Professional Documents
Culture Documents
Printable Flash Cards
Printable Flash Cards
Term 1 Definition 1
Term 2 Definition 2
Term 3 Definition 3
https://www.flashcardmachine.com/print/?topic_id=2373545 1/104
10/24/23, 1:51 PM Printable Flash Cards
Term 4 Definition 4
Term 5 Definition 5
Term 6 Definition 6
https://www.flashcardmachine.com/print/?topic_id=2373545 2/104
10/24/23, 1:51 PM Printable Flash Cards
Term 7 Definition 7
Term 8 Definition 8
Term 9 Definition 9
https://www.flashcardmachine.com/print/?topic_id=2373545 3/104
10/24/23, 1:51 PM Printable Flash Cards
Term 10 Definition 10
Term 11 Definition 11
A start date is assigned to the start
milestone and then moving
throughout the network from activity
to activity (from left to right) and in the
sequence defined by the logical
relationships start and finish dates are
Forward Pass calculated for each activity and
milestone as determined by their
defined durations. The start and finish
dates on each activity are called the
early dates and when the analysis
reaches the end of the network it
establishes the earliest possible finish
date for the project
Term 12 Definition 12
https://www.flashcardmachine.com/print/?topic_id=2373545 4/104
10/24/23, 1:51 PM Printable Flash Cards
Term 13 Definition 13
A finish date is assigned to the end
milestone (or last activity). This could
be the same date as the one
calculated by the forward pass or a
different date applied as a constraint.
The analysis process then works back
Backward Pass through the network, from right to left,
until it arrives back at the start
milestone and another set of start and
finish dates have been calculated for
each activity. This is called the
backward pass and establishes the
late dates for each activity and
milestone
Term 14 Definition 14
Term 15 Definition 15
https://www.flashcardmachine.com/print/?topic_id=2373545 5/104
10/24/23, 1:51 PM Printable Flash Cards
Term 16 Definition 16
Term 17 Definition 17
Term 18 Definition 18
https://www.flashcardmachine.com/print/?topic_id=2373545 6/104
10/24/23, 1:51 PM Printable Flash Cards
Term 19 Definition 19
When a planner-scheduler is
collecting information about the
project during the initial planning
cycle, which information is of
GREATEST value?
D. A detailed scope of work statement.
A. Contract specifications.
B. The contractor’s pre-bid site visit
meeting minutes and notes.
C. The contract’s Changes clause.
D. A detailed scope of work statement
Term 20 Definition 20
Term 21 Definition 21
https://www.flashcardmachine.com/print/?topic_id=2373545 7/104
10/24/23, 1:51 PM Printable Flash Cards
Term 22 Definition 22
Term 23 Definition 23
Term 24 Definition 24
All project stakeholders provide input
data and information during the initial
planning process to
set the overall project duration?
A. Absolutely true.
B. Absolutely false.
C. Only by analyzing the contract can B. Absolutely false.
one determine if a change in duration
is allowed.
F. Only the project owner-client may
set the overall duration, and this is
often driven by
marketing and business
considerations
https://www.flashcardmachine.com/print/?topic_id=2373545 8/104
10/24/23, 1:51 PM Printable Flash Cards
Term 25 Definition 25
Term 26 Definition 26
Which should not be a reason why
superintendent and subcontractors
are included during
planning phase?
A. They have more immediate “buy-in”
to project plan. B. Planning phase is a theoretical
B. Planning phase is a theoretical exercise, and their input is not needed
exercise and their input is not needed until execution phase.
until the execution
phase.
C. Accuracy of a resultant plan is
improved through “brainstorming.”
D. Management expectations
regarding plan are transmitted to the
Term 27 Definition 27
Constructability, in terms of schedule
modeling, is best defined as:
A. Understanding how the contractor’s
plan defines overall project duration.
B. Understanding how the owner’s
arbitrary completion milestones will D. The input data necessary to
drive resource understand the various means and
utilization. methods alternatives to
C. How the contract specifies all accomplish and execute a project.
aspects and phasing of work.
D. The input data necessary to
understand the various means and
methods alternatives to
accomplish and execute a project
https://www.flashcardmachine.com/print/?topic_id=2373545 9/104
10/24/23, 1:51 PM Printable Flash Cards
Term 28 Definition 28
Term 29 Definition 29
Term 30 Definition 30
https://www.flashcardmachine.com/print/?topic_id=2373545 10/104
10/24/23, 1:51 PM Printable Flash Cards
Term 31 Definition 31
Term 32 Definition 32
Term 33 Definition 33
https://www.flashcardmachine.com/print/?topic_id=2373545 11/104
10/24/23, 1:51 PM Printable Flash Cards
Term 34 Definition 34
Term 35 Definition 35
Term 36 Definition 36
https://www.flashcardmachine.com/print/?topic_id=2373545 12/104
10/24/23, 1:51 PM Printable Flash Cards
Term 37 Definition 37
Term 38 Definition 38
Term 39 Definition 39
https://www.flashcardmachine.com/print/?topic_id=2373545 13/104
10/24/23, 1:51 PM Printable Flash Cards
Term 40 Definition 40
Term 41 Definition 41
Term 42 Definition 42
https://www.flashcardmachine.com/print/?topic_id=2373545 14/104
10/24/23, 1:51 PM Printable Flash Cards
Term 43 Definition 43
Term 44 Definition 44
Term 45 Definition 45
Which of the following documents is
probably of LEAST value when
planning a contractor’s
baseline critical path schedule for
construction of a high-rise building on
a remote South Pacific
resort island for a private developer? B. The local government’s report on
The contract has been awarded. future resort projects on the island.
A. Specifications – as found in the
contract document.
B. The local government’s report on
future resort projects on the island.
C. International Building Codes – as
referenced in the contract document
https://www.flashcardmachine.com/print/?topic_id=2373545 15/104
10/24/23, 1:51 PM Printable Flash Cards
Term 46 Definition 46
Term 47 Definition 47
Term 48 Definition 48
https://www.flashcardmachine.com/print/?topic_id=2373545 16/104
10/24/23, 1:51 PM Printable Flash Cards
Term 49 Definition 49
Term 50 Definition 50
Term 51 Definition 51
https://www.flashcardmachine.com/print/?topic_id=2373545 17/104
10/24/23, 1:51 PM Printable Flash Cards
Term 52 Definition 52
Term 53 Definition 53
When reporting progress and
completion forecasts to the client’s
management, a schedule that is
organized by the projects work
breakdown structure (WBS) structure
provides _____________.
A. A useful reporting tool that meets D. A “late finish” constraint on the last
the client’s project team special activity
needs.
B. An “early finish” constraint with a
20 day negative lag on the last activity.
C. A “late start” constraint on the first
activity with a 20 day negative lag.
D A “late finish” constraint on the last
Term 54 Definition 54
When gathering data to document
activity progress and observed trends,
the activity’s reported
percent complete ______________.
A. Is all that is necessary to forecast C. Must analyze in conjunction with all
remaining duration for that activity? observed activity data (actual start
B. Is used as part of the 6/10 rule to dates, trends, etc.) to
determine the remaining duration for determine an estimated remaining
that activity. duration for the activity.
C. Must be analyzed in conjunction
with all observed activity data (actual
start dates, trends,
etc.) to estimate the remaining
duration for the activity
https://www.flashcardmachine.com/print/?topic_id=2373545 18/104
10/24/23, 1:51 PM Printable Flash Cards
Term 55 Definition 55
Term 56 Definition 56
Term 57 Definition 57
https://www.flashcardmachine.com/print/?topic_id=2373545 19/104
10/24/23, 1:51 PM Printable Flash Cards
Term 58 Definition 58
Term 59 Definition 59
Term 60 Definition 60
https://www.flashcardmachine.com/print/?topic_id=2373545 20/104
10/24/23, 1:51 PM Printable Flash Cards
Term 61 Definition 61
Term 62 Definition 62
Term 63 Definition 63
https://www.flashcardmachine.com/print/?topic_id=2373545 21/104
10/24/23, 1:51 PM Printable Flash Cards
Term 64 Definition 64
Term 65 Definition 65
Term 66 Definition 66
https://www.flashcardmachine.com/print/?topic_id=2373545 22/104
10/24/23, 1:51 PM Printable Flash Cards
Term 67 Definition 67
Term 68 Definition 68
Term 69 Definition 69
https://www.flashcardmachine.com/print/?topic_id=2373545 23/104
10/24/23, 1:51 PM Printable Flash Cards
Term 70 Definition 70
Term 71 Definition 71
Term 72 Definition 72
https://www.flashcardmachine.com/print/?topic_id=2373545 24/104
10/24/23, 1:51 PM Printable Flash Cards
Term 73 Definition 73
Term 74 Definition 74
Term 75 Definition 75
When reporting progress and
completion forecasts to the client’s
management, a schedule that is
organized on the project’s OBS
provides ______.
A. A list of all equipment resources D. Identifies resource utilization and
utilized on the project. identifies gaps, utilization variances,
B. A baseline for change management and areas for
reporting. management attention.
C. A useful reporting tool that meets
the client’s project team special
needs.
D. Identifies resource utilization, and
identifies gaps utilization variances
https://www.flashcardmachine.com/print/?topic_id=2373545 25/104
10/24/23, 1:51 PM Printable Flash Cards
Term 76 Definition 76
Term 77 Definition 77
A CBS:
A. Should generally not include
indirect costs.
B. Is not absolutely essential for
C. Allows ready comparison of actual
effective management of a large
versus planned costs.
project.
C. Allows ready comparison of actual
versus planned costs.
D. All of the above.
Term 78 Definition 78
https://www.flashcardmachine.com/print/?topic_id=2373545 26/104
10/24/23, 1:51 PM Printable Flash Cards
Term 79 Definition 79
How is the CBS related to the WBS The CBS is the intersection of the
and OBS? WBS and OBS.
Term 80 Definition 80
Term 81 Definition 81
https://www.flashcardmachine.com/print/?topic_id=2373545 27/104
10/24/23, 1:51 PM Printable Flash Cards
Term 82 Definition 82
Term 83 Definition 83
Term 84 Definition 84
https://www.flashcardmachine.com/print/?topic_id=2373545 28/104
10/24/23, 1:51 PM Printable Flash Cards
Term 85 Definition 85
Term 86 Definition 86
Term 87 Definition 87
https://www.flashcardmachine.com/print/?topic_id=2373545 29/104
10/24/23, 1:51 PM Printable Flash Cards
Term 88 Definition 88
Term 89 Definition 89
Term 90 Definition 90
https://www.flashcardmachine.com/print/?topic_id=2373545 30/104
10/24/23, 1:51 PM Printable Flash Cards
Term 91 Definition 91
Term 92 Definition 92
Term 93 Definition 93
https://www.flashcardmachine.com/print/?topic_id=2373545 31/104
10/24/23, 1:51 PM Printable Flash Cards
Term 94 Definition 94
Term 95 Definition 95
Term 96 Definition 96
The baseline plan results from the Identification of the project goals and
planning process. What are the basic objectives; scope of work definition;
steps in the planning and phase
process that result in the baseline identification and sequencing result in
plan? the baseline plan.
https://www.flashcardmachine.com/print/?topic_id=2373545 32/104
10/24/23, 1:51 PM Printable Flash Cards
Term 97 Definition 97
Term 98 Definition 98
Term 99 Definition 99
https://www.flashcardmachine.com/print/?topic_id=2373545 33/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 34/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 35/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 36/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 37/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 38/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 39/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 40/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 41/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 42/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 43/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 44/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 45/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 46/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 47/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 48/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 49/104
10/24/23, 1:51 PM Printable Flash Cards
Start milestone.
Finish milestone.
Start no sooner than (constraint).
Name six examples of milestones
Start no later than (constraint).
Finish no sooner than (constraint).
Finish no later than (constraint).
https://www.flashcardmachine.com/print/?topic_id=2373545 50/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 51/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 52/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 53/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 54/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 55/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 56/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 57/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 58/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 59/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 60/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 61/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 62/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 63/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 64/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 65/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 66/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 67/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 68/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 69/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 70/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 71/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 72/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 73/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 74/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 75/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 76/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 77/104
10/24/23, 1:51 PM Printable Flash Cards
AD – Activity Description
ACWP – Actual Cost of Work
Performed
ADM - Arrow Diagramming Method
ADR - Alternative Dispute Resolution
AE - Apportioned Effort
AF - Actual Finish date
ALAP - As Late As Possible
AOA - Activity on Arrow (method)
AON - Activity on Node (method)
AS - Actual Start (date)
https://www.flashcardmachine.com/print/?topic_id=2373545 78/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 79/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 80/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 81/104
10/24/23, 1:51 PM Printable Flash Cards
o Fixed price.
o Unit price.
o Cost plus (with fixed, incentive, or
award fees).
Basic types of contracts:
o Time and materials (T and M).
o Guaranteed maximum price (GMP).
Common delivery methods:
o Design-build.
https://www.flashcardmachine.com/print/?topic_id=2373545 82/104
10/24/23, 1:51 PM Printable Flash Cards
a. Labor.
b. Weather.
c. Equipment.
d. Material.
General and special conditions:
e. Environment.
f. Regional constraints.
g. Any other project-specific variables
and requirements.
- Federal.
- State.
- Local.
- Special purpose entity;
Public agencies stakeholders:
- School or university.
- Utility district.
- Special legislative, e.g., Tennessee
Valley Authority (TVA).
- Public agency
- Private entities
- Engineer-architects.
- Contractors.
Types of stakeholders:
- Subcontractors.
- Consultants.
- Vendors.
- General public
https://www.flashcardmachine.com/print/?topic_id=2373545 83/104
10/24/23, 1:51 PM Printable Flash Cards
- Owner.
- Developer.
- Individuals.
- Social or political organizations.
Private entities stakeholders:
- Individuals and special interest
groups.
- Public agencies and private
enterprises.
- Land owner.
- Activist.
General public stakeholders:
- Investor.
- Concerned citizen
o Modularization.
Methods of constructability:
o Pre-fabrication.
https://www.flashcardmachine.com/print/?topic_id=2373545 84/104
10/24/23, 1:51 PM Printable Flash Cards
o Design-build.
o Material alternatives.
o Means and methods analysis.
Pre-assembly:
o Design alternatives and constraints.
o Health, safety and environmental
(HSE) impacts.
o Time.
o Labor.
o Transportation.
o Storage.
Costing constructability: o Site access.
o Governmental requirements.
- Permitting.
- Accessibility.
- Inspections and compliance.
o Labor.
o Equipment.
Categories of resources: o Material.
o Human.
o Technology.
https://www.flashcardmachine.com/print/?topic_id=2373545 85/104
10/24/23, 1:51 PM Printable Flash Cards
- Management.
- Technical.
Labor categories of resources: - Supervisory.
- Craft.
- Subcontract.
- Construction equipment.
Equipment categories of resources:
- Engineered (installed) equipment.
- Type.
- Availability.
- Deliverables.
Material categories of resources: - Timing and phasing (need-by dates
and logistics).
- Installation.
- Protection.
https://www.flashcardmachine.com/print/?topic_id=2373545 86/104
10/24/23, 1:51 PM Printable Flash Cards
- Skill level.
- Social values.
Human categories of resources:
- Cultural impacts.
- Performance issues.
o Historical database.
Data sources:
o Program or project specific data.
https://www.flashcardmachine.com/print/?topic_id=2373545 87/104
10/24/23, 1:51 PM Printable Flash Cards
- Site survey.
Program or project specific data
- Local resource studies.
sources:
- Logistics and transportation.
Terms to Know
Value engineering (VE).
Cost effectiveness.
Materials selection.
Functional ability.
Constructability.
Design schedule.
Terms to Know
Owner
Suppliers
Contractors
Public agencies
Designers
Public groups
Third parties
Non-governmental organizations
(NGO’s)
https://www.flashcardmachine.com/print/?topic_id=2373545 88/104
10/24/23, 1:51 PM Printable Flash Cards
a) Phase
b) Milestone
Timeframe:
c) Completion
d) Operations
o Design-bid-build 48
o Design-build
o EPC (engineering-procurement-
Delivery methods:
construction)
o Design-build-operate
o Variations of above
https://www.flashcardmachine.com/print/?topic_id=2373545 89/104
10/24/23, 1:51 PM Printable Flash Cards
o Access
Infrastructure: o Utility availability
o Easements
o Labor
Productivity:
o Equipment
o Asset.
Scope of work: o Function.
o Program and project.
https://www.flashcardmachine.com/print/?topic_id=2373545 90/104
10/24/23, 1:51 PM Printable Flash Cards
o Deliverables.
Considerations and constraints: o Milestones.
o Variables.
o Milestones.
Contractual obligations:
o Deliverables.
https://www.flashcardmachine.com/print/?topic_id=2373545 91/104
10/24/23, 1:51 PM Printable Flash Cards
o Schedule.
o Budget and cost.
Baseline:
o Forecasts.
o Periodic reporting.
o Basic techniques.
- Top-down.
WBS development & OBS - Bottom-up.
development: - Template-based.
o Roll-up and summarization.
o Code or chart of accounts.
o Elements of cost.
o Labor.
o Materials.
o Direct costs.
Cost breakdown structure (CBS):
o Indirect cost.
o Work breakdown structure (WBS).
o Organization breakdown structure
(OBS).
https://www.flashcardmachine.com/print/?topic_id=2373545 92/104
10/24/23, 1:51 PM Printable Flash Cards
o Periodic
- Weekly
- Monthly
9 Quarterly
Planning for forecasting:
o Special
- Change in conditions
- Added or deleted work
- Progress variance(s)
o Progress.
o Schedule.
o Cost.
Status reporting:
o Earned value.
o Change and configuration
management.
https://www.flashcardmachine.com/print/?topic_id=2373545 93/104
10/24/23, 1:51 PM Printable Flash Cards
o Periodic.
- Weekly.
- Monthly.
- Quarterly.
Forecasts:
Special.
- Change in conditions.
- Added or deleted work.
- Progress variance(s).
https://www.flashcardmachine.com/print/?topic_id=2373545 94/104
10/24/23, 1:51 PM Printable Flash Cards
https://www.flashcardmachine.com/print/?topic_id=2373545 95/104
10/24/23, 1:51 PM Printable Flash Cards
o Gantt charts.
o Critical Path Method (CPM).
o Project Evaluation and Review
Technique (PERT).
o Linear schedule.
o Line of balance.
Schedule types:
o Rolling wave.
o Baseline.
o Target.
o Schedule control level.
o Fragmentary and work schedule.
o Recovery.
o Finish-to-start (FS).
o Start-to-start (SS).
Relationships: o Finish-to-finish (FF).
o Start-to-finish (SF)
o Leads and lags.
https://www.flashcardmachine.com/print/?topic_id=2373545 96/104
10/24/23, 1:51 PM Printable Flash Cards
o Start.
- No earlier than.
- No later than.
Date constraints:
o Finish.
- No earlier than.
- No later than.
o Milestones.
o Tasks.
o Hammocks and summaries.
o Level-of-effort (LOE).
Activity types: o Flags.
- WBS.
- Independent.
- Start.
- Finish.
o Tabular.
Reports:
o Graphic.
https://www.flashcardmachine.com/print/?topic_id=2373545 97/104
10/24/23, 1:51 PM Printable Flash Cards
o Types.
Calendars:
o Lags.
o Owner.
o Local political and community
interests.
External stakeholders:
o Permitting and code enforcing
entities.
o Owner’s users and customers.
https://www.flashcardmachine.com/print/?topic_id=2373545 98/104
10/24/23, 1:51 PM Printable Flash Cards
o Elements of work
o Related support work examples
- Ordering of long lead-time items
which impact the work.
Modeling Activity types: - Submittal processes: schedules,
submitting, approval, etc.
o Dividing of elements of work into
increments or units of work, which are
spaced over time.
https://www.flashcardmachine.com/print/?topic_id=2373545 99/104
10/24/23, 1:51 PM Printable Flash Cards
o Date.
o Resource.
o Contractual.
Constraints: o Preferential.
o Calendars
o Weather
o External.
o Resource allocation
o Resource availability
Resource loading: o Resource management
o Front-end
o Back-end
o Total.
Float:
o Free.
https://www.flashcardmachine.com/print/?topic_id=2373545 100/104
10/24/23, 1:51 PM Printable Flash Cards
o Positive change.
Scope variance:
o Negative change.
o Directed acceleration.
Schedule acceleration:
o Constructive acceleration.
https://www.flashcardmachine.com/print/?topic_id=2373545 101/104
10/24/23, 1:51 PM Printable Flash Cards
o Retained
Logic calculation methods:
o Progress override
https://www.flashcardmachine.com/print/?topic_id=2373545 102/104
10/24/23, 1:51 PM Printable Flash Cards
o Narrative status
o Variance
- Percent duration
- Float
- Milestone analysis
Types of Reports: o Trend
o Tabular and written - Percent (%)-complete
- Period
o Forecast
o Float
o Target or baseline comparison
o Earned value
https://www.flashcardmachine.com/print/?topic_id=2373545 103/104
10/24/23, 1:51 PM Printable Flash Cards
o Schedule acceleration
o Schedule compression
o Overtime
Recovery schedules:
o Multiple shifts
o Additional resources
o Schedule crashing
https://www.flashcardmachine.com/print/?topic_id=2373545 104/104