The document provides work accomplishment reports for three elevators (SE1, SE2, SE3) for the period of September 26, 2021 to October 1, 2021. For each elevator, 18 tasks are listed with their weight, description, and percentage completed in the previous and current period. Across the three elevators, mobilization and setting of plumblines/templates have seen the most progress at 50-70% completed, while many other tasks have not yet begun. Overall accomplishment across the elevators increased slightly from the previous period to the current period.
Akash Karia - Anti-Procrastination For Writers - The Writer's Guide To Stop Procrastinating, Start Writing and Create A Daily Writing Ritual-AkashKaria - Com (2014) PDF
The document provides work accomplishment reports for three elevators (SE1, SE2, SE3) for the period of September 26, 2021 to October 1, 2021. For each elevator, 18 tasks are listed with their weight, description, and percentage completed in the previous and current period. Across the three elevators, mobilization and setting of plumblines/templates have seen the most progress at 50-70% completed, while many other tasks have not yet begun. Overall accomplishment across the elevators increased slightly from the previous period to the current period.
The document provides work accomplishment reports for three elevators (SE1, SE2, SE3) for the period of September 26, 2021 to October 1, 2021. For each elevator, 18 tasks are listed with their weight, description, and percentage completed in the previous and current period. Across the three elevators, mobilization and setting of plumblines/templates have seen the most progress at 50-70% completed, while many other tasks have not yet begun. Overall accomplishment across the elevators increased slightly from the previous period to the current period.
The document provides work accomplishment reports for three elevators (SE1, SE2, SE3) for the period of September 26, 2021 to October 1, 2021. For each elevator, 18 tasks are listed with their weight, description, and percentage completed in the previous and current period. Across the three elevators, mobilization and setting of plumblines/templates have seen the most progress at 50-70% completed, while many other tasks have not yet begun. Overall accomplishment across the elevators increased slightly from the previous period to the current period.
GRAND TOTAL 100.00% 9.00% 2.00% 11.00% Project : Juan Luna Logistics Contractor :INT'L ELEVATOR & EQUIPMENT , INC. Subject : Work Accomplishment Elevator No. : SE2 Period : 09/26/2021 - 10/01/2021
Actual Accomplishment (% Weight)
Items Description % Weight Previous This Period To date 1 Mobilization 10.00% 50.00% 0.00% 50.00%
2 Setting of plumblines/TEMPLATE 5.00% 60.00% 10.00% 70.00%
3 WOS Assembly 5.00% 0.00% 0.00% 0.00%
4 Bracket Setting 10.00% 0.00% 0.00% 0.00%
5 Rail Setting and Alignment 10.00% 0.00% 0.00% 0.00%
GRAND TOTAL 100.00% 9.00% 0.50% 9.50% Project : Juan Luna Logistics Contractor :INT'L ELEVATOR & EQUIPMENT , INC. Subject : Work Accomplishment Elevator No. : SE3 Period : 09/26/2021 - 10/01/2021
Actual Accomplishment (% Weight)
Items Description % Weight Previous This Period To date 1 Mobilization 10.00% 50.00% 0.00% 50.00%
2 Setting of plumblines/TEMPLATE 5.00% 60.00% 10.00% 70.00%
3 Scaffolding Assembly 5.00% 0.00% 0.00% 0.00%
4 Bracket Setting 10.00% 0.00% 0.00% 0.00%
5 Rail Setting and Alignment 10.00% 0.00% 0.00% 0.00%
GRAND TOTAL 100.00% 9.00% 0.50% 9.50% Project : Juan Luna Logistics Contractor :INT'L ELEVATOR & EQUIPMENT , INC. Subject : Work Accomplishment Elevator No. : SE4 Period : 09/26/2021 - 10/01/2021
Actual Accomplishment (% Weight)
Items Description % Weight Previous This Period To date 1 Mobilization 10.00% 50.00% 0.00% 50.00%
2 Setting of plumblines/TEMPLATE 5.00% 60.00% 10.00% 70.00%
3 WOS Assembly 5.00% 0.00% 0.00% 0.00%
4 Bracket Setting 10.00% 0.00% 0.00% 0.00%
5 Rail Setting and Alignment 10.00% 0.00% 0.00% 0.00%
GRAND TOTAL 100.00% 9.00% 0.50% 9.50% Project : Juan Luna Logistics Contractor :INT'L ELEVATOR & EQUIPMENT , INC. Subject : Work Accomplishment Elevator No. : SE5 Period : 09/26/2021 - 10/01/2021
Actual Accomplishment (% Weight)
Items Description % Weight Previous This Period To date 1 Mobilization 10.00% 100.00% 0.00% 100.00%
2 Setting of plumblines/TEMPLATE 5.00% 100.00% 0.00% 100.00%
3 WOS Assembly 5.00% 100.00% 0.00% 100.00%
4 Bracket Setting 10.00% 80.00% 10.00% 90.00%
5 Rail Setting and Alignment 10.00% 80.00% 10.00% 90.00%
GRAND TOTAL 100.00% 43.00% 2.00% 45.00% Project : Juan Luna Logistics Contractor :INT'L ELEVATOR & EQUIPMENT , INC. Subject : Work Accomplishment Elevator No. : SE1-5 Period : 10/2/2021 - 10/08/2021