loads, and lock in loads.
.6 Details of preload, when required.
.7 Performance level.
.3 Materials:
.1 Grade of structural steel and grade of species of structural
wood.
.2 Concrete strengths.
.3 Grout strengths.
.4 Details of protection from rain and frost action.
.5 Wood lagging and size.
.6 Mill certificates or test reports from an independent
organization certified by the Standards Council of Canada
certifying that the steel meets the requirements of the grade,
where specified.
.7 Details of patented accessories, including load test data.
.4 Installation Procedure:
.1 Installation sequence and procedure, including to the
installation of piling, lagging, anchor systems, and rakers.
.5 Monitoring Method:
.1 The proposed method of monitoring the performance of the
temporary railway shoring during installation and use. The
method of monitoring shall be consistent with the requirements
specified in the Quality Control subsection of this Section
02368.
.6 Removal of Temporary Railway Shoring:
.1 The details of the procedures associated with the removal of
the temporary railway shoring, indicating: method, sequence of
work, and removal limits, except when the temporary railway
shoring is specified in the Contract Documents to be left in
place.
.1 Work shall not proceed on amendments to the temporary railway shoring until
the Contractor has received sealed and signed approval to proceed from the
CN – DESIGN & TEMPORARY RAILWAY SHORING SECTION 02368
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 6
MI. 36.79 TO 41.00 HALTON SUB
Contractor’s engineer and has submitted a copy of the approval to the
Engineer.
.3 Preconstruction Survey
.1 Prior to commencing the work, the Contractor shall submit to the Engineer a
condition survey of property and structures that may be affected by the work
in accordance with Section 02203 Condition Surveys. The survey shall
include the locations and conditions of adjacent properties, tracks, buildings,
underground structures, utility services and structures, such as walls abutting
the site within a horizontal distance of 2Hw from the face of the temporary
railway shoring, where Hw is the height of the wall from the ground surface to
the dredge line.
.6 Milestone Inspections
PART 2 - PRODUCTS
2.1 DESIGN
.1 Design shall be in accordance with AREMA Manual for Railway Engineering, except
as modified and supplemented by CN Guidelines for Design of Railway Structures
CN – DESIGN & TEMPORARY RAILWAY SHORING SECTION 02368
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 6 OF 6
MI. 36.79 TO 41.00 HALTON SUB
and CN Design Criteria for the Shoring Walls submitted by the
Consultant/Contractor.
2.2 MATERIALS
PART 3 - EXECUTION
.1 Equipment for installation, testing and monitoring of prestressed anchors in soil and
rock shall be in accordance with OPSS.PROV 942.
3.2 CONSTRUCTION
.1 Payment at the Contract price for the temporary railway shoring tender items shall be
full compensation for all labour, equipment and materials to do the work.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the requirements for rip rap for the Work.
1.3 REFERENCES
.1 OPSD 810.010 General Rip-Rap Layout for Sewer and Culvert Outlets.
CN – DESIGN & RIP RAP SECTION 02372
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 6
MI. 36.79 TO 41.00 HALTON SUB
.3 American Society of Testing and Materials International (ASTM):
.1 The Contractor is responsible for conducting its own quality assurance program
to ensure that the rip rap for the work meet the requirements of this Section and
Section 01620 Quality Control and Assurance.
1.5 SUBMITTALS
.1 The Contractor shall submit the following submittals for review in accordance
with the requirements of this Section and Section 01340 Submittals:
.1 Sample for Rip Rap. The sample shall represent the material that will be
supplied by the Contractor; and
.2 Product Data and Sample for Geotextile submittal, including the Product
Data, technical information, a sample for geotextile and copies of test
reports.
.1 Inform the Engineer of the proposed source of material and provide access for
sampling at least 4 weeks prior to commencing production.
.2 If, in the opinion of the Engineer, materials from the proposed source do not
meet, or cannot reasonably be processed to meet, specified requirements, locate
an alternative source or demonstrate that material from the source in question
can be processed to meet specified requirements. Acceptance of material at
source does not preclude future rejection if it fails to conform to requirements
specified, lacks uniformity, or if its field performance is found to be unsatisfactory.
PART 2 - PRODUCTS
2.1 RIP-RAP
.1 This specification covers the requirements for the placing of rock protection at the
locations specified in the contract drawings for median stone sizes (D50) listed in
Table 1. In addition, this table includes the rock gradation associated with the
D50 for all the locations and identifies the rock gradation that follows the
specifications outlined in OPSS 1004, November 2012.
Table 2a: Rock Gradation for Rock Protection (D50 = 125 mm)
Size Percentage
(mm) Passing (%)
180 100
155 70 - 90
125 40 - 55
60 0 - 15
CN – DESIGN & RIP RAP SECTION 02372
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 6
MI. 36.79 TO 41.00 HALTON SUB
Table 2b: Rock Gradation for Rock Protection (D50 = 150 mm)
Size Percentage
(mm) Passing (%)
225 100
188 70 - 90
150 40 - 55
75 0 - 15
.1 Scope:
.1 This special provision covers the requirements for the placement of riprap
with D50=300 mm and D50=400 mm, at the locations specified in Contract
Drawings.
.2 Materials:
.1 The rock shall be hard, dense with relative density not less than 2.65,
durable quarry stone, free from seams, cracks or other structural defects
and well graded;
.2 The riprap shall be well graded and shall meet the gradation requirements
shown in the following tables:
200 35-40
100 20-35
26.5 0-15
CN – DESIGN & RIP RAP SECTION 02372
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 6
MI. 36.79 TO 41.00 HALTON SUB
.3 Installation:
.1 This specification covers the requirements for the placing of riverstone rock
protection at the locations specified in the contract drawings that are listed in
Table 5. In addition, this table includes the rock gradation associated with the
D50 for all the locations and identifies the rock gradation that follows the
specifications outlined in OPSS 1005, November 2014.
It corresponds to gradation
200 300 See Table 6 SB-200 taken from Table 3
in OPSS 1005, Nov. 2014
CN – DESIGN & RIP RAP SECTION 02372
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 6 OF 6
MI. 36.79 TO 41.00 HALTON SUB
Table 6: Rock Gradation for Riverstone Rock Protection (D50 = 200 mm)
16 100
7 40-60
2 0-10
3.1 MEASUREMENT
.1 Measurement of Payment for the riprap placement shall be by cubic meter (m3),
including all equipment, materials and labour.
3.2 PAYMENT
.1 Payment at the contract price for the above tender item shall be full
compensation for all labour, equipment and materials required to complete the
work.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of this
Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section 02383 specifies the requirements for the supply and installation of
driven steel H-piles.
.4 ASTM D3689-07, Standard Test Methods for Deep Foundations under Static
Axial Tensile Load; and
CN – DESIGN & STEEL H-PILES SECTION 02383
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 8
MI. 36.79 TO 41.00 HALTON SUB
.5 ASTM D3966-07, Standard Test Methods for Deep Foundations under
Lateral Loads.
.1 Quality assurance shall be in accordance with OPSS.PROV 903 with the following
additions and amendments:
1.5 SUBMITTALS
.1 General
.1 All submissions shall bear the seal and signature of a Contractor’s engineer
experienced in the field of deep foundations.
.2 When welded field splices are used, welding procedures according to the
Canadian Welding Bureau shall be submitted to the Engineer.
.2 Preconstruction Survey
PART 2 - PRODUCTS
2.1 MATERIALS
.1 Steel H-Piles
.1 Steel H-Piles shall be of the grade specified in the Contract Documents and
shall be according to CSA G40.20/G40.21.
.2 When CSA G40.20/G40.21, Grade 350W has been specified, the following
steel grades may be substituted:
.1 ASTM A572, Grade 345; or
.2 ASTM A913, Grade 345.
.3 When CSA G40.20/G40.21, Grade 450W has been specified, the following
steel grades may be substituted:
.1 ASTM A572, Grade 450; or
.2 ASTM A913, Grade 450.
.2 Driving Shoes
.2 Driving shoes shall transfer the driving stresses to the pile over the full cross-
sectional area of the pile.
PART 3 - EXECUTION
3.2 CONSTRUCTION
.2 Pile driving requirements and restrictions, driving shoes, splicing, cutting off piles,
protective coating for piles, monitoring driven piles, jetting, tolerances, load test and
repair of welds shall be in accordance with OPSS.PROV 903 with the following
additions and amendments:
CN – DESIGN & STEEL H-PILES SECTION 02383
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 8
MI. 36.79 TO 41.00 HALTON SUB
.1 Clause 903.07.02.03.03 of OPSS.PROV 903 is deleted in its entirety and
replaced with the following:
.1 Welding shall be according to CSA W59 and shall be done by a
qualified welder employed by a firm certified according to CSA W47.1,
Division 1 or Division 2.
.2 Steel H-piles may be spliced providing the pieces being spliced are
not less than 3 m long, except for integral abutments’ piles, where the
pieces being spliced shall not be less than 7.0 m long. Where piles
are located in a waterbody, splices shall be located below the low
water level, unless otherwise encased in concrete.
.1 H-Piles
.2 Driving Shoes
.2 Piles retapped as part of the minimum number required for the retapping
tests described in the Retapping Tests on Piles clause shall not be measured
for payment.
.1 Payment at the Contract price for the supply equipment for driving piles
tender items shall be full compensation for all labour, equipment and
materials to do the work.
.2 For payment purposes, 50% of the work under this tender item is completed
when the satisfactory performance of the equipment has been demonstrated
to the Engineer by installation of 1% of piles.
.5 When the energy is equal to or greater than 90% of the stated potential
energy stated in the required submission, the cost verifying the hammer
performance shall be administered as a Change in the Work.
.1 Payment at the Contract price for the H-piles tender items and driving shoes
tender items shall be full compensation for all labour, equipment and
materials to do the work.
.3 Retapping Piles
.1 Payment at the Contract price for the retapping piles tender items shall be full
compensation for all labour, equipment and materials to do the work.
.2 Retapping the minimum specified number of piles for retapping tests shall
include all labour, equipment and materials to do the work and shall be
included in the Contract price for the H-piles tender item.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of this
Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section 02384 specifies the requirements for the construction of concrete
caisson piles.
.1 Preconstruction Survey of property and structures that may be affected by the work
in accordance with Section 02203 Condition Surveys; the survey shall include the
locations and conditions of adjacent properties, tracks, buildings, underground
structures, utility services and structures, such as walls abutting the site;
.2 Mill Test Certificates in accordance with Section 05120 – Structural Steel indicating
that the steel meets the requirements for the appropriate standards for casings;
.3 Concrete Mix Design Report indicating a suitable, site-specific concrete that meets
the requirements of the hardened concrete;
.4 Work Plan sealed and signed by a professional engineer experienced in the field of
deep foundations providing the following information prior to commencement of work:
.3 Detailed procedures for casing and liner installation and for withdrawal of the
liner;
.8 When load testing is specified in the Contract Documents, details of the full-
scale test, including site preparation, details of the load application,
components, equipment, testing apparatus, and method of monitoring;
PART 2 - PRODUCTS
2.1 DESIGN
2.2 MATERIALS
.3 Concrete shall be in accordance with Section 03312 – Concrete Work with the
following additions and amendments:
PART 3 - EXECUTION
3.2 CONSTRUCTION
.2 Complete access to inspect the bearing area of the caisson pile prior to the
placement of concrete shall be given to the Engineer.
CN – DESIGN & CONCRETE CAISSONS SECTION 02384
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 4
MI. 36.79 TO 41.00 HALTON SUB
PART 4 - MEASUREMENT AND PAYMENT
.1 Measurement of caisson piles shall be by length in metres of the depth along the
centreline between the approved bearing surface at the bottom and the specified
elevation at the top.
.1 Payment at the Contract price for the supply equipment for installing caisson piles
tender items shall be full compensation for all labour, equipment and materials to do
the work.
.2 Payment at the Contract price for the caisson piles tender items shall be full
compensation for all labour, equipment and materials to do the work.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of this
Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the requirements for sub-drainage for the Work.
1.3 REFERENCES
.1 The Contractor is responsible for conducting its own quality assurance program
to ensure all materials, compaction, etc. meet the requirements of this Section
and Section 01620 Quality Control and Assurance.
1.5 SUBMITTALS
.1 Contractor shall submit the following submittals for review in accordance with the
requirements of this Section and Section 01340 Submittals prior to commencing
Work:
.1 Product Data;
PART 2 - PRODUCTS
2.1 SUB-DRAINS
and fittings (tee, bends, end caps, connectors etc.) to ASTM D3350,
CAN/CSA-B182 and BNQ 3624-120;
.4 Joining system required: Soil-tight, Type 3 joint per BNQ 3624-120; and
.5 Granular Material:
.1 All subdrain pipe shall be installed with granular bedding and backfill
material as indicated on the Contract Drawings.
.1 Pipe Surround: Granular ‘A’ to Section 02701 and OPSS.PROV
1010, with no more than 4% passing the 75 µm sieve; and
.2 Backfill: Granular ‘B’ to Section 02701 and OPSS.PROV1010.
PART 3 - EXECUTION
3.1 TRENCHING
3.2 INSTALLATION
.3 Lay pipe drains on prepared bed, true to line and grade with inverts smooth and
free of sags or high points. Ensure barrel of each pipe is in contact with bed
throughout full length.
.8 Surround and cover pipe with Granular ‘A’ material to full trench depth as
indicated and compact to 98% SPMDD.
.11 Do not mix or contaminate the sub-drainage granular material with soil or other
material.
.12 Provide rodent grates for outlets other than connections to storm structures.
4.1 MEASUREMENT
4.2 PAYMENT
.1 Payment for the Work of this Section shall be included in the unit prices included
in the Form of Tender. Payment will be full compensation for all materials, labour,
excavation, use of equipment, tools and incidentals including geotextiles and
granular material necessary to complete the Work of this Section.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 The Contractor shall consider that the construction of all culverts included in this
contract shall be undertaken during the night shift and over the weekends.
.2 This Section includes the requirements for design, supply and construction of the
precast concrete culverts.
.3 This Section includes the requirements for supply and construction of the CSP
culverts located within the railway loading.
1.3 REFERENCES
.10 OPSS 1821, Material Specification for Precast Reinforced Concrete Box
Culverts and Box Sewers; and
.5 CSA W48-18 Filler Metals and Allied Materials for Metal Arc Welding
(January 2018); and
.4 Transport Canada:
.6 Limits of Construction.
.1 Provide the Engineer with copies of supplier’s test reports on all materials that
are to be incorporated in the culverts.
.2 Provide the Engineer with copies of all field quality control tests conducted on the
culverts.
.4 The Engineer may also carry out independent Quality Assurance tests as per
Section 01620 Quality Control and Assurance of these Specifications.
1.5 SUBMITTALS
.1 The Contractor shall submit the following submittals for review in accordance
with this Section and Section 01340:
.1 Design drawings for the proposed bypass system for each culvert in
accordance with the requirements in Section 02150 Temporary Flow
Diversion and Section 02160 High Flow Contingency Plan;
.2 Shop Drawings for Culverts and Sewers submittal for all types of culverts
and sewers, bearing the stamp of a professional engineer licensed to
practice in the Province of Ontario;
.3 Design calculations for precast concrete class 140-D within the railway
loading confirming that the culvert can sustain Copper E90 loading (using
AREMA safety factor).
CN – DESIGN & CULVERTS & STORM SEWERS SECTION 02630
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 6
MI. 36.79 TO 41.00 HALTON SUB
.4 Manufactures Test Data and Certification for Culverts and Sewers,
submittal providing manufacturer’s test data and certification that culverts
and sewers materials meet the requirements of this Section and Section
01620 Quality Control and Assurance including structural performance
criteria, tests and standards, and methods of jointing;
.5 Inspection and Test Reports for all tests and inspections performed by the
Contractor;
.8 Work Plan Methodology for installation of the culverts under the live
tracks by open cut. The plan shall include the following but not limited to
the following:
1. Anticipated schedule of the work
2. Details of construction methodology
3. Staging
4. Emergency action plan
PART 2 - PRODUCTS
2.1 MATERIALS
.1 Corrugated Steel Pipe (CSP) minimum wall thickness 3.5 mm with all fittings to
OPSS.PROV 1801 to size and class as shown on the Drawings. Corrugated
Spiral Rib Pipe (helical pipe) may be used where CSP is indicated on the
Contract Drawings, unless structural plate corrugated steel pipe
(circumferential/riveted) is shown on the Contract Drawings.
.4 Non-woven Geotextile:
.6 25mm thick steel plate to temporarily cap the culverts for future connection.
PART 3 - EXECUTION
3.2 CONSTRUCTION
.1 The Contractor shall consider that the construction of all culverts included in this
contract shall be undertaken during the night shift and over the weekends.
.2 The Contractor shall notify CN Rail three months in advance for tracks removal to
facilitate the construction of the culverts under the existing live tracks by open
cut. The contractor shall determine the anticipated timelines for tracks work in
coordination with CN rail and incorporate in the construction schedule.
.3 The Contractor shall install Insulation Boards, DOW Styrofoam Brand Highload
100 Extruded Polystyrene Insulation or approved equal/alternative on top of all
storm sewer placed at depth less than 1.2 m from finish grade.
.4 The contractor shall consider that installation of the culverts crossing under or
adjacent to the live tracks shall occur during the night shift or on weekends to
avoid any disruption to the rail operations. The contractor shall provide the
necessary labour and equipment to complete the work within the limited
timeframe for tracks block.
.5 Design, supply and install bypass system and flow control to facilitate the
construction of culverts in accordance with the requirements of Section 02150
Temporary Flow Diversion and 02160 High Flow Contingency Plan.
.8 Clean and inspect, culverts and sewers upon completion of installation and
remove debris and sediments and provide a report in accordance with OPSS.
PROV 411.
.9 Remove rejected and excess material from the place of work within 48 hours.
4.1 MEASUREMENT
.1 Measurement for culverts and storm sewers shall be by linear meter (m) of
properly installed culvert or storm sewer measured along the centerline of the
pipe from the inlet end to outlet end of the pipe at their inverts.
4.2 PAYMENT
.1 Payment for the Work of this Section shall be included in the unit and lump sum
prices included in the Form of Tender. Payment will be full compensation for all
materials, labour, use of equipment, tools and incidentals including but not be
limited to all excavation regardless of the depth, disposal of surplus and
unsuitable material off site, pipe, design supply, install and removal of temporary
track shoring as required and monitoring, connections, granular bedding,
granular backfill, insulation board necessary, cleaning of existing culverts,
inspections, working at night shift and weekends, temporary lighting, leakage
tests to complete the Work of this Section.
GENERAL CONDITIONS
The General Conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of this
Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the requirements for storm maintenance holes, catch basins
and ditch inlets and for the works.
.2 In this Section and on the Contract Drawings that pertain to stormwater systems,
the phrase “maintenance hole” and word “manhole” shall be understood as having
the same meaning.
1.3 REFERENCES
.1 OPSD 403.010, Galvanized Steel Honeycomb Grating for Ditch Inlets; and
.2 OPSD 708.010, Catch Basin Connection for Rigid Main Pipe Sewer.
.1 The Contractor shall be responsible to conduct their own quality assurance program
to ensure all materials, compaction, etc. meet the requirements of this Section and
Section 01620 Quality Control and Assurance.
.2 Submit manufacturer’s test data and certification that all materials meet
requirements of this section at least 2 weeks prior to commencing work.
1.5 SUBMITTALS
.1 The Contractor shall submit the following for review, in accordance with the
requirements of this Section and Section 01340 Submittals:
CN – DESIGN & DRAINAGE STRUCTURES SECTION 02631
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 5
MI. 36.79 TO 41.00 HALTON SUB
.1 Shop Drawings for Maintenance Hole Catch basins and Ditch Inlets, fully
detailed, scheduled and dimensioned, for all precast concrete structures,
grates, frames, ladders and accessories. The Contractor shall include a table
(schedule) identifying each structure, with dimensions, depth, location and
side of all openings; and
.1 The Contractor shall label each structure in accordance with he submitted schedule.
.2 The Contractor shall store structures, gratings and rings safely and neatly away
from traffic.
.3 The Contractor shall store structures, gratings and rings on wood supports of
sufficient size and strength to prevent contact with the earth and surface water.
PART 2 - PRODUCTS
2.1 MATERIALS
.1 Contractor shall ensure that all types of drainage structures specified in this
Contract located within the rail corridor are designed per AREMA manual for railway
engineering Chapter 8 using Cooper E90 loading (using AREMA safety factor).
.2 Precast manhole catch basin and ditch inlet units: to ASTM C478M and to OPSD
indicated on the Form of Tender.
.4 Mortar:
.2 Cement: to CAN/CSA-A8.
.5 Ladder rungs: to CAN/CSA-G30.18, 25M billet steel deformed bars, hot dipped
galvanized to CAN/CSA G164. Rungs to be safety pattern (drop step type).
.1 Ductile iron gratings and covers to bear evenly on frames. A frame with grating
or cover to constitute one unit. Assemble and mark unit components before
shipment;
.8 Granular bedding and backfill: Granular B Type II: to Section 02701 Granular
Materials and to Section 02315 Excavating, Trenching and Backfilling.
PART 3 - EXECUTION
.1 Excavate and backfill in accordance with Section 02315 Excavating, Trenching and
Backfilling.
3.2 INSTALLATION
.1 Construct units in accordance with details indicated, plumb and true to alignment
and grade.
.4 Set the precast concrete base on 150 mm minimum of granular bedding compacted
to 100% SPMDD.
.5 Precast units:
.1 Make each successive joint watertight with rubber ring gaskets, cement
mortar, or a combination thereof;
.2 Clean surplus mortar and joint compounds from the interior surface of the unit
as work progresses; and
.3 Plug lifting holes with precast concrete plugs set in cement mortar or mastic
compound.
CN – DESIGN & DRAINAGE STRUCTURES SECTION 02631
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 5
MI. 36.79 TO 41.00 HALTON SUB
.7 Place frame and cover on the top section to elevation as indicated. If adjustment
required, use a concrete ring.
.8 Clean units of debris and foreign materials. Remove fins and sharp projections.
Prevent debris from entering the system.
.1 Connect into existing drainage structures by use of previously installed stub pipes.
.1 Adjust the existing drainage structures indicated on the drawings to the final grade
as per OPSS 408.
.1 Visual inspection of leakage will be carried out. If any leakage is observed, correct
leakage as directed by the Engineer at no additional cost.
4.1 MEASUREMENT
.1 Measurement for manholes and catch basins shall be by each properly installed
drainage structure.
.2 Measurement for connection into existing manholes and catch basins shall be by
each properly installed connection to the existing drainage structure.
.3 Measurement for adjusting existing manholes and catch basins shall be by each
properly adjusted drainage structure.
4.2 PAYMENT
.1 Payment for the Work of this Section shall be included in the unit prices included in
the Form of Tender. Payment will be full compensation for all materials, labour, use
of equipment, tools and incidentals including but not limited to all excavation
regardless of the depth, disposal of surplus and unsuitable material off-site,
benching, bedding, backfill, grates, covers, adjusting rings and ladder rungs
necessary to complete the Work of this Section.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the requirements to clean storm pipe and drainage
structures for the works.
1.3 REFERENCES
.1 The Contractor shall be responsible for conducting their own quality assurance
program to ensure all materials, compaction, etc. Meet the requirements of this
Section and Section 01620 Quality Control and Assurance.
1.5 SUBMITTALS
.1 Not Used.
PART 2 - PRODUCTS
2.1 MATERIALS
.1 Not Used.
PART 3 - EXECUTION
3.1 CONSTRUCTION
.1 Existing manholes, catch basins and storm sewers within the construction limits
shall be cleaned out as shown or directed by the Engineer.
.2 Existing manholes, catch basins and storm sewers shall have all accumulated
materials cleaned out.
.4 Material removed from the storm system shall be disposed of off-site by the
Contractor as per OPSS.PROV 180.
.5 The Contractor shall provide the water required for flushing the storm system.
4.1 MEASUREMENT
.2 Measurement for cleaning out manholes and catch basins shall be by each
properly cleaned drainage structure.
4.2 PAYMENT
.1 Payment for the Work of this Section shall be included in the unit prices included
in the Form of Tender. Payment will be full compensation for all materials, labour,
use of equipment, tools and incidentals including but not be limited to supply of
water and off-site disposal of removed material necessary to complete the Work
of this Section.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the requirements for equipment rental for the Works.
1.3 REFERENCES
.1 Not applicable.
1.5 SUBMITTALS
.1 Not Applicable.
PART 2 - PRODUCTS
2.1 MATERIALS
.1 Not applicable.
CN – DESIGN & EQUIPMENT RENTAL SECTION 02640
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 2
MI. 36.79 TO 41.00 HALTON SUB
PART 3 - EXECUTION
.1 Requests and usage of all equipment and labour shall be under the direct
supervision of the Railway.
.2 The supplied equipment and labour shall be ready and capable of performing the
work at any time as requested by the Railway.
4.1 MEASUREMENT
.3 Payment at the Contract price shall include all labour, equipment and material to
perform the work specified herein all to the satisfaction of the Engineer.
4.2 EQUIPMENT
.1 The price per hour, for equipment, shall include mobilization and demobilization
to the site, depreciation, interest, insurance, repairs, maintenance, fuels,
lubricants, overhead, profit and any other required apparatus or attachments.
.1 The price per hour, for labourers and operators, shall include mobilization and
demobilization to the site, wages and subsistence, insurance, overhead, profit
and any other tools and equipment required to perform the work.
.1 Costs for site superintendent shall be incidental to the work and included in the
various unit prices submitted on the Form of Tender.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the granular materials requirements for the work.
1.3 REFERENCES
.1 ASTM C117-17, Standard Test Method for Materials Finer than 75um
(No. 200) Sieve in Mineral Aggregates by Washing;
.2 ASTM C136-14, Standard Test Method for Sieve Analysis of Fine and
Coarse Aggregates;
.3 The Engineer may also carry out independent Quality Assurance tests as per
Section 01620 Quality Control and Assurance of these Specifications.
1.5 SUBMITTALS
.1 The Contractor shall submit the following submittals for review in accordance
with this Section and Section 01340 Submittals:
.2 Inspection and Test Reports for all tests and inspections performed by the
Contractor.
.1 Inform the Engineer of proposed source of aggregates and provide access for
sampling at least six (6) weeks prior to commencing production.
.2 If, in opinion of the Engineer, materials from proposed source do not meet, or
cannot reasonably be processed to meet, specified requirements, locate an
alternative source or demonstrate that material from source in question can be
processed to meet specified requirements.
PART 2 - PRODUCTS
.1 Aggregate quality: sound, hard, durable material free from soft, thin, elongated or
laminated particles, organic material, clay lumps or minerals, or other substances
that would act in deleterious manner for use intended.
2.2 PRODUCTS
.1 Granular material, Granular ‘B’ Type II, OPSS 1010 and following
requirements:
.1 Crushed quarried rock or crushed pit run stone consisting of hard,
durable, angular particles, free from clay lumps, cementation,
organic material, reclaimed asphalt or concrete, frozen material
and other deleterious materials; and
.2 Gradations to be within limits specified when tested to ASTM C
136 and ASTM C 117. Sieve sizes to CAN/CGSB-8.1.
.1 Granular material, Granular ‘B’ Type II, OPSS.PROV 1010 and following
requirements:
.1 Crushed quarried rock or crushed pit run stone consisting of hard,
durable, angular particles, free from clay lumps, cementation,
organic material, reclaimed asphalt or concrete, frozen material
and other deleterious materials; and
.2 Gradations to be within limits specified when tested to ASTM C
136 and ASTM C 117. Sieve sizes to CAN/CGSB-8.1;
Sieve % Passing
Designation Sub-ballast
150 mm N/A
37.5 mm 100
26.5 mm 65 - 100
19.0 mm 55 - 80
12.5 mm 45 - 70
9.5 mm 40 - 60
4.75 mm 30 - 45
1.18 mm 15 - 30
0.300 mm 5 - 15
0.075 mm 0-8
.2 The ballast shall be loaded and placed to depth of 150 mm and width of 4.2 m for
each track (diversion and mainline).
.2 Stockpile aggregates off site, or where directed by the Engineer within the Limits
of Construction as shown on the Contract Drawings.
.4 Stockpiling sites to be level, well drained, and of adequate bearing capacity and
stability to support stockpiled materials and handling equipment.
3.2 PLACING
.6 Place material only on clean unfrozen surface, free from snow or ice.
.8 For spreading and shaping material, use spreader boxes having adjustable
templates or screens which will place material in uniform layers of required
thickness.
.9 Place material to full width in uniform layers not exceeding 150mm compacted
thickness.
.10 Shape each layer to smooth contour and compact to specified density before
succeeding layer is placed.
CN – DESIGN & GRANULAR MATERIALS SECTION 02701
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 6 OF 7
MI. 36.79 TO 41.00 HALTON SUB
.11 Remove and replace portion of layer in which material has become segregated
during spreading.
3.3 COMPACTION
.3 Equipped with device that records hours of actual work, not motor running hours.
.1 Sewer and culvert bedding: Compact to density of not less than 100%
SPMDD;
.5 Shape and roll alternately to obtain smooth, even and uniformly compacted sub
base.
3.5 PROTECTION
4.1 MEASUREMENT
.1 Measurement for work of this item shall be by the cubic meter (m3) “compacted in
place” based on cross-sections taken by the Contractor, prior to and after
placement of granular materials.
.2 The Contractor shall supply sets of original and final cross-sections, for each type
of material placed, to the Engineer for calculation purposes.
.4 Material used for culverts, drainage structures, subdrains, pipelines, etc. shall be
considered incidental to and included in this work and no separate payment shall
be made.
.5 Material used for road works shall be considered incidental to and included in this
work and no separate payment shall be made.
4.2 PAYMENT
.1 Payment for the Work of this Section shall be included in the unit prices included
in the Form of Tender. Payment will be full compensation for all materials, labour,
use of equipment, tools and incidentals necessary to complete the Work of this
Section.
.2 The Contractor will not receive payment for any quantity of material placed
outside of the site tolerances specified.
GENERAL CONDITIONS
The General Conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.2 REFERENCES
.1 The Contractor shall be responsible for conducting their own quality control
program to ensure all materials, compaction, etc., meet the requirements of the
specifications, as per Section 01620 Quality Control and Assurance of these
Specifications and OPSS 310, Clause 310.07.01.
CN – DESIGN & HOT MIX ASPHALT - SUPERPAVE SECTION 02742
CONSTRUCTION MILTON LOGISTIC HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 5
MI. 36.79 TO 41.00 HALTON SUB
.2 The Engineer may also carry out independent Quality Acceptance tests as per
Section 01620 Quality Control and Assurance of these Specifications.
1.4 SUBMITTALS
.1 HMA Superpave mix design shall be the responsibility of the Contractor and shall
conform to OPSS 1151. The Contractor shall submit to the Engineer, for
approval, the mix designs a minimum of thirty (30) days prior to commencing
paving operations.
.2 Deliver and place HMA within temperature ranges specified by the asphalt plant
for each mix design at a continuous and uniform rate and in an amount within the
capacity of paving and compacting equipment.
.4 Remove rejected and excess material from the place of work within 48 hours.
PART 2 - PRODUCTS
2.1 MATERIALS
PART 3 - EXECUTION
3.2 EQUIPMENT
.2 Place HMA in compacted lifts between 3 and 5 times the Nominal Maximum
Aggregate Size (NMAS) of the mixture or as indicated on the drawings.
.5 Taper and level within the base course lift. The intermediate and surface courses
shall be of uniform thickness.
3.6 JOINTS
.2 Where the HMA mix design changes and lift thickness changes, change
rolling pattern only as directed by the Engineer;
.4 After traverse and longitudinal joints and outside edge have been
compacted, start rolling longitudinally at low side and progress to high
side;
.1 If irregularities or defects remain after final compaction and the work is deemed
defective, remove surface course promptly and lay new material to form true and
even surface and compact immediately to specified density, at no cost to the
Engineer.
3.10 SURVEY
.1 Perform survey of finished compacted asphalt grade and submit survey data to
Engineer.
CN – DESIGN & HOT MIX ASPHALT - SUPERPAVE SECTION 02742
CONSTRUCTION MILTON LOGISTIC HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 5
MI. 36.79 TO 41.00 HALTON SUB
PART 4 - MEASUREMENT AND PAYMENT
4.1 MEASUREMENT
.1 Measurement for work of this section except as noted below shall be in square
metres (m2) of Hot Mix Asphalt - Superpave actually placed and accepted by the
Engineer.
.2 Lap joints shall be considered incidental to the works and no separate payment
will be made.
4.2 PAYMENT
.1 Payment for the Work of this Section shall be included in the unit prices included
in the Form of Tender. Payment will be full compensation for all materials, labour,
testing, use of equipment, tools and incidentals, including tack coat, necessary to
complete the Work of this section
.3 The average thickness for the core shall be based on the measurement from
each quadrant of the core, with the average thickness for the area determined by
averaging the core thickness.
.4 When average thickness is more than or equal to 95% of the specified thickness,
the payment shall be the total surface area of the HMA type laid for the course.
.5 When the average thickness is less than 95% of the specified thickness, the
surface area for payment purposes shall be calculated as follows:
GENERAL CONDITIONS
The General Conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.2 REFERENCES
.3 MTO Manual of Uniform Traffic Control Devices (Metric Edition) - latest edition.
.2 The Engineer may also carry out independent Quality Assurance tests as per
Section 01620 Quality Control and Assurance of these Specifications.
CN – DESIGN & PAINTED TRAFFIC LINES - DURABLE SECTION 02761
CONSTRUCTION MILTON LOGISTIC HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 3
MI. 36.79 TO 41.00 HALTON SUB
1.4 SUBMITTALS
.1 Submit to Engineer the following material sample quantities at least four (4)
weeks prior to commencing work:
.3 Mark samples with the name of the project and its location, paint
manufacturer's name and address, name of paint, CGSB specification
number and formulation number and batch number.
PART 2 - PRODUCTS
2.1 MATERIALS
.1 Markings:
PART 3 - EXECUTION
.1 Pavement surface to be dry, free from ponded water, frost, ice, dust, oil, grease
and other foreign materials.
3.3 APPLICATION
.3 Apply traffic paint evenly at a rate that results in uniform thickness of 1.90 mm
±0.40 mm measured dry.
.8 Thoroughly clean distributor tank before refilling with paint of different colour.
3.4 TOLERANCE
4.1 MEASUREMENT
4.2 PAYMENT
.1 Payment for the Work of this Section shall be included in the lump sum and unit
prices included the Form of Tender. Payment will be full compensation for all
materials, labour, use of equipment, tools and incidentals necessary to complete
the Work of this section.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the fabrication and installation requirements for Fences
and Gates for the works, including the following:
1.3 REFERENCES
.1 Provide the Engineer with copies of supplier’s test reports on all materials that
are to be incorporated in the fences.
.2 Provide the Engineer with copies of all field quality control tests conducted on the
fences.
.3 The Contractor shall be responsible for conducting their own quality assurance
program to ensure all materials meet the requirements of this Section and
Section 01620 Quality Control and Assurance.
.4 The Engineer may also carry out independent Quality Assurance tests as per
Section 01620 Quality Control and Assurance of these Specifications.
1.5 SUBMITTALS
.1 The Contractor shall submit the following submittals for review in accordance
with this Section and Section 01340 Submittals:
.2 Submit Shop Drawings showing the dimensions, type, size, and nature of
all components and fasteners As-Builts Drawings for Fences and gates.
PART 2 - PRODUCTS
2.1 MATERIALS
.1 Chain Link Fence with barb wire as per OPSD 972.101 and OPSD 972.130
.5 Fabric: Fence Fabric: Type 1 Steel Fabric 3.5 mm steel wire of the
following type;
.8 Post caps to provide waterproof fit, to fasten securely over posts and to
carry top rail;
.1 1.2 m high construction plastic orange fence installed with steel T-bar at
1.8 m interval.
.4 WILDLIFE FENCE
.1 Wildlife fence attached to Chain link fence OPSD 973.133 and 973.142
.6 WOODEN STAKES
PART 3 - EXECUTION
3.1 GRADING
.1 The Contractor shall remove all debris and shall correct ground undulations
along the fence line to obtain a smooth uniform gradient between posts.
.2 The Contractor shall protect all existing fences for all properties along the
perimeter that will remain in place. The Contractor shall replace the fences
damaged due to Construction activities.
.2 The Contractor shall erect fence along lines as indicated on Design Drawings
and in accordance with CAN/CGSB 138.3.
.3 The Contractor shall dispose of all excavated material in accordance with the
Contract Documents.
.5 Align top of posts to ensure that top rail varies gradually with changes in ground
elevations.
.6 Pass top rail through line post tops to form continuous bracing. Install 150mm
long couplings mid span at pipe ends.
.7 Brace each gate and corner post back to adjacent line post with horizontal center
brace rail. Install brace rail, one bay from corner and gate posts.
.8 Install 10mm steel truss rod and truss tightener diagonally from top of gate post
back to adjacent line post.
.9 Fasten fabric to top rail, line posts, braces and bottom tension wire with 3.5 mm
wire ties with maximum 500 mm centers.
.10 Attach fabric to corners and posts with tension bars and tension bar clips. Stretch
fabric between posts at intervals of 30.0 m maximum.
.1 Install wood stakes to delineate the no-go areas and construction limits at 30 m
interval in accordance with Contact Drawings.
.1 1.2m high construction plastic orange fence installed with steel T-bar at 1.8 m
Interval in accordance with the layout indicated in the Contact Drawings.
.1 Pull the mesh taut and staple or secure with screws and a metal stripping to
prevent the mesh from being ripped when pressure is applied.
.2 Installing a top rail or folding the mesh over a taut smooth wire reduces tearing.
.3 An outward facing lip installed on the species side ensures that snakes and
amphibians are unable to climb or jump over the fence.
.1 The Contractor shall ensure that any touch-up work performed is undertaken in
accordance with manufacturer’s requirements
.2 Surface preparation:
.1 Clean damaged surfaces with wire brush removing loose and cracked
coatings. Apply two coats of organic zinc rich paint to damaged areas.
.3 Painting surface:
3.7 CLEANING
.1 Clean and trim areas disturbed by operations. Dispose of surplus material off
site.
CN – DESIGN & FENCING AND ROAD SIGNAGE SECTION 02825
CONSTRUCTION MILTON LOGISTIC HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 7 OF 7
MI. 36.79 TO 41.00 HALTON SUB
PART 4 - MEASUREMENT AND PAYMENT
4.1 MEASUREMENT
.1 Measurement of all types of fences shall be by linear meters (m) of the installed
fence as measured in the field.
.2 Measurement for chain link fence on top of jersey barrier shall be by linear
meters (m) of the installed fence as measured in the field.
.3 Measurement for chain link gates shall be by each (ea) gate as installed in the
field.
.4 Measurement for wood stakes shall be by each (ea) stake as installed in the
field.
.5 Measurement for road shall be by each (ea) sign as installed in the field.
4.2 PAYMENT
.1 Payment for the Work of this Section shall be included in the unit prices included
in Form of Tender. Payment will be full compensation for all materials, labour,
use of equipment, tools and incidentals necessary to complete the Work of this
Section.
GENERAL CONDITIONS
The General Conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
.1 Not Used
1.2 REFERENCES
.1 OPSS 552 - Construction Specification for Steel Beam Guide Rail and
Cable Guide Rail, except as modified below
.1 Submit manufacturer’s test data and certification that all materials meet the
requirements of this section at least thirty days (30) prior to commencing work.
1.4 SUBMITTALS
.1 Submit shop drawings showing dimensions, type, size, and nature of all
components and fasteners.
PART 2 - PRODUCTS
2.1 MATERIALS
.2 Steel Beam Guide Rail: per OPSS 1504 and OPSD 912.185, 912.186 and
912.188 TYPE M.
.4 Steel Posts.
CN – DESIGN & STEEL BEAM GUIDE RAIL SECTION 02844
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 3
MI. 36.79 TO 41.00 HALTON SUB
PART 3 - EXECUTION
3.1 GRADING
.1 Remove debris and correct ground undulations along guide rail line to obtain
smooth uniform gradient between posts. Provide clearance between bottom of
guide rail and ground surface of 40 mm to 75 mm.
.1 Erect guide rail along lines, as indicated and in accordance with contract
drawings.
3.3 TOUCH UP
.1 Clean damaged surfaces with wire brush, removing loose and cracked coatings.
Apply two coats of organic zinc-rich paint to damaged areas.
3.4 CLEANING
.1 Clean and trim areas disturbed by operations. Dispose of surplus material off
site.
.1 Measurement for work of this section shall be in linear metres of installed guide
rail as measured in the field.
4.2 PAYMENT
.1 Payment will be at the Contract price, per lineal metre, and shall include all
labour, equipment and material to perform the work specified herein, including
CN – DESIGN & STEEL BEAM GUIDE RAIL SECTION 02844
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 3
MI. 36.79 TO 41.00 HALTON SUB
steel beam guide rail, steel channel, steel posts, steel offset blocks, concrete
footings, fasteners and all incidental items required for Work of this section.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 GENERAL
.1 This Section specifies the seed, sod and cover requirements for the Works.
.1 The Contractor is responsible for conducting its own quality assurance program
to ensure all seed, sod, and cover meet the requirements of the Specifications in
accordance with Section 01620 Quality Control and Assurance.
CN – DESIGN & SEED, SOD AND COVER SECTION 02910
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE
MI. 36.79 TO 41.00 HALTON SUB PAGE 2 OF 7
1.5 SUBMITTALS
.1 The Contractor shall submit the following submittals for review in accordance
with the requirements of this Section, Section 01340 Submittals:
.1 Topsoil, Seed and Mulch Test Report at least four weeks prior to
commencing the installation for review in accordance with the
requirements of this Section and Section 02912 Topsoil and Finish
Grading:
.1 Topsoil, Seed and Mulch Test Report shall also include suppliers’
test data and certification, including the Seed Analysis Certificates
confirming that all materials meet the requirements of this Section.
.1 The Contractor shall ensure that all Products remain in their original sealed
packaging until their installation.
PART 2 - PRODUCTS
2.1 PRODUCTS
.1 Seed Mix 1 (Stabilization Mix) for all slopes. Sow simultaneously with all
other seed mixes at a rate of 25 kg/ha.
CN – DESIGN & SEED, SOD AND COVER SECTION 02910
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE
MI. 36.79 TO 41.00 HALTON SUB PAGE 3 OF 7
% Common Name Latin Name
18 Autumn Bentgrass Agrostis perennans
18 Slender Wheat Grass Elymus trachycaulus
12 Canada Wild Rye Elymus canadensis
12 Virginia Wild Rye Elymus virginicus
12 Switchgrass Panicum virgatum
12 Indiangrass Sorghastrum nutans
5 Big Bluestem Andropogon gerardii
5 Little Bluestem Schizachyrium scoparium
2 Black-Eyed Susan Rudbeckia hirta
2 New England Aster Symphyotrichum novae-angliae
2 Common Milkweed Asclepias syriaca
Conservation Halton Upland Dry Meadow Mix or approved other. Sow at a rate of
5 kg/ha.
% Common Name Latin Name
20 Little Bluestem Schizachyrium scoparium
15 Bottlebrush grass Elymus histrix
15 Black Eyed Susan Rudbeckia hirta
15 Meadow Sedge Carex granularis
8 Canada Goldenrod Solidago canadensis
8 Evening Primrose Oenothera biennis
5 Common Milkweed Asclepias syriaca
CN – DESIGN & SEED, SOD AND COVER SECTION 02910
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE
MI. 36.79 TO 41.00 HALTON SUB PAGE 5 OF 7
% Common Name Latin Name
5 Virgin's Bower Clematis virginiana
5 Wild Bergamot Monarda fistulosa
1 Canada Anemone Anemone canadensis
1 Grass Leaved Goldenrod Euthamia graminifolia
1 Heart-leaved Aster Symphyotrichum cordifolium
1 New England Aster Aster novae-angliae
PART 3 - EXECUTION
.1 The Contractor shall ensure that grades are prepared in accordance with the
Drawings prior to installation.
.2 The Contractor shall eliminate all uneven areas and low spots of graded soil and
ensure positive drainage.
.4 The Contractor shall remove soil contaminated with calcium chloride, toxic
materials and petroleum products.
.5 The Contractor shall dispose of all removed material off-site in accordance with
the Contract Documents.
.6 The Contractor shall not use topsoil to fill variations in the prepared earth
surface, including erosion channels.
.7 The Contractor shall ensure that in all disturbed areas, prior to any planting and
mulching, existing subsoil shall be scarified and de-compacted to 30 cm or more.
3.2 SEEDING
.2 The Contractor shall ensure that all seeding used conforms to OPSS.PROV 804.
CN – DESIGN & SEED, SOD AND COVER SECTION 02910
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE
MI. 36.79 TO 41.00 HALTON SUB PAGE 6 OF 7
3.3 SOD
.1 The Contractor shall ensure that 150 mm topsoil and Number One Turfgrass
Nursery Sod is applied to all Project areas that need to be restored with Sod as
required.
3.4 COVER
.1 The Contractor shall adhere to OPSS.MUNI 804, but at a rate of 4,200 kg/ha.
Hydraulic mulch shall be mixed with water in a hydraulic seeder-mulcher at a rate
of 20-300 kg of dry Product to 500 – 600 liters of water to form homogenous
slurry.
.1 The Contractor shall restore each of its stockpile sites used to store materials to
existing conditions in accordance with Section 02315 Excavation, Trenching,
Backfilling and Compacting.
4.1 MEASUREMENT
.1 Measurement for payment shall be per square meter (m2) properly seeded by the
Contractor and inspected and approved by the Engineer or CN’s Environmental
Monitor.
.2 Seeding of disturbed areas resulting from other items of this tender (including the
removal of erosion and sediment control measures) shall be considered
incidental to the tender price. Seed shall be applied at rates indicated on the
Contract Drawings per seed mix type and shall be applied. This item will not be
considered for additional payment and the repair and restoration of disturbed
areas shall be considered as part of the entire tender price.
4.2 PAYMENT
.1 Payment at the unit price tendered in the Form of Tender shall be considered
compensation in full for all specified labour and equipment, hauling, placing,
handling, sorting, fitting, materials, and incidentals required by the Contractor.
CN – DESIGN & SEED, SOD AND COVER SECTION 02910
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE
MI. 36.79 TO 41.00 HALTON SUB PAGE 7 OF 7
*** END OF SECTION ***
CN – DESIGN & TOPSOIL AND FINISH GRADING SECTION 02912
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 1 OF 5
MI. 36.79 TO 41.00 HALTON SUB
GENERAL CONDITIONS
The General Conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 GENERAL
.1 This Section specifies the requirements of topsoil and finish grading for the
Works.
.1 The Contractor shall be responsible for conducting their own quality assurance
program to ensure all materials, compaction, etc. meet the requirements of the
specifications, as per Section 01620 Quality Control and Assurance of these
Specifications.
1.5 SUBMITTALS
.1 The Contractor shall submit the following submittals for review in accordance
with the requirements of this Section and Section 01340 Submittals:
.1 Topsoil, Seed and Mulch Test Reports providing test results for soil
analysis and information about sources of topsoil to be used. Reports are
to be provided four weeks in advance of commencing work. The
Contractor shall be responsible for soil analysis and requirements for
amendments to supply topsoil as specified:
.2 The Contractor shall submit Top Soil and Finish Grading - Topographical
Survey submittal for review. This submittal shall include a topographical
survey of the entire topsoil, seed and sod area within the Limits of
Construction and access roads of the Works prior to commencing
construction and a topographical survey of the same area following the
placing of topsoil, seed, and cover.
PART 2 - PRODUCTS
2.1 TOPSOIL
.1 The contractor shall ensure to reuse all topsoil generated from the site. In case of
additional topsoil is required, the Contractor shall ensure that all imported topsoil
for seeded and sodded areas is a mixture of mineral particulates, micro-
organisms and organic matter:
.1 The Contractor shall ensure that all soil texture conforms to the Canadian
System of Soil Classification 3rd Edition (1998), which specifies a
consistency of 20% to 70% sand and 2% to 10% organic matter by
weight;
.2 With regard to fertility, the Contractor shall ensure that all major soil
nutrients present in the following ratios:
.3 The Contractor shall ensure that installed topsoil has a Ph value in the
range of 6.5 to 8.0;
.5 Prior to installation, the Contractor shall ensure that all topsoil is free
from:
.6 The Contractor shall ensure that the consistency of topsoil is friable when
moist.
PART 3 - EXECUTION
.1 The Contractor shall ensure that the grades are prepared in accordance with the
Contract Drawings prior to installation. If discrepancies occur, the Contractor
shall notify the Engineer for review.
.2 The Contractor shall ensure that all graded soil has uneven areas and low spots
eliminated, ensuring positive drainage.
.3 The Contractor shall remove all debris, roots, branches, stones in excess of
50mm diameter and other deleterious materials.
.4 The Contractor shall remove soil contaminated with calcium chloride, toxic
materials and petroleum Products.
.5 The Contractor shall dispose of all removed material off Site in accordance with
Contract Documents.
CN – DESIGN & TOPSOIL AND FINISH GRADING SECTION 02912
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 5
MI. 36.79 TO 41.00 HALTON SUB
.1 The Contractor shall not place the topsoil until the subgrade is verified and
accepted by the Contractor-appointed survey team and an Independent
Laboratory and Sampling and Testing Company.
.2 The Contractor shall spread the topsoil in uniform layers not exceeding 150mm,
over unfrozen subgrade free of standing water.
.3 For sodded areas, the Contractor shall ensure that topsoil is 15mm below the
finished grade.
.4 The Contractor shall spread topsoil to depths as indicated on the Drawings after
settlement and compaction.
.5 The Contractor shall manually spread topsoil/planting soil around trees, shrubs
and obstacles.
.1 The Contractor shall grade to eliminate rough spots and low areas and ensure
positive drainage. The Contractor shall prepare a loose friable bed by means of
cultivation and subsequent raking.
.2 The Contractor shall consolidate topsoil to the required bulk density using
appropriate equipment. The Contractor shall ensure that it leaves surfaces
smooth, uniform and firm against deep footprinting.
.3 The Contractor shall compact and drag the topsoil to remove any equipment
depressions or any other surface irregularities that will encourage erosion.
3.4 ACCEPTANCE
.1 The Contractor shall inspect and test the topsoil in place to determine
acceptance of the material, the depth of the topsoil and the finish grading. The
Contractor shall provide the Topsoil, Seed and Mulch Test Reports for review.
.2 The Contractor shall correct any failure of topsoil, seed or cover work, as well as
any repairs of erosion, including the repair of scouring, slough, and clean-up/
excavation of eroded material (i.e. cleaning-out ditches), for a period of two
growing seasons.
.1 The Contractor shall restore stockpile sites used to store materials to their
existing conditions in accordance with Section 02315 Excavation, Trenching, and
Backfilling.
CN – DESIGN & TOPSOIL AND FINISH GRADING SECTION 02912
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 5
MI. 36.79 TO 41.00 HALTON SUB
.1 The Contractor shall dispose the unwanted and surplus materials in accordance
with Section 2311 Site Grading and Section 02315 Excavation, Trenching, and
Backfilling.
4.1 MEASUREMENT
.1 Measurement for topsoil and finish shall be by square meters of properly installed
topsoil.
.2 The Contractor will not receive payment for any quantity of material placed
outside of the site tolerances specified.
.3 Calculation of quantities shall be based on the area of material within the design,
as calculated by the Engineer.
4.2 PAYMENT
Payment for the Work of this Section shall be included in the unit prices included
in the Form of Tender. Payment will be full compensation for all materials, labour,
use of equipment, tools and incidentals to complete the Work of this Section.
***END OF SECTION***
CN – DESIGN & TREE AND SHRUB PLANTING SECTION 02970
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 1 OF 7
MI. 36.79 TO 41.00 HALTON SUB
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the requirements for tree and shrub planting including,
without limitation, all labour, materials and equipment required to install and
warranty plant material including rodent guards, staking and mulching in
accordance with the Contract Drawings and as specified herein.
.2 The Contractor shall pre-order all plant material to ensure availability immediately
upon award of contract. All plant substitutions must be approved by a
Landscape Architect prior to order.
.3 The Engineer or CN’s Environmental Monitor reserves the right to reject plant
material onsite prior to or after planting operations if poor quality stock is
observed. All plant materials shall be subject to inspection upon arrival on job site
before starting work. Immediately remove all rejected plant materials from the
site.
.5 All plant material delivered to the site shall be inspected and approved by the
Engineer or CN’s Environmental Monitor prior to installation. Plant material
deemed unsuitable shall be replaced at the sub-contractor’s expense and no
compensation for disposal or transport of rejected or replacement material shall
be made.
.2 All packing slips for delivery of plant material must be submitted to CN’s
Environmental Monitor within 48 hours of the delivery. Failure to provide
documentation may result in delayed or non-payment of items.
PART 2 - PRODUCTS
2.1 PRODUCTS
.4 Mulch: shall be coco discs or ‘Gro-Bark SPM’ shredded pine bark mulch or
approved equivalent(s). All plantings in riparian zones to be mulched with coco
discs only. Trees in riparian zones shall have a minimum 60cm diameter coco
mat and trees shall have 90 cm coco mat. All coco mats shall be minimum 4mm
in thickness.
Submit sample of proposed alternate for review and approval by the Engineer or
CN’s Environmental Monitor five (5) working days prior to installation.
.6 All plant material must be nursery grown and meet the specifications set out in
the latest Guide Specifications for Nursery Stock prepared by the Canadian
Nursery Landscape Association (C.N.L.A.) for size, height, spread, grading,
quality and method of cultivation.
.7 Plant Material: True to name and type, structurally sound, well branched; healthy
and vigorous and free from disease, insect infestations, rodent damage, sun
scald, frost cracks, and other abrasions to the bark and densely foliated with a
healthy, well developed root system. Pruning wounds must show vigorous bark
on all edges and all parts must show live and green cambium tissue when cut.
CN – DESIGN & TREE AND SHRUB PLANTING SECTION 02970
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 7
MI. 36.79 TO 41.00 HALTON SUB
.8 Trees: With straight trunks, well and characteristically branched for species
except where specified otherwise.
.10 Bare Root Stock: Nursery grown, in dormant stage, not balled and burlapped or
container grown.
.11 All material must conform to the sizes shown on the plant schedule, except that
larger material may be used when approved by the Engineer or CN’s
Environmental Monitor. Use of larger plants will not increase the contract price.
.1 Caliper - diameter of the trunk measured 150 mm above the normal grade
around the plant;
.2 Height - measured from the normal grade around the plant to the top of
the main foliage mass; and
.3 Spread - the diameter of the main foliage mass, at its widest point.
.13 Balled and Burlapped Plants or Wire Basket: plants marked B&B or W.B. are to
be balled and burlapped and shall be dug with a sufficient quantity of earth taken
equally on all sides and bottoms of the plants to include the necessary roots to
ensure growth. The thickness of depth of the balls shall be sufficient to include
the depth of the roots according to species. The balls shall be prepared in a
workmanlike manner and firmly bound.
.14 Perennial Plug: sufficient root mass to ensure long-term success and
establishment.
PART 3 - EXECUTION
.1 Provide plants to meet minimum plot size and heights indicated in plant
schedules on Contract Drawings.
.2 Provide rootballs of the following minimum sizes to meet the corresponding tree
size. Ensure the rootball is large enough to accommodate at least 75% of the
fibrous root system.
DECIDUOUS TREES CONIFEROUS TREES
Caliper Rootball Diameter Height Rootball Diameter
50 mm 70 cm 175 cm 60 cm
60 mm 80 cm 200 cm 70 cm
70 mm 80 cm 225 cm 80 cm
CN – DESIGN & TREE AND SHRUB PLANTING SECTION 02970
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 7
MI. 36.79 TO 41.00 HALTON SUB
80 mm 90 cm 250 cm 80 cm
90 mm 90 cm 275 cm 90 cm
100 mm 100 cm 300 cm 90 cm
.5 Carefully tie in all branches before transporting. Do not transport plant material in
an open truck unless it is adequately protected from sun and wind. Protect bare
roots by means of dampened straw, peat moss, saw dust or other acceptable
material to prevent loss of moisture during transit and storage.
.6 Keep roots moist and protected from sun and wind. Heel-in trees and shrubs
which cannot be planted immediately in shaded areas and keep well-watered.
Plant materials shall be planted within 24-hours of arrival on job site whenever
feasible.
.7 Provide a written warranty stating that all plant material as itemized on the plant
schedules are warrantied against defects and mortality for a period of two (2)
years from the date of complete (100%) installation for the planting works as
determined by the Engineer or CN’s Environmental Monitor. The Engineer shall
provide written confirmation of the warranty start date once a site inspection has
been completed following notice of completion from the Contractor.
.8 During the warranty period, replace material that is dead or not in a satisfactory,
healthy growing state or that does not meet the requirements of the
specifications at the sole discretion of the Engineer or CN’s Environmental
Monitor, at no extra cost to the Contract. Epicormic growth will not be considered
CN – DESIGN & TREE AND SHRUB PLANTING SECTION 02970
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 7
MI. 36.79 TO 41.00 HALTON SUB
acceptable growth. For Restoration Planting (01-L-463 to 01-L-465) the
Contractor is required to ensure a minimum 80% success rate within each
planting zone to meet the density target goals for each community.
.9 All plant materials shall be in a healthy, vigorous growing condition at the end of
the warranty period. A plant shall be assumed to be acceptable/successful when
it is structurally sound, when it is well furnished with living foliage, when it has
normal colour, when it shows adequate annual growth and formation of buds and
when it is free from blight or any description. Plant material which has severely
“died back” and has re-grown from a bud or shoot shall be considered to be in an
unsatisfactory condition and unacceptable.
.10 The Engineer or CN’s Environmental Monitor reserves the right to extend
warranty period for an additional one year if, at the end of initial warranty period,
leaf development and growth is not sufficient to ensure future survival.
.11 All replacements must be plants of the same size and species as shown on the
plant schedule, supplied and planted in accordance with the drawings and
specifications or as approved by the Engineer.
.13 Coordinate operations. Keep site clean and planting holes drained. Immediately
remove soil or debris spilled onto pavement.
.14 Plant bare root plant material during dormant period before buds have broken.
Trees, shrubs and perennials growing in potted containers may be planted
throughout the growing season.
.15 Plant only under conditions that are conducive to health and physical conditions
of plants.
.16 Provide planting schedule. Extending planting operations over long period using
limited crew will not be accepted.
.18 Small Trees (up to 3.0 m): Excavate holes to a diameter of 300 mm greater than
root spread or root ball.
.19 Large Trees: Excavate holes to a width of 600 mm greater than diameter of root
ball. In heavy soils, increase planting holes by 50 mm for each 100 mm of root
ball diameter.
.20 Locate all underground and overhead utilities and services at least 48-hours prior
to commencement of any planting.
CN – DESIGN & TREE AND SHRUB PLANTING SECTION 02970
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 6 OF 7
MI. 36.79 TO 41.00 HALTON SUB
.21 Protect all utilities from damage during planting operations. Repair any damage
as a result of planting operations to the approval of the Engineer or CN’s
Environmental Monitor and the appropriate utility authority at no additional cost to
the Contract.
.22 The location of trees and shrub plantings are approximate only and shall be field
fit to existing site conditions per the layout parameters provided on the Contract
drawings (01-L-500 and 01-L-501). All caliper-sized tree locations to be staked
out by the Contractor and approved by the Engineer or CN’s Environmental
Monitor prior to installation. Excavate approved locations only.
.23 The sides of all plant holes shall be vertical and the bottoms horizontal. On
slopes, the depth of excavation will be measured at the center of the hole. Unless
otherwise specified, the excess material excavated from the holes of potted or
wire basked plant material shall be removed from the site at the expense of the
Contractor unless otherwise directed by the Contract.
.24 The area to be planted shall be finished to line, grade, and the approval of the
Engineer before planting operations are begun.
.25 Planting shall be done during periods suitable with respect to weather conditions,
locally accepted practices and the approval of the Engineer or CN’s
Environmental Monitor.
.26 All plants shall be placed in a plumb position and set 50mm higher than the depth
they grew in the nursery. Prepared backfill shall be placed around the root
system. Tamping or watering shall accompany the backfilling operation to
eliminate air pockets.
.27 Place plant plumb in the center of the planting pit with a minimum of 150 mm of
compacted planting soil mixture around all sides of the rootball. Face the plant to
give the best appearance or relationship to adjacent structures. Cut away any
ropes or wires which might girdle the tree and remove the top one third of burlap
and wire basket.
.28 Place bare root plants so that the roots lie in a natural position and spread out
roots in a horizontal direction.
.29 Planting beds: Loosen compacted materials on planting bottoms and sides,
backfill with approved soil mix in 150 mm layers and firmly tamp each layer to
ensure the plant retains its orientation. Ensure no air pockets remain around the
roots.
.30 Water thoroughly when hole is 1/2 full of tamped soil mixture, and again when
the operation is.
.31 Except for plants in planting beds, construct an earth saucer around each tree
equal to the diameter of the root ball and 100 mm minimum depth to retain water
around the roots.
CN – DESIGN & TREE AND SHRUB PLANTING SECTION 02970
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 7 OF 7
MI. 36.79 TO 41.00 HALTON SUB
.32 Install tree supports as shown on planting details in Contract Drawings. Drive
stakes minimum 150 mm into undisturbed soil beneath root ball. Ensure stake is
secure, firm, plumb, and straight and true to line.
.33 Prune all dead, dying and broken branches, do not prune healthy branches.
Preserve the natural form and character of the plants. Do not cut leader. Use
only clean, sharp tools and make cuts flush without leaving stubs.
.34 Spread mulch to a minimum depth of 100 mm or place coco discs. Do not cover
the root flare and ensure that mulch is not mounded on the trunk and is a
minimum of 50 mm from trunk.
.35 Maintain all plant materials from time of planting until the end of the two-year
warranty period in accordance with Section 02976 Landscape Maintenance.
.36 The Contractor shall remove all staking and ties at the termination of the first
year of the two-year warranty period. Rodent guards to be left on for the duration
of the warranty period and shall be removed prior to Final Completion.
4.1 MEASUREMENT
.1 Measurement for payment shall be per each item properly installed by the
Contractor and inspected and approved by the Engineer or CN’s Environmental
Monitor.
4.2 PAYMENT
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the requirements including, without limitation, the supply,
installation, and warranty of livestakes as per the Contract Drawings.
1.3 SUBMITTALS
.1 Provide a written warranty stating that livestakes itemized on the plant schedules
are warrantied against defects and mortality for a period of two (2) years from the
date of complete installation for the planting works as determined by the
Engineer. The Engineer shall provide written confirmation of the warranty start
date once a site inspection has been completed following notice of completion
from the Sub-contractor.
PART 2 - PRODUCTS
2.1 PRODUCTS
.1 All plant material shall be harvested locally (within the same physiographic
ecoregion and plant hardiness zone) or purchased from a local nursery, with the
approval of the Engineer or CN’s Environmental Monitor. All live stakes shall be
dormant at time of acquisition and planting. Live stakes may be installed between
November 15 and March 15 in non-frozen conditions.
.1 All replacements must be plants of the same size and species as shown on the
plant schedule, supplied and planted in accordance with the drawings and
specifications or as approved by the Engineer or CN’s Environmental Monitor.
.2 During preparation, the basal ends of the live stakes shall be cleanly cut at an
angle to facilitate easy insertion into the soil, while the tops shall be cut square or
blunt for tamping. All limbs shall be removed from the sides of the live cutting
prior to installation.
.3 Cuttings for live stakes shall be harvested in manner such that they are cut,
immediately put into water to be soaked for 24-hours, and then planted
immediately after the 24-hours are completed. Cuttings shall remain wet until
they are planted. Outside storage locations should be continually shaded and
protected from wind and direct sunlight.
.4 Live stakes shall be tamped perpendicularly into the finished bank slope with a
dead blow hammer, with buds oriented in an upward direction. Stakes should be
tamped until approximately ¾ of the stake length is within the ground.
.5 The area around each live stake shall be compacted by foot after the live stake
has been installed.
.7 Where nursery availability restricts species from fall planting, accommodation for
spring planting shall be reviewed and must be approved by the Engineer or CN’s
Environmental Monitor in writing.
.8 During the warranty period, replace material that is dead or not in a satisfactory,
healthy growing state or that does not meet the requirements of the
specifications at the sole discretion of the Engineer, at no extra cost to the
Contract. Epicormic growth will not be considered acceptable growth. The Sub-
contractor is required to ensure a minimum 75% success rate within the overall
livestake planting zone to meet the minimum density target goals. A minimum of
one successful livestake shall be present in each square meter (m2) of planting
area to ensure bank stability.
.9 All live stakes shall be in a healthy, vigorous growing condition at the end of the
warranty period. A plant shall be assumed to be acceptable/successful when it is
structurally sound, when it is well furnished with living foliage, when it has normal
colour, when it shows adequate annual growth and formation of buds and when it
is free from blight or any description. A live stake which has severely “died back”
and has re-grown from a bud or shoot shall be considered to be in an
CN – DESIGN & LIVESTAKES SECTION 02972
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 3
MI. 36.79 TO 41.00 HALTON SUB
unsatisfactory condition and unacceptable (within the established allowable
mortality parameters).
4.1 MEASUREMENT
.1 Measurement for payment shall be per each item properly installed by the sub-
contractor and inspected and approved by the Engineer or CN’s Environmental
Monitor.
4.2 PAYMENT
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of this
Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section 03200 specifies the requirements for the supply and installation of steel
reinforcement and mechanical connections for concrete structures.
.2 Welding Details
.1 Mill test certificate submissions for reinforcing steel bars, stainless steel
reinforcing bars, steel welded wire reinforcement, splice bars and stainless
steel splice bars shall be according to OPSS.PROV 1440.
PART 2 - PRODUCTS
2.1 MATERIALS
.1 Reinforcing Steel Bars, Splice Bars, Tie Bars, Dowel Bars, Spirals, and Spacers
.1 Reinforcing steel bars, splice bars, tie bars, dowel bars, spirals and spacers
shall be in accordance with OPSS.PROV 1440 with the following additions
and amendments:
.1 The second paragraph of Subsection 1440.05.01 of OPSS.PROV
1440 is deleted in its entirety and replaced by the following:
.1 All reinforcing steel bars shall be Grade 400W except for a
structure, the grade shall be as specified in the Contract
Documents.
.2 Stainless Steel Reinforcing Bars, Stainless Steel Splice Bars, Tie Bars, Dowel Bars,
Spirals, Spacers, and Stainless Steel Mechanical Connectors
.1 Stainless steel reinforcing bars, stainless steel splice bars, tie bars, dowel
bars, spirals, spacers, and stainless steel mechanical connectors shall be in
accordance with OPSS.PROV 1440 with the following additions and
amendments:
.1 The first paragraph of Subsection 1440.05.02 of OPSS.PROV 1440 is
deleted in its entirety and replaced by the following:
.1 Stainless steel reinforcing bars and spirals shall be according
to ASTM A276 and ASTM A955, minimum Grade 520.
.5 Mechanical Connections Details for Reinforcing Steel Bars and Stainless Steel
Reinforcing Bars
.1 Mechanical connections details for reinforcing steel bars and stainless steel
reinforcing bars shall be in accordance with OPSS.PROV 905.
.6 Mechanical Connectors for Reinforcing Steel Bars and Stainless Steel Reinforcing
Bars
.7 Associated Hardware
2.2 PRODUCTION
.3 Fabrication of Reinforcing Steel Bar, Stainless Steel Reinforcing Bar, Splice Bar, and
Stainless Steel Splice Bars
.1 Fabrication of reinforcing steel bar, stainless steel reinforcing bar, splice bar,
and stainless steel splice bars shall be in accordance with OPSS.PROV 1440
with the following additions and amendments:
.1 The first paragraph of Subsection 1440.07.03 of OPSS.PROV 1440 is
deleted in its entirety and replaced by the following:
.1 Bars shall be cold bent at the fabricator's shop listed under
“Fabricators” in the MTO’s DSM listings for Reinforcing Steel,
for the grade specified in the Contract Documents.
.4 Identification
CN – DESIGN & CONCRETE REINFORCEMENT SECTION 03200
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 5
MI. 36.79 TO 41.00 HALTON SUB
.1 Identification of reinforcing steel bars, stainless steel reinforcing bars, splice
bars and stainless steel splice bars shall be in accordance with OPSS.PROV
1440.
PART 3 - EXECUTION
3.1 CONSTRUCTION
.1 All steel reinforcement and accessories shall be kept clean of mud, oil and other
deleterious materials, and stored clear of ground contact.
.3 Storage and protection, placing, surface condition, cutting, bending, welding, splicing
and mechanical connections of reinforcing steel bars, stainless steel reinforcing bars,
splice bars, stainless steel splice bars and steel welded wire reinforcing shall be in
accordance with OPSS.PROV 905.
.2 The next operation shall not proceed until a Notice to Proceed has been
received from the Engineer.
.1 Payment at the Contract price for the reinforcing steel bar, Grade 400W
tender items and stainless steel reinforcing bar tender items shall be full
compensation for all labour, equipment and materials to do the work.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of this
Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section 03203 specifies the requirements for concrete accessories for the
works, including the following:
.3 Supply and placing of preformed seals, joint fillers, joint sealing compounds
and proprietary joint seals; and
.3 ASTM D5329-20, Standard Test Methods for Sealants and Fillers, Hot-
Applied, for Joints and Cracks in Asphalt Pavements and Portland Cement
Concrete Pavements.
.1 Deck Joint Assemblies, Preformed Seals, Joint Fillers, Joint Sealing Compounds and
Proprietary Joint Seals
.1 Quality assurance for deck joint assemblies, preformed seals, joint fillers, joint
sealing compounds and proprietary joint seals shall be in accordance with
OPSS.PROV 920.
Testing Requirements
Notes:
1. For each batch of sealant compound used in hot mix
asphalt pavements, the Contractor shall provide results
for all of these tests. However, for re-heated sealant
compounds that are sampled during construction, these
tests will be completed at the discretion of the Engineer.
2. For each batch of “All Districts” products used as
joint/crack sealant compound in hot mix asphalt
pavements, the Contractor shall provide test results
based on bond testing that is conducted in three cycles
at -29 °C with both 50% and 200% extension. For each
batch of “Southern Ontario Only” sealant used as
joint/crack sealant compound in hot mix asphalt
CN – DESIGN & CONCRETE ACCESSORIES SECTION 03203
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 10
MI. 36.79 TO 41.00 HALTON SUB
pavement, the Contractor shall provide test results
based on bond testing that is conducted in five cycles at
-18 °C with 50% extension. All re-heated sealant
compounds sampled during construction will be tested in
five cycles at -18 °C with 50% extension, or when used
as joint/crack sealant compound in hot mix asphalt
pavements, the samples will be tested, as specified by
the Engineer.
1.5 SUBMITTALS
.1 Within 30 days of the Contract award, the name and address of the
manufacturer of the deck joint assembly shall be submitted to the Engineer.
.4 Submittals for cold weather protection for epoxy injection shall be according
to OPSS.PROV 920.
.1 Product technical data sheets and samples of preformed seals, joint fillers
and joint sealing compounds shall be submitted to the Engineer.
.1 The proprietary joint seal product technical data sheet shall be submitted to
the Engineer at least five days prior to installation.
PART 2 - PRODUCTS
2.1 DESIGN
2.2 MATERIALS
.2 Deck Joint Assemblies, Preformed Seals, Joint Fillers and Joint Sealing Compounds
.1 Deck joint assemblies, preformed seals, joint fillers and joint sealing
compounds shall be in accordance with OPSS.PROV 920.
.1 All proprietary joint seal materials shall be supplied as new from the
manufacturer and no materials shall be used that are more than two years old
from the date of manufacture.
.2 The proprietary joint seal shall be selected from the table below:
JP Series JP-150
Sealing Systems
Jeene 50-W
SPS SPS-225
Testing Requirements
Sealant Designation
Test
“Southern “All Districts”
Ontario Only” (Note 1)
Flow (mm) 5 3
Notes:
1. A successful field trial is required before a product is accepted
for placement on the MTO’s DSM.
2.3 PRODUCTION
.2 Joint Fillers
.1 Cutting and tolerance, and packaging and marking of joint fillers shall be in
accordance with OPSS.PROV 1308.
.1 Pouring Point
.1 The pouring point for hot-poured rubberized asphalt joint/crack
sealant compounds shall be at least 10 °C lower than the safe heating
temperature recommended by the manufacturer.
.2 For hot-poured rubberized asphalt joint/crack sealant compounds
used for sealing joints and cracks in Portland cement concrete
pavements, the pouring point shall also be the lowest temperature to
which the material is heated and at which it is suitable for filling a 12.5
mm wide and 40 mm deep groove formed between two blocks of
concrete without inclusions of large air voids or discontinuities and
without damage to the material.
.3 For hot-poured rubberized asphalt joint/crack sealant compounds
used for sealing joints and cracks in asphalt pavements, the pouring
point shall also be the lowest temperature to which the material is
heated and at which it is suitable for filling a 40 mm wide and 10 mm
deep groove cut in asphaltic concrete pavement without inclusions of
large air voids or discontinuities and without damage to the material.
PART 3 - EXECUTION
.1 Any equipment required to install the proprietary joint seals shall be according
to manufacturer’s requirements.
CN – DESIGN & CONCRETE ACCESSORIES SECTION 03203
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 8 OF 10
MI. 36.79 TO 41.00 HALTON SUB
.2 Equipment for Pressure Injection, Routing and Sealing of Joints/Cracks in Concrete
3.2 CONSTRUCTION
.3 Joint Fillers
.1 General
.1 The proprietary joint seals shall be installed at all locations specified in
the Contract Documents.
.2 Surface Preparation
.1 All damaged and unsound surfaces along the joint interface shall be
repaired according to the manufacturer’s recommendations. Any
concrete repairs required shall be performed in accordance with
OPSS.PROV 930. Any repairs required along the joint interface to
meet this requirement that are not specified in the Contract
Documents shall be considered a Change in the Work.
.2 For proprietary joint seal systems that require the application of primer
or adhesive, all dust, dirt, debris, and deleterious materials shall be
removed from the joint interface and abrasive blast cleaned according
to OPSS.PROV 929 for concrete surfaces, or as recommended by the
proprietary joint seal manufacturer for steel surfaces.
.3 Product Installation
CN – DESIGN & CONCRETE ACCESSORIES SECTION 03203
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 9 OF 10
MI. 36.79 TO 41.00 HALTON SUB
.1 The proprietary joint seals shall be installed in accordance with the
manufacturer’s installation guidelines and requirements.
.2 A technical representative shall be on site to review the
manufacturer’s installation guidelines and requirements prior to the
initial proprietary joint seal installation and then to observe the
installation.
.4 Post Installation
.1 A letter from each manufacturer’s technical representative shall be
submitted to the Engineer, indicating that the technical representative
was present during initial installation and that each observed
proprietary joint seal was installed according to the manufacturer’s
installation guidelines and requirements.
.2 Work shall only proceed when the temperature of the concrete is greater than
or equal to 5 °C.
.3 Access, crack identification, crack injection, and routing and sealing of cracks
shall be in accordance with OPSS.PROV 932.
.1 Payment at the Contract price for the deck joint assemblies, installation
tender items shall be full compensation for all labour, equipment and
materials to do the work.
.1 Payment for the tender items in which preformed seals, joint fillers, joint seals
and joint sealing compounds are placed shall include full compensation for all
labour, equipment and materials to do the work of placing these materials.
.1 Payment at the Contract price for the proprietary joint seal tender item shall
be full compensation for all labour, equipment, and materials to do the work.
.1 Payment at the Contract price for the routing and sealing – hot-poured
rubberized joint sealing compound tender items, and the routing and sealing
– cold-applied joint sealing compound tender items shall be full compensation
for all labour, equipment and materials to do the work.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 GENERAL
.1 This Section specifies the requirements for concrete curb and gutter, and
concrete sidewalk.
1.3 REFERENCES
.1 The Contractor shall be responsible for conducting their own quality assurance
program to ensure all materials, compaction, etc., meet the requirements of the
specifications, as per Section 01620 Quality Control and Assurance of these
Specifications.
.2 The Consultant may also carry out independent Quality Assurance tests as per
Section 01620 Quality Control and Assurance of these Specifications.
1.5 SUBMITTALS
.1 The Contractor shall submit the following submittals for review in accordance
with this Section and Section 01340 Submittals:
CN – DESIGN & CURB AND GUTTER SECTION 03310
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 4
MI. 36.79 TO 41.00 HALTON SUB
.1 Copy of mix designs, sieve analysis and specific gravity of aggregates
with report from Testing Agency, shall be submitted to the Engineer for
review.
PART 2 - PRODUCTS
2.1 MATERIALS
.8 Joint filler 10mm preformed expansion joint filler, Type A, non-extruding &
resilient bituminous type, as per OPSS 1308.
.9 Non-staining mineral type form release agent: chemically active release agents
containing compounds that react with free lime to provide water-soluble soap.
PART 3 - EXECUTION
.3 Place granular base course of OPSS Granular ‘A’ in maximum 150 mm loose lifts
and compact to a minimum of 98% of SPMDD.
3.2 CONCRETE
3.3 TOLERANCES
3.4 JOINTS
3.5 CURING
.2 Where burlap is used for moist curing, place two prewetted layers on concrete
surface and keep continuously wet during curing period.
.4 Any 28-day strength test result is more than 3.5 MPa below the specified
minimum 28-day strength.
.1 Repair defective areas while concrete is still plastic, otherwise wait until
curing is completed. Use repair methods approved by the Engineer.
.4 Install tie bars between old and new concrete as directed by the
Engineer.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of this
Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section 03312 specifies the requirements for the construction of concrete
structures, including the following:
.3 Supply, delivery and installation of approach slab seat bearings and ballast
wall bearings;
.4 Supply, delivery and installation of ethylene vinyl acetate (EVA) foam; and
.2 Forms
.1 PH-CC-433A, Concrete Mix Design Submission Form A;
.2 PH-CC-447, Concrete Aggregate Gradation Acceptance Sheets; and
.3 PH-D-10, Aggregate Sample Data Sheet.
.1 CSA A23.2-19, Test Methods and Standard Practices for Concrete; and
.5 Table 1 of OPSS.PROV 1002 is deleted in its entirety and replaced with the
following:
TABLE 1
Lot Schedule for Sampling and Testing
Notes:
1. For the purposes of this table only, the same mix design shall mean
that all the applicable mix designs involved have:
a) Aggregates with the same Nominal Maximum Aggregate Size(s),
comprised of the same individual aggregate component(s),
produced from the same source(s), and from the same bench(es)
when specific bench(es) are required in quarry source(s); AND
b) Where blended fine and/or coarse aggregates are also involved, all
the applicable mix designs have the same relative proportions of
each individual fine aggregate component within the blended fine
aggregate and the same relative proportions of each individual
coarse aggregate component within the blended coarse aggregate,
respectively.
2. For tender items with units of measurement other than m3, the
quantities shall be converted to m3, to establish the lot schedule.
3. Structural concrete items using the same mix design as defined in Note
1 for the same structure shall be combined in individual lots of up to
500 m3. If the total quantity of structural concrete items for all structures
in the contract is less than 150 m3, structural concrete items using the
same mix design as defined in Note 1 for multiple structures shall be
combined in individual lots of up to 15 m3.
4. At the discretion of the Engineer, concrete repairs, individual sections
of bridge decks or critical structural elements such as cast-in-place
girders, cantilever extensions etc., can form their own lot or lots,
regardless of Note 1 and Note 3 or their quantities.
5. Where the remaining quantity of the applicable tender item is
insufficient to form a complete lot and is:
a) Less than one half the quantity of a complete lot, then that quantity
shall be added to the previous lot, or,
b) Greater than or equal to one half the quantity of a complete lot, then
that quantity shall form its own lot.
.6 Table 2 of OPSS.PROV 1002 is deleted in its entirety and replaced with the
following:
TABLE 2
Grading Requirements for Fine Aggregates, LS-602 (Note 1)
9.5 mm 100
4.75 mm 95-100
CN – DESIGN & CONCRETE WORK SECTION 03312
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 8 OF 23
MI. 36.79 TO 41.00 HALTON SUB
2.36 mm 80-100
1.18 mm 50-85
600 µm 25-60
300 µm 10-30
150 µm 0-10
Notes:
1. Fine aggregates shall have no more than 45% passing any sieve and
retained on the next consecutive sieve.
2. The fineness modulus shall be a minimum of 2.3 and a maximum of
3.1.
3. The mean fineness modulus for the lot shall not vary by more than
±0.20 from the fineness modulus shown on the PH-CC-433A accepted
by the Engineer for the corresponding concrete tender item.
.7 Table 3 of OPSS.PROV 1002 is deleted in its entirety and replaced with the
following:
TABLE 3
Physical Property Requirements for Fine Aggregate(s)
Notes:
1. LS-615, LS-619, LS-620 and LS-635 and Sulphur content shall apply to
each individual fine aggregate component in the mix. LS-610 and LS-
613 shall be carried out either on samples taken from a stockpile of the
blended fine aggregate intended to be used in the mix or from samples
taken from stockpiles of each individual fine aggregate component and
later combined in the laboratory to the proportions provided with PH-
CC-433A, prior to testing. All sampling and blending shall be as
specified in the Aggregate Processing, Handling, and Stockpiling
subsection.
2. If the fraction of a coarse aggregate passing the 4.75 mm sieve
represents more than 10% of the grading of that aggregate, by mass,
then that fraction of the individual coarse aggregate shall also meet
these requirements.
3. Blended fine aggregate that produces a colour darker than standard
colour No. 3 shall be considered to have failed this requirement.
However, a failed blended fine aggregate may be used if comparative
mortar specimens prepared according to ASTM C87/C87M meet the
following requirements:
a) Mortar specimens prepared using unwashed fine aggregate shall
have a 7 day compressive strength that is a minimum of 95% of the
strength of mortar specimens prepared using the same fine
aggregate washed in a 3% sodium hydroxide solution. Type GU
Hydraulic cement shall be used.
b) The setting time of the unwashed fine aggregate mortar specimens
shall not differ from the washed fine aggregate mortar specimens
by more than 10%.
CN – DESIGN & CONCRETE WORK SECTION 03312
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 10 OF 23
MI. 36.79 TO 41.00 HALTON SUB
.9 Table 5 of OPSS.PROV 1002 is deleted in its entirety and replaced with the
following:
TABLE 5
Grading Requirements for Coarse Aggregate, LS-602
Concrete Pavement, Concrete Base, Full Depth Repair, and Partial
Depth Repair
Notes:
1. The combined grading shall be determined either from a sample taken
from a stockpile of uniformly blended coarse aggregate intended for
use in the mix, or from a sample of coarse aggregate blended in the
laboratory according to the proportions provided along with the mix
design submission, as specified in the Aggregate Processing, Handling,
and Stockpiling subsection. As specified in LS-600, the sample of
coarse aggregate blended in the laboratory shall be prepared by first
splitting off sufficient quantities of each of the aggregate components,
based on their individual percentages stated in the mix design and the
overall blended quantity required for LS-602. Then the split portions of
each aggregate component shall be placed in a vessel of appropriate
size and blended together by mixing. The blended aggregate shall then
be tested according to LS-602.
.10 Table 6 of OPSS.PROV 1002 is deleted in its entirety and replaced with the
following:
TABLE 6
Physical Property Requirements for Coarse Aggregate(s)
Siliceous Aggregates
Note 4
Related to LS-412
Notes:
1. LS-412, LS-618, LS-620, ASTM C666, LS-635, LS-615 and Sulphur
Content shall apply to each individual coarse aggregate component in
the mix. The remaining tests shown in this table shall be carried out
either on samples taken from a stockpile of the blended coarse
aggregate intended to be used in the mix or from samples taken from
stockpiles of each individual coarse aggregate component and later
combined in the laboratory to the proportions provided with Form A,
prior to testing. All sampling and blending shall be as specified in the
Aggregate Processing, Handling, and Stockpiling subsection.
2. If the fraction of any coarse aggregate component, passing the 4.75
mm sieve represents more than 10% of the grading of that aggregate,
by mass, then that fraction of the individual coarse aggregate
component shall also meet the fine aggregate requirements given in
Table 3.
3. When a concrete surface including pavements, base, full depth repair,
and partial depth repair and exposed bridge decks are subject to
vehicular traffic, the physical requirements for “Pavement” shown in this
table shall apply to the aggregates used in the mix.
4. LS-412 shall be conducted as specified in the Scaling Resistance
clause. LS-412 will be waived if the aggregate is from the same
bench/formation in a quarry which is listed on the current Ontario
Ministry of Transportation Structural Concrete Aggregate Sources List
or the Concrete Aggregate Sources List for Concrete Base/Pavement
Coarse Aggregates, if, at the discretion of the Owner, the aggregate
under consideration is still representative of the aggregate that the
Owner originally approved.
5. The requirement for this test shall be waived provided that the
Contractor has submitted a written request that the coarse aggregate
meet the alternative requirements for LS-606, magnesium sulphate
soundness, as specified in the Alternative to LS-614 clause.
6. The need to demonstrate compliance with this requirement shall be
waived by the Engineer if the aggregate component is from a source on
the current Ontario Ministry of Transportation Structural Concrete
Aggregate Sources List or the Concrete Aggregate Sources List for
Concrete Base/Pavement Coarse Aggregates.
7. If the aggregate is produced from quarried sandstone, siltstone, granite
or gneiss, the expansion shall be less than 0.080% after 14 days. If an
CN – DESIGN & CONCRETE WORK SECTION 03312
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 14 OF 23
MI. 36.79 TO 41.00 HALTON SUB
aggregate is produced from quarried Gull River, Bobcaygeon, Verulam,
Lindsay Formations, or their stratigraphic equivalents, the expansion
shall be less than 0.100% after 14 days.
8. The test shall be conducted as specified in the D-Line Cracking clause.
The testing shall be waived if the aggregate is from the same
bench/formation in a quarry which is listed on the current Ontario
Ministry of Transportation Structural Concrete Aggregate Sources List
or the Concrete Aggregate Sources List for Concrete Base/Pavement
Coarse Aggregates, if, at the discretion of the Owner, the aggregate
under consideration is still representative of the aggregate that the
Owner originally approved.
9. This requirement only applies to aggregates produced from quarried
Gull River, Bobcaygeon Formations, and their stratigraphic equivalents.
.2 Quality assurance for approach slab seat bearings and ballast wall bearings shall be
in accordance with OPSS.PROV 904.
.3 Quality assurance for abrasive blast cleaning of concrete surfaces and reinforcing
steel shall be in accordance with OPSS.PROV 929.
1.5 SUBMITTALS
.2 Structural Concrete
.1 Approach slab seat elastomer and ballast wall elastomer submissions shall
be according to OPSS.PROV 904.
.4 EVA Foam
CN – DESIGN & CONCRETE WORK SECTION 03312
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 15 OF 23
MI. 36.79 TO 41.00 HALTON SUB
.1 A minimum of seven days prior to installation, a product data sheet for the
EVA foam to be used in the work shall be submitted to the Engineer. The
data sheet shall clearly identify that the supplied EVA foam meets the
requirements of this specification.
PART 2 - PRODUCTS
2.1 DESIGN
.2 Structural Concrete
2.2 MATERIALS
.2 Structural Concrete
.4 EVA Foam
.1 Structural Concrete
CN – DESIGN & CONCRETE WORK SECTION 03312
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 19 OF 23
MI. 36.79 TO 41.00 HALTON SUB
.1 Equipment for production and delivery of structural concrete shall be in
accordance with OPSS.PROV 1350.
2.4 PRODUCTION
.1 Structural Concrete
PART 3 - EXECUTION
.1 Structural Concrete
3.2 CONSTRUCTION
.2 Structural Concrete
.1 Structural Concrete
.1 No deductions from the volume of concrete shall be made for any of the
following:
.1 Drainage openings, load reducing devices, embedded timbers, and
utility and prestressing steel ducts, each of which has a cross-
sectional area of less than 0.1 m2.
.2 Timber, steel, concrete, or concrete filled tubular piles.
.3 Steel reinforcement, miscellaneous hardware, and structural steel.
CN – DESIGN & CONCRETE WORK SECTION 03312
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 23 OF 23
MI. 36.79 TO 41.00 HALTON SUB
.2 Measurement of concrete shall be by volume in cubic meters.
.1 Payment for formwork and falsework shall be included in the work in which
they are used.
.2 Where formwork is required for the work under a concrete tender item, it shall
be deemed for progress payment purposes that the formwork, together with
its supporting falsework, when installed, constitutes 35% of the work to be
carried out under the tender item.
.3 Partial payment for construction of the formwork and falsework shall be made
on a prorated basis.
.2 Structural Concrete
.1 Payment at the Contract price for the concrete tender items shall be full
compensation for all labour, equipment and materials to do the work.
.3 Payment for approach slab seat bearings and ballast wall bearings, EVA foam, and
abrasive blast cleaning of concrete surfaces and reinforcing steel shall be included in
the work in which they are used.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
.1 Conform with the National Building Code of Canada 2010 and any applicable
acts of any authority having jurisdiction and the following:
.2 Where there are differences between the specifications and drawings and the
codes, standards or acts, the most stringent shall govern
.2 The Engineer may also carry out independent Quality Assurance tests as per
Section 01620 – Quality Control and Assurance of these Specifications.
1.5 SUBMITTALS
.2 Submit mix design to Engineer for approval two weeks prior to commencing
work. Mix design shall show details of cementitious materials, compressive and
flexural strengths for the proposed mix and required density after placement, all
with certification by a registered Professional Engineer.
.3 Each shop drawing shall bear the stamp of qualified professional engineer
registered or licensed in the Province of Ontario.
CN – DESIGN & WET CAST CONCRETE PAVEMENT SECTION 03320
CONSTRUCTION MILTON LOGISTIC HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 5
MI. 36.79 TO 41.00 HALTON SUB
.1 All concrete covered in this section of the specification at 28 days shall have a
minimum compressive strength of:
.1 35 MPa
1.7 SAMPLING
.2 A minimum of one full concrete test will be executed for each day of placing
concrete pavement. Sufficient concrete samples will be taken to carry out 7, 14 &
28 days concrete compressive tests. Refer to Section 01620 Quality Control and
Assurance.
1.8 TESTING
.2 Copy of detailed mix designs, sieve analysis and specific gravity of aggregates,
and alkali content of cement with report from Testing Agency, shall be submitted
to the Engineer for their review a minimum of 3 weeks prior to intended use. The
design mixes should indicate all proportions and constituents of the design mix.
.3 Tests for determining alkali content shall be carried out in accordance with ASTM
Standard C114-83A paragraph 17.1 Standard Method of Chemical Analysis of
Hydraulic Cement.
.4 The portland cement shall be tested for alkali aggregate reactivity utilizing the
mortar bar accelerated expansion tests (CSA A23.2-25A) and concrete prism
expansion tests (CSA A23.2-14A). Results of the accelerated mortar bar tests
are subject to acceptance of CN prior to the use of these materials on any
project.
.5 Historical concrete prism expansion tests using the same concrete mix and
aggregate source as proposed for use on specific projects are also subject to
acceptance. The accelerated mortar bar test takes 14 days. The prism expansion
test normally requires readings to be taken over a one year period.
PART 2 - PRODUCTS
2.1 MATERIALS
2.2 JOINTS
.1 Provide expansion joints between new concrete pavement and existing / new
structural elements.
PART 3 - EXECUTION
.2 Before depositing any concrete all debris shall be removed from the space to be
occupied by the concrete. Mortar splashed upon the reinforcement, and surfaces
of forms shall be removed. Reinforcement shall be checked for position and
fastening and approval of the Engineer obtained. Water shall be removed from
the space to be occupied by the concrete before concrete is deposited, unless
otherwise directed by the Engineer.
.3 Any flow of water into an excavation shall be diverted through proper side drains
to a sump, or be removed by other approved methods which will avoid washing
the freshly deposited concrete. If directed by the Engineer, water ventipipes and
drains shall be filled after the concrete has thoroughly hardened by grouting or
otherwise.
.4 All concrete shall be properly vibrated. The vibrators must not be used for shifting
masses of wet concrete, but for compaction only.
3.3 CURING
.1 All concrete shall be thoroughly "cured" to the entire satisfaction of the Engineer
and as described in C.S.A. Standard A23.1.
CN – DESIGN & WET CAST CONCRETE PAVEMENT SECTION 03320
CONSTRUCTION MILTON LOGISTIC HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 5
MI. 36.79 TO 41.00 HALTON SUB
3.4 PROTECTION
.1 Place and maintain suitable barriers to protect finished concrete from equipment,
vehicles or pedestrian traffic.
4.1 MEASUREMENT
4.2 PAYMENT
.1 The Unit Prices submitted in the Form of Tender shall include all labour,
materials and equipment required to supply and place the concrete, including
concrete accessories and joints, where shown on the drawings and as called for
in this specification.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of this
Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 Manual for Railway Engineering, Volume 2, Chapter 8, Part 28, Article 28.5.4
(2020), including all applicable references specified therein.
.1 Structural Steel
.1 Quality assurance for coating structural steel and railing systems shall be in
accordance with OPSS.PROV 911.
1.5 SUBMITTALS
.1 Structural Steel
PART 2 - PRODUCTS
2.1 DESIGN
.1 Structural Steel
.1 Structural Steel
2.4 PRODUCTION
.1 Structural Steel
.1 General
.1 The extent of work, cleaning requirements, surface preparation,
environmental protection requirements, and type of coating system
shall be as specified in the Contract Documents.
.2 Where there is a conflict between the manufacturer’s
recommendations and the Contract Documents, the more stringent
requirements shall apply as determined by the Engineer.
CN – DESIGN & STRUCTURAL STEEL SECTION 05120
CONSTRUCTION MILTON LOGISTICS HUB - PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 6 OF 8
MI. 36.79 TO 41.00 HALTON SUB
.3 All components coated off-site shall be protected from handling or
shipping damage by using padded slings, separators, and tie downs
or other similar devices. Loading procedures shall be designed to
protect coated surfaces from any possible damage to the coating.
.4 The Engineer shall be granted access to the galvanizing and painting
shops where components are being cleaned and coated, during all
hours of work.
.5 Galvanized steel components, when stored, shall be stored in a
manner to avoid wet storage stain. Components shall be stored above
ground on skids or other supports. Careful consideration shall be
given to how galvanized steel components are stacked and bundled
to ensure adequate air flow.
PART 3 - EXECUTION
3.1 CONSTRUCTION
.1 Structural Steel
.1 Structural Steel
.1 Structural Steel
.4 Bearings
.1 Payment for the supply and installation of bearings shall be according
to Section 07109 Bearings.
.1 Payment at the Contract price for the coating new structural steel tender
items shall be full compensation for all labour, equipment and materials to do
the work.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of this
Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section 05121 specifies the requirements for metal railings for structures
including posts and anchorage assembly.
1.5 SUBMITTALS
PART 2 - PRODUCTS
2.1 MATERIALS
2.2 PRODUCTION
3.1 CONSTRUCTION
.1 Measurement of metal railings for structures shall be by length in meters from end to
end of railing.
.1 Payment at the Contract price for the parapet wall railing tender items shall be full
compensation for all labour, equipment and materials to do the work.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of this
Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section 07100 specifies the requirements for waterproofing of concrete bridge
decks with hot applied asphalt membrane.
.2 For Lower Baseline Road bridge, this Section 07100 specifies the requirements for
waterproofing of the abutment walls and wingwalls.
.3 ASTM D5329-20, Standard Test Methods for Sealants and Fillers, Hot-
Applied, for Joints and Cracks in Asphalt Pavements and Portland Cement
Concrete Pavements.
.1 Quality assurance shall be in accordance with OPSS.PROV 914 with the following
additions and amendments:
Testing Requirements
Procedures Procedures
Test Required for Hot- Required for Hot-
Poured Rubberized Poured Rubberized
Joint/Crack Sealing Joint/Crack Sealing
Compounds Used Compounds Used
in Hot Mix Asphalt in Portland Cement
Pavements Concrete
Pavements
Notes:
1. For each batch of sealant compound used in hot mix asphalt
pavements, the Contractor shall provide results for all of these
tests. However, for re-heated sealant compounds that are
sampled during construction, these tests will be completed at
the discretion of the Owner.
2. For each batch of “All Districts” products used as joint/crack
sealant compound in hot mix asphalt pavements, the Contractor
shall provide test results based on bond testing that is
conducted in three cycles at -29 °C with both 50% and 200%
extension. For each batch of “Southern Ontario Only” sealant
used as joint/crack sealant compound in hot mix asphalt
pavement, the Contractor shall provide test results based on
bond testing that is conducted in five cycles at -18 °C with 50%
extension. All re-heated sealant compounds sampled during
construction will be tested in five cycles at -18 °C with 50%
extension, or when used as joint/crack sealant compound in hot
mix asphalt pavements, the samples will be tested, as specified
by the Owner.
PART 2 - PRODUCTS
2.1 MATERIALS
.1 Materials shall be in accordance with OPSS.PROV 914 with the following additions
and amendments:
Testing Requirements
Sealant Designation
CN – DESIGN & WATERPROOFING BRIDGE DECKS SECTION 07100
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 6
MI. 36.79 TO 41.00 HALTON SUB
Flow (mm) 5 3
Notes:
1. A successful field trial is required before a product is accepted
for placement on the MTO’s DSM.
2.2 PRODUCTION
PART 3 - EXECUTION
3.2 CONSTRUCTION
.1 Payment at the Contract price for the waterproofing system and membrane
reinforcement tender items shall be full compensation for all labour, equipment and
materials to do the work.
.2 When the Contract does not contain separate tender items for the work required by
this Section 07100, payment at the Contract price for the bridge deck waterproofing
CN – DESIGN & WATERPROOFING BRIDGE DECKS SECTION 07100
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 6 OF 6
MI. 36.79 TO 41.00 HALTON SUB
tender item shall be full compensation for all labour, equipment and materials to do
the work.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of this
Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section 07109 specifies the construction requirements for the installation of
bearings.
PART 2 - PRODUCTS
2.1 DESIGN
.1 The bearings, including any fasteners or dowels, shall be designed according to CSA
S6 and the MTO Structural Manual, Division 1.
.2 The effective elastomer thickness for plain bearings shall be greater than or equal to
15 mm and less than or equal to 25 mm.
.3 All internal layers of elastomer in a laminated elastomeric bearing shall have the
same thickness.
2.2 MATERIALS
.1 Materials shall be in accordance with OPSS.PROV 922 with the following additions
and amendments:
2.3 PRODUCTION
.1 Production of steel-laminated elastomeric bearings for bridges and for approach slab
bearings and ballast wall bearings shall be in accordance with OPSS.PROV 1202.
PART 3 - EXECUTION
3.1 CONSTRUCTION
.1 For measurement purposes, a count shall be made of the number of the bearings
installed.
.1 Payment at the Contract price for the bearings – elastomeric, laminated tender items
shall be full compensation for all labour, equipment and materials to do the work.
.2 Payment at the Contract price shall include full compensation for any additional
bearings supplied for destructive testing.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of this
Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section 07112 specifies the requirements for waterproofing of concrete bridge
decks with high performance waterproofing system, including the following:
.1 Surface preparation;
.10 ASTM D4541-17, Standard Test Method for Pull-Off Strength of Coatings
Using Portable Adhesion Testers.
.1 Technical Reports:
.1 EOTA TR 003 (May 1999), Determination of the Watertightness;
.2 EOTA TR 004 (May 2004), Determination of the Resistance to
Delamination;
CN – DESIGN & HIGH PERFORMANCE WATERPROOFING SECTION 07112
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 9
MI. 36.79 TO 41.00 HALTON SUB
.3 EOTA TR 006 (May 1999), Determination of the Resistance to
Dynamic Indentation;
.4 EOTA TR 007 (May 2004), Determination of the Resistance to Static
Indentation;
.5 EOTA TR 008 (May 2004), Determination of the Resistance to
Fatigue Movement; and
.6 EOTA TR 013 (May 2004), Determination of Crack-Bridging
Capability.
1.5 SUBMITTALS
PART 2 - PRODUCTS
2.1 MATERIALS
.5 Sealer coat, applied to protect the exposed waterproofing membrane and low
modulus waterproofing membrane from UV damage, shall be one
component, solvent-free, 100% reactive, acrylic-based methyl methacrylate
(MMA) resin requiring only the addition of a catalyst; it shall be capable of full
CN – DESIGN & HIGH PERFORMANCE WATERPROOFING SECTION 07112
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 6 OF 9
MI. 36.79 TO 41.00 HALTON SUB
cure in less than one hour at 0°C (32°F); the sealer coat is MATACRYL STC
by RPM Belgium Vandex or Engineer approved equal/alternative.
.1 The Contractor shall ensure that all components of the high performance
waterproofing system are supplied to the job site in the manufacturer’s sealed and
labeled containers ready for use.
2.3 PRODUCTION
PART 3 - EXECUTION
3.2 CONSTRUCTION
.2 All components of the high performance waterproofing system shall be stored at the
job site in strict accordance with the manufacturer’s printed instructions and relevant
health and safety regulations; handling, mixing and addition of components is
performed in a safe manner in strict accordance with the manufacturer’s printed
instructions.
.3 Waterproofing operations shall be carried out only when the air temperature and
substrate temperature are between -15°C (5°F) and 35°C (95°F); waterproofing is
not carried out when wind, rain, snow or moisture from any source are capable of
contaminating surfaces.
.5 Prior to priming of the surface, the Manufacturer’s On-Site Representative and the
Engineer shall inspect the prepared substrate and identify any defects; waterproofing
CN – DESIGN & HIGH PERFORMANCE WATERPROOFING SECTION 07112
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 7 OF 9
MI. 36.79 TO 41.00 HALTON SUB
does not commence until all defects identified by this inspection are remedied to the
satisfaction of the Manufacturer’s On-Site Representative and the Engineer.
.2 Natural quartz aggregate is broadcast into wet primer at a rate of 0.30 kg/m²;
.5 Debonding material is placed below steel joint cover plate assemblies at deck
joints as shown in the Drawings; the steel joint cover plate assemblies are
fully centered onto the deck joints in concrete;
.6 Low modulus waterproofing membrane is hand packed into the gaps between
plates and adjacent to the plates of the steel joint cover plate assemblies, up
to the top of joint cover plate assemblies, to ensure total filling of the gaps;
immediately thereafter, a layer of low modulus waterproofing membrane
which will achieve a minimum dry layer thickness of 3mm (120 mils) is
applied over the steel joint cover plate assemblies, extending to the
waterproofing membranes on each side of the deck joints; the low modulus
CN – DESIGN & HIGH PERFORMANCE WATERPROOFING SECTION 07112
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 8 OF 9
MI. 36.79 TO 41.00 HALTON SUB
waterproofing membrane overlaps the waterproofing membrane by a
minimum of 150mm;
.8 Sealer coat is applied at a coverage rate of 0.80 to 1.00 kg/m²; the surface of
waterproofing membrane and low modulus waterproofing membrane is
flooded with sealer to achieve full coverage; immediately thereafter, sealer is
back rolled in order to remove excess sealer.
.10 The treatment of rejectable lots shall be in accordance with the manufacturer’s repair
proposal if deemed acceptable by the Engineer. If the repair proposal is deemed
unacceptable by the Engineer, the high performance waterproofing system shall be
rejected and replaced.
.11 Material Sampling and Acceptance Testing shall be in accordance with the following:
.2 B. The Applicator shall furnish a Daily Work Report detailing all recorded
temperatures, humidity levels, installation details & schedules etc.
.1 Payment at the Contract price for the high performance waterproofing system tender
items shall be full compensation for all labour, equipment and materials to do the
work.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of this
Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section 07113 specifies the requirements for ballast mat system for concrete
bridge decks with high performance waterproofing system, including the following:
.1 Prepare substrate;
.3 Bond the ballast mat protection layer using thermal fusion; and
.2 The Contractor shall be responsible for conducting its own quality assurance
program to ensure that the ballast mat system for the Works meets the requirements
of the Specifications.
1.5 SUBMITTALS
.1 The Contractor shall submit Manufacturer’s Product Data – Ballast Mats at least six
(6) weeks prior to installation indicating:
.5 Samples:
.1 300 mm x 300 mm samples of ballast mat.
PART 2 - PRODUCTS
2.1 MATERIALS
.2 Ballast mat shall be Under Ballast Mat Sylodyn DN 1019 by Getzner Werkstoffe
GmbH or Owner approved equal/alternative that is comprised of a 15 mm thick
closed cell foamed polyurethane resilient layer and a 3 mm thick protection layer of
geotextile bonded to the top of resilient layer for the purpose of resisting ballast
penetration and enabling thermal fusion bonded joints in ballast mat; ballast mat
CN – DESIGN & BALLAST MAT SYSTEM SECTION 07113
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 6
MI. 36.79 TO 41.00 HALTON SUB
shall meet or exceed the following properties within a 20% tolerance, unless
otherwise noted:
.3 The thermal fusion bonded protection layer joining strips over joints in ballast mat
shall be of the composition and geometry specified by the manufacturer of the ballast
mat system; ballast mat systems that do not feature thermal fusion bonded geotextile
joining strips commercially endorsed by the manufacturer of the ballast mat system
are not acceptable;
.1 All components of the ballast mat system shall be supplied to the job site in the
manufacturer’s sealed and labeled packaging ready for use.
PART 3 - EXECUTION
3.1 EQUIPMENT
.1 Equipment shall be approved by the manufacturers of ballast mat system and high
performance waterproofing system and shall be in strict accordance with the
manufacturers’ printed instructions regarding all aspects of the health and safety
requirements, environmental control and product installation procedures.
.2 Cutting of ballast mat shall be performed in a manner that prevents damage to the
high performance waterproofing system; cutting through the ballast mat placed on
top of the high performance waterproofing system with knives or similar tools
capable of damaging the high performance waterproofing system is strictly
prohibited.
3.2 CONSTRUCTION
.1 The Engineer shall be notified in writing prior to commencement of any ballast mat
system installation operations; installation of ballast mat system shall not commence
until permission is given by the Engineer.
.2 All components of the ballast mat system shall be stored at the job site in strict
accordance with the manufacturer’s printed instructions and relevant health and
CN – DESIGN & BALLAST MAT SYSTEM SECTION 07113
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 6
MI. 36.79 TO 41.00 HALTON SUB
safety regulations; handling, mixing and addition of components shall be performed
in a safe manner in strict accordance with the manufacturer’s printed instructions.
.3 The installation of the ballast mat system shall be carried out only when the air
temperature and substrate temperature are between 15°C (59°F) and 35°C (95°F),
providing the substrate is above the dew point; installation of ballast mat system is
not carried out when wind, rain, snow or moisture from any source are capable of
contaminating surfaces.
.5 Prior to applying the ballast mat adhesive, the Ballast Mat System Specialist
Subcontractor and the Engineer shall inspect the prepared substrate and identify any
defects; installation of ballast mat shall not commence until all defects identified by
this inspection are remedied to the satisfaction of the Ballast Mat System Specialist
Subcontractor and the Engineer.
.8 Application of ballast mat adhesive, installation of ballast mat and thermal fusion
bonding of ballast mat protection layer shall be in strict accordance with the
manufacturer’s printed instructions and the following:
.1 Sections of ballast mat are left to relax after they are unrolled for a minimum
of three hours, unless specified otherwise by the manufacturer; during this
time, ballast mat shall be protected from moisture contamination;
.2 Ballast mat adhesive shall not be applied on the areas that are specified in
the Drawings to remain unbonded; and
.3 The maximum gap at joints between ballast mat sections does not exceed 5
mm.
.9 The Contractor shall ensure that the treatment of rejectable lots is in accordance with
the manufacturer’s repair proposal if deemed acceptable by the Contract
Administrator. If the repair proposal is deemed unacceptable by the Contract
Administrator, the ballast mat system shall be rejected and replaced.
CN – DESIGN & BALLAST MAT SYSTEM SECTION 07113
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 6 OF 6
MI. 36.79 TO 41.00 HALTON SUB
PART 4 - MEASUREMENT AND PAYMENT
.1 Payment at the Contract price for the high performance waterproofing system tender
items shall be full compensation for all labour, equipment and materials to do the
work.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 GENERAL
.1 Prior to tendering, the Contractor and all subcontractors and suppliers shall read
and be governed by all Parts, Specifications, Drawings and Addenda of the
Tender and Contract Documents which affect the respective work of each.
.2 The complete work under this Contract shall be governed by the dictates of good
practice and shall be complete in all details of materials and methods even if not
minutely specified. The Work shall be properly coordinated with the requirements
of all work specified in other sections. The work includes testing as specified,
start up and placing of the work into operation (commissioning), ready for use by
the Owner.
1.2 INTENT
.1 The Contractor shall furnish all labour, materials and necessary equipment to
provide complete and operating electrical systems as set forth on the plans and
in these Specifications, and as called for elsewhere in the Contract documents.
Any work, even if not shown or specified, which is obviously necessary or
reasonably implied to complete the work, shall be carried out as if it was both
shown and specified.
.2 The electrical installation shall comply with the latest edition of the Ontario
Electrical Safety Code, and all applicable municipal and local codes and the
regulations of local inspection authorities.
CN - DESIGN & COMMON WORK RESULTS SECTION 16010
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 6
MI. 36.79 TO 41.00 HALTON SUB
.2 For work involving specialties such as instrumentation, etc., the Contractor shall
employ only tradesmen or Subcontractors fully qualified and experienced in such
work.
.3 All materials to be new, meeting the quality specified and conform to the
standards of the Underwriter Laboratory Canada. Where equipment or materials
are specified by technical description only, they are to be of the best commercial
quality obtainable for the purpose.
.4 Electrical equipment that is shown on the plans or called for in the specifications
that is not ULC approved to be treated in one of the following ways:
.1 Make known to the Engineer in writing not less than ten (10) days prior to
closing date of tender, or
.5 Uniformity Of Equipment:
.2 Follow civil, structural, and mechanical Drawings for details of this work and
install electrical conduits, boxes and fittings to coordinate with civil, structural and
mechanical work and details.
.1 The Contractor shall examine carefully the civil, structural, and mechanical
Drawings and work of other trades, to satisfy themself that the work under this
Contract can be satisfactorily carried out without changes to the buildings and
layouts as shown on the plans.
CN - DESIGN & COMMON WORK RESULTS SECTION 16010
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 3 OF 6
MI. 36.79 TO 41.00 HALTON SUB
.2 Should any item arise indicating conflict with equipment of other trades or
requiring additional work beyond the intent as described in the Specifications and
shown on the Drawings, the Contractor shall immediately bring the matter to the
attention of the Engineer before submitting their Tender. Failure to do so
constitutes acceptance of responsibility for any necessary work.
.1 The Contractor shall obtain all permits required, (paying all fees levied) and after
completion of the work, shall furnish to the Engineer a Certificate of Final
Inspection and Approval from the Electrical Inspection Authorities. Permits shall
be taken out at the beginning of the work.
.1 The Contractor shall thoroughly examine the Drawings and Specifications and
especially figured dimensions immediately after the Contract is awarded and
report any discrepancy, error, or omission to the Engineer. The Contractor shall
give the work their personal supervision, lay out their own work, do all necessary
leveling and measuring or employ a competent engineer to do so. Figures, full
size and dimensioned Drawings shall take precedence over scale measurements
of Drawings. No plea as to the actions and directions of other than the Engineer
will be admitted as justification for any departure made from the Drawings,
Specifications, or Contract. It shall remain the duty of the Contractor to take their
own measurements of the work.
.2 The Contractor shall be responsible for correcting all work completed contrary to
the intent of the Drawings and Specifications and shall bear all costs for same.
Where the intent of the Drawings and Specifications is not clear, he should obtain
a clarification from the Engineer before proceeding with the work, otherwise no
compensation will be forthcoming for any necessary adjustments.
.4 Where any equipment supplied by this Contractor must be built in with the work
of other Contractors, this Contractor shall be responsible for the supply of the
equipment to be built in or measurements to allow necessary openings to be left
so as not to delay the work.
.5 The Contractor shall protect all work executed both from the elements and the
progress of construction and shall make good any work supplied that has been
damaged from any cause whatsoever.
.6 The Contractor, in setting out of their work, shall make reference to architectural,
civil, structural and mechanical Drawings. He shall consult with the respective
trades in setting out locations for conduit runs, luminaires, panel assemblies, etc.,
CN - DESIGN & COMMON WORK RESULTS SECTION 16010
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 6
MI. 36.79 TO 41.00 HALTON SUB
.1 The Contractor to be responsible for all cutting required for electrical installation.
Structural members not to be cut without the written consent of the Engineer.
.3 Where work damages work of other trades, repair and make good such damage
to the satisfaction of the trade concerned and the Engineer.
.4 Locate and provide holes and sleeves required for electrical work. Relocate
improperly located holes and sleeves at no cost.
1.10 ALTERATIONS
.1 Alterations entailing additional work or deletions shall be carried out only upon
written request by the Engineer.
.1 Submit Shop Drawings, product data and samples for all electrical components
as indicated in the respective sections of these Specifications and as required by
the Engineer.
.3 Submit design drawings showing the location of all existing and new handwells
and duct banks.
.5 Submit specifications for all new handwells (handholes, manholes and pull
boxes).
.7 Submit the method of proving continuity of all conduits installed to the consultant
for approval.
.8 Submit to the Engineer, in writing for approval, the proposal method of proofing
the conduits.
CN - DESIGN & COMMON WORK RESULTS SECTION 16010
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 5 OF 6
MI. 36.79 TO 41.00 HALTON SUB
.9 Provide testing result to support proof that conduits are clear, properly connected
one piece to the next and waterproof and capable of being filled with wires s
required.
.10 Submit to the Engineer, in writing for approval, the proposed method of proofing
the ducts are free of water, debris, breakage or distortion.
1.12 PROTECTION
.1 Protect the work of others from damage resulting from the work of this Division.
.2 Protect the work of this Division from that of others, make good any damage,
remove all debris and rubbish and leave the project site in a clean and tidy
condition to the approval of the Engineer.
.3 Guard exposed live electrical equipment during construction for personnel safety
and provide applicable warning signs.
.2 All conduit runs must be shown on the Record Drawings complete with size,
routing, wire count and wire termination numbers.
1.14 FINISHES
.1 Shop finish metal enclosure surfaces by removal of rust and scale, cleaning,
application of rust resistant primer inside and outside and at least two (2) coats of
finish enamel.
.1 The contractor shall be responsible for coordinating the incoming service power
connections with the Owner.
.2 All lamps used for a period longer than three (3) months shall be replaced prior to
final acceptance.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 REFERENCES
.1 CAN/CSA C22.2 No. 18, Outlet Boxes, Conduit Boxes, Fittings and
Associated Hardware, A National Standard of Canada;
.3 CSA C22.2 No. 56, Flexible Metal Conduit and Liquid-Tight Flexible Metal
Conduit;
.1 The Drawings do not show all conduits. Those shown are in diagrammatic form
only. Conduits are to be provided to create complete raceway systems.
2.1 CONDUITS
.1 Rigid metal conduit: to CSA C22.2 No. 45, hot dipped galvanized steel threaded.
.2 Epoxy coated conduit: to CSA C22.2 No. 45, with zinc coating and corrosion
resistant epoxy finish inside and outside.
.3 Electrical metallic tubing (EMT): to CSA C22.2 No. 83, with couplings.
.5 Flexible metal conduit: to CSA C22.2 No. 56, aluminum liquid-tight flexible metal.
.1 Provide all pull boxes, junction boxes, terminal boxes, fittings, seals, plugs, cover
plates, bushing, clips, rods and accessories as required and as applicable:
.1 Fittings: to CAN/CSA C22.2 No. 18, manufactured for use with conduit specified.
Coating: same as conduit.
.2 Ensure factory "ells" where 90 degrees bends for 27 mm and larger conduits.
.1 Weatherproof expansion fittings with internal bonding assembly suitable for 103
mm linear expansion.
.2 Watertight expansion fittings with integral bonding jumper suitable for linear
expansion and 21 mm deflection in all directions.
.4 Opening through fire rated walls shall be sealed with ULC listed fire proofing
assembly
CN – DESIGN & CONDUITS, CONDUIT FASTENINGS SECTION 16034
CONSTRUCTION AND CONDUIT FITTINGS SEPTEMBER 2023
MILTON LOGISTICS HUB – PHASE 2A PAGE 3 OF 5
GRADING & DRAINAGE
MI. 36.79 TO 41.00 HALTON SUB
2.5 FISH CORD
.1 Verify all wall, partition, and door locations, coordinate with other disciplines and
then mark the conduit/device layouts prior to start of work.
PART 3 - EXECUTION
3.2 INSTALLATION
.2 Use rigid PVC conduit underground and buried in or under concrete slab on
grade and in corrosive areas.
.8 Install all conduit, conduit fittings and accessories in accordance with the latest
edition of the Ontario Electrical Safety Code in a manner that does not alter,
change or violate any part of the installed system components or the CSA/UL
certification of these components.
CN – DESIGN & CONDUITS, CONDUIT FASTENINGS SECTION 16034
CONSTRUCTION AND CONDUIT FITTINGS SEPTEMBER 2023
MILTON LOGISTICS HUB – PHASE 2A PAGE 4 OF 5
GRADING & DRAINAGE
MI. 36.79 TO 41.00 HALTON SUB
.9 Use epoxy coated conduit underground in corrosive areas and where exposed to
exterior elements. (ie: pole mounted service entrance conduits)
.10 Use rigid galvanized conduit except above 2.4 m not subject to mechanical
injury, as well as concealed work in masonry or poured concrete construction.
.11 Cap all conduits at both ends with waterproof ends immediately after the proofing
process. Contractor shall ensure that the conduits are ready for future use.
.5 Conduits in slabs: minimum slab thickness four (4) times conduit diameter.
.1 No Measurement or separate Payment will be made for this work. All work under
this section will be paid under the Lump Sum Prices listed in the Schedule of
Prices.
END OF SECTION
CN – DESIGN & INSTALLATION OF CONDUITS IN TRENCHES SECTION 16043
CONSTRUCTION AND IN DUCTS SEPTEMBER 2023
MILTON LOGISTICS HUB – PHASE 2A PAGE 1 OF 4
GRADING & DRAINAGE
MI. 36.79 TO 41.00 HALTON SUB
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 REFERENCES
.2 Product Data:
.2 Store and protect cables from nicks, scratches, and blemishes; and
PART 2 - PRODUCTS
.1 PVC tubing shall be schedule-40. Sunlight resistance, FT-4 rating, fire resistant,
impact and chemical resistant, non-corrosive and non-magnetic.
PART 3 - EXECUTION
.3 Install fish wire in empty conduits/ducts to facilitate wire and cable pulling.
CN – DESIGN & INSTALLATION OF CONDUITS IN TRENCHES SECTION 16043
CONSTRUCTION AND IN DUCTS SEPTEMBER 2023
MILTON LOGISTICS HUB – PHASE 2A PAGE 3 OF 4
GRADING & DRAINAGE
MI. 36.79 TO 41.00 HALTON SUB
.5 Cap all conduits at both ends with waterproof ends immediately after the proofing
process in the handholes or manholes. The Contractor shall ensure that the
conduits are ready for future use.
.6 Place red plastic warning tape above centreline of each conduit/duct, 300 mm
below grade, through entire length of run unless indicated otherwise.
.7 Close both ends of spare ducts and future ducts with bell end plug of same
material duct, inserted into a coupling to form a watertight seal.
.3 Arrange conduits in duct bank and secure in place with plastic or concrete
separators, installed at 1500 mm intervals. Joints shall be staggered at 150 mm
in adjacent layers.
.4 Provide fish wires in empty ducts and secure wire at both ends.
.5 Close both ends of spare ducts and incomplete runs with bell and plugs of same
material as conduits/ducts. Ends shall have watertight seals.
.6 Cap all conduits at both ends with waterproof ends immediately after the proofing
process in the handholes or manholes. The Contractor shall ensure that the
conduits are ready for future use.
.7 Lay red plastic warning tape above centreline of each duct bank, 300 mm below
grade, throughout entire length of run. Duct bank over 500 mm wide, use two (2)
tapes, laid 100 mm from duct bank edge.
3.3 PROTECTION
.1 No Measurement or separate Payment will be made for this work. All work under
this section will be paid under the Lump Sum Prices listed in the Schedule of
Prices.
END OF SECTION
CN – DESIGN & BASIC ELECTRICAL SECTION 16050
CONSTRUCTION MATERIALS AND METHODS SEPTEMBER 2023
MILTON LOGISTICS HUB – PHASE 2A PAGE 1 OF 6
GRADING & DRAINAGE
MI. 36.79 TO 41.00 HALTON SUB
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.2 REFERENCES
.2 Shop Drawings:
.1 Material Delivery Schedule: provide Engineer of Record with schedule within two
(2) weeks after award of Contract.
.1 Provide for each system and principal item of equipment as specified in technical
sections for use by operation and maintenance personnel.
.5 Ensure operating instructions will not fade when exposed to sunlight and are
secured to prevent easy removal or peeling.
.3 Names and addresses of local suppliers for items must be included in the
Maintenance Manuals; and
PART 2 - PRODUCTS
.1 Colour code conduits, boxes and metallic sheathed cables. Provide engraved
nameplate, size 2.
2.4 FINISHES
.1 Shop finish metal enclosure surfaces by application of rust resistant primer inside
and outside, and at least two coats of finish enamel;
PART 3 - EXECUTION
3.1 INSTALLATION
.1 Sleeves through concrete: schedule 40 steel pipe, sized for free passage
of conduit, and protruding 50 mm.
3.4 CLEANING
4.1 GENERAL
.3 When multiple conduits are installed in a single ductbank, the measurement will
be the linear length of the center conduit only. Payment will not be made for each
individual conduit.
CN – DESIGN & BASIC ELECTRICAL SECTION 16050
CONSTRUCTION MATERIALS AND METHODS SEPTEMBER 2023
MILTON LOGISTICS HUB – PHASE 2A PAGE 6 OF 6
GRADING & DRAINAGE
MI. 36.79 TO 41.00 HALTON SUB
.4 Payment at the Contract price shall include all labour, equipment and material to
perform the work specified herein including but not be limited to all excavation
regardless of the depth, bedding, conduits, fittings, connections, concrete
encasement and granular backfill all to the satisfaction of the Engineer.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.2 REFERENCES
.1 Drawings do not indicate all conduit runs. Those indicated are in diagrammatic
form only. It is intended to have two parallel conduit systems, one for power
distribution and one for communication cable.
PART 2 - PRODUCTS
2.1 CONDUITS
.1 All conduits to be Rigid PVC (CSA Std. C22.2 No. 211.2) unless otherwise
stated.
.1 One-hole steel straps to secure surface conduits 2” and smaller. Two-hole steel
straps for conduits larger than 2”.
.1 Fittings: manufactured for use with conduit specified. Coating: same as conduit.
.2 Factory "ells" where 90° bends are required for 1” and larger conduits.
.2 Watertight expansion fittings with integral bonding jumper suitable for linear
expansion and 20mm deflection in all directions.
PART 3 - EXECUTION
3.1 INSTALLATION
.3 Use rigid PVC conduit for surface mounting and for underground installation.
.4 Install fish cord in empty conduits. Provide identification tag for each conduit in a
junction box that identifies its destination point.
.5 Cap all conduits at both ends with waterproof ends immediately after the proofing
process. Contractor shall ensure that the conduits are ready for future use.
.6 Where conduits become blocked, remove, and replace blocked section. Do not
use liquids to clean out conduits.
.8 Provide a proof the installed conduits are free of water, derbis, breakage or
distortion. Submit to the consultant, in writing for approval, the proposed method
of proofing the ducts.
.9 Have site inspected by Owner’s Representative after laying conduits but before
backfilling or concrete pouring.
.5 Install conduits prior to installation of concrete slab and provide all elbows to
terminate the conduit above ground and in a junction box.
4.1 GENERAL
.3 When multiple conduits are installed in a single duct bank, the measurement will
be the linear length of the center conduit only. Payment will not be made for
each individual conduit.
.4 Payment at the Contract price shall include all labour, equipment and material to
perform the work specified herein including but not be limited to all excavation
regardless of the depth, bedding, conduits, fittings, connections, concrete
encasement and granular backfill all to the satisfaction of the Engineer.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
.1 This Section covers general requirements for supply, installation, and testing of
mechanical systems and equipment as indicated in the Contract Documents.
1.4 SUBMITTALS
.1 The Contractor shall submit the following all submittals for review in accordance
with the requirements of this Section and Section 01340 Submittals at least four
weeks prior to commencing use:
.1 Product data;
.2 Shop Drawings;
.3 Test reports.
CN – DESIGN & MECHANICAL GENERAL REQUIREMENTS SECTION 20 05 00
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 2 OF 7
MI. 36.79 TO 41.00 HALTON SUB
.4 Test certificates and in accordance with authorities having jurisdiction;
.5 Commissioning package;
.2 Whether located on site or not, protect all equipment from dust, dirt and the
elements.
1.7 TRAINING
1.8 DIMENSIONS
.1 Verify dimensions by reference to Product data sheets, Shop Drawings and field
measurement where applicable.
1.9 COORDINATION
.7 Where conflicts or Site conditions require appreciable deviation from the Work as
specified or indicated, notify the Engineer before proceeding.
.1 Provide spare part list including component parts availability, names and
addresses of spare part suppliers, and list of specialized tools necessary for
maintenance.
PART 2 - PRODUCTS
.1 Provide new materials and new Products only. Equipment to bear approval
stamp of CSA, or approval label of other authority having jurisdiction for particular
application and location used.
.2 Provide units of same manufacture where two (2) or more units of same class or
type of equipment required.
2.2 SLEEVES
.2 Clean, prime and paint exposed hangers, racks, and fasteners to prevent rust.
PART 3 - EXECUTION
3.1 WELDING
3.2 FASTENINGS
.1 Provide anchor bolts, sleeves and fasteners of same finish as adjacent materials,
unless stainless steel or other material specified.
.2 Space anchors within their load limit or shear capacity and ensure they provide
positive permanent anchorage. Organic material plugs unacceptable.
3.4 CONSUMABLES
.1 Test equipment and systems provided under this Division for electrical and
mechanical defects in accordance with Standards and recommendations of
manufacturers, and corrections and adjustments made prior to requesting
inspection by the Engineer.
3.7 COMMISSIONING
.2 General:
3.8 CLEANING
.2 Review drawings and submittals as they become available and identify potential
interference problems to the Engineer before construction of same commences.
.3 Adjust equipment location where required to allow clearances and access for
routine maintenance.
.1 Prepare and submit interference Drawings on hard copy and on disk in format
suitable to the Engineer
.2 Provide plan and section Drawings at the appropriate locations and scales, with
sufficient detail and dimensions to clearly indicate coordination described below.
.6 Installation shall not commence until final interference drawings have been
submitted and review comments have been incorporated to satisfaction of The
Engineer.
CN – DESIGN & MECHANICAL GENERAL REQUIREMENTS SECTION 20 05 00
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 7 OF 7
MI. 36.79 TO 41.00 HALTON SUB
3.11 MAINTENANCE
.1 No Measurement or separate Payment will be made for this work. All work under
this section will be paid under the Lump Sum Prices listed in the Schedule of
Prices.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the Labour, Products, equipment and services necessary
for pipe welding for the Work.
1.3 REFERENCES
.4 CSA W48, Filler Metals and Allied Materials for Metal Arc Welding;
.4 Welding Procedures:
.5 Regulatory requirements:
.6 Mock-up:
.1 The Contractor shall submit the following all submittals for review in accordance
with the requirements of this Section and Section 01340 Submittals at least four
weeks prior to commencing use:
.1 Documentation Package:
.2 Closeout Submittals:
PART 2 - PRODUCTS
2.1 MATERIALS
2.2 ELECTRODES
.2 Verification of Performance.
CN – DESIGN & PIPE WELDING SECTION 20 05 17
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 6
MI. 36.79 TO 41.00 HALTON SUB
PART 3 - EXECUTION
3.1 EXAMINATION
3.2 WORKMANSHIP
.1 Do not proceed with any work before obtaining welding/cutting permit from Fire
Prevention Section of the Engineer Safety Department.
.1 Review all weld quality requirements and defect limits of applicable codes and
standards with The Engineer before any work is started.
.2 Prepare and submit "Inspection and Test Plan" to the Engineer prior to starting.
Submit final "Inspection and Test Plan Report".
.3 Do not conceal welds and pipe markings until inspected, tested and approved by
inspector.
.4 Provide for inspector to visually inspect all welds during early stages of welding
procedures to AWS W1. Repair or replace all defects as required by codes and
as specified herein.
.1 General:
.4 Failure of radiographic tests: If any weld fails tests, tests will be extended
to all welds made by welder responsible.
.2 In addition, to above:
.1 Claims for delays in completion of Contract not entertained for reasons of failures
of welds to pass examinations.
3.9 CLEANING
.1 Upon completion of a weld, hammer to loosen slag and weld spatter. Wire brush
internal pipe at weld and blow debris out of pipe.
3.10 PROTECTION
.1 No Measurement or separate Payment will be made for this Work. All work under
this section will be paid under the Lump Sum Prices listed in the Schedule of
Prices.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
.1 The Contractor is responsible for conducting its own quality assurance program
to ensure that the work for pressure gauges meet the requirements of this
Section and Section 01620 Quality Control and Assurance.
1.5 SUBMITTALS
.1 The Contractor shall submit the following submittals for review in accordance
with the requirements of this Section and Section 01340 Submittals:
.1 Product Data:
PART 2 - PRODUCTS
2.1 GENERAL
.3 Type 304 stainless steel case with relief valve and polished stainless steel
bayonet.
.4 Stainless steel rotary movement with stainless steel bushings and socket.
.1 Manufacturers:
.7 Options:
PART 3 - EXECUTION
3.1 GENERAL
.1 Install so easily read from grade, from platform or from above for gauges
installed below grade level.
.1 In locations as indicated.
.1 No Measurement or separate Payment will be made for this work. All work under
this Section will be paid under the Lump Sum Prices listed in the Schedule of
Prices.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
.1 This Section specifies the labour, products, equipment and services required for
valves – pressure piping, for the Work.
1.3 REFERENCES
.3 ASTM A194M, Standard Specification for Carbon and Alloy Steel Nuts for
Bolts for High Pressure and High Temperature Service;
.1 MSS SP-25, Standard Marking System for Valves, Fittings, Flanges and
Unions;
.3 SAE J518, Hydraulic Flanged Tube, Pipe and Hose Connections, Four-
Bolt Split Flange Type “HS-150/2000”.
.1 Select valves rated and certified for operating and test pressures indicated.
.1 The Contractor is responsible for conducting its own quality assurance program
to ensure that work for valves for pressure piping meets the requirements of this
Section and Section 01620 Quality Control and Assurance:
.3 Regulatory requirements:
1.6 SUBMITTALS
.1 The Contractor shall submit the following submittals for review in accordance
with the requirements of Section 01340 Submittals:
.1 Product Data:
.3 As-Built Drawings.
PART 2 - PRODUCTS
2.1 GENERAL
.4 Flanged valves:
.5 Butt-weld valves:
.9 Identification:
.2 Locking handle;
.4 MSS-SP-110; and
.2 Arrange valve so that venting port is directed away from operator’s position.
.1 Perform pressure testing of valves with piping systems specified under Section
20 11 12 Pressure Piping.
2.7 PROTECTION
.1 During construction, testing and start-up, tag and lock out all valves that may
result in leaks or injury if unwittingly opened.
PART 3 - EXECUTION
3.1 INSTALLATION
.1 Install all valves in upright position with stem or axis of rotation above horizontal.
.1 No Measurement or separate Payment will be made for this work. All work under
this Section will be paid under the Lump Sum Prices listed in the Schedule of
Prices.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the design, Labour, Products, equipment and services
necessary for mechanical identification for the Work.
1.3 REFERENCES
.2 CPPI - Colour Symbol System to Mark Equipment and Vehicles for Product
Identification.
1.4 SUBMITTALS
.1 The Contractor shall submit the following all submittals for review in accordance
with the requirements of this Section and Section 01340 Submittals at least four
weeks prior to commencing use:
.1 Product Data:
.2 Shop Drawings:
.3 Samples:
PART 2 - PRODUCTS
.1 General:
.8 Indicate:
.1 Size;
.2 Equipment model;
.3 Manufacturer's name;
.4 Serial number;
.6 Performance Data;
.9 Date of Manufacturer.
.1 General:
.4 Manufacturers:
1. Seton;
2. Brady; or
3. Smillie McAdams Summerlin.
Tag
Product
Description Identifier Mounting Location
Type
Wording
Tag
Product
Description Identifier Mounting Location
Type
Wording
Tag
Product
Description Identifier Mounting Location
Type
Wording
Gas Meter GM On equipment E-1
Pressure Regulator/Relief Valve PRV On equipment E-3
.1 General:
.4 Manufacturers:
.1 Seton.
.2 Brady.
.1 General:
.1 Pipe: Paint all piping to base colour indicated in the Pipe Identification
Schedule in accordance with Section 09 91 00 and in accordance with
authorities having jurisdiction;
.3 Pipe Markers:
.2 Marker band:
.2 Minimum length:
1. Up to 50 mm outside diameter: 200 mm long band;
2. 65 to 150 mm outside diameter: 300 mm long band;
3. Over 200 mm outside diameter: 600 mm long band;
and
4. Band length suitable to accommodate required text,
arrows and pictograms as indicated.
.3 Text:
.4 Identifier Arrow:
.2 Manufacturer:
1. Seton – Ultramark Snap-on, special order as
required where identifier wording varies from
manufacturer’s standards and for outside diameters
150 mm and larger; and
2. Smillie McAdams Summerlin, special order as
required where identifier wording varies from
manufacturer’s standards and for outside diameters
150 mm and larger.
Marker
PART 3 - EXECUTION
3.1 PREPARATION
.1 General:
.1 Verify substrate surfaces solid, free from surface water, frozen matter,
dust, oil, grease, scaling or laitance, projections and other foreign matter
detrimental to performance; and
.2 Manufacturer's Nameplates:
.5 Pipework Identification:
.1 On the long straight runs in the open areas and equipment rooms,
one identification marker minimum clearly visible from any one (1)
viewpoint in the area and at 20 m maximum intervals;
.4 At the beginning and end points of each run and at each piece of
equipment in the run;
.1 No Measurement or separate Payment will be made for this work. All work under
this section will be paid under the Lump Sum Prices listed in the Schedule of
Prices.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
.1 This Section specifies the labour, products, equipment and services required for
installation, testing, and certification of pressure piping systems for the Work in
accordance with the Contract Documents and all applicable Codes, including:
.2 Any other system governed by the Boilers and Pressure Vessels Act and
Code.
.3 All work carried out including, but not limited to, related work described in other
Sections:
.6 ASME B16.5, Pipe Flanges and Flanged Fittings: NPS ½ through 24;
.4 SAE J343, Test and Test Procedures for SAE 100R Series – Hydraulic
Hose and Hose Assemblies.
1.4 DEFINITIONS
.1 Rusty: Piping that is covered by rust over more than 5% of its surface area.
.1 All systems shall be free of leaks at maximum operating and test pressures.
.3 Select all pressure piping, valves, fittings, hoses and joining methods in
accordance with this Section to meet maximum working pressure in each system
as noted on the Contract Drawings, typically determined by the compressed air
generating system components.
.1 The Contractor is responsible for conducting its own quality assurance program
to ensure that the pressure piping work meet the requirements of this Section
and Section 01620 Quality Control and Assurance.
CN – DESIGN & PRESSURE PIPING SECTION 20 11 12
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 27
MI. 36.79 TO 41.00 HALTON SUB
.2 Installer’s qualifications:
.3 Regulatory requirements:
.2 Schedule and pay for regular general inspections with authority having
jurisdiction at the regular intervals throughout construction period
including, but not limited to, the following:
.2 Welding procedure;
1.7 SUBMITTALS
.1 Prior to submitting Shop Drawings and/or Product Data for any system governed
by the Boilers and Pressure Vessels Act, Contractor shall review Contract
Drawings and Specifications for conformance with CSA B51 and related
standards and bring any discrepancies to attention of The Engineer well in
advance so as not to delay construction. This review is intended to avoid
installation of products that may later be rejected by the TSSA.
.2 The Contractor shall submit the following submittals for review in accordance
with the requirements of this Section and Section 01340 Submittals:
.1 Commissioning Procedures.
.3 Items to include:
.5 Safety precautions;
1.8 APPROVALS
1.9 GENERAL
.2 All system components (including tanks, receivers, piping, fittings, hoses and
valves) clearly identified and marked in accordance with Section 20 05 53
Mechanical Identification so their maximum operating pressure and temperature,
manufacturer, and standard of manufacture easily determined.
.3 All pressure piping, valves, fittings, hoses, and joints specified herein supplied
from single manufacturer.
1.10 INSPECTIONS
.1 Inspect new piping prior to hydrostatic test by design engineer and by authorities
having jurisdiction. Where Province has approved drawings, TSSA certified
inspector to inspect installation.
.3 Remove piping from site, or reject delivery of piping, that is dirty or rusty.
PART 2 - PRODUCTS
.1 Materials:
.1 All piping, valves, fittings, hoses and joints free of leaks while operating at
the maximum rated operating pressure of delivery system and during
pressure testing. All components rated for maximum rated operating
pressure of delivery system. Maximum expected operating pressure for
each system shown on the Contract Drawings;
.1 Threaded:
.1 Select fitting class to suit maximum pipe working pressure at listed pipe
size and operating temperature as follows:
.1 Type: Raised face, Class: 150, to suit listed working pressure shown on
the Contract Drawings, Gasket: full, material to suit liquid.
.1 Code 61, 3000 psi flat socket pipe, SAE four-bolt pattern and O-ring
gasket; and
.2 Code 62, 6000 psi flat socket pipe, SAE four-bolt pattern and O-ring
gasket.
.6 Pipe Threads: In accordance with ANSI/ASME B31.1 and B1.20 using approved
oil resistant compound.
.8 Cast Iron Fittings (In accordance with ASME B16.4): Not permitted.
.3 Fittings:
.4 Joints:
.7 Flanges:
.2 Banded clamp end and gear clamp connection fittings are not permitted
for use;
.2 Working pressure;
.4 Date of fabrication.
2.5 CASINGS:
.1 Under tracks or above storm piping, compressed air carrier pipe casings shall be
steel, minimum 4.8 mm thick, watertight, Butt welding capable of withstanding
railway loading (Cooper E-80 Live Load).
.2 Ensure that the casing pipe has two layers of protection coating and cathodic
protection in accordance with CSA Z662-19.
.3 Ensure that casing pipe inside diameter accommodates pipe and spacers.
PART 3 - EXECUTION
3.1 INSTALLERS
3.2 PREPARATION
.3 Adjust pipe route and/or equipment location to avoid conflicts with new and/or
existing.
3.3 INSPECTIONS
.1 Leave joints in the piping systems uncovered until tests completed and system
inspected and approved by the Engineer.
.3 The Engineer and authorities having jurisdiction to inspect new piping prior to
hydrostatic pressure tests for compliance with reviewed Drawings and
Specifications.
.5 Obtain from the Engineer requirements for inspection and testing of system
modifications, design changes and repairs performed in house.
.2 Schedule regular TSSA inspection of all welds and joints as they are
made;
.9 Put no system governed by Boilers and Pressure Vessels Act into service
until approval granted by TSSA and The Engineer.
CN – DESIGN & PRESSURE PIPING SECTION 20 11 12
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 15 OF 27
MI. 36.79 TO 41.00 HALTON SUB
3.4 INSTALLATION - GENERAL
.1 Install all systems required governed by the Boilers and Pressure Vessels Act to
latest requirements of CSA B51 – Boiler, Pressure Vessel, and Pressure Piping
Code, and all related codes and standards governing selection and installation of
piping, fittings, joining methods, welding, valves, etc.
.2 Clean piping before installation. Remove rust and scale. Deburr pipe after cutting
and chips after threading.
.3 Clearances:
.4 Coordinate location of piping, valves and reels with all other services. Provide
necessary clearance for maintenance. Identify potential interferences to The
Engineer for resolution.
.6 Drain valves:
.3 Install piping drain valves at the low point of the piping entry into manifold
and/or charging valve stations.
.7 Branch take-offs:
.2 Where reducing tees of proper size are unavailable, use available tees
with reducers. Tees with increasers not acceptable; and
.10 Revisions to location of piping require approval of the Engineer. Prepare and
submit Drawings of all proposed revisions.
.2 Joints:
.1 At the valves connected to hose reels: One (1) only screwed joint
permitted; and
.3 Screwed joints:
.4 Branch connections:
.1 Piping Installation:
.1 Installers shall be trained and certified to install the pipe according to the
manufacturer’s guidelines. Contact your local Aquatherm representative
for training;
.2 Install listed pipe materials and joining methods below in the following
applications:
CN – DESIGN & PRESSURE PIPING SECTION 20 11 12
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 17 OF 27
MI. 36.79 TO 41.00 HALTON SUB
.1 Underground Piping: Polypropylene (PP-R) piping in SDR 7.4 per
manufacturer’s instructions and ASTM D2774.
.5 Do not backfill piping trench until field quality-control testing has been
completed and results approved;
.10 Thrust blocks shall not be required with PP-R piping; and
.11 Expansion loops shall not be required for direct buried underground PP-R
piping.
.2 Trench Installation:
.3 Bed the pipe on a minimum 150 mm layer of granular fill material with a
minimum 150 mm clearance between the pipes;
.5 Place backfill after field quality-control testing has been completed and
results approved;
.3 Prior to joining, the pipe and fittings shall be prepared in accordance with
ASTM F 2389 and the manufacturer’s specifications. The black plastic
coating on the UV pipe shall be removed before fusing the pipe; and
.3 The reason for the required testing criteria is to enable installers to locate
faulty joints and pipe and workmanship issues that may result in leaks.
Finding such faulty joints, pipe cracks, etc. is critical in the preliminary
stages of construction in order to eliminate or, at least, to minimize costly
damages that may occur once the system is put into service;
.4 Test new and modified parts of existing piping. Test piping as specified by
the piping system manufacturer with dry air, or nitrogen to a pressure of
150 psi or 150% of working pressure, whichever is greater;
.5 Do not leave butt fusion machines connected to the piping when testing;
.7 For the entire duration of the procedure, the test section and the work
area around the test section and equipment shall be supervised or
secured with barricades and warnings so that unauthorized persons are
kept a safe distance away;
CN – DESIGN & PRESSURE PIPING SECTION 20 11 12
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 19 OF 27
MI. 36.79 TO 41.00 HALTON SUB
.8 A failure in the piping system or mechanical components and connections
may result in sudden, violent, uncontrolled, and dangerous movement of
system piping, or components, or parts of components;
.9 Take measures to ensure that all parts of the section under test are
structurally restrained against movement if failure occurs. Observe
manufacturer’s precautions for securing and restraining temporary
mechanical end (test) caps. Defective or improperly secured temporary
end closures or mechanical end caps shall not be used;
.10 When connections, joints and seals are to be exposed for observation
during the test, use restraint methods to control movement in the event of
joint or connection separation, giving due consideration to restraining
forces in both the lateral/outward and longitudinal/axial directions;
.11 Pipe connected to connections, joints and seals that are exposed for
leakage observation shall be restrained. The unrestrained exposed pipe
distance to the side of the exposed connection, joint or seal shall not
exceed the greater of 5 pipe diameters or 3 ft. (1 m); and
.12 When properly made, heat fusion joints in polypropylene pipe are
structurally comparable to the parent (PP-R) pipe material and do not
leak. Leakage at a fusion joint indicates a possible poor joint having the
imminent potential for complete separation. If leakage is observed at a
fusion joint, move away immediately, and depressurize the test section.
.5 Identification:
.1 Provide recesses on trench bottom for couplings, fittings, and valves to ensure
bearing will occur along barrel of pipe.
.2 Lay service line pipe on proper grade to drain from end device to compressed air
main.
.3 Lay compressed air pipe on trench bottom that are graded in accordance with
Specifications to prevent sags and low points in piping.
.4 Ensure minimum of 1000 mm distance between compressed air pipe and any
underground structure that runs parallel to the pipe unless noted otherwise.
.5 Ensure minimum of 100 mm distance between compressed air pipe and any
underground structure that crosses compressed air pipe unless noted otherwise.
.6 Ensure that the location and arrangement of pipe and connections provides
protection from mechanical damage.
.7 Provide shut off valve above grade where shown and upstream of all
compressed air outlets/connections.
.9 Provide tracer wire on all non-metallic and uncased buried pipe. Extend up at
each riser with minimum 450 mm length above finished grade. Bring tracer wire
up to surface every 300 m and using 50 mm diameter valve boxes for locating
purposes. Connect tracer wires together using split bolt #10 connectors. Wrap
split bolts in electrical putty.
.10 Coordinate installation of cathodic protection anodes with other utility trades to
avoid interference. Identify locations of anodes on As-Built Drawings.
.11 Mark routing of piping with marker tape placed along centerline of the trench,
approximately 250 mm below finished grade or as indicated on the Drawings.
.1 Surface preparation:
.2 Primer Application:
.1 TC Color Coat Primer – Apply TC Color Coat Primer four mils thick with
gloved hand. Ensure to prime the total surface to be coated.
.3 Tape application:
.2 Cigarette wrap tape strips when conditions do not allow for spiral
wrapping.
.2 As tape is applied use hand pressure to seal the overlap and smooth out
wrinkles, assuring that the tape has contact with the substrate and the
tape overlap has melded and sealed to the preceding layer. Ensure that:
.3 For coating vertical or riser pipe: start wrapping at the low end of
the pipe segment, wrap in an upward direction from ground toward
sky.
.5 Handling of coated pipe: Take required measures to handle the coated pipe to
prevent exposure to abrasion or damage prior to, during and after installation.
CN – DESIGN & PRESSURE PIPING SECTION 20 11 12
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 22 OF 27
MI. 36.79 TO 41.00 HALTON SUB
3.9 WELDING
3.10 HOUSEKEEPING
.2 Protect all Product certification markings from soiling and damage during
handling and installation. Install and orient all equipment, piping, fittings, hoses,
and valves so certification markings remain visible for inspection.
.3 Do not paint, cover or conceal system piping, valves, hoses, fittings, and
especially certification markings until all inspections and pressure tests
conducted successfully and system approved for operation by TSSA.
3.12 VALVES
.4 Install only steel valves for all flammable and combustible fluids.
.3 Give the Engineer and TSSA minimum of five Business Days’ notice of
intention to perform pressure tests;
.5 Prior to tests, isolate equipment and other parts which are not designed
to withstand test pressure or test media and indicate in test report;
.6 Bear costs for tests, for repairs or replacement, retesting, and making
good;
.8 Use test media indicated on the Contract Drawings, and unless indicated
otherwise, use fluid intended to be carried by each piping system;
.10 Test gauges not new: Submit calibration certificate dated within one
month of test date;
.12 Provide equipment that will safely and accurately generate test pressures,
under controlled conditions, and without potential for human error. Submit
proposed test equipment to the Engineer for approval;
.14 Any pressure test procedure found unsafe, in opinion of the Engineer staff
or TSSA inspector, will be cancelled and rescheduled at the Contractor’s
expense; and
.15 Upon successful completion of pressure test for each individual pressure
piping system, prepare and submit detailed test report.
3.14 PAINTING
.1 Clean, prime and paint all piping in accordance with Section 20 05 53 Mechanical
Identification.
.3 Do not cover pipe identification markings until the Engineer and TSSA inspector
have inspected them.
3.15 IDENTIFICATION
.1 Cleaning Solutions:
.3 Install Products such as flow meters and dispensing valves only after cleaning
certified as complete.
.1 At all drip legs and dirt pockets (at air hose stations and air
regulators); and
.1 Purchase and supply all fluid Products required for flushing of each system.
.2 Arrange for bulk/drum delivery of Products as required to suit system and activity.
.3 Allow for disposal and/or recycling of waste Product for each system.
.4 Where directed by The Engineer, reserve waste Products for priming and testing
of waste oil and/or waste glycol systems.
3.18 COMMISSIONING
.2 Pressure test;
.6 Other.
.3 Reports:
.1 Timing after:
.1 Cleaning is completed;
.13 Record pressure of air supply and relief setting for each system.
.1 Complete and submit TSSA form “Piping Systems Installation and Test Data
Report”.
.1 No Measurement or separate Payment will be made for this work. All work under
this Section will be paid under the Lump Sum Prices listed in the Schedule of
Prices.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
.1 This Section specifies the labour, products, equipment and services required for
compressed air system for the Work in accordance with the Contract Documents,
including but not limited to:
.1 Air Compressors;
.2 Air Dryers;
.3 Filters;
1.3 REFERENCES
.1 The Contractor is responsible for conducting its own quality assurance program
to ensure that the compressed air system work meet the requirements of this
Section and Section 01620 Quality Control and Assurance:
.1 Manufacturer's qualifications:
.3 Regulatory requirements:
1.5 SUBMITTALS
.1 The Contractor shall submit the following submittals for review in accordance
with the requirements of this Section and Section 01340 Submittals:
.1 TSSA forms;
.5 Safety precautions;
.7 Consumables;
.3 Warranty information.
CN – DESIGN & COMPRESSED AIR SYSTEM SECTION 22 15 00
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 4 OF 12
MI. 36.79 TO 41.00 HALTON SUB
1.6 TRAINING
.1 Provide training plan, training course material, training schedule, and training.
PART 2 - PRODUCTS
.1 Two fully packaged compressed air system stations no. 1 & 2, each package
consisting of (but not limited to) the following:
.2 Each fully packaged system shall be internally pre-piped (including flanges for
piping connections between internal compressed air components and exterior
receiver tank), ducted and electrical ready for final connections by the installing
contractor.
.1 Each air compressor shall be a single stage, air cooled, oil injected, rotary screw
air compressor complete with high efficiency TEFC drive blower motor, inlet air
filter, vibration mounts, lubrication system, coolant/air separation,
compressor/capacity controls, starter, controller, packaged pre-filter and moisture
separator & condensate drain. Available options shall include surge
protection and power outage restart.
.2 Capacity:
.1 269 ACFM at operating pressure of 145 psig or 248 ACFM at 150 psig.
.3 Operating Pressure:
.4 Motor:
.5 Voltage:
.1 575/3/60.
.6 Cooling Fan:
.1 Cooling fan – 1.5 HP (1.1 kW) motor, selected for direct ducting of cooling
exhaust; and
.2 Air end: Rotary screw compressor with optimized screw profile, oversized,
low speed, 1:1 drive, operating at motor speed.
.7 Inlet Filter:
.8 Separator:
.9 Control:
.2 Dryer shall employ twin-drying towers comprising ASME code welded pressure
vessels, spherical-particle, non-corrosive activated alumina desiccant, and
desiccant fill and empty ports. A continuous supply of dry air shall be provided by
the automatically cycled operation of the drying vessels on a fixed cycle,
including drying, pressure stabilization and regeneration. Automatic cycling shall
be controlled by an electronic controller. Airflow shall be directed through
alternate drying vessels by pneumatically operated valves which require no
lubrication. Dryers shall use high performance, stainless steel angle seated
valves.
.3 Fire rated pressure relief valves shall be located on each pressure vessel.
.4 The purge air control system shall include mufflers to reduce the noise level of
the purge air exhaust to within OSHA standards. No electrical or other energy
shall be supplied to the dryers from an outside source for reactivation. Total
electrical requirements shall not exceed 5 Amperes at 110, 115 or 120 Vac. The
dryers shall include, as a minimum, gauges showing pressure in each drying
tower, a gauge showing purge pressure, a manual purge adjustment valve, UL
type 4 PLC with a keypad & screen, and a light indication panel that indicates the
status of the dryer including ON/OFF & tower status.
.5 The PLC controller shall incorporate a user display screen that will provide
information regarding dryer status (ON/OFF), dryer step sequence information,
operating hours for various components (including main flow & purge valves),
alarm status & notification, and maintenance information. The PLC shall be
provided with RS485 communication as standard.
.7 The PLC controller display shall include the dew-point value, system status,
enable / disable function, cycle point indication, ability to facilitate adjustment of
the set-point, and a common alarm dry contact.
.8 Acceptable Manufacturers:
.1 A prefilter shall be included for installation upstream of the dryers to remove oil
and liquid water down to 0.01 mg/m³ content at 21°C (0.008 ppm W at 70°F).
Prefilter shall be capable of removing solid particles as small as 0.01 micron.
Prefilter shall employ a no-touch replaceable element. Filters shall include an
automatic drain valve for periodic removal of separated contaminants. Filter is
equipped with a dual scale differential pressure gauge for indication of element
replacement.
.2 Acceptable Manufacturers:
.4 Acceptable Manufacturers:
.1 Provide for each air compressor packaged system station, one single use
shipping container, approximately 30’ long by 8’ wide, with barn style double
doors on one end and a swing type access door to facilitate regular access for
maintenance.
.2 Each container (two total required) is to contain the compressed air components
package; consisting of 2 x Ingersoll Rand Model RS45i - 60 hp Rotary Screw Air
Compressors, 1 x HL300 Desiccant Air dryer and 1 x Oil Water Separator. The
CN – DESIGN & COMPRESSED AIR SYSTEM SECTION 22 15 00
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 8 OF 12
MI. 36.79 TO 41.00 HALTON SUB
container interiors are to be skinned with sheet metal and painted for a smooth
finish.
.3 Supply and install all lighting required for a safe working environment (110 volts).
.4 Supply and install a voltage transformer from 575 volts to 220, 110, and 24 volts,
of a suitable size to operate the ventilation fan and louvers, the lighting, the
electronic auto drains and some additional plugs for maintenance use. Supply
and install a mounting panel, splitter, disconnect, and all other electrical
requirements to operate each compressor and air dryer. Supply a fused main
disconnect to operate all the equipment and all other electrical components
required to ensure that the hydro supply and wiring meets specified ESA code.
Supply and install a junction box (splitter) to connect the electrical feed. All
electrical components shall be suitable for the compressed air packaged systems
supplied.
.7 Insulate the Container package internally to reduce noise and heat loss complete
with steel cladding
.2 Cut ventilation openings required for venting the compressors intake, discharge,
and ventilation. Provide a suitable duct and shroud to ventilate the compressor
room. Provide an electric damper and programmable thermostat. Provide and
install all ducting required for ventilation/heating.
.3 Supply and install all Carbon steel piping required to connect the air compressors
through the filters, air dryers, to a discharge port on the outside of the container,
and install a manual ball drain valve to prevent water from accumulating in the
discharge pipe. Connect all drain points to a common area and pipe into the
oil/water separator. Install all condensate lines to OWS inside container.
CN – DESIGN & COMPRESSED AIR SYSTEM SECTION 22 15 00
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 9 OF 12
MI. 36.79 TO 41.00 HALTON SUB
.6 Manufacturers:
.1 Ingersoll Rand;
.2 Steel Fab;
.3 Aircom Technologies;
.4 Manchester; and
.5 CAI.
2.9 ACCESSORIES
.2 Pressure Gauge:
CN – DESIGN & COMPRESSED AIR SYSTEM SECTION 22 15 00
CONSTRUCTION MILTON LOGISTICS HUB – PHASE 2A SEPTEMBER 2023
GRADING & DRAINAGE PAGE 10 OF 12
MI. 36.79 TO 41.00 HALTON SUB
.3 Condensate Drain:
.4 Air Hose:
PART 3 - EXECUTION
.1 Install compressed air piping from main line to outlets, equipment, and
connections as shown on Contract Drawings. Take branch connections serving
equipment and air hose stations off top of main line.
.2 Install isolation valves at beginning of each branch serving more than one piece
of equipment.
.3 Install isolation valves at beginning of each branch serving more than one piece
of equipment.
.5 Prime, paint and identify compressed air piping and unpainted equipment as per
Section 20 05 53 Mechanical Identification.
.7 Leave complete system ready for continuous, efficient and satisfactory operation.
.3 Connect compressed air lines from air receiver tanks to each main compressed
air line.
.4 Set controls to schedule operation of intake and relief dampers to control room
temperature. Provide additional wiring as required for complete system
operation, in accordance with standards of Division 26. Set system to recirculate
when room temperature is below 10°C.
.5 Leave equipment ready to operate. Set to deliver 145 psig supply air pressure.
.5 Extend drain line from condensate management system to an exterior drain point
complete with an insect/pest screen located within the interior of the container to
avoid cold weather freeze up.
.1 Conduct pressure tests and certification of new compressed air piping as per
Section 20 11 12 Pressure Piping. Isolate piping and equipment not part of test.
.2 Arrange for the Engineer and all inspection authorities having jurisdiction to
witness tests.
.5 Submit complete testing and startup reports for the entire compressed air system
to the Engineer.
3.7 COMMISSIONING
.1 Perform Commissioning
.3 Air dryer;
3.8 MAINTENANCE
.1 No Measurement or separate Payment will be made for this work. All work under
this Section will be paid under the Lump Sum Prices listed in the Schedule of
Prices.
GENERAL CONDITIONS
The general conditions (Annex “A”) of Contract Form No. 3819 and all Sections of Division 1 of
this Specification apply equally to this Section of the Specification.
PART 1 - GENERAL
1.1 SCOPE
.1 This Section specifies the Labour, Products, equipment and services necessary
for piping, valves and fittings (gas) for underground propane piping work.
.1 Conduct a quality assurance program to ensure that all of the work for
underground gas piping, meets the requirements of the Specifications.
.2 Ensure all work of this Section is performed by a contractor licensed for gas
systems installation.
1.5 SUBMITTALS
.2 The Contractor shall submit the following all submittals for review in accordance
with the requirements of this Section and Section 01340 Submittals at least four
weeks prior to commencing use:
.2 Commissioning Plan;
.4 Inspection and Test Reports for Underground Propane Piping for all
inspections and tests, ten (10) working days after each inspection and
test;
.6 Closeout Submittals:
CN – DESIGN & PIPING, VALVES AND FITTINGS SECTION 23 11 23
CONSTRUCTION (GAS/PROPANE) SEPTEMBER 2023
MILTON LOGISTICS HUB – PHASE 2A PAGE 3 OF 9
GRADING & DRAINAGE
MI. 36.79 TO 41.00 HALTON SUB
.1 Include final test and commissioning reports into Operations
Manual; and
.2 As-Built Drawings.
PART 2 - PRODUCTS
.1 Black Steel pipe, ASTM A53 grade B, Schedule 40 complete with ‘yellow jacket’
polyethylene covering to CSA Z245.30-18.
.2 Fittings: ASTM A234, 150 lb, steel butt welded fittings; complete with field fitted
heat shrink polyethylene joint and fitting wrap, half lapped 10 mil polyethylene.
.3 Anti-corrosion protection for valves and exposed metal parts: TC COLOR COAT
ENVIROTAPE WAX COATING as manufactured by CHASE Construction
Products (TAPECOAT/ROYSTON):
.4 Buried section of steel piping shall be protected with corrosion resistant Epoxy
coating, Pre affixed to buried section of piping. Refer to Drawings for specific
buried piping locations.
CN – DESIGN & PIPING, VALVES AND FITTINGS SECTION 23 11 23
CONSTRUCTION (GAS/PROPANE) SEPTEMBER 2023
MILTON LOGISTICS HUB – PHASE 2A PAGE 4 OF 9
GRADING & DRAINAGE
MI. 36.79 TO 41.00 HALTON SUB
.5 Welded joints underground to have epoxy coating applied to the joint to have a
monolithic corrosion protection covering.
.1 Buried propane main piping shall be HDPE in compliance with CSA B137.4 and
ASTM B2513, DR 11 or less.
.2 Fittings shall be HDPE heat socket fusion type in compliance with CSA B137.4.
2.3 VALVES
.2 Vented type, spring-loaded self - operated design, tight closing, selected for site
gas pressure and piping pressure loss, and connected equipment load at full
firing rate plus 20% spare, suitable for outdoor application.
.3 1035 kPa (150psi) rated cast iron body finished with corrosive resistant epoxy
enamel.
.4 Aluminum diaphragm and spring case with Nitrile diaphragm, disc, and body o-
ring.
2.5 CASINGS
.1 Under tracks gas carrier pipe casings shall be HDPE DR11 capable of
withstanding railway loading (Cooper E-80 Live Load).
.2 Ensure that casing pipe inside diameter accommodates pipe and spacers.
.1 Tracer wire shall be R.W.U. 90, number 12-gauge, single strand insulated copper
with cross-linked polyethylene insulation manufactured for direct burial
applications, 1000 V rating.
.2 Provide cathodic protection for tracer wire, one 5.4 kg zinc anode installed for
every maximum 1000 m of tracer wire.
PART 3 - EXECUTION
3.1 CONSTRUCTION
.2 Ensure that the construction of underground gas piping is in accordance with the
CSA Z662, CSA B149.1, work requirements of this Section and all other
applicable codes and regulations, including the requirements of the local
authority having jurisdiction.
.4 Ensure that the granular materials provided are in accordance with the contract
documents for Granular Materials.
.5 Excavate, cover and backfill in accordance with the contract documents relating
to Excavation, Trenching, Backfilling and Compacting.
.6 Clean and flush before testing and inspection in accordance with requirements of
CSA Z662.
.7 Remove rejected and excess material from the place of work within 48 hours.
CN – DESIGN & PIPING, VALVES AND FITTINGS SECTION 23 11 23
CONSTRUCTION (GAS/PROPANE) SEPTEMBER 2023
MILTON LOGISTICS HUB – PHASE 2A PAGE 6 OF 9
GRADING & DRAINAGE
MI. 36.79 TO 41.00 HALTON SUB
.8 Coordinate the work for installation of underground gas piping with the work
performed by the local authorized gas company.
.1 Provide complete yellow jacket pipe system complete with heat shrink sleeves.
.2 Provide recesses on trench bottom for couplings, fittings, and valves to ensure
bearing will occur along barrel of pipe.
.3 Lay service line pipe on proper grade to drain from gas fired device to gas main.
.4 Lay gas pipe on trench bottom that are graded in accordance with Specifications
to prevent sags and low points in piping.
.5 Ensure minimum of 1000 mm distance between gas pipe and any underground
structure that runs parallel to the pipe unless noted otherwise.
.6 Ensure minimum of 100 mm distance between gas pipe and any underground
structure that crosses gas pipe unless noted otherwise.
.7 Field cut HDPE pipe using pipe and tubing cutting tools designed for plastic pipe.
.8 Ensure that the location and arrangement of pipe and connections provides
protection from mechanical damage. Ensure that all bends in tubing are smooth,
free of kinking and twisting, and free of flattening.
.9 Provide shut off valve above grade where shown and required by CSA B149.1.
.11 Provide tracer wire on all non-metallic and uncased buried pipe. Extend up at
each riser with minimum 450 mm length above finished grade. Bring tracer wire
up to surface every 300 m and using 50 mm diameter valve boxes for locating
purposes. Connect tracer wires together using split bolt #10 connectors. Wrap
split bolts in electrical putty.
.12 Coordinate installation of cathodic protection anodes with other utility trades to
avoid interference. Identify locations of anodes on As-Built Drawings.
.13 Mark routing of piping with marker tape placed along centerline of the trench,
approximately 250 mm below finished grade or as indicated on the Drawings.
CN – DESIGN & PIPING, VALVES AND FITTINGS SECTION 23 11 23
CONSTRUCTION (GAS/PROPANE) SEPTEMBER 2023
MILTON LOGISTICS HUB – PHASE 2A PAGE 7 OF 9
GRADING & DRAINAGE
MI. 36.79 TO 41.00 HALTON SUB
.14 Install prominent warning markers at the right-of-way edge on both sides of track
for propane pipeline under crossings and, along the right-of-way, for the propane
gas main running along the South side of the corridor at intervals that will permit
viewing from any direction, not exceeding 150 m.
.1 Surface preparation:
.2 Primer Application:
.1 TC Color Coat Primer – Apply TC Color Coat Primer four mils thick with
gloved hand. Ensure to prime the total surface to be coated.
.3 Tape application:
.2 Cigarette wrap tape strips when conditions do not allow for spiral
wrapping.
.2 As tape is applied use hand pressure to seal the overlap and smooth out
wrinkles, assuring that the tape has contact with the substrate and the
tape overlap has melded and sealed to the preceding layer. Ensure that:
.5 Handling of coated pipe: Take required measures to handle the coated pipe to
prevent exposure to abrasion or damage prior to, during and after installation.
3.4 TESTING
.1 Inspection of piping systems by TSSA. If required, schedule and pay for regular
general inspections with authority having jurisdiction at the regular intervals
throughout construction period including, but not limited to, the following:
.2 Welding procedure.
.4 Ensure to fill piping with test medium for 24 hours prior to actual test.
.5 For polyethylene piping, Subject pipe to pressure of 350 kPa or 1.5 times
maximum operating pressure, whichever is greater, for 24 hours.
.7 Ensure that test consist of visual “soap bubble” inspection of the joints for leaks
and of measuring the pressure after 24 hours. No pipe installation will be
accepted if leaks are detected or if pressure at end of test is less than 95% of
original test pressure.
.8 If air or inert gas is used for testing, purge lines with propane before using.
CN – DESIGN & PIPING, VALVES AND FITTINGS SECTION 23 11 23
CONSTRUCTION (GAS/PROPANE) SEPTEMBER 2023
MILTON LOGISTICS HUB – PHASE 2A PAGE 9 OF 9
GRADING & DRAINAGE
MI. 36.79 TO 41.00 HALTON SUB
.9 Ensure to test the tracer wire at the time of pipe pressure testing.
3.5 RESTORATION
.1 Ensure that, upon completion of the Work of this Section, the Site is restored in
accordance with the requirements of Contract Documents. Ensure that any
previously existing areas that are disturbed as a result of the Works are restored
to its original condition.
.1 No Measurement or separate Payment will be made for this Work. All work under
this section will be paid under the Lump Sum Prices listed in the Schedule of
Prices.