Professional Documents
Culture Documents
WBS Reference
WBS Reference
of hospital
1.1.2 Preparation of
proposal by developers
1.1.3 Evaluation of
proposal by GIFTCL
1.1.5 Boarding of
Hospital
Developer(lilavati
Hospital)
1.2.2 Developement
Phase 1.2.3 Construction
1.2.1 Inception Phase 1.2.4 Closeout Phase
Phase
1.2.1.1 Procurement of
Feasibility Consultant 1.2.2.1 Procurement by
Developer 1.2.2.2 Approvals 1.2.2.3 Design Delivery
1.2.4.1 Technical
1.2.1.2 Closeout
Feasibility Study
1.2.2.2.1Approvals
1.2.3.1 Pre- 1.2.3.2 Execution
1.2.2.1 Procurement of 1.2.2.2 Procurement of 1.2.2.1.4 Procurement Construction 1.2.4.2 Commercial
1.2.2.1.3 Procurement of
1.2.1.2.1 Location 1.2.1.2.2 Market and 1.2.1.2.4 Cost Benefit 1.2.1.2.5 Project Management healthcare Architect of Bio Medical 1.2.3.3 Closure Closeout
1.2.1.2.3 EIA Study Material 1.2.2.3.2 Finalisation of
Analysis Demand Analysis Analysis Risk Assessment Consultant Equipment 1.2.2.3.1 Finalisation of
1.2.2.2.2 Provisional Fire Architecture,Structure,M MEP Low side, Interior
NOC EPF,Fascade & External development 1.2.3.2.1 Civil Works 1.2.3.2.2 MEPF works 1.2.3.2.5 External
1.2.2.2.9 Procurement of 1.2.5.1.1 Site 1.2.3.2.3 Façade works 1.2.3.2.4 Interior Works 1.2.3.2.6 Building
1.2.2.1.9 Procurement of Development 1.2.3.3.1 Handing over
1.2.1.2.1.1 1.2.1.2.1.2 Geotechnical Structural Consultant Barrication Management System 1.2.4.3 Snag List
Main ontractor Documents to PMC by
Topographical survey Investigation Rectification
1.2.2.3.2.1 MEP Low 1.2.2.3.2.3 Interior contractor
1.2.2.2.3 Development 1.2.2.3.2.2 Elevator 1.2.3.2.2.1 Mechanical
1.2.2.3.1.1Civil 1.2.2.3.1.3 MEP High side Drawing
1.2.2.1.2.8 Procurement Permission 1.2.2.3.1.2Facade Works
(Architecture,Structure) Side 1.2.3.2.1.1 Sub 1.2.3.2.1.2 Super
of MEPF consultant 1.2.5.1.2 Site Clearance Structure Structure
1.2.3.3.2 As Built 1.2.4.4 Project
1.2.2.2.4 Commencemen Drawings Handover
1.2.2.3.2.1.1 1st cut 1.2.3.2.2.1.1 HVAC
t certificate
drawing delivery system
1.2.5.1.3 Electricity & 1.2.3.2.1.1.1 Excavation 1.2.3.2.1.2.1 RCC Frame
1.2.2.2.5 Plinth water connection 1.2.3.3.3 Testing of
Completion Certificate 1.2.3.2.2.1.2 SITC of MEPFworks
1.2.2.3.2.1.2Working Elevator
drawing
1.2.3.2.1.1.2 Ani- 1.2.3.2.1.2.2 Blockwork
1.2.2.2.6 Progress 1.2.5.1.4 Setting up of Termite & Plaster
1.2.3.2.2.1.3 Medical 1.2.3.3.4 Defect
Certificate labour colony
Gas Pipeline system Liability Period
1.2.2.3.2.1.3 Flow of
GFC drawings
1.2.2.2.7Lift License 1.2.3.2.1.1.3 PCC,Raft 1.2.3.2.1.2.3 Strucural
Footing , retaining walls Steel 1.2.3.2.2.1.4 Garbage
Chute system
1.2.2.3.2.1.4Approval of
1.2.2.2.8 Fire Safety GFC drawings
certificate 1.2.3.2.1.1.4 1.2.3.2.1.2.4 Flooring 1.2.3.2.2.1.5 Basement
waterproofing works works Ventilation system
1.2.2.2.9 Certificate by
chief electrical
inspector 1.2.3.2.2.2 Electrical
1.2.3.2.1.1.5 Block Work 1.2.3.2.1.2.5 Internal
Works
and Plaster Finishes
1.2.2.2.10 Green
building certificate 1.2.3.2.2.2.1 Low &
High side
1.2.3.2.1.1.6 Finishes
1.2.2.1.5.10 Occupancy
certificate 1.2.3.2.2.2.2 Nurse Call
system
1.2.3.2.1.1.7 RCC frame
1.2.3.2.2.3 Plumbing
works
1.1.2 Preparation of
proposal by developers
1.1.3 Evaluation of
proposal by GIFTCL
1.1.5 Boarding of
Hospital
Developer(lilavati
Hospital)
1.2.2.1.2.10.1 Preparation
and issuance of the RFP
1.2.2.1.2.10.2 Pre-
proposal meeting
1.2.2.1.2.10.3 Preparation
of proposals
1.2.2.1.2.10.4 Date of
technical bid opening
1.2.2.1.2.10.5 Evaluation
of technical proposals
1.2.2.1.2.10.6 Date of
financial bid opening
1.2.2.1.2.10.7 Evaluation
of financial proposals
1.2.2.1.2.10.8 Award of
the contract of the
selected firm
1 GIFTCL-Construction
of hospital
1.1.2 Preparation of
proposal by developers
1.1.3 Evaluation of
proposal by GIFTCL
1.1.5 Boarding of
Hospital
Developer(lilavati
Hospital)
1.2.1.1
Procurement
of Feasibility
Consultant
1.2.1.2
Feasibility
Study
1.2.1.2.2
1.2.1.2.1
Market and 1.2.1.2.3 EIA 1.2.1.2.4 Cost 1.2.1.2.5
Location
Demand Study Benefit Risk
Analysis
Analysis Analysis Assessment
1.2.1.2.1.1 1.2.1.2.1.2 Ge
Topographical otechnical
survey Investigation
1.2.2
Developement
Phase
1.2.2.1
Procurement by 1.2.2.3 Design
1.2.2.2 Approvals
Developer Delivery
1.2.2.3.1 1.2.2.3.2
1.2.2.2.1Approvals Finalisation of Finalisation of
1.2.2.1 1.2.2.2 1.2.2.1.4 Architecture,Struc MEP Low side,
Procurement of Procurement of 1.2.2.1.3 ture,MEPF,Fascad Interior & External
Procurement of
Project healthcare Procurement of e development
Medical
Management Architect Material
Equipment
Consultant 1.2.2.2.2
1.2.2.2.9 Provisional Fire
Procurement of NOC
1.2.2.1.9 Structural
Procurement of Consultant
Main ontractor
1.2.2.2.3 1.2.2.3.2.1 MEP 1.2.2.3.2.2 1.2.2.3.2.3 Interior
Development 1.2.2.3.1.1Civil Low side Elevator Drawing
1.2.2.1.2.8 1.2.2.3.1.3 MEP
Permission (Architecture,Stru 1.2.2.3.1.2Facade
Procurement of High Side
cture)
MEPF consultant
1.2.2.2.5 Plinth
Completion
Certificate 1.2.2.3.2.1.2Worki
ng drawing
1.2.2.2.6 Progress
Certificate
1.2.2.3.2.1.3 Flow
of GFC drawings
1.2.2.2.7Lift
License
1.2.2.3.2.1.4Appro
val of GFC
1.2.2.2.8 Fire drawings
Safety certificate
1.2.2.2.9
Certificate by
chief electrical
inspector
1.2.2.2.10 Green
building
certificate
1.2.2.1.5.10
Occupancy
certificate
1.2.3
Construction 1.2.4 Closeout
Phase Phase
1.2.4.1 Technical
Closeout
1.2.3.2.1 Civil 1.2.3.2.2 MEPF 1.2.3.2.3 Façade 1.2.3.2.4 Interior 1.2.3.2.5 External 1.2.3.2.6 Building
1.2.5.1.1 Site Works works 1.2.3.3.1 Handing
works Works Development Management
Barrication over Documents
System 1.2.4.3 Snag List
to PMC by
Rectification
1.2.3.2.2.1 contractor
Mechanical
1.2.3.2.1.1 Sub 1.2.3.2.1.2 Super Works
1.2.5.1.2 Site
Structure Structure
Clearance 1.2.3.3.2 As
Built Drawings 1.2.4.4 Project
1.2.3.2.2.1.1 Handover
HVAC system
1.2.5.1.3 1.2.3.2.1.1.1 1.2.3.2.1.2.1 RCC
Electricity & Excavation Frame
1.2.3.3.3 Testing
water connection of MEPFworks
1.2.3.2.2.1.2 SITC
of Elevator
1.2.3.2.1.1.3
PCC,Raft Footing 1.2.3.2.1.2.3
1.2.3.2.2.1.4
, retaining walls Strucural Steel
Garbage Chute
system
1.2.3.2.1.1.4 1.2.3.2.2.1.5
waterproofing 1.2.3.2.1.2.4 Basement
works Flooring works Ventilation
system
1.2.3.2.2.2.1 Low
& High side
1.2.3.2.1.1.6
Finishes
1.2.3.2.2.2.2 Nur
se Call system
1.2.3.2.1.1.7 RCC
frame
1.2.3.2.2.3 Plumb
ing works
1.2.3.2.2.4 Fire
Fighting works
1.2.1 Inception
Phase
1.2.1.1
Procurement of
Feasibility
Consultant
1.2.1.2
Feasibility
Study
1.2.1.2.2
1.2.1.2.1 1.2.1.2.5
Market and 1.2.1.2.3 EIA 1.2.1.2.4 Cost
Location Risk
Demand Study Benefit Analysis
Analysis Assessment
Analysis
1.2.2
Developement
Phase
1.2.2.1
1.2.2.2 1.2.2.3 Design
Procurement by
Approvals Delivery
Developer
1.2.2.3.2
1.2.2.1.3 1.2.2.3.1
1.2.2.1 1.2.2.2 1.2.2.1.4 Finalisation of
Procurement of Finalisation of
Procurement of Procurement of Procurement of MEP Low side,
Hospital Architecture,Stru
Project Principal design Medical Interior &
Furniture cture,MEPF,Fasc
Management consultant Equipment External
ade
Consultant development
1.2.2.2.9
Procurement of
1.2.2.1.9 Structural
Procurement of Consultant
Main Contractor
1.2.2.1.2.8
Procurement of
MEPF
consultant
1.2.3 Construction 1.2.4 Closeout
Phase Phase
1.2.3.2.1 Civil 1.2.3.2.2 MEPF 1.2.3.2.3 Façade 1.2.3.2.4 Interior 1.2.3.2.5 External 1.2.3.2.6 Building 1.2.3.3.1 Handing
Works works works Works Development Management over Documents 1.2.4.2 Commerci
1.2.5.1.1 Site
System to PMC by al Closeout
Barrication
contractor
1.2.3.2.2.1
Mechanical
1.2.3.2.1.1 Sub 1.2.3.2.1.2 Super
Works 1.2.3.3.2 As Built 1.2.4.3 Snag List
1.2.5.1.2 Site Structure Structure
Drawings Rectification
Clearance
1.2.3.2.2.1.1
HVAC system
1.2.3.2.1.1.1 1.2.3.2.1.2.1 RCC
1.2.5.1.3 1.2.3.3.3 Testing 1.2.4.4 Project
Excavation Frame
Electricity & of MEPFworks Handover
1.2.3.2.2.1.2 Elev
water connection
ator
1.2.3.2.1.1.2 Ani- 1.2.3.2.1.2.2
Termite Blockwork &
1.2.5.1.4 Setting 1.2.3.2.2.1.3
Plaster
up of labour Medical Gas
colony Pipeline system
1.2.3.2.1.1.3
PCC,Raft Footing , 1.2.3.2.1.2.3 1.2.3.2.2.1.4
retaining walls Strucural Steel Garbage Chute
system
1.2.3.2.1.1.4 1.2.3.2.2.1.5Base
waterproofing 1.2.3.2.1.2.4
ment Ventilation
works Flooring works
system
1.2.3.2.2.2 Electric
1.2.3.2.1.1.5 Block 1.2.3.2.1.2.5
al Works
Work and Plaster Internal Finishes
1.2.3.2.2.2.1 Low
& High side
1.2.3.2.1.1.6
Finishes
1.2.3.2.2.2.2 Nurs
1.2.3.2.1.1.7 RCC e Call system
frame
1.2.3.2.2.3 Plumb
ing works
1.2.3.2.2.4 Fire
Fighting works