Professional Documents
Culture Documents
Sample 6-2
Sample 6-2
Sample 6-2
ARBAMINCH UNIVERSITY
ARBAMINCH INSTITUTE OF TECHNOLOGY
DEPARTEMENT OF CIVIL ENGINEERING
FIRST MONTH INTERNSHIP REPORT
ABUKELEMSIS CONDTRUCTION AND CONSULTING PLC.
This week I was totally committed to the work of the site and the site
engineer intended to share his knowledge as he can. The tasks that we had
done in this weak are construction of formwork, placement of concrete for
shear wall and grade beam, fix the mesh on the hard core and concrete
work for semi basement slab.
In addition to this site mobilization and clearing of waste material from the
site, removal of form work from shear wall and fixing of probs for ground
floor slab are some of the task that we had executed in this week.
Bar cutting and bending was also done in this weak.
ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT
During this weak there was a lot of task that we had done in the site, such as
preparation of takeoff sheet, bar schedule and BOQ for ground floor slab, in the
other hand construction of bottom soffit and side board for ground floor slab and
stair case.
Beside this reinforcement of ground floor beam, slab and stair case was
executed.to the next day of the week excavation of axis X3-X4 and provide water
proof and construction of mason was done.
Eventually I was check the number of bar provided on ground floor slab and
beam.
During this week the work progress in the site was very fast, and we had executed a lot of
task. The task that we had executed in this week was back filling of axis X3-X4, compact the
back filled soil and construct a grade beam on it.
Installation of electrical and sanitary work.
Dress the hard core and fixing mesh on the compacted soil, continually concrete fill for ground
floor slab and construction of column was also done in this week.
Formwork on axis X3-X4 grade beam Placement of hard core and fixing mesh
Concrete work for ground floor slab concrete fills for stair case
During this week we had perform a few tasks, such as form work
removal from ground floor column, site mobilization and checking
the alignment of the floor, construction of retaining wall to support
the backfilled soil was also one of the task that executed in this
week.
ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT
Beside this some problems was occurred in the site. Cause of the
challenges are:
1. Challenge number A-the compacted fill consolidated, so that
there was settlement to an acceptable degree.
2. Challenge number B-error occurred in the alignment the
Couse of this problem are
Separated excavation(leads to unconventional error)
False squadra
Border property
Actual land property is not the same as the given
drawing.
Generally it was a great week for me because I was able to observer
different problems with in their solution.
Pictorially presentation of site progress
Removal of column from ground floor column
ABUKELEMSIS CONSTRUCTION MONTHLY INTERNSHIP REPORT
MONTHLY REPORT