BILL OF QUANTITY

BUILDING : Additional of new genset foundation & cable trench


LOCATION : TARJUOWON MILL
DRAWING NO. :

QUANTITY
NO WORK BREAKDOWN STRUCTURE UNIT

Estimation

1 New genset foundation (Caterpillar) Unit 1,00


Demolishing existing concrete m2 1,13
Soil Excavation m3 14,91
Excess Soil Disposal m3 17,90
3
Sand Pile Work m 1,80
Plastic Coating m2 11,28
Formwork (Foundation) m2 10,92
Reinforcement
Rebar D 13 mm kg 404,50
Concrete (f'c 20 MPa) m3 7,38
Asphalt Aplication m3 0,06
3
Sand Gravel Pile Work m 7,72
2 New cable trench (Caterpillar) Lot 1,00
2
Demolishing tiles & existing concrete m 0,32
3
Soil excavation m 1,60
Sand backfill m3 0,32
Reinforcement of floor (D6) kg 13,06
3
Reconcrete 20 Mpa m 0,32
Tiles installation m2 3,20
3
Removal of excess soil m 1,92
3 New cable trench (Old Genset) Lot 1,00
Demolishing tiles & existing concrete m2 0,48
Soil excavation m3 2,40
3
Sand backfill m 0,48
Reinforcement of floor (D6) kg 8,70
3
Reconcrete 20 MPa m 0,48
2
Tiles installation m 4,80
Removal of excess soil m3 2,88
TRJM‐List of materials
Project : Additional of genset foundation & cable trench

No. Materials Unit Qtty Remarks


1 Cement Sak 58
2 Sand m3 7
3 Gravel m3 10
4 D6 pcs 10 To substitute wiremesh M6
5 D13 pcs 39
6 Tiles box 8
7 Plywood pcs 4
8 Plank (1x2") pcs 9
9 Plank (2x4") pcs 7
10 Plastic sheet m2 12
11 Asphalt m3 0,1