Professional Documents
Culture Documents
Calculations - Nikhil
Calculations - Nikhil
• NPSH CALCULATION
• DYKE WALL HEIGHT AND WIDTH CALCULATION
• MITER BEND CALCULATION
• P-T RATING
• LINE SIZING CALCULATION
• PIPE ELBOW CENTRE CALCULATION
• INSULATION THICKNESS FOR PIPES
• ESTIMATION OF PIPE PAINT QUANTITY
- निखिल चौंडकर
What is NPSH ?
Example 1
Example 2
Example 3
DYKE WALL CALCULATION
❑ Exercise-
➢ Calculate dyke wall height and width for below
mentioned tanks :
• Tanks Vol (m3)
• A 350
• B 270
• C 750
• D 995
• E 200
• F 500
Dyke wall Ht (M) Dyke wall thickness (M) ➢ Aggregate capacity in one dyke enclosure:
o Group of Fixed roof tanks: Upto 60,000 m3
Up to 1 0.6 o Group of Floating roof tanks: Upto 120,000 m3
1 to 2 1 o Fixed cum floating roof tanks shall be treated as
fixed roof tanks.
Total angle
• Angle of cut = No of miters
1.L2 : Distance of first and last reference line from pipe ends.
2.L1 : Distance between reference lines.
3.Cut Back : Offset distance of cut lines from reference lines at the top and bottom of pipe.
Exercise-
Consider we want to create 90 degree elbow of 10″ size with elbow center radius same as standard elbow
150LB - 150LBS - 150# - CLASS 150
Step:2 Determine required Flange Rating based on Pressure Temperature rating = table 2-1.1
Exercise-
1) we want to use ASTM A105 flange for our service that has a pressure rating 1,200 psig and at 500 °F.
2)What is the P-T rating of C.S. material at 15 kg/cm2 design pressure & 2000 C design temperature ?
2) What is the P-T rating of S.S316 material at 21 kg/cm2 design pressure & 2250 C design temperature ?
Why Line Sizing is so important? Velocity Consideration
Fluid Recom. Velo. in m/s
Steam
➢ Continuity Equation Superheated steam 40 to 75
Saturated steam 20 to 40
➢ Selection of velocity depends on : Wet steam 20 to 30
• Pressure Drop Water
• NPSH Pump Suction 0.5 to 1.5
• Noise Pump Delivery 1 to 3
• Pipe Erosion Boiler feed discharge 3 to 6
• Water Hammer & Surge Pressure City water 0.5 to 1.5
OIL
EXERCISE-
Heavy oil 1 to 2
Light oil 1 to 2
The water flowing through CS pipe at 300 m3/hr, having viscosity 1cp. Pipe Gases
Sch is 40. find out pressure drop for 100 M length and line size. Ccompressed Air 5 to 15
Fuel gas 10 to 30
Vaccum 100 to 200
Procedure for line sizing
1. Select prelim size.
2. Assume velocity ( as per chart )
3. Examine the suitability of the selected size.
Available pressure drop > calculated pressure drop
Example 1:
Calculate elbow center to end dimension for 4 inch nominal
pipe diameter elbow at 60 degree angle,
cut from 90 degree LR elbow.
Example 2:
Calculate elbow center to end dimension for 2 inch nominal
pipe diameter elbow at 30 degree angle, cut from 45 degree
LR elbow.
Estimation of Pipe Paint Quantity
Wastage
During painting process, some amount of paint gets wasted which depends on method of paint application.
Typical wastage percentages are :
➢ Brush or Roller Painting : 10%.
➢ Airless Spray Painting : 20%.
➢ Conventional Spray Painting : 30%
So, we have to add wastage to calculated paint quantity to get actual paint quantity.
Actual Paint Quantity = Theoretical Paint Quantity / Fraction Actual Paint Usage.
EXAMPLE CALCULATION
PIPE OF NOMINAL PIPE DIAMETER 10″ TO BE PAINTED WITH INORGANIC ZINC SILICATE COATING WITH SOLIDS
PERCENTAGE OF 60%. REQUIRED DRY FILM THICKNESS IS 70 MICRONS. METHOD OF APPLICATION IS CONVENTIONAL
SPRAY PAINTING. CALCULATE AMOUNT OF PAINT REQUIRED FOR LENGTH OF 100 METERS.
3. Surface area of pipe for one meter (A) = Pi X D = 3.141 X 254 = 0.797814 Sq. MM. (It is not necessary to take actual pipe
outside diameter from pipe data tables. Difference is negligible.)
8. Theoretical volume of paint required = Total Surface Area X WFT = 79781400 X 0.1167 = 9310489 Cubic MM. =
9.310489 Liters.
9. For conventional spray painting method, estimated wasted is around 30%. So only 70% paint gets used for actual
painting. So amount of actual paint required is theoretical paint quantity divided by fraction of actual paint usage.
10. Actual Paint Volume = Theoretical Paint Volume/0.7 = 9.310489/0.7 = 13.3 Liters.
Ca e s
lculatio
n of Insulation Thickness for Pip
Total heat transferred (Q) from pipe through such insulating material depends on following factors :
N : Length of Pipe.
Tp : Operating temperature of fluid inside pipe.
Ti : Maximum temperature allowed on the outside surface of insulation. Typically 50°C.
Rp : Radius of Pipe.
Ri : Radius of Insulation.
k : Thermal conductivity of insulating material.
Example Calculation
Suppose we have a pipe of Diameter 12″ with hot oil at a temperature of 200°C flowing through it.
Maximum allowed insulation temperature at the outer wall is 50°C. Allowed heat loss per meter
of pipe is 80 W/m. Insulation used is Glass Mineral Wool with thermal conductivity for that
temperature range of 0.035W/m.K. Now we have to find out required insulation thickness.
Thermal conductivity is expressed in Watts per meter per Kelvin (W/m.K) which is essentially same
as Watts per meter per degree celsius (W/m.C) (There is no multiplier in conversion from Kelvin to
degrees. So incremental change in Kelvin is same as incremental change in Celsius.)
In above formula, Q is total heat loss and N is length of pipe. So Q/N becomes our allowed heat loss
per meter of pipe which is 80W/m.
A thick walled tube of S.S having a k = 21.63 W/m k with dimensions of 0.0254m ID & 0.0508m OD is covered
With a 0.0254m layer of Asbestos insulation k = 0.2453 W/m k. The inside wall temperature of the pipe is
811K and the outside surface of the insulation is at 310.8 K. For a 0.305m length of pipe, calculate the heat
Loss and also the temperature at the interface between the metal and also the interface between the metal
And the insulation.