JOB CARD PACKAGE TITLE: ABQ -

Fill the Hydraulic Fluid Reservoir with a Hand Tail Number - MSN -
Pump FSN
ALL

MPD Reference Title DocType

Fill the Hydraulic Fluid Reservoir with a Hand


NONE 12-12-29-611-001-A AMM
Pump

Job Cards Package is made of: 1 job cards.

JCP Title: Fill the Hydraulic Fluid CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 1 of 2
Reservoir with a Hand Pump PRINT DATE: Aug 21/2023
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
JOB CARD PACKAGE TITLE: ABQ -
Fill the Hydraulic Fluid Reservoir with a Hand Tail Number - MSN -
Pump FSN
ALL

INTENTIONALLY LEFT BLANK

JCP Title: Fill the Hydraulic Fluid CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 2 of 2
Reservoir with a Hand Pump PRINT DATE: Aug 21/2023
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Aug
JOB CARD
01/2023
AMM - ABQ - A318/A319/A320/A321 TASK:
12-12-29-611-001-A
12-12-29-03 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 12-12-29-611-001-A - Fill the Hydraulic Fluid Reservoir with a NONE
ALL Hand Pump

MECH. INSP.

** ON A/C FSN ALL


TASK 12-12-29-611-001-A
Fill the Hydraulic Fluid Reservoir with a Hand Pump
FIN: 1000GQ 2000GQ 3000GQ

WARNING: DO NOT GET THE FLUID ON YOUR SKIN OR IN YOUR EYES. IF


YOU DO:
- FLUSH IT AWAY WITH CLEAN WATER
- GET MEDICAL AID.

WARNING: MAKE SURE THAT THE TRAVEL RANGES OF THE FLIGHT


CONTROLS SURFACES ARE CLEAR. MOVEMENT OF FLIGHT
CONTROLS CAN CAUSE INJURY TO PERSONS AND/OR DAMAGE
TO EQUIPMENT.

WARNING: BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY


THE MATERIAL MANUFACTURER'S INSTRUCTIONS AND YOUR
LOCAL REGULATIONS.

1. Reason for the Job

NOTE: If the hydraulic reservoir is too full, adjust the fluid level accurately. It
is not necessary to drain the hydraulic reservoir fully.

2. Job Set-up Information

A. Fixtures, Tools, Test and Support Equipment

REFERENCE QTY DESIGNATION


No specific 1 ACCESS PLATFORM 2M (6 FT)
No specific 1 CONTAINER - HYDRAULIC FLUID
RESISTANT
No specific 1 THERMOMETER-INFRARED
No specific 1 WARNING NOTICE(S)

B. Consumable Materials

JCP Title: Fill the Hydraulic Fluid CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 1 of 18
Reservoir with a Hand Pump PRINT DATE: Aug 21/2023
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Aug
JOB CARD
01/2023
AMM - ABQ - A318/A319/A320/A321 TASK:
12-12-29-611-001-A
12-12-29-03 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 12-12-29-611-001-A - Fill the Hydraulic Fluid Reservoir with a NONE
ALL Hand Pump

MECH. INSP.

REFERENCE DESIGNATION
02ABA1 Phosphate Ester Hydraulic Fluid-General
Power - -

C. Work Zones and Access Panels

ZONE/ACCESS ZONE DESCRIPTION


197CB, 197EB,
198CB

D. Referenced Information

REFERENCE DESIGNATION
Ref. Fill the Hydraulic Power Accumulators with
12-14-29-614-001-A Nitrogen
Ref. Energize the Aircraft Electrical Circuits from
24-41-00-861-002-A the External Power
Ref. Energize the Aircraft Electrical Circuits from
24-41-00-861-002- the APU
A01
Ref. Energize the Aircraft Electrical Circuits from
24-41-00-861-002- Engine 1(2)
A02
Ref. De-energize the Aircraft Electrical Circuits
24-41-00-862-002-A Supplied from the External Power
Ref. De-energize the Aircraft Electrical Circuits
24-41-00-862-002- Supplied from the APU
A01
Ref. De-energize the Aircraft Electrical Circuits
24-41-00-862-002- Supplied from the Engine 1(2)
A02
Ref. Put the Related Hydraulic System in the
29-00-00-864-001-A Depressurized Configuration before
Maintenance Action

JCP Title: Fill the Hydraulic Fluid CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 2 of 18
Reservoir with a Hand Pump PRINT DATE: Aug 21/2023
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Aug
JOB CARD
01/2023
AMM - ABQ - A318/A319/A320/A321 TASK:
12-12-29-611-001-A
12-12-29-03 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 12-12-29-611-001-A - Fill the Hydraulic Fluid Reservoir with a NONE
ALL Hand Pump

MECH. INSP.

REFERENCE DESIGNATION
Ref. Bleeding Procedure of the Green Hydraulic
29-00-00-870-003-A System Downstream of the Engine Pump
Ref. Bleeding Procedure of the Yellow Hydraulic
29-00-00-870-007-A System Downstream of the Engine Pump
Ref. Bleeding Procedure of the Blue Hydraulic
29-00-00-870-008-A System Upstream of the Blue E-Pump
Ref. Bleeding Procedure of the Blue Hydraulic
29-00-00-870-009-A System Downstream of the Blue E-Pump
Ref. Safety Procedures of the Hydraulic System
29-00-00-910-002-A
Ref. Drainage of the Reservoir of the Green
29-10-00-680-001-A Hydraulic System
Ref. Drainage of the Reservoir of the Yellow
29-10-00-680-002-A Hydraulic System
Ref. Drainage of the Reservoir of the Blue
29-10-00-680-003-A Hydraulic System
Ref. Pressurization of the Hydraulic Reservoirs
29-14-00-614-002-A through the Ground Connector
Ref. Pressurization of the Hydraulic Reservoirs
29-14-00-614-002- with the Auxiliary Power Unit (APU)
A01
Ref. Pressurize the Yellow Hydraulic System with
29-24-00-863-001-A the Electric Pump
Ref. Depressurize the Yellow Hydraulic System
29-24-00-864-001-A
Ref. Access to the Parameter Call-Up Menus
31-36-00-740-008-A
Ref. Open the Main Gear Doors for Access
32-12-00-010-001-A
Ref. Close the Main Gear Doors after Access
32-12-00-410-001-A

JCP Title: Fill the Hydraulic Fluid CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 3 of 18
Reservoir with a Hand Pump PRINT DATE: Aug 21/2023
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Aug
JOB CARD
01/2023
AMM - ABQ - A318/A319/A320/A321 TASK:
12-12-29-611-001-A
12-12-29-03 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 12-12-29-611-001-A - Fill the Hydraulic Fluid Reservoir with a NONE
ALL Hand Pump

MECH. INSP.

REFERENCE DESIGNATION
Ref. Functional Check of Parking/Emergency
32-44-11-200-001-A Brake Accumulator by Reading the Charge
Pressure on the Accumulator Gauge
Ref. Fig. Ground Service Panel of the Green Hydraulic System
Ref. Fig. Example of the Label Call Up Decoding

3. Job Set-up

SUBTASK 12-12-29-860-051-A
A. Aircraft Maintenance Configuration

WARNING: OBEY THE HYDRAULIC SAFETY PROCEDURES.


(1) Obey the hydraulic safety procedures Ref. AMM TASK
29-00-00-910-002.
(2) Make sure that the aircraft is in this configuration:
- The speed brakes and the spoilers are retracted
- The thrust reversers are stowed (closed)
- The landing gear is extended and the landing gear
doors are closed

NOTE: One main landing gear door may be kept open.


- The FWD and aft cargo-compartment doors 825 and
826 are closed
- All the other hydraulically controlled systems are in the
normal position.

(3) Make sure that the hydraulic systems are depressurized and
put them in the maintenance configuration
Ref. AMM TASK 29-00-00-864-001.

NOTE: Do not depressurize the system reservoirs.

JCP Title: Fill the Hydraulic Fluid CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 4 of 18
Reservoir with a Hand Pump PRINT DATE: Aug 21/2023
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Aug
JOB CARD
01/2023
AMM - ABQ - A318/A319/A320/A321 TASK:
12-12-29-611-001-A
12-12-29-03 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 12-12-29-611-001-A - Fill the Hydraulic Fluid Reservoir with a NONE
ALL Hand Pump

MECH. INSP.

(4) Energize the aircraft electrical circuits Ref. AMM TASK


24-41-00-861-002.

SUBTASK 12-12-29-010-054-A
B. Get Access
(1) Open the left and right Main Landing Gear (MLG) doors Ref.
AMM TASK 32-12-00-010-001.
(2) Open the access panels 197CB, 198CB and 197EB.
(3) Put the ACCESS PLATFORM 2M (6 FT) in position.

SUBTASK 12-12-29-210-052-A
C. Inspection of the Pressure Values
(1) Make sure that the nitrogen fill pressure of the brake
accumulator 2582GM is correct Ref. AMM TASK
32-44-11-200-001.
(2) Make sure that the hydraulic accumulators 1070GM, 2070GM
and 3070GM have a nitrogen pressure of 130 bar (1885.4901
psi) at 20 deg.C (68.00 deg.F).
If necessary, adjust the nitrogen pressure Ref. AMM TASK
12-14-29-614-001.
(3) Make sure that the pressure on the indicator of the related
reservoir is 3.5 -0 bar or +0.3 bar (50.7632 -0 psi or +4.3511
psi). If necessary, pressurize the reservoir Ref. AMM TASK
29-14-00-614-002.

NOTE: If you pressurize the Hydraulic Reservoir with the


APU, the Hydraulic Reservoir pressure will be
approximately 1.65 bar (24 psi).

SUBTASK 12-12-29-863-050-A
D. Pressurization of the Auxiliary Braking System
(1) Pressurize the Yellow hydraulic system with the Yellow E-pump
Ref. AMM TASK 29-24-00-863-001 to pressurize the brake
accumulator system to 206 bar (2987.7766 psi).

JCP Title: Fill the Hydraulic Fluid CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 5 of 18
Reservoir with a Hand Pump PRINT DATE: Aug 21/2023
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Aug
JOB CARD
01/2023
AMM - ABQ - A318/A319/A320/A321 TASK:
12-12-29-611-001-A
12-12-29-03 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 12-12-29-611-001-A - Fill the Hydraulic Fluid Reservoir with a NONE
ALL Hand Pump

MECH. INSP.

(2) On the panel 110VU, put the parking brake control switch
73GG to the ON position.
(3) Make sure that the pressure on the triple indicator 60GG shows
the left and right pressure values.
(4) Close the left and right MLG doors Ref. AMM TASK
32-12-00-410-001.
(5) Depressurize the Yellow hydraulic system Ref. AMM TASK
29-24-00-864-001.

NOTE: Do not depressurize the alternate braking system.

(6) Put the WARNING NOTICE(S) on the panel 40VU in the


cockpit to tell persons not to pressurize the hydraulic systems.

4. Procedure
Ref. Fig. Ground Service Panel of the Green Hydraulic System

SUBTASK 12-12-29-611-052-A
A. Fill the Hydraulic Reservoirs (Refer to the Tables)
(1) Remove the hand pump lever 3270GM from the service panel
of the Yellow hydraulic system.
(2) On the service panel of the Green hydraulic system, connect
the hand pump lever 3270GM to the shaft of the hand pump
1009GM.
(3) Remove the flexible hose 1699GM from the service panel
compartment of the Green hydraulic system.
(4) Remove the blanking cap and connect the flexible hose to the
fill valve 1698GM. Put the other end in the CONTAINER -
HYDRAULIC FLUID RESISTANT with the Phosphate Ester
Hydraulic Fluid-General Power - - (Material Ref. 02ABA1).

NOTE: Do not use the Phosphate Ester Hydraulic Fluid-


General Power - - (Material Ref. 02ABA1) for

JCP Title: Fill the Hydraulic Fluid CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 6 of 18
Reservoir with a Hand Pump PRINT DATE: Aug 21/2023
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Aug
JOB CARD
01/2023
AMM - ABQ - A318/A319/A320/A321 TASK:
12-12-29-611-001-A
12-12-29-03 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 12-12-29-611-001-A - Fill the Hydraulic Fluid Reservoir with a NONE
ALL Hand Pump

MECH. INSP.

outside air temperature on ground below -40 deg.C


(-40 deg.F).

NOTE: It is not permitted to use high-density fluid Skydrol


500B-4 for A320NEO family.

(5) Turn the selector 1134GQ to the position that is correct for the
system you will fill.
(6) Make sure that on the quantity indicator 1834GQ the colored
light of the related system comes on.
(7) Get the reservoir temperature using one of the methods:

(a) Read out reservoir temperature through ACMS RTM


(Real Time Monitoring) and use the related AIDS label
call-up:

1 For the reservoir of the Green hydraulic system


- 029/1/172/01/08,

2 For the reservoir of the Yellow hydraulic system


- 029/1/172/10/08,

3 For the reservoir of the Blue hydraulic system -


029/1/172/11/08.
Refer to Ref. AMM TASK 31-36-00-740-008 to
get access to the parameter call-up menus .
Ref. Fig. Example of the Label Call Up
Decoding

(b) As an alternative to previous method, use the


THERMOMETER-INFRARED to record the hydraulic
fluid temperature.

NOTE: Measure the temperature on the lower part


of the reservoir in the range of the fluid level.

JCP Title: Fill the Hydraulic Fluid CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 7 of 18
Reservoir with a Hand Pump PRINT DATE: Aug 21/2023
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Aug
JOB CARD
01/2023
AMM - ABQ - A318/A319/A320/A321 TASK:
12-12-29-611-001-A
12-12-29-03 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 12-12-29-611-001-A - Fill the Hydraulic Fluid Reservoir with a NONE
ALL Hand Pump

MECH. INSP.

(c) As different alternative use the OAT (Outside Air


Temperature), if the aircraft was parked for last 3h
before servicing.

(8) Fill the hydraulic reservoir:

CAUTION: MAKE SURE THAT YOU DO NOT PUT TOO


MUCH FLUID IN THE RESERVOIR. IF THE
RESERVOIR IS TOO FULL, YOU CANNOT
PRESSURIZE IT SUFFICIENTLY. LOW AIR
PRESSURE CAN CAUSE THE MESSAGE
"RSVR LO AIR PR" TO SHOW IN FLIGHT
ON THE UPPER AND LOWER ECAM
DISPLAY UNITS.
(a) Operate the hand pump 1009GM.

(b) Monitor the increase of the fluid level of the related


system on the quantity indicator and do these steps:

1 Stop the flow of the hydraulic fluid when the


pointer is almost to the fill level given in the
table 2 (HYDRAULIC RESERVOIR FILLING
CAPACITIES).

2 Slowly continue to fill again, until the pointer


shows almost to the fill level given in the table 2
(HYDRAULIC RESERVOIR FILLING
CAPACITIES).

NOTE: Each open MLG door decreases the


volume in the green reservoir by
0.25 l (0.0660 USgal).

NOTE: Each open cargo door decreases


the volume in the yellow reservoir by
0.2 l (0.0528 USgal).

JCP Title: Fill the Hydraulic Fluid CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 8 of 18
Reservoir with a Hand Pump PRINT DATE: Aug 21/2023
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Aug
JOB CARD
01/2023
AMM - ABQ - A318/A319/A320/A321 TASK:
12-12-29-611-001-A
12-12-29-03 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 12-12-29-611-001-A - Fill the Hydraulic Fluid Reservoir with a NONE
ALL Hand Pump

MECH. INSP.

NOTE: After servicing of the reservoir with


the temperature adjustment
instruction, the cockpit reservoir
filling level is permitted to be above
the normal filling range, if the
reservoir gauge on the ground
service panel is in permitted range.

NOTE: The temperature of the hydraulic


fluid can change when you use
different method of measurement.
The differences agree with the
tolerance.

HYDRAULIC RESERVOIR CAPACITIES

SYSTEM/ QUANTITY QUANTITY


REMARKS
RESERVOIR LITERS US GAL
GREEN At 20.0 deg.C
SYSTEM (68 deg.F).
Total 23 6.1
Capacity
Max. 18 4.8
Capacity
shown on
the Gage
Fill Level 14 3.7 See the table
-
HYDRAULIC
RESERVOIR
FILLING
CAPACITIES.
Low Level 3 0.8
Warning

JCP Title: Fill the Hydraulic Fluid CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 9 of 18
Reservoir with a Hand Pump PRINT DATE: Aug 21/2023
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Aug
JOB CARD
01/2023
AMM - ABQ - A318/A319/A320/A321 TASK:
12-12-29-611-001-A
12-12-29-03 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 12-12-29-611-001-A - Fill the Hydraulic Fluid Reservoir with a NONE
ALL Hand Pump

MECH. INSP.

SYSTEM/ QUANTITY QUANTITY


REMARKS
RESERVOIR LITERS US GAL
BLUE At 20.0 deg.C
SYSTEM (68 deg.F).
Total 10 2.6
Capacity
Max. 8 2.1
Capacity
shown on
the Gage
Fill Level 6 1.6 See the table
-
HYDRAULIC
RESERVOIR
FILLING
CAPACITIES.
Low Level 2 0.5
Warning
YELLOW At 20.0 deg.C
SYSTEM (68 deg.F).
With the
normal
nitrogen
precharging
pressure in
the brake
accumulator
2582GM and
the auxiliary
brake system
pressurized.
Total 20 5.3
Capacity

JCP Title: Fill the Hydraulic Fluid CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 10 of 18
Reservoir with a Hand Pump PRINT DATE: Aug 21/2023
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Aug
JOB CARD
01/2023
AMM - ABQ - A318/A319/A320/A321 TASK:
12-12-29-611-001-A
12-12-29-03 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 12-12-29-611-001-A - Fill the Hydraulic Fluid Reservoir with a NONE
ALL Hand Pump

MECH. INSP.

SYSTEM/ QUANTITY QUANTITY


REMARKS
RESERVOIR LITERS US GAL
Max. 18 4.8
Capacity
shown on
the Gage
Fill Level 12 3.2 See the table
-
HYDRAULIC
RESERVOIR
FILLING
CAPACITIES.
Low Level 3 0.8
Warning

HYDRAULIC RESERVOIR FILLING


CAPACITIES

RESERVOIR
SYSTEM/ QUANTITY QUANTITY
TEMPERATURE
RESERVOIR LITERS US GAL
(deg.C/deg.F)
GREEN -20 deg.C (-4 12.00 3.2
SYSTEM deg.F) or less
-10 deg.C (14 12.50 3.3
deg.F)
0 deg.C (32 13.00 3.4
deg.F)
10 deg.C (50 13.50 3.6
deg.F)
20 deg.C (68 14.00 3.7
deg.F)
30 deg.C (86 14.50 3.8
deg.F)

JCP Title: Fill the Hydraulic Fluid CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 11 of 18
Reservoir with a Hand Pump PRINT DATE: Aug 21/2023
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Aug
JOB CARD
01/2023
AMM - ABQ - A318/A319/A320/A321 TASK:
12-12-29-611-001-A
12-12-29-03 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 12-12-29-611-001-A - Fill the Hydraulic Fluid Reservoir with a NONE
ALL Hand Pump

MECH. INSP.

RESERVOIR
SYSTEM/ QUANTITY QUANTITY
TEMPERATURE
RESERVOIR LITERS US GAL
(deg.C/deg.F)
40 deg.C (104 15.00 4.0
deg.F)
50 deg.C (122 15.50 4.1
deg.F) or more
BLUE -20 deg.C (-4 5.25 1.4
SYSTEM deg.F) or less
-10 deg.C (14 5.50 1.5
deg.F)
0 deg.C (32 5.50 1.5
deg.F)
10 deg.C (50 5.75 1.5
deg.F)
20 deg.C (68 6.00 1.6
deg.F)
30 deg.C (86 6.25 1.7
deg.F)
40 deg.C (104 6.50 1.7
deg.F)
50 deg.C (122 6.50 1.7
deg.F) or more
YELLOW -20 deg.C (-4 11.00 2.9
SYSTEM deg.F) or less
-10 deg.C (14 11.25 3.0
deg.F)
0 deg.C (32 11.50 3.0
deg.F)
10 deg.C (50 11.75 3.1
deg.F)

JCP Title: Fill the Hydraulic Fluid CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 12 of 18
Reservoir with a Hand Pump PRINT DATE: Aug 21/2023
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Aug
JOB CARD
01/2023
AMM - ABQ - A318/A319/A320/A321 TASK:
12-12-29-611-001-A
12-12-29-03 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 12-12-29-611-001-A - Fill the Hydraulic Fluid Reservoir with a NONE
ALL Hand Pump

MECH. INSP.

RESERVOIR
SYSTEM/ QUANTITY QUANTITY
TEMPERATURE
RESERVOIR LITERS US GAL
(deg.C/deg.F)
20 deg.C (68 12.00 3.2
deg.F)
30 deg.C (86 12.25 3.2
deg.F)
40 deg.C (104 12.50 3.3
deg.F)
50 deg.C (122 12.75 3.4
deg.F) or more

3 After servicing of the reservoir, refer to previous


work step:
- The cockpit reservoir full level is
permitted to be above the normal full
limit, if the reservoir level has been
adjusted before or the reservoir gauge
on the ground service panel is
according to the table 2 (HYDRAULIC
RESERVOIR FILLING CAPACITIES).

(9) If a reservoir is filled too much, drain the unwanted hydraulic


fluid:
- For the reservoir of the Green hydraulic system Ref.
AMM TASK 29-10-00-680-001.
- For the reservoir of the Yellow hydraulic system Ref.
AMM TASK 29-10-00-680-002.
- For the reservoir of the Blue hydraulic system Ref.
AMM TASK 29-10-00-680-003.

(10) Turn the selector 1134GQ to the NEUTRAL position.


(11) Make sure that the colored light on the quantity indicator
1834GQ goes off.

JCP Title: Fill the Hydraulic Fluid CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 13 of 18
Reservoir with a Hand Pump PRINT DATE: Aug 21/2023
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Aug
JOB CARD
01/2023
AMM - ABQ - A318/A319/A320/A321 TASK:
12-12-29-611-001-A
12-12-29-03 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 12-12-29-611-001-A - Fill the Hydraulic Fluid Reservoir with a NONE
ALL Hand Pump

MECH. INSP.

(12) Remove the flexible hose and install the blanking cap on the
pump.
(13) Put the flexible hose back in position in the service panel
compartment of the Green hydraulic system.
(14) Remove the hand pump lever 3270GM from the hand pump
1009GM. Then put the hand pump lever in position on the
service panel of the Yellow hydraulic system.
(15) If you filled the hydraulic reservoir after:
- Maintenance
- Removal/installation of hydraulic components
- Hydraulic fluid low level (loss of the hydraulic system)
- High loss of hydraulic fluid:

(a) Use the related bleeding procedure as follows:


- For the reservoir of the Green hydraulic system
Ref. AMM TASK 29-00-00-870-003
- For the reservoir of the Yellow hydraulic system
Ref. AMM TASK 29-00-00-870-007
- For the reservoir of the Blue hydraulic system
Ref. AMM TASK 29-00-00-870-008 and Ref.
AMM TASK 29-00-00-870-009.

5. Close-up

SUBTASK 12-12-29-410-054-A
A. Close Access
(1) Make sure that the work area is clean and clear of tools and
other items.
(2) Close the access panels 197CB, 198CB and if necessary
197EB.

SUBTASK 12-12-29-860-050-A
B. Put the aircraft back to its initial configuration.

JCP Title: Fill the Hydraulic Fluid CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 14 of 18
Reservoir with a Hand Pump PRINT DATE: Aug 21/2023
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Aug
JOB CARD
01/2023
AMM - ABQ - A318/A319/A320/A321 TASK:
12-12-29-611-001-A
12-12-29-03 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 12-12-29-611-001-A - Fill the Hydraulic Fluid Reservoir with a NONE
ALL Hand Pump

MECH. INSP.

(1) De-energize the aircraft electrical circuits Ref. AMM TASK


24-41-00-862-002.
(2) Remove the WARNING NOTICE(S).
(3) Remove the access platform(s).

JCP Title: Fill the Hydraulic Fluid CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 15 of 18
Reservoir with a Hand Pump PRINT DATE: Aug 21/2023
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Aug
JOB CARD
01/2023
AMM - ABQ - A318/A319/A320/A321 TASK:
12-12-29-611-001-A
12-12-29-03 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 12-12-29-611-001-A - Fill the Hydraulic Fluid Reservoir with a NONE
ALL Hand Pump

MECH. INSP.

B
A

Figure 12-12-29-991-00100-00-A (SHEET 1) - Ground Service Panel of the Green


Hydraulic System

JCP Title: Fill the Hydraulic Fluid CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 16 of 18
Reservoir with a Hand Pump PRINT DATE: Aug 21/2023
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Aug
JOB CARD
01/2023
AMM - ABQ - A318/A319/A320/A321 TASK:
12-12-29-611-001-A
12-12-29-03 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 12-12-29-611-001-A - Fill the Hydraulic Fluid Reservoir with a NONE
ALL Hand Pump

MECH. INSP.

** ON A/C FSN ALL

JCP Title: Fill the Hydraulic Fluid CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 17 of 18
Reservoir with a Hand Pump PRINT DATE: Aug 21/2023
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE
REV DATE: Aug
JOB CARD
01/2023
AMM - ABQ - A318/A319/A320/A321 TASK:
12-12-29-611-001-A
12-12-29-03 CONF 00
Tail Number - MSN - TITLE:
MPD TASK:
FSN: 12-12-29-611-001-A - Fill the Hydraulic Fluid Reservoir with a NONE
ALL Hand Pump

MECH. INSP.

A I DS : L ABEL CAL L - UP 1 / 8
EQ SYS L A B SD I DATAB I TS
_ 0 2 9 1 1 7 2 0 1 0 8
1 7 2 0 1 3 8
SSM: 1 1 0 D ATAB I TS 2 8 - 1 1 :
0 0 1 0 0 1 1 0 0 0 0 0 0 0 0 0 0 0

EQ SYS L AB SD I DATA B I T S
_ 0 2 9 1 1 7 2 1 0 0 8
1 7 2 1 0 4 1
SSM: 1 1 0 DATAB I TS 2 8 - 1 1 :
0 0 1 0 1 0 0 1 0 0 0 0 0 0 0 0 0 0
<RE TURN PR I NT *

Figure 12-12-29-991-00200-00-A (SHEET 1) - Example of the Label Call Up Decoding

** ON A/C FSN ALL


© *** END OF CARD ***

JCP Title: Fill the Hydraulic Fluid CERTIFICATE OF TASK / INSPECTION COMPLETION: Page 18 of 18
Reservoir with a Hand Pump PRINT DATE: Aug 21/2023
CERTIFIES THAT THE TASK / INSPECTION HAS BEEN
COMPLETED TO THE REQUIRED STANDARD AND SUPPORTS
THE FINAL MAINTENANCE RELEASE / CERTIFICATE OF
RELEASE TO SERVICE

You might also like