[M.4] Materials Reuse [M.5] Existing Structure Reuse [M.6] Design for
Results
Calculator Calculator Disassembly Calculator
Performance 2
Indicator(s)
Responsibly sourced
materials (X) Level
X=0 0
X=1 1
X=2 2
X=3 3
Criterion Level 2
Incentive Score (%) 0.67%
GLOBAL SUSTAINABILITY ASSESSMENT SYSTEM
Legend
User Input
Reference Information
Calculated Values
Fixed Values
Material Cost
Material Type
(currency unit)
DIVISION 03 Concrete
03 21 00 Reinforcement Bars 54,501,607
03 22 00 Fabric and Grid Reinforcing
03 25 00 Composite Reinforcing
03 30 00 Cast-in-Place Concrete 76,842,357
03 33 16 Lightweight Architectural Concrete
03 37 00 Specialty Placed Concrete
03 38 00 Post-Tensioned Concrete
03 41 00 Precast Structural Concrete
03 45 00 Precast Architectural Concrete 9,820,109
03 49 00 Glass-Fiber-Reinforced Concrete
03 52 16 Lightweight Insulating Concrete
03 53 00 Concrete Topping
03 61 00 Cementitious Grouting
03 63 00 Epoxy Grouting
Total Cost of
Material Division Materials per
Division
DIVISION 03 Concrete 141,164,073
DIVISION 04 Masonry 49,714,303
DIVISION 05 Metals 77,333,362
DIVISION 06 Wood, Plastics, & Composites 36,825,411
DIVISION 07 Thermal & Moisture 72,423,305
DIVISION 08 Openings 19,640,218
DIVISION 09 Finishes 86,650,189
DIVISION 10 Specialties 0
DIVISION 31 Earthwork 0
DIVISION 32 Exterior Improvements 20,189,654
Others (non - Electrical, Mechanical or Plumbing) 11,101,674
Electrical, Mechanical and Plumbing 97,870,249
Total Cost of Materials 612,912,437
Instructions
Inputs
¤Materials Inputs
• Input in this section the materials costs that are going to be considered in the different materials calculators as per the
CSI materials classification.
• If any of the materials to be considered is not in the list, use one of the blank lines within the corresponding Division.
• This section is also used to calculate the Total Cost of Materials for the development. In order to do so, use the ‘Not
broken-down materials’ lines at the bottom of each Division and the Total Cost of MEP line. Ensure that after populating
this section, the calculated Total Cost of Materials at the bottom matches the one in the BOQ of the project.
Calculations
¤Materials Division Calculations
• Sub-total Cost of Materials per Division = sum of the Costs of Materials per Division, including the lump sums (Not
Broken-Down Materials).
GLOBAL SUSTAINABILITY ASSESSMENT SYSTEM
Legend
User Input
Reference Information
Calculated Values
Fixed Values
Cost of Local
Description of Locally Manufactured/Assembled Material Cost in Percentage of Local Content in currency
Material Currency Unit Content Factor (f) unit
(c) (c*f)
Summary
Percentage of
Local Content Cost Availability Fraction
in Major for Minor
Construction Construction
Materials (a) Materials (b)
Weight 2 1
Instructions
General
• Determine the specifications and bill of quantities of the construction materials and products.
• Determine the specified locally sourced construction materials and products.
• Determine from the material data sheets the percentage of the local content of the specified locally sourced
construction materials and products.
• Determine from the bill of quantities the itemized cost of each material and the total cost of the construction materials.
• Prepare the descriptions of the construction materials following the latest Construction Specification Institute (CSI)
MasterFormat and use a uniform currency for costings and pricings.
• Input the data into the calculator of M.1 Locally Sourced Materials to determine the percentages of the local content
cost in major construction materials and the availability fraction for minor construction materials.
• Prepare all applicable documentation.
Inputs
¤Part 1 – Major Construction Materials Inputs
• Input the descriptions of the locally manufactured or assembled major construction materials.
• Input the costs of the materials.
• Select from the pulldown menu the percent of local content or “Locally Assembled” in case the local content is 0% but
the material is assembled in the country.
¤Part 2 – Minor Construction Materials Inputs
• Input the descriptions of the locally manufactured or assembled minor construction materials.
• Select from the pulldown menu the percent of local content or “Locally Assembled” in case the local content is 0% but
the material is assembled in the country.
Calculations
¤Part 1 – Major Construction Materials Calculations
• Local content factor = assigned value based on the selected percent of local content of the major construction material.
• Cost of local content = calculated value based on the cost of material and the local content factor.
• Total cost of the local content = sum of the local content costs of the major construction materials.
• Total cost of construction materials = sum of the sub-total costs and lump sum cost of the construction materials.
• Percent of the local content cost = calculated value based on the total cost of the local content over the total cost of
the construction materials.
¤Part 2 – Minor Construction Materials Calculations
• Availability fraction = calculated value based on the local content factor of minor construction material.
• Total availability fraction = sum of the availability fraction of all minor construction materials.
Summary Calculations
• Achieved values = results of Part 1 and Part 2 calculations.
• Maximum targets = fixed values assigned for the calculations of the percentages of the local content cost in major
construction materials and availability fraction for minor construction materials.
• Weights = fixed values assigned to give relative importance for the calculations of local content cost and availability
fraction.
• Weighted percentage of the local content cost = calculated value based on the achieved value, maximum target, and
the assigned weight for major construction materials.
• Weighted percentage of the availability fraction = calculated value based on the achieved value, maximum target, and
the assigned weight for minor construction materials.
• (X) = sum of the percentages of the local content cost in major construction materials and the availability fraction of
minor construction materials.
• M.1 criterion level = the generated criterion level for M.1 Locally Sourced Materials based on the specified range from
the criterion levels.
GLOBAL SUSTAINABILITY ASSESSMENT SYSTEM
Legend
User Input
Reference Information
Computed Values
Constants
Locally Sourced
Material Cost
Material Type Source Factor Material Cost
(currency unit)
(Cost X Factor)
DIVISION 03 Concrete
03 21 00 Reinforcement Bars 54,501,607 Locally Manufactured with Local materials 1.00 54,501,607
03 22 00 Fabric and Grid Reinforcing - 0.00 0
03 25 00 Composite Reinforcing - 0.00 0
03 30 00 Cast-in-Place Concrete 76,842,357 Locally Manufactured with External materials 0.70 53,789,650
03 33 16 Lightweight Architectural Concrete - 0.00 0
03 37 00 Specialty Placed Concrete - 0.00 0
03 38 00 Post-Tensioned Concrete - 0.00 0
03 41 00 Precast Structural Concrete - 0.00 0
03 45 00 Precast Architectural Concrete 9,820,109 0.00 0
03 49 00 Glass-Fiber-Reinforced Concrete - 0.00 0
03 52 16 Lightweight Insulating Concrete - 0.00 0
03 53 00 Concrete Topping - 0.00 0
03 61 00 Cementitious Grouting - 0.00 0
03 63 00 Epoxy Grouting - 0.00 0
- 0.00 0
- 0.00 0
- 0.00 0
- 0.00 0
- 0.00 0
- 0.00 0
- 0.00 0
DIVISION 04 Masonry
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
04 21 13 Brick Masonry - 0.00 0
04 21 29 Terra Cotta Masonry - 0.00 0
04 22 00 Concrete Unit Masonry 49,714,303 0.00 0
04 43 00 Stone Masonry - 0.00 0
DIVISION 05 Metals
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
05 12 00 Structural Steel Framing 17,062,440 0.00 0
05 14 00 Structural Aluminum Framing - 0.00 0
05 16 00 Structural Cabling - 0.00 0
05 21 00 Steel Joist Framing - 0.00 0
05 31 00 Steel Decking - 0.00 0
05 51 00 Metal Stairs - 0.00 0
05 52 00 Metal Railings 32,038,107 0.00 0
DIVISION 06 Wood, Plastics, & Composites
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
DIVISION 07 Thermal & Moisture
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
07 12 13 Built-Up Asphalt Waterproofing - 0.00 0
07 13 00 Sheet Waterproofing 60,148,169 0.00 0
07 14 00 Fluid-Applied Waterproofing - 0.00 0
07 17 00 Bentonite Waterproofing - 0.00 0
DIVISION 08 Openings
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! Locally Manufactured with Local materials 1.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
08 12 00 Metal Frames - 0.00 0
08 13 00 Metal Doors 14,730,163 0.00 0
08 14 00 Wood Doors - 0.00 0
08 31 13 Access Doors and Frames - 0.00 0
08 31 16 Access Panels and Frames - 0.00 0
08 32 00 Sliding Glass Doors - 0.00 0
08 33 16 Coiling Counter Grilles - 0.00 0
08 33 23 Overhead Coiling Doors - 0.00 0
08 33 43 Overhead Coiling Smoke Curtains - 0.00 0
08 34 00 Special Function Doors - 0.00 0
08 42 13 Aluminum-Framed Entrances - 0.00 0
08 42 26 All-Glass Entrances - 0.00 0
08 42 29.23 Sliding Automatic Entrances - 0.00 0
08 43 00 Storefronts - 0.00 0
08 44 13 Glazed Aluminum Curtain Walls - 0.00 0
08 44 26 Structural Glass Curtain Walls - 0.00 0
DIVISION 09 Finishes
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
09 21 16 Gypsum Board Assemblies 15,129,106 0.00 0
09 23 00 Gypsum Plastering - 0.00 0
09 24 00 Cement Plastering - 0.00 0
09 25 13 Acrylic Plastering - 0.00 0
09 27 13 Glass Fiber Reinforced Gypsum - 0.00 0
09 30 13 Ceramic Tiling 5,603,600 0.00 0
09 51 13 Acoustical Panel Ceilings - 0.00 0
09 51 33 Acoustical Metal Ceilings - 0.00 0
09 54 23 Linear Metal Ceilings - 0.00 0
09 54 43 Stretched-Fabric Ceiling - 0.00 0
09 63 40 Stone Flooring 5,892,065 0.00 0
09 65 13 Resilient Base - 0.00 0
09 65 36 Static Control Resilient Flooring - 0.00 0
09 67 23 Resinous Flooring - 0.00 0
09 68 16 Sheet Carpeting 1,718,519 0.00 0
DIVISION 10 Specialties
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
DIVISION 31 Earthwork
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
DIVISION 32 Exterior Improvements
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
Others (non - Electrical, Mechanical or Plumbing)
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
#VALUE! #VALUE! #VALUE! 0.00 #VALUE!
Summary
Total Cost of
Locally Sourced
Material Division Materials per
Material Cost
Division
#VALUE! #VALUE! 108,291,257
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! -
#VALUE! #VALUE! Total Cost of Locally Sourced Materials #VALUE!
M.1 - Performance Indicator #VALUE!
INSTRUCTIONS
MEASUREMENT
The calculator computes the criterion score based on the percentage of Locally sourced materials cost to the total project's material cost.
USER INPUT
Source: Select the source of the material and its raw materials. Select either "Locally manufactured with Local materials", "Locally manufactured with External
materials" or Leave it blank if imported materials.
REFERENCE INFORMATION
Material Type: Materials as entered in Materials - Input Sheet and as per the CSI MasterFormat 2016.
Material Cost (currency unit): Material Cost as entered in Materials - Input Sheet.
GIVEN DATA
Level: Levels of -1 to 3 are associated with where the performance indicator falls within a pre-defined range.
COMPUTED VALUES
Total Cost of Locally Sourced Materials =Sum(Locally Sourced Material Cost)
Performance Indicator = (Total Cost of Locally Sourced Materials / Total Cost of Materials)
Projected Criterion Level = Based on the performance indicator value achieved by the project, a final level is assigned for the criterion.
GLOBAL SUSTAINABILITY ASSESSMENT SYSTEM
Legend
User Input
Reference Information
Calculated Values
Fixed Values
Material Cost
Description of Major Materials with Eco-Labelling Eco-Label (currency unit)
-
-
-
-
-
-
-
-
Availability Fraction of Eco-Labelled Materials (b) -
Summary
Weight 1 2
Inputs
¤Part 1 – Major Construction Materials Inputs
• Input the descriptions of the major construction materials with eco-labeling (QM certificates). Include in the
descriptions of the name of the manufacturer of the supplied materials and products.
• Input the costs of the materials.
• Select from the pulldown menu the QM certificates of the eco-labeled major construction materials.
¤Part 2 – Minor Construction Materials Inputs
• Input the descriptions of the minor construction materials with eco-labeling (QM certificates).
• Select from the pulldown menu the QM certificates of the eco-labeled specialty materials.
• Extended List of eco-labeled materials. In case there are more than four eco-labeled minor materials, enter them in
this list to achieve incentive score.
Calculations
¤Part 1 – Major Construction Materials Calculations
• Total cost of major construction materials with eco-labeling = sum of the itemized major construction materials with
eco-labeling.
• Total cost of construction materials = sum of the sub-total costs and lump sum cost of construction materials.
• Percentage of the cost of major materials with eco-labeling = calculated value based on the total cost of major
construction materials with eco-labeling over the total cost of the materials for the development.
¤Part 2 – Minor Construction Materials Calculations
• Availability fraction = calculated value based on the QM certificate of minor construction materials.
• Total availability fraction = sum of the availability fraction of all minor construction materials.
• Availability fraction of extended list (for incentive weight) = sum of the availability fraction of incentivized minor
construction materials.
Summary Calculations
• Achieved values = results of Part 1 and Part 2 calculations.
• Maximum targets = fixed values assigned for the calculations of the percentages of the cost of major construction
materials with eco-labeling and availability fraction for minor construction materials.
• Weights = fixed values assigned to give relative importance for the calculations of cost of major construction materials
with eco-labeling and availability fraction.
• Weighted percentage cost of major construction materials with eco-labeling = calculated value based on the achieved
value, maximum target, and the assigned weight for major construction materials.
• Weighted percentage of the availability fraction = calculated value based on the achieved value, maximum target, and
the assigned weight for minor construction materials.
• (X) Indicator = sum of the percentages of cost of major materials with eco-labeling and the availability fraction of eco-
labeled materials plus incentive.
• Incentive score (%) = calculated value based on the availability fraction of the eco-labeled materials in the extended
list.
• M.2 criterion level = the generated criterion level for M.2 Materials Eco-Labeling based on the specified range from the
criterion levels.
GLOBAL SUSTAINABILITY ASSESSMENT SYSTEM
Legend
User Input
Reference Information
Calculated Values
Fixed Values
Total Cost of
Total Cost of
Material Division Materials per
Recycled Content
Division
DIVISION 03 Concrete 141,164,073 15,636,069
DIVISION 04 Masonry 49,714,303 4,971,430
DIVISION 05 Metals 77,333,362 42,815,064
DIVISION 06 Wood, Plastics, & Composites 36,825,411 0
DIVISION 07 Thermal & Moisture 72,423,305 8,469,844
DIVISION 08 Openings 19,640,218 7,365,082
DIVISION 09 Finishes 86,650,189 13,134,335
DIVISION 10 Specialties - 0
DIVISION 31 Earthwork - 0
DIVISION 32 Exterior Improvements 20,189,654 1,135,668
Others (non - Electrical, Mechanical or Plumbing) 11,101,674 0
Total Cost of Materials (Excluding MEP) 515,042,188 93,527,491
M.3 - Performance Indicator (X) 18.16%
Instructions
General
• For this criterion, use the unified Materials Inputs tab in the calculator to list all the specified construction materials
and cost estimates. The list follows the format of the Construction Specification Institute (CSI) MasterFormat 2016. The
Materials Inputs includes cells for inputting all other materials that are not listed by default in the calculator’s materials
division numbers.
• Determine the specified materials with recycled content.
• Determine from the material data sheets the percentage of recycled content in the materials.
• Determine from the bill of quantities and specification, the percentage of the recycled content weight to the total
material weight.
• Prepare all applicable documentation.
Inputs
¤Recycled Content Inputs
• Input the percentage of recycled content of the construction materials.
Calculations
¤Recycled Content Calculations
• Descriptions and costs of construction materials with recycled content = referenced from materials input section.
• Cost of recycled content = calculated value based from the cost of material with recycled content and the percentage
of cost of the recycled content.
• Sub-total cost per division = sum of the breakdown of costs of materials per division.
• Total cost of recycled content per division = sum of the sub-total cost of recycled content per division.
• Total cost of materials (excluding MEP) = sum of the sub-total costs excluding MEP.
• (X) Indicator = calculated value based on the percentage of total cost of recycled content over the total cost of
materials, excluding MEP.
• M.3 criterion level = the generated criterion level for M.3 Recycled Content of materials based on the specified range
from the criterion levels.
GLOBAL SUSTAINABILITY ASSESSMENT SYSTEM
Legend
User Input
Reference Information
Calculated Values
Fixed Values
Reused Material
Material Cost
Material Type Value
(currency unit)
(currency unit)
DIVISION 03 Concrete
03 21 00 Reinforcement Bars 54,501,607
03 22 00 Fabric and Grid Reinforcing -
03 25 00 Composite Reinforcing -
03 30 00 Cast-in-Place Concrete 76,842,357
03 33 16 Lightweight Architectural Concrete -
03 37 00 Specialty Placed Concrete -
03 38 00 Post-Tensioned Concrete -
03 41 00 Precast Structural Concrete -
03 45 00 Precast Architectural Concrete 9,820,109
03 49 00 Glass-Fiber-Reinforced Concrete -
03 52 16 Lightweight Insulating Concrete -
03 53 00 Concrete Topping -
03 61 00 Cementitious Grouting -
03 63 00 Epoxy Grouting -
-
-
-
-
-
-
-
-
-
-
Not broken down Materials -
DIVISION 04 Masonry
04 21 13 Brick Masonry -
04 21 29 Terra Cotta Masonry -
04 22 00 Concrete Unit Masonry 49,714,303
04 43 00 Stone Masonry -
-
-
-
-
-
-
Not broken down Materials -
DIVISION 05 Metals
05 12 00 Structural Steel Framing 17,062,440
05 14 00 Structural Aluminum Framing -
05 16 00 Structural Cabling -
05 21 00 Steel Joist Framing -
05 31 00 Steel Decking -
05 51 00 Metal Stairs -
05 52 00 Metal Railings 32,038,107
05 53 00 Metal Gratings -
05 54 00 Metal Floor Plates -
05 70 00 Decorative Metal -
Metal Fabrication 28,232,815
-
-
-
-
-
-
-
-
Not broken down Materials -
DIVISION 06 Wood, Plastics, & Composites
06 11 00 Wood Framing -
06 15 00 Wood Decking -
06 40 00 Architectural Woodwork 36,825,411
06 43 13 Wood Stairs -
06 43 16 Wood Railings -
06 48 13 Exterior Wood Door Frames -
06 48 16 Interior Wood Door Frames -
06 81 13 Glass-Fiber-Reinforced Plastic Railings -
06 42 00 Wood Paneling -
-
-
-
-
-
-
Not broken down Materials -
DIVISION 07 Thermal & Moisture
07 12 13 Built-Up Asphalt Waterproofing -
07 13 00 Sheet Waterproofing 60,148,169
07 14 00 Fluid-Applied Waterproofing -
07 17 00 Bentonite Waterproofing -
07 18 00 Traffic Coatings -
07 19 00 Water Repellents -
07 21 00 Thermal Insulation 12,275,136
07 32 00 Roof Tiles -
07 42 00 Wall Panels -
07 60 00 Flashing and Sheet Metal -
07 76 00 Roof Pavers -
07 81 00 Applied Fireproofing -
07 95 00 Expansion Control -
-
-
-
-
-
-
-
-
Not broken down Materials -
DIVISION 08 Openings
08 12 00 Metal Frames -
08 13 00 Metal Doors 14,730,163
08 14 00 Wood Doors -
08 31 13 Access Doors and Frames -
08 31 16 Access Panels and Frames -
08 32 00 Sliding Glass Doors -
08 33 16 Coiling Counter Grilles -
08 33 23 Overhead Coiling Doors -
08 33 43 Overhead Coiling Smoke Curtains -
08 34 00 Special Function Doors -
08 42 13 Aluminum-Framed Entrances -
08 42 26 All-Glass Entrances -
08 42 29.23 Sliding Automatic Entrances -
08 43 00 Storefronts -
08 44 13 Glazed Aluminum Curtain Walls -
08 44 26 Structural Glass Curtain Walls -
08 44 26.13 Glass Framed Point Supported Glass Curtain Walls -
08 45 00 Translucent Wall and Roof Assemblies -
08 50 00 Windows -
08 63 00 Metal-Framed Skylights -
08 80 00 Glazing -
08 91 00 Louvers 4,910,054
08 95 00 Vents -
-
-
-
-
-
-
-
-
-
-
-
-
Not broken down Materials -
DIVISION 09 Finishes
09 21 16 Gypsum Board Assemblies 15,129,106
09 23 00 Gypsum Plastering -
09 24 00 Cement Plastering -
09 25 13 Acrylic Plastering -
09 27 13 Glass Fiber Reinforced Gypsum -
09 30 13 Ceramic Tiling 5,603,600
09 51 13 Acoustical Panel Ceilings -
09 51 33 Acoustical Metal Ceilings -
09 54 23 Linear Metal Ceilings -
09 54 43 Stretched-Fabric Ceiling -
09 63 40 Stone Flooring 5,892,065
09 65 13 Resilient Base -
09 65 36 Static Control Resilient Flooring -
09 67 23 Resinous Flooring -
09 68 16 Sheet Carpeting 1,718,519
09 69 00 Access Flooring -
09 72 00 Wall Coverings -
09 73 00 Wall Carpeting -
09 74 00 Flexible Wood Sheets -
09 75 00 Stone Facing -
09 77 13 Stretched-Fabric Wall Systems -
09 83 13 Acoustic Wall Coating -
09 83 16 Acoustic Ceiling Coating -
09 84 13 Fixed Sound-Absorptive Panels -
09 84 16 Fixed Sound-Reflective Panels -
09 84 33 Sound-Absorbing Wall Units -
09 84 36 Sound-Absorbing Ceiling Units -
09 91 00 Painting 16,939,688
Concrete Flooring 14,361,910
Paver Flooring 8,592,596
Terrazo Flooring 2,455,027
Precast Concrete Floor 9,820,109
Epoxy Flooring 982,011
Vinyl Flooring 5,155,557
-
-
-
Not broken down Materials -
DIVISION 10 Specialties
10 14 53 Traffic Signage -
10 21 13 Toilet Compartments -
10 21 16 Shower and Dressing Compartments -
10 26 13 Corner Guards -
10 26 16 Bumper Guards -
10 28 13 Toilet Accessories -
10 28 16 Bath Accessories -
10 28 19 Tub and Shower Enclosures -
10 51 00 Lockers -
10 57 23 Closet and Utility Shelving -
10 57 36 Closet Doors -
10 71 13.19 Rolling Exterior Shutters -
10 73 16.23 Fabric Canopies -
10 82 13 Exterior Grilles and Screens -
-
-
-
-
-
-
-
-
-
-
Not broken down Materials -
DIVISION 31 Earthwork
31 23 23 Fill -
-
-
-
-
-
-
-
Not broken down Materials -
DIVISION 32 Exterior Improvements
32 11 00 Base Courses -
32 12 00 Flexible Paving -
32 13 13 Concrete Paving 12,618,534
32 14 00 Unit Paving -
32 14 13 Precast Concrete Unit Paving 7,571,120
32 32 13 Cast-in-Place Concrete Retaining Walls -
32 33 00 Site Furnishings -
32 90 00 Planting -
-
-
-
-
-
-
-
-
Not broken down Materials -
Others (non - Electrical, Mechanical or Plumbing)
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Not broken down Materials 11,101,674
Summary
Instructions
General
• For this criterion use the unified Materials Inputs tab in the calculator to list all the specified construction materials and
cost estimates. The list follows the format of the Construction Specification Institute (CSI) MasterFormat 2016. The
Materials Inputs includes cells for inputting all other materials that are not listed by default in the calculator’s materials
division numbers.
• Determine the specified reused materials.
• Determine the current economic value or market value of the reused materials.
• Input the data into the calculator of M.4 Materials Reuse to determine the percentage of reused materials over the
total material cost of the development (excluding MEP).
• Prepare all applicable documentation.
Inputs
¤Reused Material Value Inputs
• Input the current economic value or market value or contract value of the reused materials.
Calculations
¤Reused Material Value Calculations
• Sub-total cost of materials per division = sum of the breakdown of costs of construction materials.
• Total cost of materials (excluding MEP) = sum of the sub-total cost of materials per division excluding MEP.
• Sub-total value of reused materials per division = sum of the breakdown of reused material value.
• Total value of reused materials = sum of the sub-total value of reused materials per division excluding MEP.
• (X) Indicator = calculated value based on the percentage of reused materials over the total cost of materials (excluding
MEP).
• M.4 criterion level = the generated criterion level for M.4 Materials Reuse based on the specified range from the
criterion levels.
GLOBAL SUSTAINABILITY ASSESSMENT SYSTEM
Legend
User Input
Reference Information
Calculated Values
Fixed Values
Cost of Demolition
Cost as per Savings from
and New
Description of Major Structural Systems Design Reusing Structural
Construction
(Scenario 2) Sysems
(Scenario 1)
Foundations 0.00
Pillars 0.00
Slabs 0.00
Roof structure 0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Total Savings from 0.00
Reusing Existing Structure
Total Cost of Demolition and 0.00
New Construction (Scenario 1)
Percentage of Cost Savings 0.00%
- M5 - Performance Indicator (X)
Instructions
General
• Determine the specified existing structural elements.
• Determine the design cost and demolition and new construction cost of each existing structural element to be reused.
• Input the data into the calculator of M.5 Existing Structure Reuse to determine the percentage of total savings from
reusing existing structures.
• Prepare all applicable documentation.
Inputs
¤Inputs for Existing Structural Elements to be Reused
• Select from the pulldown menu if there is an existing structure on site or there was an existing structure and has
already been demolished.
• Input the descriptions of all the existing structural systems regardless if they are going to be reused or not. Structural
elements not in usable condition are excluded.
• Input the cost of demolition and new construction scenario.
• Input the cost of the structural systems per the design scenario.
Calculations
• Savings from reusing structural systems = the cost difference between the cost of demolition and new construction to
the cost per design.
• Total savings from reusing existing structure = sum of the breakdown of savings from reusing structural systems.
• Total costs of demolition and new construction = sum of the cost breakdowns of the demolition and new construction
works.
• (X) Indicator = calculated value based on the percentage of total savings from reusing existing structure over the total
costs of demolition and new construction works.
• (Y) = selected status of on-site structure whether existing/demolished or none.
• M.5 criterion level = the generated criterion level for M.5 Existing Structure Reuse based on the specified range from
the criterion levels.
GLOBAL SUSTAINABILITY ASSESSMENT SYSTEM
Legend
User Input
Reference Information
Computed Values
Constants
Cost Savings
Description of Major Structural Systems
(Currency Unit)
Full Structural System (of foundation, columns, beams and slabs)
Retaining Walls
Roof
INSTRUCTIONS
MEASUREMENT
The calculator computes the percentage of the structural systems that is reused. The cost of the
required and reused structural systems are determined by project documents. The calculator uses
these costs to compute the percentage of cost savings by the reused structural systems. The
criterion is assigned a final level based on the percentage of structural elements reused out of the
total amount of required structural elements. Projects which has no existing structure receive a
default score of 0.
USER INPUT
Description of Major Structural Systems: Enter the description of the reused structural system.
Single components such as beams or columns can participate in M.4 Material Reuse criterion, but
not in this criterion.
Cost Savings (Currency Unit): Enter the cost of the new structural system replaced by the reused
one.
Total Structural Systems Value (Currency Unit): Enter the estimated costs of the structural systems
in the project. Consider the cost of new structural systems replaced by the reused ones.
GIVEN DATA
Scoring: Levels from -1 to 3 are associated with a percent of structural elements reused.
COMPUTED VALUES
Percent of Major Structural Elements Reused (%) = Sum (Cost Savings of Structural Elements
Reused) / (Total Structural systems value)
Projected Criterion Level = Based on the total weighted value earned by the project, a final level is
assigned for the criterion.
GLOBAL SUSTAINABILITY ASSESSMENT SYSTEM
Legend
User Input
Reference Information
Calculated Values
Fixed Values
Cost of Materials
Material Cost Designed for
Material Type
(currency unit) Disassembly
(currency unit)
DIVISION 03 Concrete
03 21 00 Reinforcement Bars 54,501,607
03 22 00 Fabric and Grid Reinforcing -
03 25 00 Composite Reinforcing -
03 30 00 Cast-in-Place Concrete 76,842,357
03 33 16 Lightweight Architectural Concrete -
03 37 00 Specialty Placed Concrete -
03 38 00 Post-Tensioned Concrete -
03 41 00 Precast Structural Concrete -
03 45 00 Precast Architectural Concrete 9,820,109
03 49 00 Glass-Fiber-Reinforced Concrete -
03 52 16 Lightweight Insulating Concrete -
03 53 00 Concrete Topping -
03 61 00 Cementitious Grouting -
03 63 00 Epoxy Grouting -
-
-
-
-
-
-
-
-
-
-
Not broken down Materials -
DIVISION 04 Masonry
04 21 13 Brick Masonry -
04 21 29 Terra Cotta Masonry -
04 22 00 Concrete Unit Masonry 49,714,303
04 43 00 Stone Masonry -
-
-
-
-
-
-
Not broken down Materials -
DIVISION 05 Metals
05 12 00 Structural Steel Framing 17,062,440 13,649,952
05 14 00 Structural Aluminum Framing -
05 16 00 Structural Cabling -
05 21 00 Steel Joist Framing -
05 31 00 Steel Decking -
05 51 00 Metal Stairs -
05 52 00 Metal Railings 32,038,107 25,630,486
05 53 00 Metal Gratings -
05 54 00 Metal Floor Plates -
05 70 00 Decorative Metal -
Metal Fabrication 28,232,815 22,586,252
-
-
-
-
-
-
-
-
Not broken down Materials -
DIVISION 06 Wood, Plastics, & Composites
06 11 00 Wood Framing -
06 15 00 Wood Decking -
06 40 00 Architectural Woodwork 36,825,411 18,412,706
06 43 13 Wood Stairs -
06 43 16 Wood Railings -
06 48 13 Exterior Wood Door Frames -
06 48 16 Interior Wood Door Frames -
06 81 13 Glass-Fiber-Reinforced Plastic Railings -
06 42 00 Wood Paneling -
-
-
-
-
-
-
Not broken down Materials -
DIVISION 07 Thermal & Moisture
07 12 13 Built-Up Asphalt Waterproofing -
07 13 00 Sheet Waterproofing 60,148,169
07 14 00 Fluid-Applied Waterproofing -
07 17 00 Bentonite Waterproofing -
07 18 00 Traffic Coatings -
07 19 00 Water Repellents -
07 21 00 Thermal Insulation 12,275,136
07 32 00 Roof Tiles -
07 42 00 Wall Panels -
07 60 00 Flashing and Sheet Metal -
07 76 00 Roof Pavers -
07 81 00 Applied Fireproofing -
07 95 00 Expansion Control -
-
-
-
-
-
-
-
-
Not broken down Materials -
DIVISION 08 Openings
08 12 00 Metal Frames -
08 13 00 Metal Doors 14,730,163 11,784,131
08 14 00 Wood Doors -
08 31 13 Access Doors and Frames -
08 31 16 Access Panels and Frames -
08 32 00 Sliding Glass Doors -
08 33 16 Coiling Counter Grilles -
08 33 23 Overhead Coiling Doors -
08 33 43 Overhead Coiling Smoke Curtains -
08 34 00 Special Function Doors -
08 42 13 Aluminum-Framed Entrances -
08 42 26 All-Glass Entrances -
08 42 29.23 Sliding Automatic Entrances -
08 43 00 Storefronts -
08 44 13 Glazed Aluminum Curtain Walls -
08 44 26 Structural Glass Curtain Walls -
08 44 26.13 Glass Framed Point Supported Glass Curtain Walls -
08 45 00 Translucent Wall and Roof Assemblies -
08 50 00 Windows -
08 63 00 Metal-Framed Skylights -
08 80 00 Glazing -
08 91 00 Louvers 4,910,054 3,928,044
08 95 00 Vents -
-
-
-
-
-
-
-
-
-
-
-
-
Not broken down Materials -
DIVISION 09 Finishes
09 21 16 Gypsum Board Assemblies 15,129,106 7,564,553
09 23 00 Gypsum Plastering -
09 24 00 Cement Plastering -
09 25 13 Acrylic Plastering -
09 27 13 Glass Fiber Reinforced Gypsum -
09 30 13 Ceramic Tiling 5,603,600
09 51 13 Acoustical Panel Ceilings -
09 51 33 Acoustical Metal Ceilings -
09 54 23 Linear Metal Ceilings -
09 54 43 Stretched-Fabric Ceiling -
09 63 40 Stone Flooring 5,892,065
09 65 13 Resilient Base -
09 65 36 Static Control Resilient Flooring -
09 67 23 Resinous Flooring -
09 68 16 Sheet Carpeting 1,718,519
09 69 00 Access Flooring -
09 72 00 Wall Coverings -
09 73 00 Wall Carpeting -
09 74 00 Flexible Wood Sheets -
09 75 00 Stone Facing -
09 77 13 Stretched-Fabric Wall Systems -
09 83 13 Acoustic Wall Coating -
09 83 16 Acoustic Ceiling Coating -
09 84 13 Fixed Sound-Absorptive Panels -
09 84 16 Fixed Sound-Reflective Panels -
09 84 33 Sound-Absorbing Wall Units -
09 84 36 Sound-Absorbing Ceiling Units -
09 91 00 Painting 16,939,688
Concrete Flooring 14,361,910
Paver Flooring 8,592,596 6,874,077
Terrazo Flooring 2,455,027
Precast Concrete Floor 9,820,109
Epoxy Flooring 982,011
Vinyl Flooring 5,155,557
-
-
-
Not broken down Materials -
DIVISION 10 Specialties
10 14 53 Traffic Signage -
10 21 13 Toilet Compartments -
10 21 16 Shower and Dressing Compartments -
10 26 13 Corner Guards -
10 26 16 Bumper Guards -
10 28 13 Toilet Accessories -
10 28 16 Bath Accessories -
10 28 19 Tub and Shower Enclosures -
10 51 00 Lockers -
10 57 23 Closet and Utility Shelving -
10 57 36 Closet Doors -
10 71 13.19 Rolling Exterior Shutters -
10 73 16.23 Fabric Canopies -
10 82 13 Exterior Grilles and Screens -
-
-
-
-
-
-
-
-
-
-
Not broken down Materials -
DIVISION 31 Earthwork
31 23 23 Fill -
-
-
-
-
-
-
-
Not broken down Materials -
DIVISION 32 Exterior Improvements
32 11 00 Base Courses -
32 12 00 Flexible Paving -
32 13 13 Concrete Paving 12,618,534
32 14 00 Unit Paving -
32 14 13 Precast Concrete Unit Paving 7,571,120
32 32 13 Cast-in-Place Concrete Retaining Walls -
32 33 00 Site Furnishings -
32 90 00 Planting -
-
-
-
-
-
-
-
-
Not broken down Materials -
Others (non - Electrical, Mechanical or Plumbing)
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Not broken down Materials 11,101,674
Summary
Cost of Materials
Total Cost of Materials Designed for
Material Division
per Division Disassembly
(currency unit)
Inputs
¤Materials Designed for Disassembly Inputs
• Input the cost of materials designed for disassembly.
Calculations
¤Materials Designed for Disassembly Calculations
• Total cost of materials (excluding MEP and materials subject to wear & tear) = sum of the sub-total cost of materials per
division excluding MEP and materials subject to wear & tear.
• Sub-total cost of materials designed for disassembly per division = sum of the cost breakdown of materials designed for
disassembly.
• Total cost of materials designed for disassembly = sum of the sub-total costs of materials designed for disassembly per
division.
• (X) Indicator = calculated value based on the percentage of total cost of materials designed for disassembly over the
total cost of construction materials, excluding MEP and materials subject to wear & tear.
• M.6 criterion level = the generated criterion level for M.6 Design for Disassembly based on the specified range from the
criterion levels.
GLOBAL SUSTAINABILITY ASSESSMENT SYSTEM
Legend
User Input
Reference Information
Calculated Values
Fixed Values
Instructions
General
• Determine the specified responsibly sourced materials.
• Input the data into the calculator of M.7 Responsible Sourcing to determine the numbers of responsibly sourced
materials and the associated incentive score.
• Prepare all applicable documentation.
Inputs
¤Inputs for Responsibly Sourced Materials
• Input the descriptions of responsibly sourced materials with GSAS approved certificates.
• Input the title of the GSAS approved certificates of the responsibly sourced materials.
Calculations
• (X) Indicator = number of responsibly sourced materials.
• M.7 criterion level = the generated criterion level for M.7 Responsible Sourcing based on the specified range from the
criterion levels.
GLOBAL SUSTAINABILITY ASSESSMENT SYSTEM
Legend
User Input
Reference Information
Computed Values
Constants
INSTRUCTIONS
MEASUREMENT
All projects will complete the Responsible Sourcing of Materials - Input Sheet to determine the percent, by cost, of materials that can be traced through
the supply chain. Applicable materials include all primary building elements.
All projects will only consider materials permanently installed in the project. To ensure the selection of socially and environmentally conscious materials
that employ responsible practices throughout the supply chain, all materials must comply with the following standards, where applicable, and should
be accounted for in the calculator to qualify as responsibly sourced.
USER INPUT
Responsibly Sourced Material : Select "Yes" if the material is responsibly sourced. Select "Partial" if certain part of the material is responsibly sourced.
Cost of Responsibly Sourced part (currency unit): If part of the material is responsibly sourced, then enter the cost of the relevant part.
REFERENCE INFORMATION
Material Type: Materials as entered in Materials - Input Sheet and as per the CSI MasterFormat 2016.
Material Cost (currency unit): Material Cost as entered in Materials - Input Sheet.
GIVEN DATA
Level: Levels of -1 to 3 are associated with where the performance indicator falls within a pre-defined range.
COMPUTED VALUES
Total Cost of Responsibly Sourced Materials =Sum(Cost of Responsibly Sourced Material)
Performance Indicator = (Total Cost of Responsibly Sourced Materials / Total Cost of Materials)
Projected Criterion Level = Based on the performance indicator value achieved by the project, a final level is assigned for the criterion.