ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT

ARBAMINCH UNIVERSITY
ARBAMINCH INSTITUTE OF TECHNOLOGY
DEPARTEMENT OF CIVIL ENGINEERING
FIRST MONTH INTERNSHIP REPORT
ABUKELEMSIS CONDTRUCTION AND CONSULTING PLC.

2ND MONTH REPORT


FITSUM GIZAWE-RAMIT/682/09
MAY 2020
ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT

ARBAMINCH INSTITUTE OF TECHNOLOGY

Week No. 1 Date APRIL13 to APRIL 16

WEEK DAYS ACTIVITY


MONDAY  ERECTION OF SHEAR WALL
(APRIL 13) FORMWORK.
 CONCRETE FILL FOR SHEAR
WALL AND GRADE BEAM.

TUESDAY  PREPARE MESH AND PLACED ON


(APRIL 14) THE HARD CORE
 CONCRETE WORK FOR SEMI
BASEMENT SLAB

WENSDAY  SITE MOBILIZATION AND


(APRIL 15) CLEARING.
 REMOVAL OF FORM WORK FROM
SHEAR WALL.

THURSDAY  FIXING OF PROBS FOR GROUND


(APRIL 16) FLOOR SLAB
 BAR CUTTING,AND BENDING FOR
GROUND FLOOR SLAB

ABSTRACT FOR WEAK 1

 This week I was totally committed to the work of the site and the site
engineer intended to share his knowledge as he can. The tasks that we had
done in this weak are construction of formwork, placement of concrete for
shear wall and grade beam, fix the mesh on the hard core and concrete
work for semi basement slab.
 In addition to this site mobilization and clearing of waste material from the
site, removal of form work from shear wall and fixing of probs for ground
floor slab are some of the task that we had executed in this week.
 Bar cutting and bending was also done in this weak.
ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT

Pictorial presentation of site progress


Concrete fill for shear wall fix mesh on the hard core

Formwork removal from sw fixes prob for ground floor slab


ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT

ARBAMINCH INSTITUTE OF TECHNOLOGY

Week No.2 Date APRIL20 to APRIL 25

WEEKLY DAYS ACTIVITY


MONDAY  PREPARE TAKE OFF SHEET,BAR
(APRIL 20) SCHEDULE AND BOQ FOR
GROUND FLOOR

TUESDAY  CONSTRUCTION OF BOTTOM


(APRIL 21) SOFFIT AND SIDE BOARDFOR
GROUND FLOOR SLAB
 SOFFIT AND SIDE BOARD WORK
FOR STAIRE CASE.
WEDNESDAY  CONSTRUCTION OF BOTTOM
(APRIL 22) SOFFIT AND SIDE BOARDFOR
GROUND FLOOR SLAB
 REINFORCEMENT OF GROUND
FLOOR BEAM
THURSDAY  REINFORCEMENT OF GROUND
(APRIL 23) FLOOR SLAB
 EXCAVATION OF AXIS X3-X4
 PROVIDE WATER PROOF
 REINFORCEMENT OF SEMI
BASEMENT COLUMN

FRIDAY  CONSTRUCT MASON ON AXIS


(APRIL 24) X3-X4
 FORM WORK CONSTRUCTION FOR
AXIS X4 COLUMN
SATURDAY  CONCRETE FILL FOR AXIS X4
(APRIL 25) COLUMN
 CHECK THE NUMBER OF BAR
PROVIDEDE ON GROUND FLOOR
SLAB.
ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT

ABSTRACT FOR WEAK 2

 During this weak there was a lot of task that we had done in the site, such as
preparation of takeoff sheet, bar schedule and BOQ for ground floor slab, in the
other hand construction of bottom soffit and side board for ground floor slab and
stair case.
 Beside this reinforcement of ground floor beam, slab and stair case was
executed.to the next day of the week excavation of axis X3-X4 and provide water
proof and construction of mason was done.
 Eventually I was check the number of bar provided on ground floor slab and
beam.

PICTORIAL PRESENTATION OF SITE PROGRESS

BOTTOM SOFIT AND REINFORCEMENT OF GROUND FLOOR SLAB


ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT

SOFFIT WORK, FIXING SIDE BOARD AND REINFORCEMENT OF STAIR


ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT

EXCAVATION WORK OF AXIS X3-X4


ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT

ARBAMINCH INSTITUTE OF TECHNOLOGY

Week No.3 Date APRIL 27 to MAY 3

WEEKLY DAYS ACTIVITY


MONDAY  BACKFILL AND SOIL COMPACTION
(APRIL 27) ON AXIS X3-X4
 LEAN CONCRETE WORK AND
REINFORCEMENT OF GRADE BEAM
ON AXIS X3-X4
 ELECTRICAL AND SANITERY PIPE
INSTALETION.
TUESDAY  GRADE BEAM FORMWORK
(APRIL 28) CONSTRUCTION FOR AXIS X3-X4.
 CONCRETE FILL FORAXIS X3-X4
GRADE BEAM.

WEDNESDAY  REMOVAL OF FORMWORK FROM


(APRIL 29) AXIS X3-X4 GRADE BEAM
 DRESS THE HARD CORE ON THE
COMPACTED SOIL.
THURSDAY  CONCRETE FILL FOR GROUN
(APRIL 30) FLOOR SLAB FROM AXIS X1-X3
 MESH FIXING ON THE HARD CORE
 CONCRETE FILL IN AXIS X3-X4

FRIDAY  REINFORCEMENT WORK FOR


(MAY 1) GROUND FLOOR COLUMN.
 PROVIDE SPACER ON THE
COLUMN.

SATURDAY  CHECK THE NUMBER OF BAR


(MAY 2) PROVIDED ON THE COLUMN.
 FORMWORK CONSTRUCTIONFOR
GROUND FLOOR COLUMN.

SUNDAY  CONCRETE FILL FOR GROUND


(MAY 3) FLOOR COLUMN.
ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT

ABSTRACT FOR WEEK 3

 During this week the work progress in the site was very fast, and we had executed a lot of
task. The task that we had executed in this week was back filling of axis X3-X4, compact the
back filled soil and construct a grade beam on it.
 Installation of electrical and sanitary work.
 Dress the hard core and fixing mesh on the compacted soil, continually concrete fill for ground
floor slab and construction of column was also done in this week.

PICTORIAL PRESENTATION OF SITE PROGRESS

Installation of electrical and sanitary pipe reinforcement of grade beam


ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT

Formwork on axis X3-X4 grade beam Placement of hard core and fixing mesh

Concrete work for ground floor slab concrete fills for stair case

Reinforcement of ground floor column


ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT

Reinforcement of ground floor column

Erection of form work for ground floor column


ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT

ARBAMINCH INSTITUTE OF TECHNOLOGY

Week No.4 Date MAY 4 to MAY 9

WEEKLY DAYS ACTIVITY


MONDAY  REMOVAL OF FORMWORK FROM
(MAY 4) GROUND FLOOR COLUMN
 SITE MOBILIZATION WORK

TUESDAY  CHECK THE ALIGNMENT OF


(MAY 5) GROUND FLOOR
 OBSERVATION OF THE OVERALL
WORK IN THE SITE
 SEGREGATION OCCURRED IN THE
GROUND FLOOR COLUMN AND
SETTLEMENT OCCURRED IN AXIS
X3-X4.
 TRY TO FIND THE CAUSE OF THE
PRBLEM AND its SOLUTION.
WEDNESDAY  CONSTRUCTION OF RETAINING
(MAY 6) WALL TO SUPPPORT THE BACK
FILLED FOIL
THURSDAY
(MAY 7)
FRIDAY
(MAY 8)

ABSTRACT FOR WEEK 4

 During this week we had perform a few tasks, such as form work
removal from ground floor column, site mobilization and checking
the alignment of the floor, construction of retaining wall to support
the backfilled soil was also one of the task that executed in this
week.
ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT

 Beside this some problems was occurred in the site. Cause of the
challenges are:
1. Challenge number A-the compacted fill consolidated, so that
there was settlement to an acceptable degree.
2. Challenge number B-error occurred in the alignment the
Couse of this problem are
 Separated excavation(leads to unconventional error)
 False squadra
 Border property
 Actual land property is not the same as the given
drawing.
 Generally it was a great week for me because I was able to observer
different problems with in their solution.
Pictorially presentation of site progress
Removal of column from ground floor column
ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT

Removal of column from ground floor column

Segregation of column caused by loss of vibration


ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT

Demolishing work of segregated column

Settlement occurred within an acceptable degree


ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT

CONSTRUCTION OF RETAUNING WALL TO SUPPORT THE BACK FILLED SOIL


ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT

MONTHLY REPORT

 In my monthly stay at Ato KITAW ZEWDU G+3 residential building


projects still teach me new things that I never know in practically.
During the second month of my internship program things was gone
better and I am more familiar, dedicated and experienced from the
previous month.
 Most of the time I have been attended in the site, even though there
was a time where I was doing tasks in the office.
 The building has shown a real progress at this month, the task we
had executed during this month was erection of formwork and
placement off concrete for shear wall, regularly excavation work in
axis x3-x4, compaction, placement of the hard core, fixing mesh on
the hard core and concrete fill for semi basement slab was done.
 Beside this erection of probs, bottom soffit for ground floor slab,
provision of reinforcement and also placement of concrete for ground
floor slab has done.
 Since reinforcement for ground floor slab I was done checking the
number of bar provided in the slab based on the structural drawing,
in addition to this reinforcement was provided for ground floor
column, production of spacer and fix it in the column and in the
bottom of slab.
 Construction of retaining wall, concrete fill and checking the number
of bar provided andthe vertical alignment of column was also as a
part of the task.
 In the office I was done take off, bar schedule, and BOQ for ground
floor slab.
 The challenge that I was observed in this month is segregation of
ground floor column in axis x4(C4), the problem was caused by loss
of vibration due to concrete fill, as we know that there is no skilled
ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT

man power and they are worked in experience so continual


supervision work deserve in the site.
 So the only solutions for this type of problem are demolishing the
segregated column and reconstruct it. Due this fact I have got a lot of
technical experience.
 Generally this month I have been able to gather more knowledgeable
and my confidence in the site has been great as ever.