ESTIMATE
Project: PROPOSED 3RD FLOOR EXTENSION
RESIDENCE
Prepared by:
Prepared by:
PAINTING
1 LOT 80,000.00
80,000.00
ROOF DECK ADDITIONAL
STEEL WORKS
SUSPENDED SLAB
160 PCS. D10 gr40 TEMPERATURE & EXTRA BARS 35,040.00
18 KGS #16 TIE WIRE 1,530.00
BEAMS/ROOF BEAMS
90 PCS. D16 gr40 MAIN BARS 50,220.00
110 PCS. D10 gr40 STIRRUP 24,090.00
25 PCS. D12 gr40 WEB BARS 7,850.00
18 KGS #16 TIE WIRE 1,530.00
COLUMNS 1.2 meter high
40 PCS. D16 gr40 MAIN BARS 22,320.00
60 PCS. D10 gr40 LATERAL TIES 13,140.00
6 KGS #16 TIE WIRE 510.00
STEEL DECKING
58 SQ.M .8mm STEEL DECK 33,640.00
189,870.00
Prepared by:
PAINTING
1 LOT 80,000.00
80,000.00
SQ. MTS.
1 LOT ROOF FRAMING 240,000.00
240,000.00
Prepared by: