Professional Documents
Culture Documents
Larson8e CH06 PowerPoint-merged
Larson8e CH06 PowerPoint-merged
Chapter Six
Developing a Project
Schedule
© 2021 McGraw-Hill Education. All rights reserved. Authorized only for instructor use in the classroom.
No reproduction or further distribution permitted without the prior written consent of McGraw-Hill Education.
Where We Are Now
© McGraw-Hill Education 2
Learning Objectives
06-01 Understand the linkage between WBS and the project network.
06-02 Diagram a project network using AON methods.
06-03 Calculate early, late, and slack activity times.
06-04 Identify and understand the importance of managing the critical
path.
06-05 Distinguish free slack from total slack.
06-06 Demonstrate understanding and application of lags in
compressing projects or constraining the start or finish of an
activity.
© McGraw-Hill Education 3
Chapter Outline
© McGraw-Hill Education 4
6.1 Developing the Project Network
© McGraw-Hill Education 5
6.2 From Work Package to Network
Terminology
- Activity: an element of the project that requires time but may not require
resources
- Parallel activities: activities that can take place at the same time, if
desired.
- Burst activity: an activity that has more than one activity immediately
following it (more that one dependency arrow flowing from it)
- Merge activity: an activity that has more than one activity immediately
preceding it (more than one dependency arrow flowing to it)
- Path: a sequence of connected, dependent activities
- Critical path: the path with the longest duration through the network
Two approaches
- Activity-on-Node (AON) uses a node to depict an activity.
- Activity-on-Arrow (AOA) uses an arrow to depict an activity.
© McGraw-Hill Education 7
Basic Rules to Follow in Developing Project Networks
© McGraw-Hill Education 8
6.4 Activity-on-Node (AON) Fundamentals
© McGraw-Hill Education 13
Network Information (Automated Warehouse)
• Add activity times along each path in the network (ES + Duration =
EF).
• Carry the early finish (EF) to the next activity where it becomes its
early start (ES) unless…
• The next succeeding activity is a merge activity, in which case the
largest early finish (EF) number of all its immediate predecessor
activities is selected.
© McGraw-Hill Education 17
Activity-on-Node Network Backward Pass
• Subtract activity times along each path starting with the project end
activity (LF – Duration = LS).
• Carry the late start (LS) to the next preceding activity where it
becomes its late finish (LF) unless…
• The next succeeding activity is a burst activity, in which case the
smallest late start (LS) number of all its immediate successor activities
is selected.
© McGraw-Hill Education 19
Forward and Backward Pass Completed with Slack Times
• Is the network path(s) that has (have) the least slack in common.
• Is the longest path through the activity network.
• Is the shortest expected time in which the entire project can be
completed.
• Is important because it impacts completion time.
• Is where you put best people on.
• Is where you pay extra attention when doing risk assessment.
• Is where you don’t look when other managers are asking to ‘borrow’
people or equipment.
• Is where you look when you don’t have time to monitor all activities.
© McGraw-Hill Education 22
Sensitivity
© McGraw-Hill Education 23
6.8 Practical Considerations
© McGraw-Hill Education 24
Network Logic Errors—Illogical Loop
Laddering
• Activities are broken into segments so the following activity can begin
sooner and not delay the work.
Use of Lags to Reduce Schedule Detail and Project Duration
• A lag is the minimum amount of time a dependent activity must be
delayed to begin or end.
• Lengthy activities are broken down to reduce the delay in the start of
successor activities.
• Lags can be used to constrain finish-to-start, start-to-start, finish-to-
finish, start-to-finish, or combination relationships.
© McGraw-Hill Education 28
Example of Laddering Using Finish-to-Start Relationship
Finish-to-Start Relationship
Start-to-Start Relationship
Finish-to-Finish
Relationship
Start-to-Finish
Relationship
Combination
Relationships
© McGraw-Hill Education 35
Hammock Activity Example
© McGraw-Hill Education 37
Because learning changes everything. ®
www.mheducation.com
© 2021 McGraw-Hill Education. All rights reserved. Authorized only for instructor use in the classroom.
No reproduction or further distribution permitted without the prior written consent of McGraw-Hill Education.
Because learning changes everything.®
Chapter Eight
Scheduling Resources
and Costs
© 2021 McGraw-Hill Education. All rights reserved. Authorized only for instructor use in the classroom.
No reproduction or further distribution permitted without the prior written consent of McGraw-Hill Education.
Where We Are Now
© McGraw-Hill Education 2
Learning Objectives
© McGraw-Hill Education 3
Chapter Outline
© McGraw-Hill Education 4
Project Planning Process
© McGraw-Hill Education 6
The Resource Scheduling Problem
Resource Smoothing
- Involves attempting to even out varying demands on resources by
delaying non-critical activities (using slack) to lower peak resource
demand and, thus, increase resource utilization when resources are
adequate over the life of the project.
Resource-Constrained Scheduling
- Occurs when resources are not adequate to meet peak demands.
The late start of some activities must be delayed, and the duration of
the project may be increased.
© McGraw-Hill Education 7
Types of Project Constraints
© McGraw-Hill Education 8
Constraint Examples
Time-Constrained Project
- Must be completed by an imposed date.
- Time (project duration) is fixed and resources are flexible. If required,
resources can be added to ensure the project is completed by a specific
date.
Resource-Constrained Project
- Assumes the level of resources available cannot be exceeded.
- Resources are fixed and time is flexible. If the resources are inadequate,
it will be acceptable to delay the project.
Limiting Assumptions
- Splitting activities will not be allowed.
• Splitting refers to interrupting work on one task and assigning the
resources to work on a different task for a period of time, then
reassigning them to work on the original task.
- Level of resources used for an activity cannot be changed.
Risk Assumptions
- Activities with the most slack pose the least risk.
- Reduction of flexibility does not increase risk.
- The nature of an activity (easy, complex) doesn’t increase risk.
© McGraw-Hill Education 11
Time-Constrained Projects
© McGraw-Hill Education 12
Botanical Garden
© McGraw-Hill Education 14
Resource-Constrained Schedule through Period 2-3
EMR Project
- The development of a hand-held electronic medical reference guide to
be used by emergency medical technicians and paramedics
Resource Problem
- Only eight design engineers can be assigned to the project due to the
shortage of design engineers and commitments to other projects.
- The peak demand is 21 design engineers.
© McGraw-Hill Education 17
EMR Project Network View Schedule before Resources Leveled
© McGraw-Hill Education 24
8.6 Splitting Activities
Splitting Tasks
- Can be useful if the work involved does not include large start-up or
shut-down costs.
© McGraw-Hill Education 25
Splitting Activities
© McGraw-Hill Education 27
8.8 Assigning Project Work
Reasons why we should not always assign the best people the most
difficult tasks
• Best people: resent to the fact that they are always given the toughest
assignments
• Less experienced participants: resent to the fact that they are never
given the opportunity to expand their skill/knowledge base
Factors to be considered in deciding who should work together
• Minimize unnecessary tension; complement each other
• Experience: veterans team up with new hires
• Future needs: have people work together early on so that they can
become familiar with each other
© McGraw-Hill Education 28
8.9 Multiproject Resource Schedules
© McGraw-Hill Education 29
Managing Multiproject Scheduling
© McGraw-Hill Education 30
8.10 Using the Resource Schedule to Develop a Project Cost Baseline
© McGraw-Hill Education 31
Direct Labor Budget Rollup ($000)
Heuristics
Leveling
Planned value (PV)
Resource-constrained project
Resource-constrained scheduling
Resource smoothing
Splitting
Time-constrained project
Time-phased budget baseline
© McGraw-Hill Education 39
Because learning changes everything. ®
www.mheducation.com
© 2021 McGraw-Hill Education. All rights reserved. Authorized only for instructor use in the classroom.
No reproduction or further distribution permitted without the prior written consent of McGraw-Hill Education.
Land Acknowledgement
We acknowledge that Western University is located on the traditional lands of the Anishinaabek,
Haudenosaunee, Lūnaapéewak, and Chonnonton Nations, on lands connected with the London
Township and Sombra Treaties of 1796 and the Dish with One Spoon Covenant Wampum. With this, we
respect the longstanding relationships that Indigenous Nations have to this land, as they are the original
caretakers. We acknowledge historical and ongoing injustices that Indigenous Peoples (First Nations,
Métis and Inuit) endure in Canada, and
we accept responsibility as members of
a public institution to contribute toward
revealing and correcting miseducation as
well as renewing respectful relationships
with Indigenous communities through our
teaching, research, community service,
and employment endeavors.
COMMMGT 9330A
Session 5
Project Schedule Management
COMMMGT 9330A
Project Schedule
Management
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
Learning Objectiv
es
o Apply effective scheduling tools and techniques to
sequence and accurately estimate activity duration.
o Outline the benefits of using scheduling tools such as
Gantt chart and network diagrams.
o Create a draft schedule
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
Introduction to Schedule
Planning
• Once project scope is defined,
next step create a schedule.
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
Project Schedule
Planning
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
The triple
constraint
• The “iron triangle” is a very popular metaphor pointing out that
the project manager is asked to reach a reasonable trade-off
among various concurrent, heterogeneous, and visible
constraints.
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
Plan Schedule
Management
• Process of establishing the policies, procedures, and
documentation for planning, developing, managing, executing,
and controlling the project schedule.
o The processes:
o Define Activities
o Sequence Activities
o Estimate Activity Durations
o Develop Schedule
o Control Schedule
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Page 173-230
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
KEY CONCEPTS | PROJECT SCHEDULE MANAGEMENT
• The project management team selects a scheduling method, such as critical path or
an agile approach.
o The project-specific data namely activities, planned dates, durations,
resources, dependencies, and constraints, are entered into a scheduling tool
to create a schedule model for the project.
o The result is a project schedule.
o The schedule management plan establishes the criteria and the activities for
developing, monitoring, and controlling the schedule.
o Part of the Project Management Plan
o Formal or Informal
o Scheduling Methodology and Software
o Schedule Baseline
o Performance Measures
o Schedule Variances
o Schedule Change Control Procedures
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
TRENDS & PRACTICES IN PROJECT SCHEDULE
MANAGEMENT
• Iterative scheduling with a backlog:
o Rolling wave planning based on adaptive life cycles,
such as the agile approach for product development.
o Requirements are documented in user stories that are
then prioritized and refined just prior to construction, and
the product features are developed using time-boxed
periods
• On-demand scheduling:
o Kanban system, is based on the Theory-of-constraints
and pull-based scheduling concepts from lean
manufacturing to limit a team’s work in progress to
balance demand against the team’s delivery throughput.
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
PLAN SCHEDULE MANAGEMENT ITTO
Tools & Techniques
•Project charter
•Project management plan
Inputs Outputs Schedule management plan
•Scope management plan ❑ Expert judgment
•Development approach ❑ Data analysis
Estimate
Plan Schedule Define Sequence Develop Control
Activity
Management Activities Activities Schedule Schedule
Durations
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Page 179
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
DEFINE
ACTIVITIES Tools & Techniques
• Activity list
•Project management plan • Activity attributes
•Schedule management plan ❑ Expert judgment
Inputs Outputs • Milestone list
❑ Decomposition
•Scope baseline • Change requests
❑ Rolling wave planning • Project management plan updates
•Enterprise environmental factors
❑ Meetings • Schedule baseline
•Organizational process assets • Cost baseline
Estimate
Plan Schedule Define Sequence Develop Control
Activity
Management Activities Activities Schedule Schedule
Durations
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Page 183
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
• Process of identifying the specific and
documenting actions to be performed to produce
the project deliverables
• The key benefit of this process is that it
decomposes work packages into schedule
DEFINE activities that provide a basis for estimating,
scheduling, executing, monitoring, and controlling
ACTIVITIES the project work.
• This process is performed throughout the project.
• Work packages are decomposed into activities
• Provides a basis for estimating, scheduling,
executing, and monitoring and controlling the
project work
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
SEQUENCE
ACTIVITIES
Tools & Techniques
• Project management plan
• Schedule management plan
• Scope baseline ❑ Precedence diagramming • Project schedule network diagrams
• Project documents
method
• Project documents updates
❑ Dependency determination and
• Activity attributes Inputs
integration
Outputs • Activity attributes
• Activity list ❑ Leads and lags • Activity list
• Assumption log ❑ Project management • Assumption log
• Milestone list information system
• Milestone list
• Enterprise environmental factors
• Organizational process assets
Estimate
Plan Schedule Define Sequence Develop Control
Activity
Management Activities Activities Schedule Schedule
Durations
Project Management, the Managerial Process 7E, by Erik W. Larson and Clifford F. Gray – Chapter 5 & 6
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Page 187
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
• Sequence Activities is the process of
SEQUENC identifying and documenting relationships
E among the project activities. The key
benefit of this process is that it defines the
ACTIVITIE logical sequence of work to obtain the
S greatest efficiency given all project
constraints.
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
PRECEDENCE DIAGRAMMING METHOD
• PDM is a method used(PDM)
in Critical Path Methodology (CPM)
• Commonly called Activity on Node (AON), most used sequencing
method
• Boxes represent tasks with arrows used for dependencies
• Arrows show the logical relationships that exist between them
• 4 types of dependencies:
oFinish to Start (FS) – Task must finish before next one can start
oFinish to Finish (FF) – One task must finish before other can finish
oStart to Start (SS) – One task must start before the other can start
oStart to Finish (SF) – One task must start before the other can finish
Activity Activity
A B
Dependency Node
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
PRECEDENCE DIAGRAMMING METHOD
(PDM)
Finish
Start Finish Start
Finish Start
Start Finish
Finish Start
Start Finish
Finish
Start Start Finish
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
LEADS &
LAGS
Leads (-) FS-10:
•Allows an acceleration of the successor activity
•Added to start (begin early) an activity before the predecessor activity is
completed
•Landscaping can be started earlier
•Develop test plans ten days before all the programming is done (FS-10D)
Start Finish Start Finish
Dela
y
Start Finish Start Finish
Early
LAGS (+)
•Waiting time between activities
•Directs a delay (late start) in the successor activity
•Curing of concrete takes time
•Curing of binder course on a road must happen before a surface course is paved
•Start editing ten days after you start writing (SS+10D)
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
ARROW DIAGRAMMING METHOD (ADM)
• Commonly called Activity on Arrow (AOA)
• Boxes represent dependencies with arrows used for tasks
o Only Finish to Start (FS) relationships
o Can use “dummy” activities
• Used for CPM and PERT estimating methods
Task
Activity A
Dependency
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
METHOD
COMPARISON
PDM Build Build Build
(AON) Start Foundation Walls Finish
Roof
Method
Install
Grass
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
ESTIMATE ACTIVITY DURATIONS
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
ESTIMATE ACTIVITY DURATIONS
• Project management plan Tools & Techniques
• Schedule management plan
• Scope baseline ❑ Expert judgment
• Project documents ❑Analogous estimating
• Duration estimates
• Activity attributes ❑ Parametric estimating
• Activity list
• Basis of estimates
Inputs ❑ Three-point estimating Outputs
• Assumption log • Project documents updates
• Lessons learned register ❑ Bottom-up estimating – Activity attributes
• Milestone list ❑ Data analysis – Assumption log
• Project team assignments ❑ Alternatives analysis
• Resource breakdown structure ❑ Reserve analysis
– Lessons learned register
• Resource calendars ❑ Decision making
• Resource requirements
❑ Meetings
• Risk register
• Enterprise environmental factors
• Organizational process assets
Estimate
Plan Schedule Define Sequence Develop Control
Activity
Management Activities Activities Schedule Schedule
Durations
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
TECHNIQUES FOR ESTIMATING
DURATIONS • One estimate per activity
• Expert Judgment or Guessing
ONE POINT • Chance of padding
ESTIMATING • Difficult to get buy-in
• Project Manager must provide the estimator as much information as possible
• Should not be used for a highly probable schedule
• Top down
ANALOGOUS • Gross Value Estimating Approach
ESTIMATING • Expert Judgment or Historical Information
• Less costly and time consuming but less accurate
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
DATA ANALYSIS
• Alternative analysis:
o Used to compare various levels of resource capability or skills;
scheduling compression techniques; different tools {manual versus
automated); and make, rent, or buy decisions regarding the resources.
This allows the team to weigh resource, cost, and duration variables to
determine an optimal approach for accomplish project work.
• Reserve analysis:
o Determine amount of contingency and management reserve needed
for the project.
o Duration estimates may include contingency reserves, sometimes
referred to as schedule reserves, to account for schedule
uncertainty.
o Contingency reserves are the estimated duration within the schedule
baseline, which is allocated tor identified risks that are accepted.
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
DATA ANALYSIS
• Contingency reserves
o Associated with the known-unknowns, which may be
estimated to account for this unknown amount of rework. The
contingency reserve may be a percentage of the estimated
activity duration or a fixed number of work periods.
oContingency reserves may be separated from the
individual activities and aggregated. As more precise
information about the project becomes available, the
contingency reserve may be used, reduced, or eliminated.
Contingency should be clearly identified in the schedule
documentation.
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
RESERVE
ANALYSIS
• Duration estimates may include reserves:
o Contingency Reserves:
•Time reserves or buffers
•These are for risks remained after Plan Risk Responses Process
o Management Reserve:
•These are for unforeseen risks
o Heuristic:
o Rule of Thumb | Duration for design work | 20% of total project duration
o 80/20 Rule
o Results of parametric estimates can become heuristics
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
THREE POINT
ESTIMATES
• PERT (Program Evaluation and Review Technique)
o tE = Expected Duration
o tP = Pessimistically estimated duration
o tO = Optimistically estimated duration
o tM = Most Likely Estimate
o tE = (tO + 4tM + tP) /6 (Beta)
o tE = (tO + tM + tP) /3 (Triangular)
o SD: Ϭ = (P-O)/6
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
IMPORTANT FACTORS WHEN
ESTIMATING
• Law of diminishing returns
o When one factor (e.g.,
resource) used to determine
the effort required to produce a
unit of work is increased while
all other factors remain fixed, a
point will eventually be reached
at which additions of that one
factor start to yield
progressively smaller or
diminishing increases in
output. PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
IMPORTANT FACTORS WHEN
ESTIMATING
• Number of resources:
o Increasing the number of resources to twice the original
number of the resources does not always reduce the time
by half, as it may increase extra duration due to risk, and at
some point, adding too many resources to the activity may
increase duration due to knowledge transfer, learning curve,
additional coordination, and other factors involved.
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
DEVELOP
SCHEDULE
• Develop Schedule is the process of analyzing activity
sequences, durations, resource requirements, and schedule
constraints to create a schedule model for project execution
and monitoring and controlling.
o This process is performed throughout the project.
o Process of analyzing activity sequences, durations, resource
requirements, and schedule constraints to create the project
schedule
o Process is iterative and can occur many times over the life
cycle of the project
o Project Manager performs calculations and What-If analysis
o Schedule is calendar based
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
DEVELOP
SCHEDULE
• Project management plan Tools & Techniques
• Schedule management plan • Schedule baseline
• Scope baseline ❑ Schedule network analysis • Project schedule
• Project documents • Schedule data
❑ Critical path method
• Activity attributes • Project calendars
• Activity list ❑Resource optimization
• Change requests
• Assumption log Inputs ❑ Data analysis Outputs • Project management plan updates
• Basis of estimates
• Duration estimates ❑ What-if scenario analysis • Schedule management plan
• Lessons learned register • Cost baseline
❑ Simulation
• Milestone list • Project documents updates
• Project schedule network diagrams ❑ Leads and lags • Activity attributes
• Project team assignments • Assumption log
❑ Schedule compression
• Resource calendars
❑ Project management • Duration estimates
• Resource requirements information system
• Risk register
• Lessons learned register
❑ Agile release planning • Resource requirements
• Agreements
• Enterprise environmental factors • Risk register
• Organizational process assets
Estimate
Plan Schedule Define Sequence Develop Control
Activity
Management Activities Activities Schedule Schedule
Durations
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Page 205
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
EARLY START/FINISH, LATE START/FINISH
ES DR EF
ES DR EF
ES DR EF
LS TF LF
ES DR EF
LS TF LF
LS TF LF
ES DR EF
LS TF LF
EF = ES + DR - 1
LS = LF - DR + 1
Slack = LF – EF or LS -
ES
LS TF LF
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Page 211. Figure 6-16: Example of Critical Path method.
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
EARLY START/FINISH, LATE START/FINISH
• EF=ES+DUR-1
ES DUR EF
• LS=LF-DUR+1 Task Name
• Slack=LF-EF or LS- LS Slack LF
ES
3 2 4
Task B
1 2 2 7 4 8 9 2 10
Task A Task D
1 0 2 3 6 8 9 0 10
Task C
3 0 8
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
SCHEDULE NETWORK ANALYSIS
A technique that generates the project schedule
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
CRITICAL PATH
METHOD
o Determines the longest path in the
network diagram which is critical
path
o A critical path is normally
characterized by zero total float on
the critical path
o Schedule activities on a critical path
are called “critical activities”
o Near-critical path is close in
duration to the critical path
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
CRITICAL CHAIN
METHOD
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
SCHEDULING FROM ESTIMATES
• Critical Path
o Longest time through the network
diagram, the shortest time the project
is expected to take
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
CRITICAL PATH DETERMINATION EXAMPLE
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
FLOAT
(SLACK)
• Total Float/Slack
o Amount of time an activity can be delayed without delaying the
planned project end date
• Free Float/Slack
o Amount of time an activity can be delayed without delaying the early
start date of its successor(s)
• Project Float
o Amount of time a project can be delayed without delaying the
externally imposed project completion date
• Forward pass
o Determines the early start and finish dates
• Backward pass
o Determines the late start and finish dates
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
FLOAT (SLACK)
CALCULATION
ES DR EF ES DR EF ES DR EF ES DR EF ES DR EF
1. Precedence Diagram
2. Durations
ES D EF
3. Forward Pass (ES -> EF)
“X”
LS F LF 4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF -> LS)
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
CALCULATING FLOAT ES DR EF ES DR EF ES DR EF
6 7 5
Start “A” “F” “B” End
LS TF LF LS TF LF LS TF LF
ES DR EF ES DR EF ES DR EF ES DR EF ES DR EF
4 8 5 7 8
“D” “E” “G” “H” “C”
LS TF LF LS TF LF LS TF LF LS TF LF LS TF LF
1. Precedence Diagram
2. Durations
ES DR EF
3. Forward Pass (ES -> EF)
“X”
LS F LF 4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF -> LS)
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
CALCULATING FLOAT
0+6=6
ES DR EF ES DR EF ES DR EF
0 6 6 6 7 13 13 5 18
Start “A” “F” “B” End
LS TF LF
ES DR EF ES DR EF ES DR EF ES DR EF
0 4 4 4 8 12 13 5 18 18 7 25 25 8 33
“D” “E” “G” “H” “C”
The latest Late Finish of the preceding activities determines Early Start
1. Precedence Diagram
2. Durations
ES DR
D EF 3. Forward Pass (ES -> EF)
“X” 4. Critical Path
LS F LF
5. Float of Critical Path Activities
6. Backward Pass (LF -> LS)
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
CALCULATING FLOAT ES DR EF ES DR EF ES DR EF
0 6 6 6 7 13 13 5 18
Start “A” “F” “B” End
A–F–G–H–C
ES DR EF ES DR EF ES DR EF ES DR EF ES DR EF
0 4 4 4 8 12 13 5 18 18 7 25 25 8 33
“D” “E” “G” “H” “C”
The latest Early Finish of the preceding activities determines Critical Path
1. Precedence Diagram
2. Durations
ES DR EF 3. Forward Pass (ES -> EF)
“X” 4. Critical Path
LS F LF 5. Float of Critical Path Activities
6. Backward Pass (LF -> LS)
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
CALCULATING FLOAT
0 6 6 6 7 13 13 5 18
Start “A” “F” “B” End
0 0
0 4 4 4 8 12 13 5 18 18 7 25 25 8 33
“D” “E” “G” “H” “C”
0 0 0
1. Precedence Diagram
2. Durations
ES DR EF 3. Forward Pass (ES EF)
“X” 4. Critical Path
LS F LF
5. Float of Critical Path Activities
6. Backward Pass (LF LS)
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
CALCULATING FLOAT
ES DR EF Latest
ES DR EF Total
Start Float
0 6 6 6 7 13 13 5 18
Start “A” “F” “B” End
LF – DR = LS
0 0 6 6 0 13 28 15 33 33 – 5 = 28
LS TF LF LS TF LF
LS TF LF
LS – ES = LF - EF
28 – 13 =
4 8 5 15 7 8
0 4 4 12 13 18 18 25 25 33
“D” “E” “G” “H” “C”
1 1 5 5 1 13 13 0 18 18 0 25 25 0 33
LS TF LF LS TF LF LS TF LF LS TF LF LS TF LF
The earliest Late Start of the following activities determines Late Finish
1. Precedence Diagram
2. Durations
ES DR EF 3. Forward Pass (ES -> EF)
“X” 4. Critical Path
LS F LF 5. Float of Critical Path Activities
6. Backward Pass (LF -> LS)
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
CALCULATING FLOAT
0 6 6 6 7 13 13 5 18
Start “A” “F” “B” End
0 0 6 6 0 13 28 15 33
0 4 4 4 8 12 13 5 18 18 7 25 25 8 33
“D” “E” “G” “H” “C”
1 1 5 5 1 13 13 0 18 18 0 25 25 0 33
1. Precedence Diagram
ES D EF 2. Durations
“X” 3. Forward Pass (ES EF)
LS F LF 4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
CALCULATING FLOAT
0 6 6 6 7 13 13 5 18
Start “A” “F” “B” End
0 0 6 6 0 13 28 15 33
0 4 4 4 8 12 13 5 18 18 7 25 25 8 33
“D” “E” “G” “H” “C”
1 1 5 5 1 13 13 0 18 18 0 25 25 0 33
1. Precedence Diagram
2. Durations
ES D EF 3. Forward Pass (ES EF)
4. Critical Path
“X”
5. Float of Critical Path Activities
LS F LF
6. Backward Pass (LF LS)
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
RESOURCE OPTIMIZATION
• Resource optimization
o Used to adjust the start and finish
dates of activities to adjust
planned resource use to be equal
to or less than resource
availability.
• Examples of resource
optimization techniques
o Resource leveling
o Resource Smoothing
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
RESOURCE LEVELING
• Resource leveling is
necessary when resources
have been over-allocated
• Produces a resource-
limited schedule
• Resource re-allocation
from non-critical to critical
activities
• Resource leveling can
often cause the original
critical path to change
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
RESOURCE SMOOTHING
• A technique that adjusts the activities of
a schedule model such that the
requirements for resources on the
project do not exceed certain
predefined resource limits.
o In resource smoothing, as opposed to
resource leveling, the projects critical
path is not changed, and the
completion date may not be delayed.
o Activities may only be delayed within
their tree and total float.
o Resource smoothing may not be able
to optimize all resources.
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
WHAT-IF SCENARIO
• Can be used to assess the
feasibility of the project schedule
under adverse conditions
• For preparing contingency and
response plans
• Monte Carlo Analysis simulates the
outcomes and uses three-point
estimate
• What-if it happens?
o Can help in dealing with path
convergence
o Activity durations may change
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
SIMULATION
• Simulation models the combined effects of individual project
risks and other sources of uncertainty to evaluate their
potential impact on achieving project objectives.
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Figure 6-18: Example of Probability Distribution of a Target Milestone. Page 213
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
SCHEDULE COMPRESSION
• Schedule compression techniques are
used to shorten or accelerate the
schedule duration without reducing
the project scope to meet schedule
constraints, imposed dates, or other
schedule objectives.
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
POSTIVE & NEGATIVE FLOAT
• FLOAT (SLACK) is extra time that a
project task, a branch of project tasks,
or the entire project can be extended
by. Less Float equals more urgent
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
FAST TRACKING Vs CRASHING
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Figure 6-19: Schedule Compression comparison. Page
215
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
PROJECT SCHEDULE PRESENTATIONS
• Result of schedule network analysis
• The iterated and realistic schedule is called
the Schedule Baseline
• Schedule can be in the form:
o Network Diagram
o Milestone Chart
o Milestone Schedule
o Summary Schedule
o Detailed Schedule
o Bar Chart (Gantt Chart)
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
EXAMPLE PROJECT SCHEDULE
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
CONTROL SCHEDULE
• Control Schedule is the process of monitoring the status of
the project to update the project schedule and managing
changes to the schedule baseline.
• The key benefit of this process is that the schedule baseline
is maintained and performed throughout the project.
o Control means measure, against the plan
o Project Managers are measuring, measuring, and measuring
against the plan and controlling the project
o Project Manager will be considered a failure if the end date
agreed to in planning is not met
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
CONTROL SCHEDULE
Tools & Techniques
• Project management plan ❑Data analysis • Work performance information
• Schedule management plan
❑ Earned value analysis • Schedule forecasts
❑ Iteration burndown chart • Change requests
• Schedule baseline
❑ Performance reviews
• Scope baseline • Project management plan updates
❑ Trend analysis
–Schedule management plan
• Performance measurement baseline Inputs ❑ Variance analysis Outputs –Schedule baseline
• Project documents ❑ What-it scenario analysis –Cost baseline
• Lessons learned register –Performance measurement baseline
❑Critical path method
• Project calendars • Project documents updates
• Project schedule ❑ Project management –Assumption log
information system –Basis of estimates
• Resource calendars –Lessons learned register
• Schedule data ❑ Resource optimization –Project schedule
–Resource calendars
• Work performance data ❑ Leads and lags –Risk register
• Organizational process assets ❑Schedule compression –Schedule data
Estimate
Plan Schedule Define Sequence Develop Control
Activity
Management Activities Activities Schedule Schedule
Durations
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Page 222
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
REFERENCES
• Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide)–Sixth Edition, Project Management Institute, Inc., 2017.
• Project Management: The Managerial Process by Erik W. Larson & Clifford F. Gray 8th Edition
• Managing Project Quality by Kloppenborg & Petrick, 2002 edition.
• Principles of Project Management by John R. Adams
• Project Management Processes, Methodologies, and Economics, 3E by Avraham Shtub & Moshe
Rosenwein
• Successful Project Management seventh Edition by Jack Gido, James P. Clements & Rose M. Baker
• Understanding the Project Environment, A Practical Guide, Second Edition by Dave C. Barrett
• Project Management by Adrienne Watt
COMMMGT 9330A
Land Acknowledgement
We acknowledge that Western University is located on the traditional lands of the Anishinaabek,
Haudenosaunee, Lūnaapéewak, and Chonnonton Nations, on lands connected with the London
Township and Sombra Treaties of 1796 and the Dish with One Spoon Covenant Wampum. With this, we
respect the longstanding relationships that Indigenous Nations have to this land, as they are the original
caretakers. We acknowledge historical and ongoing injustices that Indigenous Peoples (First Nations,
Métis and Inuit) endure in Canada, and
we accept responsibility as members of
a public institution to contribute toward
revealing and correcting miseducation as
well as renewing respectful relationships
with Indigenous communities through our
teaching, research, community service,
and employment endeavors.
COMMMGT 9330A
Session 4
Project Scope Management
COMMMGT 9330A
WHAT IS PROJECT SCOPE MANAGEMENT?
• Scope refers to all the work involved in creating the
products of the project and the processes used to
create them
• A deliverable is a product produced as part of a
project, such as hardware or software, planning
documents, or meeting minutes
• Project scope management includes the processes
involved in defining and controlling what is or is not
included in a project
How is project scope defined?
COMMMGT 9330A
7
PROJECT SCOPE PLANNING
Project Scope
o While the Project Charter defines the project’s goals and objectives, it does
not provide detailed information about what will be produced during the
project. Therefore, additional planning should be performed in order to
provide a clear definition of the requirements and details of the project’s
scope.
Project
management
plan
components
include but
are not
limited to:
Define Project Scope
Project Scope Project Scope Statement
▪Defines what needs done ▪Usually contains
▪Includes ▪ Customer requirements
▪ Items contained in project ▪ Statement of Work
charter, RFP, proposal ▪ Deliverables
▪ More detail ▪ Acceptance Criteria
▪ Work Breakdown Structure
▪Establishes common
understanding of scope with ▪Establishes baseline
stakeholders ▪Change control system to avoid
scope creep
1
2
DEFINING THE PROJECT SCOPE
Project Scope
o definition of the end result or mission of the project—a
product or service for the client/customer
Figure 8.1: Scope input-output by Flaming Sevens (http://en.wikibooks.org/wiki/File:ScopeIO.JPG) in the Public Domain
(http://en.wikipedia.org/wiki/Public_domain).
• The project manager gathers initial project facts from the project charter.
• In addition, background information on the stakeholder’s, project sponsor,
customers, competitors, suppliers, regulators, users, management strategic
plan, existing business model and rules, etc. assist in creating the vision of
the final product/service, and consequently, the project scope
1
8 Scope Management Policy
• PRODUCT SCOPE:
o What features and functions are
wanted in a product
• PROJECT SCOPE:
o The work that needs to be
accomplished to deliver a product,
service, or result
2
0
WORK
BREAKDOWN STRUCTURE
2
3
CREATE WBS
• Indentured List
2
6
THE WBS
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Page 154.
It includes:
o Account Codes
o Description of Work
o Responsible Entity
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Page 156
Project Management, the Managerial Process 7E, by Erik W. Larson and Clifford F. Gray – Chapter 4 Page 115-116
SCOPE VERIFICATION
It is very difficult to create a good scope statement and WBS
for a project
It is even more difficult to verify project scope and minimize
scope changes
Scope verification involves formal acceptance of the
completed project scope by the stakeholders
Acceptance is often achieved by a customer inspection and
then sign-off on key deliverables
Project Management, the Managerial Process 7E, by Erik W. Larson and Clifford F. Gray – Chapter 4 Page 102-108
CONTROL SCOPE
Control Scope is the process of monitoring
the status of the project and product scope
and managing changes to the scope baseline.
SCOPE CREEP
• The uncontrolled expansion to product or project scope
without adjustments to time, cost, and resources is
referred to as scope creep.
• This can occur when the scope of a project is not properly
defined, documented, or controlled.
• It is generally considered harmful.
• If budget, resources, and schedule are increased along with
the scope, the change is usually considered an acceptable
addition to the project, and the term “scope creep” is not
used.
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management
Institute, Inc., 2017. Page 722
2
GOLD PLATING
• Refers to continuing to work on a project or task well past the
point where the extra effort is worth the value it adds (if any).
• Act of giving the customer more than what he originally
asked for; something that wasn’t scoped, and often
something that the he may not want. So why do it?
• Mostly without the knowledge of the Project Manager
• Gold Plating is unethical and not allowed as per the Project
Management Code of Conduct.
Chapter Four
Defining the Project
© 2021 McGraw-Hill Education. All rights reserved. Authorized only for instructor use in the classroom.
No reproduction or further distribution permitted without the prior written consent of McGraw-Hill Education.
Where We Are Now
© McGraw-Hill Education 2
Learning Objectives
© McGraw-Hill Education 3
Chapter Outline
© McGraw-Hill Education 4
Five General Steps for Collecting Project Information
© McGraw-Hill Education 5
4.1 Step 1: Defining the Project Scope
© McGraw-Hill Education 6
Project Scope Checklist
1. Project objective
2. Product scope description
3. Justification
4. Deliverables
5. Milestones
6. Technical requirements
7. Limits and exclusions
8. Acceptance criteria
© McGraw-Hill Education 7
Project Scope: Terms and Definitions
Scope Statements
• Is a short, one- to two-page summary of key elements of the scope,
followed by extended documentation of each element.
• Is also referred to as “statements of work (SOWs)”
Project Charter
• Is a documentation that authorizes the project manager to initiate and
lead the project.
• Often includes a brief scope description as well as such items as risk
limits, business case, spending limits, and even team composition.
Scope Creep
• Is the tendency for the project scope to expand over time—usually by
changing requirements, specifications, and priorities.
© McGraw-Hill Education 8
Five of the Most Common Causes of Scope Creep
© McGraw-Hill Education 9
4.2 Step 2: Establishing Project Priorities
© McGraw-Hill Education 10
Project Management Trade-offs
© McGraw-Hill Education 13
Hierarchical Breakdown of the WBS
* This breakdown groups work packages by type of work within a deliverable and
allows assignment of responsibility to an organizational unit. This extra step
facilitates a system for monitoring project progress (discussed in Chapter 13).
© McGraw-Hill Education FIGURE 4.3 14
How WBS Helps the Project Manager
• Assures project managers that all products and work elements are identified, to
integrate the project with the current organization, and to establish a basis for
control.
• Facilitates the evaluation of cost, time, and technical performance at all levels in
the organization over the life of the project.
• Provides management with information appropriate to each organizational level.
• Helps project managers to plan, schedule, and budget the project.
• Helps in the development of the organization breakdown structure (OBS), which
assigns project responsibilities to organization units and individuals.
• Provides the opportunity to “roll up” (sum) the budget and actual costs of the
smaller work packages into larger work elements.
• Defines communication channels and assists in understanding and coordinating
many parts of the project.
© McGraw-Hill Education 15
Work Breakdown Structure
© McGraw-Hill Education 17
Each Work Package in the WBS
© McGraw-Hill Education 18
4.4 Step 4: Integrating the WBS with the Organization
© McGraw-Hill Education 19
Integration of WBS and OBS
© McGraw-Hill Education 21
Coding the WBS
© McGraw-Hill Education 23
PBS for Software Development Project
© McGraw-Hill Education 25
Responsibility Matrix for a Market Research Project
© McGraw-Hill Education 28
Steps for Developing a Communication Plan
© McGraw-Hill Education 29
Stakeholder Communications
© McGraw-Hill Education 32
Because learning changes everything. ®
www.mheducation.com
© 2021 McGraw-Hill Education. All rights reserved. Authorized only for instructor use in the classroom.
No reproduction or further distribution permitted without the prior written consent of McGraw-Hill Education.
Land Acknowledgement
We acknowledge that Western University is located on the traditional lands of the Anishinaabek,
Haudenosaunee, Lūnaapéewak, and Chonnonton Nations, on lands connected with the London
Township and Sombra Treaties of 1796 and the Dish with One Spoon Covenant Wampum. With this, we
respect the longstanding relationships that Indigenous Nations have to this land, as they are the original
caretakers. We acknowledge historical and ongoing injustices that Indigenous Peoples (First Nations,
Métis and Inuit) endure in Canada, and
we accept responsibility as members of
a public institution to contribute toward
revealing and correcting miseducation as
well as renewing respectful relationships
with Indigenous communities through our
teaching, research, community service,
and employment endeavors.
COMMMGT 9330A
Session 5
Project Cost Management
COMMMGT 9330A
PROJECT COST MANAGEMENT
COMMMGT 9330A
PROJECT COST MANAGEMENT
The Project Cost Management processes are:
1
PLAN COST • process of defining how the project costs will be estimated,
budgeted, managed, monitored, and controlled.
MANAGEMENT
2
ESTIMATE • process of developing the approximation of the monetary
resources needed to complete project work.
COSTS
DETERMINE • process of aggregating the estimated costs of individual
3 activities or work packages to establish an authorized cost
BUDGET baseline.
4
CONTROL • process of monitoring the status of the project to update the
project costs and manage changes to the cost baseline.
COSTS
COMMMGT 9330A
PROJECT COST MANAGEMENT
• Higher project costs may have one or more of the following impacts:
o A change to the project’s Business Case justification, leading to the potential
cancellation of the project
o Deferral of other projects due to reduced availability of funding
o Fewer funds available for expenditure within the organization
o Reduction of the company’s profit (in for-profit organizations) or increased
deficits and/or tax increases (in government or not-for-profit organizations)
COMMMGT 9330A
PROJECT COST MANAGEMENT
There are two main steps when planning for project cost:
@ Dave C. Barrett
COMMMGT 9330A
KEY CONCEPTS FOR COST MANAGEMENT
COMMMGT 9330A
TAILORING
CONSIDERATIONS
Each project is unique, and the project manager needs to tailor the way Cost
Management processes are applied.
Considerations for tailoring include but are not limited to:
KNOWLEDGE • does the organization have a formal knowledge management and
financial database repository that a project manager is required to use and
MANAGEMENT that is readily accessible?
ESTIMATING AND • does the organization have existing formal or informal cost
estimating and budgeting-related policies, procedures, and
BUDGETING guidelines?
EARNED VALUE • does the organization use earned value management in managing
MANAGEMENT projects?
USE OF AGILE • does the organization use agile methodologies in managing projects?
APPROACH How does this impact cost estimating?
COMMMGT 9330A
PLAN COST
MANAGEMENT
Tools & Techniques
• Project charter
❑ Expert judgment
• Project management plan
Inputs Outputs • Cost Management Plan
• Schedule management plan ❑ Data analysis
• Risk management plan
• Enterprise environmental factors ❑ Meetings
• Organizational process assets
COMMMGT 9330A
CONTROL
THRESHOLDS
• Thinking ahead how costs will
be controlled
• Control Thresholds are the
amount of variation allowed
before taking action
• Determined in planning while
creating the Cost
Management Plan
• Thresholds are normally
expressed as percentage
deviations (%∑) from the
baseline plan
COMMMGT 9330A
ESTIMATE COSTS
Quantitative assessment of the likely costs for resources
required to complete the activity.
@ Dave C. Barrett
COMMMGT 9330A
ESTIMATE COSTS Direct Cost
Indirect
Fixed Cost
Variable
Sunk Cost
Cost Cost
Other Examples:
Other Examples: Other Examples: Other Examples: Other Examples: Marketing /
Project resources, Management fees, Salaries, Rentals, Work, Material, Advertising cost,
Licenses, Software HR, General fees Machinery, Tooling Consultant, Energy R&D cost, Training
cost, Hiring cost
COMMMGT 9330A
ESTIMATE COSTS
Tools & Techniques
❑ Expert Judgment
• Project management plan ❑ Analogous estimating
• Cost management plan
• Quality management plan ❑ Parametric estimating • Cost estimates
• Scope baseline • Basis of estimates
❑ Bottom-up estimating
• Project documents Inputs Outputs • Project documents
• Lessons learned register ❑ Three-point estimating updates
• Project schedule
❑ Data analysis – Assumption log
• Resources requirements
– Lessons learned register
• Risk register ❑ Alternatives analysis
– Risk register
• Enterprise environmental factors ❑ Reserve analysis
• Organizational process assets ❑ Cost of quality
❑ Project management
information system
❑ Decision making
❑ Voting
COMMMGT 9330A
ENTERPRISE ENVIRONMENTAL FACTORS
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Page 242
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc.
COMMMGT 9330A
TOOLS AND
TECHNIQUES
COMMMGT 9330A
BUILD BUDGET AND CONTROL COSTS
COMMMGT 9330A
DETERMINE
BUDGET
Determine Budget is the process of aggregating the estimated
costs of individual activities or work packages to establish an
authorized cost baseline.
The key benefit of this process is that it BUDGET
determines the cost baseline against which
project performance can be monitored
and controlled.
COMMMGT 9330A
DETERMINE
BUDGET
Tools & Techniques
❑ Expert Judgment
• Project management plan ❑ Analogous estimating
• Cost management plan
• Quality management plan ❑ Parametric estimating • Cost estimates
• Scope baseline
❑ Bottom-up estimating • Basis of estimates
• Project documents Inputs Outputs • Project documents
• Lessons learned register ❑ Three-point estimating updates
• Project schedule
❑ Data analysis – Assumption log
• Resources requirements
– Lessons learned register
• Risk register ❑ Alternatives analysis
– Risk register
• Enterprise environmental factors ❑ Reserve analysis
• Organizational process assets ❑ Cost of quality
❑ Project management
information system
❑ Decision making
❑ Voting
COMMMGT 9330A
COST AGGREGATION
Contingency Reserves are
kept aside for “known
unknowns” risks captured in the
risk register and controlled by
project manager
COMMMGT 9330A
PROJECT FUNDING
COMMMGT 9330A
BAC – Budget at Completion
COMMMGT 9330A
CONTROL
COSTS
Control means measure
• You measure and measure and measure
• Follow the cost management plan
• You need to have an “attitude” of
control
• It is your project and your career
• Be assertive and make sure the project
goes according to the plan
• This process is performed throughout the
project.
COMMMGT 9330A
INCREMENTAL
MILESTONE
COMMMGT 9330A
CONTROL
COSTS
Tools & Techniques
• Cost estimates
–Lessons learned register
–Risk register
COMMMGT 9330A
EARNED VALUE
MEASUREMENT
• EVM integrates cost, time, and the work done
• Scope, Schedule, and Cost baselines constitute Performance
Measurement Baseline
• Earned Value will lead to budget forecasts, change requests,
and other items that will need to be communicated
• EV is an effective tool for measuring performance and
determining the need to request changes
COMMMGT 9330A
EARNED VALUE
TERMS
*BAC – Budget At
Completion
COMMMGT 9330A
EARNED VALUE TERMS
(Cont.)
COMMMGT 9330A
EARNED VALUE
TERMS
Estimate At Completion
Project Budget Base
Performance Measurement Base Budget At Completion
Estimate To Completion
Management Reserve (MR) is a portion of the Project Budget Base (PBB) withheld for
management control purposes rather than being identified and distributed to
accomplish specific tasks.
Performance Measurement Baseline (PMB) - PMB equals the total allocated budget
less MR
COMMMGT 9330A
EARNED VALUE
TERMS
Estimate at Completion (EAC):
• What do we currently expect the total project to cost (a forecast)
COMMMGT 9330A
EARNED VALUE
TERMS
COST VARIANCE (CV)
CV = EV – AC
• Negative is over budget
• Positive is under budget
COMMMGT 9330A
EARNED VALUE
TERMS
COST PERFORMANCE INDEX (CPI)
CPI = EV / AC
• We are getting $ ------ worth of work out of every $ 1 spent
• Funds are or are not being used efficiently
COMMMGT 9330A
EARNED VALUE
TERMS
ESTIMATE AT COMPLETION (EAC)
• As of now, how much do we expect the total project to
cost? i.e., $ ----------
• There are many ways to calculate EAC, depending on
the assumptions made
• The purpose of the formulas really is to create forecasts
based on past performance of the project
COMMMGT 9330A
EARNED VALUE
TERMS
ESTIMATE AT COMPLETION (EAC):
o AC + Bottom up ETC:
• Actual + New estimate for the remaining work.
• Used when the original estimate was fundamentally flawed
o BAC/Cumulative CPI:
• Used if no variances from the BAC have occurred or you will continue
at the same rate of spending
COMMMGT 9330A
EARNED VALUE
TERMS
ESTIMATE AT COMPLETION (EAC):
o AC+(BAC-EV):
• Calculates actual to date plus remaining budget.
• Used when current variances are thought to be atypical of
the future
• AC plus the remaining value of work to perform
COMMMGT 9330A
EARNED VALUE
TERMS
ESTIMATE AT COMPLETION (EAC):
o AC + [(BAC-EV) / (Cumulative CPI x Cumulative SPI)]:
• Calculates actual to date plus the remaining budget modified
by performance
• Used when current variances are thought to be typical of the
future
• Assumes poor cost performance and a need to hit a firm
completion date
COMMMGT 9330A
EARNED VALUE
TERMS
FORECASTING
• Using the information, you have about the project at a given time
and predict how close it will come to its goals if it keeps going
the way it has been
• Forecasting uses earned value numbers to help you come up
with preventive and corrective actions that can keep your
project on the right track
COMMMGT 9330A
EARNED VALUE
TERMS
TO-COMPLETE PERFORMANCE INDEX
• TCPI is a calculation that you can use to help you figure out how
well your project needs to perform in the future in order to stay
on budget
• If the cumulative CPI falls below the baseline plan, all future work
of the project will need to immediately be performed in the range
of the TCPI (BAC)
COMMMGT 9330A
TO-COMPLETE PERFORMANCE INDEX (TCPI)
COMMMGT 9330A
PERFORMANCE
REVIEWS
• Reviews are meetings where the project team reviews performance
data to examine the variance between actual performance and
the baseline
• Earned value management (EVM) is used to calculate and track
the variance
• Over time, these meetings are a good place to look into trends in
the data
COMMMGT 9330A
VARIANCE
ANALYSIS
Throughout your project, you are looking at how you are doing
as compared to your plan
The variance between planned and actual performance needs
to be carefully analyzed so you can head off problems before
they make your project go over budget
The percentage range of acceptable variances will tend to
decrease as more work is accomplished
The larger percentage variances allowed at the start of the
project can decrease as the project nears completion
Project Management, the Managerial Process 7E, by Erik W. Larson and Clifford F. Gray – Chapter 13, Page 468-469
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Page 262-268
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute, Inc. COMMMGT 9330A
PROJECT MANAGEMENT SOFTWARE
• Software packages can be used to track your budget and
make it easier to know where you might run into trouble
• Monitors the three EVM dimensions (PV, EV, AC)
• Displays graphical trends
• Forecasts a range of possible final project results
COMMMGT 9330A
REFERENCES
• Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide)–Sixth Edition, Project Management Institute, Inc., 2017.
• Project Management: The Managerial Process by Erik W. Larson & Clifford F. Gray 8th Edition
• Managing Project Quality by Kloppenborg & Petrick, 2002 edition.
• Principles of Project Management by John R. Adams
• Project Management Processes, Methodologies, and Economics, 3E by Avraham Shtub & Moshe
Rosenwein
• Successful Project Management seventh Edition by Jack Gido, James P. Clements & Rose M.
Baker
• Understanding the Project Environment, A Practical Guide, Second Edition by Dave C. Barrett
• Project Management by Adrienne Watt
COMMMGT 9330A
Land Acknowledgement
We acknowledge that Western University is located on the traditional lands of the Anishinaabek,
Haudenosaunee, Lūnaapéewak, and Chonnonton Nations, on lands connected with the London
Township and Sombra Treaties of 1796 and the Dish with One Spoon Covenant Wampum. With this, we
respect the longstanding relationships that Indigenous Nations have to this land, as they are the original
caretakers. We acknowledge historical and ongoing injustices that Indigenous Peoples (First Nations,
Métis and Inuit) endure in Canada, and
we accept responsibility as members of
a public institution to contribute toward
revealing and correcting miseducation as
well as renewing respectful relationships
with Indigenous communities through our
teaching, research, community service,
and employment endeavors.
COMMMGT 9330A
Session 4
Project Scope Management
COMMMGT 9330A
How is project scope defined?
COMMMGT 9330A
7
PROJECT SCOPE PLANNING
Project Scope
o While the Project Charter defines the project’s goals and objectives, it does not
provide detailed information about what will be produced during the project. Therefore,
additional planning should be performed to provide a clear definition of the
requirements and details of the project’s scope.
COMMMGT 9330A
8
PROJECT SCOPE PLANNING
COMMMGT 9330A
9
SCOPE PLANNING AND THE SCOPE MANAGEMENT
PLAN
• The scope management plan is a document that includes
descriptions of how the team will prepare the project scope
statement, create the WBS, verify the completion of the project
deliverables, and control requests for changes to the project
scope
• Key inputs include the project charter, preliminary scope
statement, and project management plan
• It should be reviewed with the project sponsor to make sure the
approach meets expectations
COMMMGT 9330A
PROJECT MANAGEMENT PLAN
Project
management plan
components
include but are not
limited to:
COMMMGT 9330A
Define Project Scope
COMMMGT 9330A
DEFINING THE PROJECT
SCOPE
Project Scope
o Define the (end) result or mission of the project—a product or service for the
client/customer
COMMMGT 9330A
Project Requirements
COMMMGT 9330A
BEST PRACTICES FOR AVOIDING SCOPE PROBLEMS
1. Keep the scope realistic: Don’t make projects so large that they can’t be
completed; break large projects down into a series of smaller ones
2. Involve users in project scope management: Assign key users to
the project team and give them ownership of requirements definition and scope
verification
3. Follow good project management processes: As described in this
chapter and others, there are well-defined processes for managing project
scope and other aspects of projects
COMMMGT 9330A
SUGGESTIONS FOR IMPROVING USER INPUT
• Develop a good project selection process and insist that sponsors are
from the user organization
• Have users on the project team in important roles
• Have regular meetings with defined agendas, and have users sign off
on key deliverables presented at meetings
• Deliver something to users and sponsors on a regular basis
• Don’t promise to deliver when you know you can’t
• Co-locate users with developers
COMMMGT 9330A
USING SOFTWARE TO ASSIST IN PROJECT SCOPE
MANAGEMENT
• Word-processing software helps create several scope-related
documents
• Spreadsheets help to perform financial calculations and weigh
scoring models, and develop charts and graphs
• Communication software like e-mail and the Web help clarify
and communicate scope information
• Project management software helps in creating a WBS, the
basis for tasks on a Gantt chart
• Specialized software is available to assist in project scope
management
COMMMGT 9330A
Scope Inputs / Tools + Techniques / Outputs
TOOLS/TECHNIQUE
OUTPUTS
INPUTS S
• The project manager gathers initial project facts from the project
charter.
• In addition, background information on the stakeholders, project
sponsor, customers, competitors, suppliers, regulators, users,
management strategic plan, existing business model and rules,
etc. assist in creating the vision of the final product/service, and
consequently, the project scope
COMMMGT 9330A
Scope Management Policy
COMMMGT 9330A
KEY CONCEPTS OF
SCOPE
• PRODUCT SCOPE:
o What features and functions are wanted in a product
• PROJECT SCOPE:
o The work that needs to be accomplished to deliver a
product, service, or result
COMMMGT 9330A
PROJECT SCOPE MANAGEMENT
PROCESSES
Plan Scope Management:
o Deciding how the scope will be defined, verified, and controlled
Collect Requirements
o The process of determining, documenting, and managing stakeholder
needs and requirements to meet objectives.
Scope definition:
o Reviewing the project charter and preliminary scope statement and adding
more information as requirements are developed and change requests are
approved
COMMMGT 9330A
PROJECT SCOPE MANAGEMENT PROCESSES
COMMMGT 9330A
2
2
WORK
BREAKDOWN STRUCTURE
COMMMGT 9330A
CREATE WBS
• Process of subdividing project deliverables and project work into
smaller, more manageable components.
• A hierarchical outline (map) that identifies the products and work
elements involved in a project
• Defines the relationship of the final deliverable (the project) to its
sub-deliverables, and in turn, their relationships to work packages.
• Provides a framework of what has to be delivered. Performed
once/at predetermined points.
COMMMGT 9330A
Create Work Breakdown Structure
• Deliverable-oriented hierarchical decomposition
• Organize project work/deliverables - logical groupings
• Subdivide into more manageable components
• Deliverable is the output of the work package
• Resource requirements and durations can be assigned
• Accountability can be assigned; PM can monitor and control
• Decomposition is subdividing project deliverables into smaller
pieces
• A work package is a task at the lowest level of the WBS
• Tasks on a WBS represent work that needs to be done to
complete the project, not specifications (e.g., type of server)
COMMMGT 9330A
WBS
• Graphic Chart
• Indentured List
COMMMGT 9330A
THE
WBS
COMMMGT 9330A
CREATING THE
WBS
• The WBS defines the scope of the project and breaks the
work down into components that can be scheduled,
estimated, and easily monitored and controlled.
• Decompose a complicated task into smaller tasks, until you
reach a level that cannot be further subdivided.
• Stop breaking down the work when you reach a low enough
level to perform an estimate of the desired accuracy.
COMMMGT 9330A
EXAMPLE
WBS
COMMMGT 9330A
HIERARCHICAL BREAKDOWN OF THE WBS
COMMMGT 9330A
PROJECT SCOPE
STATEMENT
• The Project Scope Statement, WBS, and WBS Dictionary make the
Scope Baseline
• Project Scope Statement includes:
• Constraints and Assumptions
• Product Scope
• Deliverables
• Exclusions
• Acceptance Criteria
• Risks
COMMMGT 9330A
PROJECT SCOPE
STATEMENT
The detailed project scope statement, either directly or by reference to other documents, includes the
following:
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Page 154.
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute, Inc.
COMMMGT 9330A
WBS DICTIONARY
Provides a detailed description of the components in the
WBS, including work packages, and control accounts
It includes:
o Account Codes
o Description of Work
o Responsible Entity
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute, Inc.
COMMMGT 9330A
THE WBS DICTIONARY AND SCOPE BASELINE
• Many WBS tasks are vague and must be explained more so
people know what to do and can estimate how long it will
take and what it will cost to do the work
• A WBS dictionary is a document that describes detailed
information about each WBS item
• The approved project scope statement + its WBS + WBS
dictionary = scope baseline, which is used to measure
performance in meeting project scope goals
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Page 156
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute, Inc. COMMMGT 9330A
CREATING A WBS & WBS
DICTIONARY
• Project team members should be involved in developing the
WBS to ensure consistency and buy-in
• Each WBS item must be documented in a WBS dictionary to
ensure an accurate understanding of the scope of work
included and not included in that item
• The WBS must be a flexible tool to accommodate inevitable
changes while properly maintaining control of the work content
in the project according to the scope statement
Project Management, the Managerial Process 7E, by Erik W. Larson and Clifford F. Gray – Chapter 4 Page 115-116
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute, Inc. COMMMGT 9330A
APPROACHES TO DEVELOPING A
WBS’s
• Using guidelines: some organizations, provide guidelines for
preparing WBSs
• The analogy approach: review WBSs of similar projects and tailor
them to your project
• The top-down approach: start with the largest items of the project
and break them down
• The bottom-up approach: start with the specific tasks and roll
them up
• Mind-mapping approach: mind mapping is a technique that uses
branches radiating out from a core idea to structure thoughts and
ideas
COMMMGT 9330A
SCOPE VERIFICATION
It is very difficult to create a good scope statement and WBS for a project
It is even more difficult to verify project scope and minimize scope changes
Scope verification involves formal acceptance of the completed project scope
by the stakeholders
Acceptance is often achieved by a customer inspection and then sign-off on key
deliverables
Project Management, the Managerial Process 7E, by Erik W. Larson and Clifford F. Gray – Chapter 4 Page 102-108
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute, Inc. COMMMGT 9330A
SCOPE
CONTROL
Scope control involves controlling changes to the project scope
The goals of scope control are to:
o Influence the factors that cause scope changes
o Assure changes are processed according to procedures developed as part of
integrated change control
o Manage changes when they occur
o Tools for performing scope control include a change control system and
configuration management
Variance is the difference between planned and actual performance
Project Management, the Managerial Process 7E, by Erik W. Larson and Clifford F. Gray – Chapter 4 Page 102-108
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute, Inc. COMMMGT 9330A
VALIDATE
8
SCOPE
Validate Scope is the process of formalizing acceptance of
the completed project deliverables.
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Page 163
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute, Inc. COMMMGT 9330A
9
DIFFERENCE BETWEEN QUALITY CONTROL AND
VALIDATE SCOPE
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute, Inc. COMMMGT 9330A
CONTROL
0
SCOPE
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute,
Inc. COMMMGT 9330A
SCOPE1
CREEP
• The uncontrolled expansion of
product or project scope without
adjustments to time, cost, and
resources is referred to as scope
creep.
• This can occur when the scope of a
project is not properly defined,
documented, or controlled.
• It is generally considered harmful.
• If budget, resources, and schedule
are increased along with the scope,
the change is usually considered an
acceptable addition to the project,
and the term “scope creep” is not
used.
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Page 722
COMMMGT 9330A
GOLD 2
PLATING
• Refers to continuing to work on a project or task well past the point where
the extra effort is worth the value it adds (if any).
• Act of giving the customer more than what he originally asked for;
something that wasn’t scoped, and often something that he/she may not
want. So why do it?
• Mostly without the knowledge of the Project Manager
• Gold Plating is unethical and not allowed as per the Project
Management Code of Conduct.
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute, Inc. COMMMGT 9330A
WHICH 3PROCESS COMES FIRST?
• There is no “right order” for the control scope and scope verification
• Control Scope can occur either before and after the scope
verification/validation
• The goal of Control Scope is updating the scope, plan, baseline,
and WBS info
PMI, PMBOK, PMP, and CAPM are registered marks of Project Management Institute, Inc. COMMMGT 9330A
REFERENCES
• Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide)–Sixth Edition, Project Management Institute, Inc., 2017.
• Project Management: The Managerial Process by Erik W. Larson & Clifford F. Gray 8th Edition
• Managing Project Quality by Kloppenborg & Petrick, 2002 edition.
• Principles of Project Management by John R. Adams
• Project Management Processes, Methodologies, and Economics, 3E by Avraham Shtub & Moshe
Rosenwein
• Successful Project Management seventh Edition by Jack Gido, James P. Clements & Rose M.
Baker
• Understanding the Project Environment, A Practical Guide, Second Edition by Dave C. Barrett
• Project Management by Adrienne Watt
COMMMGT 9330A
Because learning changes everything.®
Chapter Three
Organization: Structure
and Culture
© 2021 McGraw-Hill Education. All rights reserved. Authorized only for instructor use in the classroom.
No reproduction or further distribution permitted without the prior written consent of McGraw-Hill Education.
Where We Are Now
© McGraw-Hill Education 2
Learning Objectives
© McGraw-Hill Education 3
Chapter Outline
© McGraw-Hill Education 4
3.1 Project Management Structures
© McGraw-Hill Education 5
Organizing Projects within the Functional Organization
© McGraw-Hill Education 6
Functional Organizations
Advantages Disadvantages
1. No change 1. Lack of focus
2. Flexibility 2. Poor integration
3. In-depth expertise 3. Slow
4. Easy post-project transition 4. Lack of ownership
© McGraw-Hill Education 8
Organizing Projects as Dedicated Teams
• Dedicated project teams operate as units separate from the rest of the
parent organization.
• A full-time project manager is designated to pull together a core group
of specialists who work full time on the project.
• The project manager recruits necessary personnel from both within
and outside the parent company.
• In a projectized organization where projects are the dominant form of
business, the entire organization is designed to support project teams.
• “Projectitis” is referred to as a negative dimension to dedicated project
teams. A we-they attitude can emerge between project team
members and the rest of the organization.
© McGraw-Hill Education 9
Dedicated Project Team
Strengths Weaknesses
1. Simple 1. Expensive
2. Fast 2. Internal strife
3. Cohesive 3. Limited technological expertise
4. Cross-functional integration 4. Difficult post-project transition
© McGraw-Hill Education 12
Organizing Projects within a Matrix Arrangement
• There are usually two chains of command, one along functional lines and the
other along project lines.
© McGraw-Hill Education 13
Matrix Organization Structure
Weak matrix
• This form is very similar to a functional approach with the exception
that there is a formally designed project manager responsible for
coordinating project activities.
• Functional managers are responsible for managing their segment of
the project.
• The project manager acts as a staff assistant who draws the
schedules and checklists, collects information on the status of the
work, and facilitates project completion.
© McGraw-Hill Education 16
Different Matrix Forms (Continued)
Balanced matrix
• The project manager is responsible for defining what needs to be
accomplished. The project manager establishes the overall plan for
completing the project, integrates the contribution of the different
disciplines, set schedules, and monitors progress.
• The functional managers are concerned with how it will be
accomplished. The functional managers are responsible for assigning
personnel and executing their segment of the project according to the
standards and schedules set by the project manager.
© McGraw-Hill Education 17
Different Matrix Forms (Continued)
Strong matrix
• The project manager controls most aspects of the project, including
scope trade-offs and assignment of functional personnel. The project
manager controls when and what specialists do and has final say on
major project decisions.
• The functional managers have title over their people and are consulted
on a need basis. The functional managers serve as subcontractors for
the project.
© McGraw-Hill Education 18
Advantages and Disadvantages of Matrix Management
Advantages Disadvantages
1. Efficient 1. Dysfunctional conflict
2. Strong project focus 2. Infighting
3. Easier post-project transition 3. Stressful
4. Flexible 4. Slow
© McGraw-Hill Education 19
3.2 Project Management Office (PMO)
© McGraw-Hill Education 20
3.3 What Is the Right Project Management Structure?
Organization Considerations
• How important is the project management to the success of the firm?
• What percentage of core work involves projects?
• What level of resources are available?
Project Considerations
• Size of project
• Strategic importance
• Novelty and need for innovation
• Need for integration (number of departments involved)
• Environmental complexity (number of external interfaces)
• Budget and time constraints
• Stability of resource requirements
© McGraw-Hill Education 21
3.4 Organizational Culture
© McGraw-Hill Education 22
Key Dimensions Defining an Organization’s Culture
© McGraw-Hill Education 24
Organizational Culture Diagnosis Worksheet
© McGraw-Hill Education 26
Cultural Dimensions of an Organization Supportive of Project Management
Balanced matrix
Dedicated project team
Matrix
Organizational culture
Projectitis
Projectized organization
Project management office (PMO)
Strong matrix
Weak matrix
© McGraw-Hill Education 28
Because learning changes everything. ®
www.mheducation.com
© 2021 McGraw-Hill Education. All rights reserved. Authorized only for instructor use in the classroom.
No reproduction or further distribution permitted without the prior written consent of McGraw-Hill Education.
Land Acknowledgement
We acknowledge that Western University is located on the traditional lands of the Anishinaabek,
Haudenosaunee, Lūnaapéewak, and Chonnonton Nations, on lands connected with the London
Township and Sombra Treaties of 1796 and the Dish with One Spoon Covenant Wampum. With this, we
respect the longstanding relationships that Indigenous Nations have to this land, as they are the original
caretakers. We acknowledge historical and ongoing injustices that Indigenous Peoples (First Nations,
Métis and Inuit) endure in Canada, and
we accept responsibility as members of
a public institution to contribute toward
revealing and correcting miseducation as
well as renewing respectful relationships
with Indigenous communities through our
teaching, research, community service,
and employment endeavors.
COMMMGT 9330A
Session 3
Organization Structure & Culture
COMMMGT 9330A
Chapter Outline
• Project Management Structures
• Project Management Office (PMO)
• What Is the Right Project Management Structure?
• Organizational Culture
• Implications of Organizational Culture for Organizing Projects
• Project Manager
COMMMGT 9330A
Project Management
Structures
Project Management Structures
Functional
organization
Dedicated
project
teams
Matrix
• Weak matrix
structure • Balanced matrix
• Strong matrix
Organizing Projects within the Functional Organization
• Top management decides to implement the project, and
different segments of the project are distributed to
appropriate areas.
• Coordination is maintained through normal management
channels.
• It is commonly used when one functional area plays a
dominant role in completing the project or has a dominant
interest in the success of the project.
COMMMGT 9330A
Projects and Organization Structure
COMMMGT 9330A
Project Organization Chart:
Who Are The Team Members?
COMMMGT 9330A
Project Management by Adrienne Watt
COMMMGT 9330A
Functional Organizations
• FIGURE 3.1
• Access the text alternative for slide images.
COMMMGT 9330A
Advantages and Disadvantages of Using Functional
Organization to Administer and Complete Projects
• Advantages • Disadvantages
1. No change 1. Lack of focus
2. Flexibility 2. Poor integration
3. In-depth expertise 3. Slow
4. Easy post-project transition 4. Lack of ownership
COMMMGT 9330A
Dedicated Project Team
COMMMGT 9330A
Organizing Projects as Dedicated Teams
• Dedicated project teams operate as units separate from the rest of the parent
organization.
• A full-time project manager is designated to pull together a core group of specialists
who work full-time on the project.
• The project manager recruits necessary personnel from both within and outside the
parent company.
• In a projectized organization where projects are the dominant form of business, the
entire organization is designed to support project teams.
• “Projectitis” is referred to as a negative dimension to dedicated project teams. A we-
they attitude can emerge between project team members and the rest of the
organization.
COMMMGT 9330A
Strengths and Weaknesses of the Dedicated Project Team
Approach
• Strengths • Weaknesses
1. Simple 1. Expensive
2. Fast 2. Internal strife
3. Cohesive 3. Limited technological
expertise
4. Cross-functional integration
4. Difficult post-project transition
COMMMGT 9330A
Projectized Organization Structure
• FIGURE 3.3
• Access the text alternative for slide images.
COMMMGT 9330A
Organizing Projects within a Matrix Arrangement
Matrix management is a hybrid organizational form in which a horizontal project
management structure is overlaid on the normal functional hierarchy.
• There are usually two chains of command, one along functional lines and the other along project
lines.
• Project participants report simultaneously to both functional and project managers.
The matrix structure is designed to utilize resources optimally.
• Individuals work on multiple projects as well as being capable of performing normal functional
duties.
• It attempts to achieve greater integration by creating and legitimizing the authority of a project
manager.
• It provides a dual focus between functional/technical expertise and project requirements.
COMMMGT 9330A
Matrix Organization Structure
What has to be done? Who will do the task? How will it be done?
How much money is Why will the task be done? How will the project involvement
available to do the task? impact normal functional
activities?
How well has the total project Is the task satisfactorily How well has the functional input
been done? completed? been integrated?
• TABLE 3.1
COMMMGT 9330A
Different Matrix Forms
• Weak matrix
• This form is very similar to a functional approach with the exception that there is a formally
designed project manager responsible for coordinating project activities.
• Functional managers are responsible for managing their segment of the project.
• The project manager acts as a staff assistant who draws the schedules and checklists, collects
information on the status of the work, and facilitates project completion.
COMMMGT 9330A
Different Matrix Forms
• Balanced matrix
• The project manager is responsible for defining what needs to be accomplished.
• The project manager establishes the overall plan for completing the project, integrates the contribution of the
different disciplines, set schedules, and monitors progress.
COMMMGT 9330A
Different Matrix Forms
• Strong matrix
• The project manager controls most aspects of the project, including scope trade-offs and
assignment of functional personnel.
• The project manager controls when and what specialists do and has final say on major project decisions.
• The functional managers have title over their people and are consulted on a need basis.
• The functional managers serve as subcontractors for the project.
COMMMGT 9330A
Advantages and Disadvantages of Matrix Management
• Advantages • Disadvantages
1. Efficient 1. Dysfunctional conflict
2. Strong project focus 2. Infighting
3. Easier post-project 3. Stressful
transition
4. Slow
4. Flexible
COMMMGT 9330A
Project Management Office (PMO)
• Is a centralized unit within an organization or a department that oversees and
supports the execution of projects.
• Plays a critical role in helping matrix systems mature into more effective project
delivery platforms.
• Can be characterized in different kinds:
• Weather station—tracks and monitors project performance.
• Control tower—improves project execution.
• Resource pool—provides the organization with a cadre of trained project managers and
professionals.
• Command and control center—has direct authority over the project.
COMMMGT 9330A
Project Management Office (PMO)
• Supportive | Degree of control: LOW
• Consultative role to projects
• Providing templates, best practices, training, lessons learned
• Serves as project repository
• Controlling | Degree of control: MODERATE
• Support to projects
• Require compliance namely adoption of frameworks or methodologies
• Use of prescriptive templates, forms, tools, etc.
• Conformance to governance frameworks
• Directive | Degree of control: HIGH
• Take control of the projects directly
• Project Managers directly report to PMO
COMMMGT 9330A
Project Manager
• PMBOK Definition | Person assigned by the performing organization to lead the
team that is responsible for achieving the project objectives
• Mainly involved from initiation to closing
• May be involved in evaluation and analysis activities prior to initiation
• May consult with executives and business unit leaders to advance strategic
objectives, improve organizational performance, or meet customer needs
• May assist in business analysis, business case development, and portfolio
management
• Performs communication between stakeholders, team, and sponsors
• Apt in using soft skills to defuse conflicts and build consensus
COMMMGT 9330A
Project Manager Influence
COMMMGT 9330A
• Technical Project Management | Knowledge, Skills, and • Ways of Working | Apply the right techniques (predictive, agile,
Behaviors related to specific domains of project, program, design thinking, etc.) at the right time, delivering winning results
and portfolio management • Power Skills | Communication, Collaborative leadership, innovative
• Leadership | Knowledge, Skills, and Behaviors needed to mindset, for-purpose orientation, and empathy. A critical component
guide, motivate, and direct a team, to help an organization for making change – maintaining influence with a variety of
achieve its business goals stakeholders
• Strategic & Business Management | Knowledge and • Business Acumen | Understand micro and macro influences in the
expertise in industry and organization that enhance organization and industry, function-specific or domain-specific
performance and better deliver business outcomes knowledge to make good decisions
COMMMGT 9330A
What Is the Right Project Management Structure?
• Organization Considerations
• How important is project management to the success of the firm?
• What percentage of core work involves projects?
COMMMGT 9330A
Organizational Culture
• Organizational Culture Defined
• Is a system of shared norms, beliefs, values, and assumptions that blinds people
together, thereby creating shared meanings.
• Reflects the “personality” of the organization.
• Performs several important functions in organizations.
• Provides a sense of identity for its members
• Helps legitimize the management system
• Clarifies and reinforces standards of behavior
• Helps create social order
COMMMGT 9330A
Key Dimensions Defining an Organization’s Culture
COMMMGT 9330A
Identifying Cultural Characteristics
COMMMGT 9330A
Organizational Culture Diagnosis Worksheet
• Power Corp.
• I. Physical Characteristics:
• Corporate HQ is a 20-story modern building—president on top floor. Offices are bigger in the top floors than lower floors. Formal business attire (white shirts, ties, power suits, . .
.). Power appears to increase the higher up you are.
• II. Public Documents:
• At the heart of the Power Corp. way is our vision . . . to be the global energy company most admired for its people, partnership, and performance.
• Integrity. We are honest with others and ourselves. We meet the highest ethical standards in all business dealings. We do what we say we will do.
• III. Behavior:
• Pace, language, meetings, issues discussed, decision-making style, communication patterns, rituals
• Hierarchical decision making, pace brisk but orderly, meetings start on time and end on time, subordinates choose their words very carefully when talking to superiors, people
rarely work past 6:00 p.m., president takes top-performing unit on a boat cruise each year. . . .
• IV. Folklore:
• Young project manager was fired after going over his boss’s head to ask for additional funds.
• Stephanie C. was considered a hero for taking complete responsibility for a technical error.
• Jack S. was labeled a traitor for joining chief competitor after working for Power Corp. for 15 years.
• FIGURE 3.6
COMMMGT 9330A
Implications of Organizational Culture for Organizing
Projects
• Project managers interact with:
• The culture of their parent organizations as well as the subcultures of various departments.
• The project’s clients or customer organizations.
• Other organizations connected to the project such as suppliers and vendors, subcontractors,
consulting firms, government and regulatory agencies, and community groups.
COMMMGT 9330A
Cultural Dimensions of an Organization Supportive of Project
Management
COMMMGT 9330A
Project Initiating Process Group
Processes performed to define a new project or a new phase of an existing project by obtaining authorization
to start the project or phase
COMMMGT 9330A
Project Initiating Process Group | Charter
COMMMGT 9330A
Project Initiating Process Group | Identify Stakeholders
COMMMGT 9330A
Project Initiating Process Group | Identify Stakeholders
• Examples of Project Management Plan Components | Inputs
• Communication management plan
• Stakeholder engagement plan
COMMMGT 9330A
REFERENCES
• Project Management Institute, A Guide to the Project Management Body of
Knowledge, (PMBOK® Guide)–Sixth Edition, Project Management Institute, Inc.,
2017.
• Project Management: The Managerial Process by Erik W. Larson & Clifford F. Gray
8th Edition
• Managing Project Quality by Kloppenborg & Petrick, 2002 edition.
• Principles of Project Management by John R. Adams
• Project Management Processes, Methodologies, and Economics, 3E by Avraham
Shtub & Moshe Rosenwein
• Successful Project Management seventh Edition by Jack Gido, James P. Clements
& Rose M. Baker
• Understanding the Project Environment, A Practical Guide, Second Edition by
Dave C. Barrett
• Project Management by Adrienne Watt
COMMMGT 9330A
Land Acknowledgement
We acknowledge that Western University is located on the traditional lands of the Anishinaabek,
Haudenosaunee, Lūnaapéewak, and Chonnonton Nations, on lands connected with the London
Township and Sombra Treaties of 1796 and the Dish with One Spoon Covenant Wampum. With this, we
respect the longstanding relationships that Indigenous Nations have to this land, as they are the original
caretakers. We acknowledge historical and ongoing injustices that Indigenous Peoples (First Nations,
Métis and Inuit) endure in Canada, and
we accept responsibility as members of
a public institution to contribute toward
revealing and correcting miseducation as
well as renewing respectful relationships
with Indigenous communities through our
teaching, research, community service,
and employment endeavors.
COMMMGT 9330A
Session 2
Organization Strategy &
Project Selection
COMMMGT 9330A
Learning Objectives
1. Explain why it is important for project managers to understand their
organization’s strategy
2. Identify the significant role projects contribute to the strategic direction of the
organization
3. Understand the need for a project priority system
4. Distinguish among three kinds of projects
5. Describe how the phase gate model applies to project management
6. Apply financial and nonfinancial criteria to assess the value of projects
7. Understand how multi-criteria models can be used to select projects
8. Apply an objective priority system to project selection
9. Understand the need to manage the project portfolio
COMMMGT 9330A
Why do project
managers need to
understand strategy?
COMMMGT 9330A
1. So they can make appropriate
decisions and adjustments.
• How a project manager would respond to a suggestion to modify the
design of a product or to delays may vary depending upon strategic
concerns.
COMMMGT 9330A
The Strategic Management Process: An Overview
COMMMGT 9330A
Four Activities of the Strategic Management Process
The sequence of activities of the strategic management process is:
1. Review and define the organizational mission
• The mission identifies “what we want to become.” Mission statements identify
the scope of the organization in terms of its product and service.
2. Analyze and formulate strategies
• Formulating strategy answers the question of what needs to be done to reach
objectives. Strategy formulation includes determining and evaluating alternatives
that support the organization’s objectives and selecting the best alternative.
3. Set objectives to achieve strategies
• Objectives translate the organization’s strategy into specific, concrete,
measurable terms. Objectives answer in detain where a firm is headed and when
it is going to get there.
4. Implement strategies through projects
• Implementation answers the question of how strategies will be realized, given
available resources.
COMMMGT 9330A
4 ACTIVITES OF THE STRATEGIC MANAGEMENT PROCESS
COMMMGT 9330A
STRATEGIC MANAGEMENT PROCESS
COMMMGT 9330A
The Need for a Project Priority System
Implementation of projects without a strong priority system linked to
strategy create problems.
Problem 1: The
Implementation Gap
The implementation gap is the lack of understanding and consensus of
organization strategy among top and middle-level managers.
Problem 2: Project selection may be based not so much on facts and sound reasoning
Organization Politics as on the persuasiveness and power of people advocating projects.
The term sacred cow is often used to denote a project that a powerful, high-
ranking official is advocating.
Problem 3: Resource
Conflicts and A multi-project environment creates the problems of project
Multitasking interdependency and the need to share resources. Resource sharing leads
to multitasking—involves starting and stopping work on one task to go and
work on another project, then returning to the work on the original task.
COMMMGT 9330A
Benefits of Project Portfolio Management
COMMMGT 9330A
2.4 Project Classification
COMMMGT 9330A
Phase Gate Model
COMMMGT 9330A
Phase Gate Process Diagram
FIGURE 2.3 © McGraw Hill Access the text alternative for slide images.
COMMMGT 9330A
DEVELOP PROJECT CHARTER
© mudassiriqbal
COMMMGT 9330A
DEVELOP PROJECT CHARTER
• issued by the Sponsor
• authorizes the Project Manager to spend money and
commit resources
• high-level document
• Summarizes key conditions and parameters
• Establishes the framework to develop baseline plan
• does not need to change as the project progresses
• project does not exist without a charter
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017 Page 75-81
COMMMGT 9330A
THE BUSINESS CASE AND
THE PROJECT CHARTER
COMMMGT 9330A
DEVELOP PROJECT CHARTER
Tools & Techniques
❑ Expert Judgment: Available
from many sources,
including:
₋ Other units within the
organization. Consultants,
Stakeholders, Professional
and technical associations,
Industry groups, Subject
Inputs matter experts, PMO Outputs • Project Charter
• Assumption Log
❑ Data gathering
₋ Brainstorming
₋ Focus Groups
₋ Interviews
❑ Meetings
❑ Interpersonal & Team Skills
₋ Conflict Management
₋ Facilitation
₋ Meeting Management
Develop Perform
Develop Direct & Manage Monitor &
Project Integrated Close Project
Project Manage Project Control
Management change or Phase
Charter Project Work Knowledge Project Work
Plan control
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Page 75-81
COMMMGT 9330A
DEVELOP PROJECT CHARTER
COMMMGT 9330A
BUSINESS CASE (cont’d)
Market
Demand
Organizational
Social Needs Need
Business
Case is
created as
Ecological Customer
Impacts
a result of: Request
Legal Technological
Requirements Advance
COMMMGT 9330A
BUSINESS CASE (cont’d)
COMMMGT 9330A
Selection Criteria
• Financial Criteria
• Payback
• Net present value (NPV)
• Nonfinancial Criteria
• Projects of strategic importance to the firm
• Two Multi-Criteria Selection Models
• Checklist Models
• Multi-Weighted Scoring Models
COMMMGT 9330A
Financial Criteria: The Payback Model
Pv = Fv / (1+r)n
Fv = future Value,
r = interest rate,
n = number of time
periods
COMMMGT 9330A
PRESENT VALUE
Example:
Suppose FV = $10,000, r = 5% and n = 10 years
COMMMGT 9330A
Financial Criteria: Net Present Value (NPV)
• Net Present Value (NPV)
• Uses management’s minimum desired rate of return (discount rate) to compute the
present value of all net cash inflows.
• Prefers positive NPV to negative NPV.
• Desires higher positive NPVs.
• Is more realistic because it considers the time value of money, cash flows, and
profitability.
COMMMGT 9330A
NET PRESENT VALUE
NPV = Σ{Ct/(1+r)t} – C0
• Where
• Ct = net cash inflow during the period t
• Co = total initial investment costs
• r = discount rate
• t = number of time periods
• Σ = From t=1 to T
COMMMGT 9330A
Project Management, the Managerial Process 7E, by Erik W. Larson and Clifford F. Gray – Chapter 2 Page 38-40
COMMMGT 9330A
CALCULATING FUTURE VALUE
• FV with compounded interest is calculated in the following
manner:
For example, John invests $1,000 for five years with an interest
rate of 10%, compounded annually. What is the future value of
John's investment?
COMMMGT 9330A
CALCULATING FUTURE VALUE (cont’d)
• Another Example:
A friend mentions that in four years they would like to buy a home
in one of London’s fastest-growing communities. You research the
area and learn that home prices are expected to rise 7% per year.
Today, your ideal house costs $125,000. What can you reasonably
expect a similar home to cost in four years?
Fv = Pv * (1 + r)^n Does not include adjustments for inflation
fluctuating interest rates or
Fv = $125,000 * (1+ 0.07)^4
fluctuating currency values likely to affect
=$125,000*1.31079 the true value of money or assets in the
=$163,849.50125 future.
Project Management, the Managerial Process 7E, by Erik W. Larson and Clifford F. Gray – Chapter 2 Page 38-40
COMMMGT 9330A
NET PRESENT VALUE
COMMMGT 9330A
Example Comparing Two Projects Using Net Present Value Method
COMMMGT 9330A
Nonfinancial Criteria
COMMMGT 9330A
Two Multi-Criteria Selection Models
• Checklist Models
• Use a list of questions to review potential projects and to determine their
acceptance or rejection.
• Allow greater flexibility in selecting among many different types of projects
and are easily used across different divisions and locations.
• Fail to answer the relative importance or value of a potential project to the
organization and does not allow for comparison with other potential projects.
COMMMGT 9330A
Checklist Models: Sample Selection Questions Used in Practice
Topic Question
Strategy/alignment What specific organization strategy does this project align with?
Driver What business problem does the project solve?
Sponsorship Who is the project sponsor?
Risk What is the impact of not doing this project?
Risk How risky is the project?
Benefits, value, ROI What is the value of the project to this organization?
Benefits, value, ROI When will the project show results?
Objectives What are the project objectives?
Organization culture Is our organizational culture right for this type of project?
Resources Will internal resources be available for this project?
Schedule How long will this project take?
Finance/portfolio What is the estimated cost of the project?
Portfolio How does this project interact with current projects?
• EXHIBIT
2.4
COMMMGT 9330A
Multi-Weighted Scoring Models: Project Screening Matrix
COMMMGT 9330A
2.7 Applying a Selection Model 1
• Project Classification
• Deciding whether the project fits with the organization strategy.
• Selecting a Model
• Weighted scoring criteria seem the best alternative because:
• They reduce the number of wasteful projects using resources.
• They help to identify project goals that can be communicated using the
selection criteria as corroboration.
• They help project managers understand how their project was selected,
how their project contributes to organization goals, and how it compares
with other projects.
COMMMGT 9330A
Applying a Selection Model 2
COMMMGT 9330A
A Proposal Form for an Automatic Vehicular Tracking (AVL) Public
Transportation Project
•
• FIGURE 2.5A Access the text alternative for slide images.
COMMMGT 9330A
Risk Analysis for a 500-Acre Wind Farm
• FIGURE 2.5B
COMMMGT 9330A
Project Screening Process
• FIGURE 2.6
COMMMGT 9330A
Priority Screening Analysis
• FIGURE 2.7
COMMMGT 9330A
2.8 Managing the Portfolio System
• Senior Management Input
• Provides guidance in establishing selection criteria that strongly align
with the current organization strategies.
• Annually decides how to balance the available organizational resources
(people and capital) among the different types of projects.
• Governance Team Responsibilities
• Publish the priority of every project.
• Ensure the selection process is open and free of power politics.
• Evaluate the progress of current projects.
• Constantly scan the external environment to determine if organization
focus and/or selection criteria need to be changed.
Balancing the Portfolio for Risks and Types of Projects
COMMMGT 9330A
BALANCING THE PORTFOLIO FOR RISKS AND TYPES OF
PROJECTS
Bread-and-Butter Projects Oysters
COMMMGT 9330A
BALANCING THE PORTFOLIO FOR RISKS AND TYPES OF
PROJECTS
COMMMGT 9330A
REFERENCES
• Project Management Institute, A Guide to the Project Management Body of
Knowledge, (PMBOK® Guide)–Sixth Edition, Project Management Institute, Inc.,
2017.
• Project Management: The Managerial Process by Erik W. Larson & Clifford F.
Gray 7th Edition
• Managing Project Quality by Kloppenborg & Petrick, 2002 edition.
• Principles of Project Management by John R. Adams
• Project Management Processes, Methodologies, and Economics, 3E by Avraham
Shtub & Moshe Rosenwein
• Successful Project Management seventh Edition by Jack Gido, James P. Clements
& Rose M. Baker
• Understanding the Project Environment, A Practical Guide, Second Edition by
Dave C. Barrett
COMMMGT 9330A