Download as pdf or txt
Download as pdf or txt
You are on page 1of 28

METHOD STATEMENT FOR

INSTALLATION OF EARTHING AND LIGHTNING


PROTECTION SYSTEM

PROPOSED ZEE STORE ON PLOT NO. KHIA9-18M, KIZAD,


ABUDHABI

Revision Record
This cover page is a record for all the revision of the document identified above by number and title.
All previous cover pages are hereby suspended and are to be destroyed.

Rev.
Date Prepared By Reviewed By Approved By Remark
No

00 25/10/2023 Sulieman Eng. Mustafa

1. Purpose:

Page 1 of 15
The purpose of generating this Method Statement is to describe the procedure to implement the
correct practices for Installation of Earthing and lightning protection system and works to ensure that
all operations comply with the requirements of project specification for Al-Forsan International
equestrian club expansion phase 02. It also outlines the safety, quality and other related procedure to
be followed when performing such works and presents systematic and sequential instructions to be
implemented by construction crew.

2. Scope:

Scope of this method statement covers processes, operations and sequential activities
encountered in execution of installation Earthing and lightning protection works as per approved
relevant shop drawings of the project.

3. Legislation and code of practice:

Lightning Protection: BS EN 62305 1-4


Earthing: BS 7430
Local Regulation: ADWEA Wiring Regulation

4. References and Related Documents:

• Project specifications: Section 26 05 26 (Electrical Specifications)


• Project Contract Documents and Drawings: Project tender drawings
• ISO Standards
• Program of works
• Approved project safety plan and procedures

5. Definitions:
• MS - Method Statement
• ITP - Inspection & Test Plan
• RA - Risk Assessment
• ITL - Independent Testing Lab
• PVC - Polyvinyl Chloride

6. Resources:

6.1 Materials and their approval

• Approved Materials used for Earthing and lightning protection system

Page 2 of 15
6.2 Sub-Contractor approval

M/s IPCO General Contracting L.L.C under the supervision of Stonewood construction LLC

6.3 Shop Drawing/Design Drawing Approvals

TBA

6.4 Equipment

• Portable hand tools


• Portable drilling machine & Grinding machine
• Cutting saw
• Spirit level/ Level threads
• Step ladder/ Scaffolding with platform
• Safety requirements tools such as safety shoes, safety helmet, safety glasses, fluorescent
vest, and safety gloves to ensure maximum ability of safe work and dust mask when require.

6.5 Man Power

• Project Manager
• MEP Manager
• QC Engineer
• Site Engineer
• HSE Officer
• Foremen
• Electrician
• Helpers

7. Responsibilities:

7.1 Project Manager


• He will be responsible for the overall implementation of this procedure, as well as the
coordination with all concerned authorities.
• Ensure the activities are carried out according to approved shop drawings, specifications
and approved MS/ITP.
• Ensure all required submittal are made in a timely manner.
• Ensure that progress is carried out according to the planned program and all the equipment
required to execute the works are available as per the project planning and are in good
condition.
• Coordination with the Consultant, Project Engineer, Safety Engineer and Subcontractors for
the safe and proper execution of the work.

Page 3 of 15
• Specific attention is paid to all safety measures and quality assurance and quality control in
coordination with Safety Engineer/QA/QC Engineer.

7.2 MEP Manager


• He will be responsible for the co-ordination between the civil works and MEP works
accordingly and to plan the work as per priority.
• Ensure the activities are carried out according to approved shop drawings, specifications
and approved MS/ITP.
• Ensure all required submittal for MEP works are made in a timely manner.
• Ensure that progress is carried out according to the planned program and all the equipment
required to execute the works are available as per the project planning and are in good
condition.
• Coordination with the Consultant, Project Engineer, Safety Engineer and Subcontractors for
the safe and proper execution of the work.
• Specific attention is paid to all safety measures and quality assurance and quality control in
coordination with Safety Engineer/QA/QC Engineer

7.3 Site Engineer


• SE along with supervisors/surveyor/foreman will ensure that all the activities related to
electrical works are carried out according to the specification, drawings and approved method
statements, complying with the HSE requirements according to approved project HSE Plan.
• Proper execution of work as per approved MS/ITP and approved shop drawings.
• Timely provision of relevant full information and Consultant approved documents to site
execution team. To distribute responsibilities among site staff.
• Adopt all safety measures as required and under supervision of site / Consultant safety
personnel.
• Preparation of Daily Progress Report and planning activities for the next day in association
with Foreman.
• Follow sequence of execution of work and Consultant instructions and approvals.
• Coordinate with QA/QC Engineer to raise SIR when work is completed for Consultant
inspection and approval.

7.4 QA/QC Engineer


• He will ensure that works are carried out as per project requirement and with good quality to
ensure the work is suitable and safe to the purpose of accommodating the project construction
site preparation works.
• Shall be responsible to organize, implement, conduct and manage in accordance with
approved MS/RA and approved PQP. Coordinate in accordance with the approved ITP in
all inspections, monitor the required tests and inspections as per Contract Plan and
Specifications. Liaise with the Consultant's representatives in conducting day-to-day
quality related project activities. Maintain jointly with the document controller the registries
of all the documents.
• To initiate Inspection or Test Requests for Consultant inspection / approvals.
• To advise Site Foreman / Supervisor of the specific requirement related to work quality
and requirement of consultant inspections and approvals at different stages of the work
Page 4 of 15
progress.
• Implementations of Consultant comments through site team and preparing for final
inspection and approval by consultant.
• To maintain a comprehensive inspection and test record as per Quality Standards and
approved Project Quality Plan.
• To monitor the activity progress as per requirements of Quality Procedure.
• Ensure work related to it is ready / completed prior to inform Consultant inspection.

7.5 HSE Officer

• He will ensure all the work is being executed as per the Contractor’s approved Project
HSE Plan/procedures and will report to Project Manager and will coordinate along with
Client Safety Representative.
• Ensure safe and sound implementation of all safety procedures and measures specific to the
nature and type of site installation / execution work being carried out at site.
• To ensure that all project personnel’s /site execution team are fully aware of their
responsibilities and have full understanding of the related safety rules and procedures.
• To advise the involved personnel of the involved risk at work and necessary health and
safety precautions / measures to avoid it.
• To keep informed the management and Consultant about the adopted safety measures at
site ensuring their adequacy.
• To maintain safety statistics / record and regular reporting to consultant.
• To maintain a continuous inspection / surveillance of site activities, making sure of
implementations of HSE Policies, advising and training site staff to prevent accidents,
personnel injury and property damage.
• Implementation of housekeeping to keep the site clean and tidy.
• To coordinate with Consultant Engineers for ensuring the implementation as per the
approved HSE requirements and procedures for the required job in order to ensure a safe
working environment.
• Coordination with Project Engineer for the completion of executed work for inspection.

7.6 Foreman

• Proper distribution of the workforce as required and planned locations at the required time.
• Continuous coordination and following Project Engineers instructions.
• To ensure that all workers have required information and knowledge of their duties.
• Controlling disposal of waste material and keeping a good housekeeping.
• Coordination with site Safety Engineer for maintaining a safe working place.
• Educating site workers for the required safety instructions.
• Shall have day to day responsibility to ensure that works under his control are carried out
safely, in accordance with this Method Statement and other requirements.

8. Safety Precautions:
• Specific safety measures have to follow as applicable, and all the safety measures are
covered separately in the project safety plan.
Page 5 of 15
• All the safe practices will be adopted during the ongoing works.
• All necessary personal protective equipment shall be used.

9. Procedure:

9.1 Work Sequence:


• Receive and verify approved material delivery at site.
• Prepare approved drawings for site execution.
• Commence work according to civil program for pre cast hollow core slab, columns &
beams, block work wall partition.
• QA/QC to check the installation against approved drawings and after for inspection by
consultant.
• After consultant approval, hand over to Main contractor for clearance for necessary
slab/wall finishing.

9.2 General Requirement:


• All material received at site shall be inspected, handle and store properly upon receipt in
accordance with manufactures recommendations.
• All time deliveries and all items shall be inspected by the consultant /client.
• Upon verifying the received materials in compliance with approved material submittal,
material inspection request (MIR) shall be raised to consultant for review and approval.
• All installation / construction / testing works shall be carried out in compliance with
project specification, approved shop drawings, method statement, local and international
standards, manufacture recommendation, client safety manual.
• Prior to start installation, refer to the approved shop drawing related to the work area and
ensure that required material is available at store.
• While issuing from site store, ensure that the materials are free of any damage or
deformity of any kind.
• Ensure the materials are properly packed to permit the ease of handling.
• All relevant issued for construction drawings are available at site for execution of job.
• The work area shall be inspected for the completion and safety to start the installation
work.
• Material of different categories like size and type should be store separately.
• Verification, inspection checklist will be verified, recorded on approved forms and sign
QC inspector and consultant.
Page 6 of 15
9.3 Pre-installation Procedure:
• Site Engineer (Electrical) must ensure that all the civil related work has been completed.
• Prior to start installation, Site Engineer should ensure that approved shop drawings
related to the installation area are referred and that required materials are available at site
as per approved material submittals.
• Identify and obtain appropriate installation tools and equipment’s. Ensure that tools and
equipment’s used are inspected, maintained and calibrated to fit for purpose.
• Determine the manpower required and assigned tasks to team members. Ensure that they
are experienced and competent.
• All installation and workmanship shall be to the satisfaction of the company. Particular
attention shall be paid to a neat, orderly well-arrange installation, carried out in a
methodical competent manner.
• Ensure all necessary permit are in place prior to commencing works.
• Make sure that installer will read and understand the risk assessment before work will
start on site.
• On satisfactory completion of the installation works, the relevant internal inspection will
be carried out to ensure correct installation (as per approved drawing, specification &
method statement) prior to offering for consultant inspection.
• On satisfactory completion of the internal inspection, an inspection request will be issued
to the main contractor and a formal inspection of works carried out. This inspection will
be documented via Inspection & Test Request (ITR)
• Verification and Inspection Checklist shall be verified, recorded on approved forms and
signed by the site QC Engineer and company’s Representatives.
• Ensure all the Tools/Devices are calibrated wherever applicable. (Calibration Certificate
for all test equipment’s shall be submitted and attached to inspection format)
• Safe and tidy workplace, clear access to the workplace & modes to shift material.

9.4 Installation Procedure:


Design Philosophy

• The whole Lightning Protection System shall be designed completely in accordance


with:

• BSEN 62305 (I – IV): 2012 CENELEC standard for Lightning Protection

Page 7 of 15
• BS EN 50164-1: 2000
• Lightning Protection Components (LPC) Part 1: Requirements for connection
components.
• BS EN 50164-2: 2000
• Lightning Protection Components (LPC) Part 2: Requirements for conductors and earth
electrodes.

• The following design details are aimed at protection against the risk of damage D1, D2
and D3 as mentioned in the Part 2 of the above-mentioned standard.

• The risk evaluation has been done based on the BSEN 62305 – Part 2 and an LPL level
IV will
• have be implemented to protect the building and the services to minimize R1.

• The calculation requires using the buildings.

• Earth Pit Installation at Ground Floor;

• The terminated head of each electrode shall be located in a Concrete inspection Earth
pit.

• The earth termination network comprises of 20mm x 1200mm Solid copper earth rod
driven at the base of each down conductor position. Each down conductor has a
separate earth termination.

• The earthing shall be done as per local authorities’ requirements. A minimum of 3600
mm length solid copper electrode shall be provided with each down conductor
separately. However, it is important to submit the calculation for deciding the number
of earth rods in each earth pit. Solid copper rods to ensure the longevity of the earth
termination network. The sections of earth rod
• shall be coupled together with threaded hexagonal rod couplings.

• The complete Lightning Protection System measured at any point, should not exceed 10
ohms. With the test clamp disconnected, the resistance of each individual earth should
be no more than ten times the number of down conductors in the complete system.

DOWN CONDUCTORS

• The down conductor spacing has to be 20 meters for Level IV.

• With reference to the standard BS EN 62305-3, 25x3mm PVC covered copper tape
inside outside the building wall should be used as down conductor for lightning

Page 8 of 15
protection system. Ensure overall electrical continuity of the down conductor measure
from lower to upper level shall not be greater than .2 ohm.

• All metallic parts protruding outside the extended air termination network (e.g., balcony
hand rails etc.) shall be connected to the air termination using suitable clamps (material
complying to BSEN 50164).

AIRTERMINATION NETWORK

• The air termination network will comprise of 25mmx3mm bare copper tape of 99.99%
purity and shall form an air termination network consisting of mesh of 20 x 20 m for
Level IV on the accessible side. This will be installed along ridges to form a grid over
the roof structure. Should there be metallic structures forming the roof of the required
thickness and characteristics, they can be connected to form the desired air termination
network. The conductor will be fixed to the roof with DC clips to suit the final roof
finish at a distance of every 1-meter.

• All joints between conductors will be made with square tape clamps.

• Air terminations on roofs of different levels will be bonded together to form an


integrated lightning protection system. Any roof (e.g., staircase) on top of the main roof
shall have air termination network and it shall be connected to lower roof network.

• The equipment’s on the roof (i.e., Chiller units etc.) shall be protected using vertical air
terminals of suitable height so that it provides the zone of protection. This air terminal
shall be installed at a suitable separation distance so that the partial lightning current
doesn’t flow through the equipment. The cable from the equipment shall be protected
using an over – voltage protector. The equipment shall not be bonded to the air
termination network.

Preparation & Pre-installation Work

• Works shall not proceed until an approved construction drawing or detail is issued.
• Safe access to work areas shall be provided by the main contractor.
• Materials shall be moved to the work area in a safe manner and shall not block access /
egress from the site. Suitable mechanical aids shall be used where heavy loads are to be
moved or lifted into position. Such equipment shall be planned for in advance of works.

• Inspection, Testing & Commissioning

• In process works shall be monitored for quality of workmanship and installation against
approved construction drawings by the Electrical Engineer & Supervisor.

Page 9 of 15
• All works shall be inspected for quality of workmanship and conformance to
specification.

• Visual Inspection, Continuity Tests, and Electrode Resistance Test shall be done and
recorded as per attached formats. This document, complete with inspection and test
format’s is issued for comment and approval.

• A Megger complete with current calibration certification shall be used for the relevant
measurements for these works.

• Earth resistance measurements for the reinforced concrete piles, used as earth
electrodes, shall be tested & recorded. Minimum permissible earth resistance value for
lightning protection is to below 10 ohms.

• The reinforced concrete piles shall be connected in parallel, if minimum resistance


requirement is not met.

Measurement of earth electrodes resistance

• Measurement of the resistance to earth of an earth electrodes is not necessary a simple


matter. While certain fairly simple rules can be laid down.. Circumstances frequent
arise which make it necessary to modify them. The resistance of an earth electrode is
unique in that the terminal provided by the electrode itself is definite, the other terminal
of the resistance being theoretically at an infinite distance. In practice a measurement
has to be made which includes the greatest part, say 98% of the total resistance. There
is no point in striving for a high degree of accuracy with such a measurement since
within the volume of such a resistance, there may be considerable non-uniformity in the
soil and other disturbing features. An accuracy of 2% is more than adequate, and
accuracies of the order of 5% are usually quite acceptable.

• A measurement current is passed between electrodes X, the one being tested and an
auxiliary current electrode Y. The voltage drop between electrode X and a second
auxiliary electrode Z is measured and the resistance of the electrode X is then the
voltage between X and Z. The source of current and the means of metering either the
current and voltage or their ratio are often, but not necessarily, combined in one device.

Testing

• On the completion of the installation or of any modification to it, the following isolated
and combined measurements and/or checks should be made and the results recorded in
a lightning Protection system logbook.

Page 10 of 15
• The resistance to earth of each local earth electrode and in addition the resistance to
earth of the complete earth termination system
• Each local earth electrode should be measured in isolated with the test point between
the down conductor and earth electrode in the disconnected position (isolated
measurement)
• A further measurement should be taken with the test point in the connected position
(combined measurement) If there are any significant differences in the measurements in
relation to other positions, the reason for such differences should be investigated

• The results of a visual check of all conductors’ bonds and joints or their measured
electrical continuity

• Tests should be repeated at fixed intervals, preferably not exceeding 12 months

• Note : It may be advantageous to choose a period slightly shorter than 6 months in


order to vary the season in which tests are made.

• Note : It is emphasized that before disconnecting a lightning protection earth, it should


be tested to ensure that it is not “live” using a sensitive voltage-testing device

Records

• The person has to keep on site or the following records, responsible for the upkeep of
the installation:

• Approved shop drawings, showing the nature, dimensions, materials and position of all
component parts of the lightning protection system.

• The nature of the soil and any special earthing arrangements.

• The type and position of the earth electrodes, including reference electrodes.

• The test conditions and the result obtained.


• Any alteration, additions or repairs to the system.

• The name of the person responsible for the installation upkeep.

• A label should be attached at the origin of the electrical installation, worded as follows

• “This structure is provided with a lightning protection system in accordance with BS


6651 and BSEN 50164 and the bonding to the services and the main equi-potential
bonding should be maintained accordingly”
• Maintenance
Page 11 of 15
• The periodic inspections and tests recommended will show what maintenance, if any is
needed. Particular attention should be given to the following:

Earthing

• Evidence of corrosion or conditions likely to lead to corrosion

• Alterations and additions to the structure which may affect the lightning protection
system (e.g., erection of radio and television aerials, installation of crane tracks, glass /
window cleaning system etc.)

10.Requirements

10.1 Trainings

• Trained / Experienced & Skilled persons shall be used for the work.
• All operator / laborer is safety trained and toolbox shall be conducted.

10.2 Risk Assessment

• Risk assessment to be ensured that it is available in work spot.


• All control measure as per the risk assessed to be implemented and ensured before start
of work.

10.3 Personal Protective Equipment

• Protective Clothing
• Protective footwear
• Protective Gloves
• Safety Helmet
• Safety Goggles
• Hi-visibility jacket

11. Related Forms:

ITP
CL
Check list

12. Attachments:

ITP
CL
Risk assessment
Page 12 of 15
APPENDIX- A
(Inspection and Testing Plan- ITP)

Page 13 of 15
INSPECTION & TEST PLAN (ITP) FOR INSTALLATION OF EARTHING AND LIGHTNING PROTECTION SYSTEM

PROPOSED ZEE STORE ON PLOT NO. KHIA9-


Client ZEE STORES Project Prepared By Sulieman
18M, KIZAD, ABU DHABI

Consultant AWAJ ENGINEERING CONSULTANTS Discipline MEP Reviewed By Engr. Mustafa

STONEWOOD CONSTRUCTION LLC ITP Ref. No. ZEE-EE-MOS-ITP-002 Approved By


Contractor
Date 25/10/2023

Works Location (This ITP reflects status of testing/ inspection in the following area/ zone within the Project)

Responsibility1
Frequency of Applicable
Control Data / Inspection Contractor
SN Inspection / Test to be carried out Test / Acceptance Criteria Specification / Completion Date
Forms Method Engineer
Inspection Standard Subcontractor Main
(if applicable) Contractor
1 Preliminary Works

VERIFICATION/VALIDATION OF APPROVED Approved


Every start of
1.1 DOCUMENTS AND RECORDS (Drawings, MS, Approval of Docs. Section - 16452 Documents / Review of Docs. R R R
works
CL/ITP, Work Permits, Licenses, etc. Records

2 Preparation
As per site Survey Records /
2.1 Seting-Out Coordination with Civil Section - 16452 Witness H H W
progress SIR
Approved
As per site
2.2 Material Delivery & Availability Approval of Docs. Section - 16452 Documents / Inspection R R R
progress
Records
3 Installation & Inspection
Approved
Routing the copper strips and down conductors as per the As per site
3.1 As per Specifications Section - 16452 Documents / Inspection H H W
approved shop drawings and standard. progress
Records
Approved
Location of earth pit as per approved shop drawings and As per site
3.2 As per Specifications Section - 16452 Documents / Inspection H H W
specifications. progress
Records
Approved
As per site
3.3 Installation of conductors, terminals and earth rods. As per Specifications Section - 16452 Documents / Inspection H H W
progress
Records
As per site
3.4 Visual/ Practical inspection Checklist Section - 16452 WIR Inspection H H H
progress

Note (1): H: Hold Point, W: Witness, R: Review, S: Surveilance, A: Approval, P: Perform / Execute
APPENDIX- B
(Checklist)

Page 14 of 15
CHECK LIST FOR INSTALLATION OF PVC CONDUITS & BOXES
Proposed Zee store on plot no. KHIA9-18M,
Project Name Client ZEE STORES
KIZAD, AbuDhabi
Contractor Stonewood Construction LLC Consultant AWAJ Engineering Consultant

Checklist Title: Installation of Earthing and Lightning protection Checklist No. ZEE-EE-MOS-CH-002
system
Works Location: All Buildings Related ITP # ZEE-EE-MOS-ITP-002
Project tender drawings Related MS # EE-MOS-ZEE-002
Related Drawing(s)

Status - Acceptable
SN Description of checking to be carried out Remarks
Yes No NA

1 Preliminary Works
Method Statement Approved prior to commencement of
1.1
work
1.2 Shop Drawing Approved prior to commencement of work

2 Preparation

2.1 Check the job site is ready for activity to commence


Material are visually inspected (by MIR) prior to
2.2
installation
Check and verify that the copper strip and earth pit are
2.3
damage free,clean and tidy prior to installation
3 Installation
Check sleeves and openings for continuous installation
3.1
are located as per approved drawings

3.2 Check proper supports are provided as per specifications.

Check all earth pits are located as per approved shop


3.3
drawings.
Check all terminals are located as per approved shop
3.4
drawing.

3.5 Check the resistance is as per specification and standards.

Remarks:

Accompanying document :

For Contractor
For Supervision Consulatnt (Engineer)
Site Engineer Quality Engineer
Name
Designation
Signature
Date

Form Ref: TMT114, Rev-1, Date: 09-Feb-17


ELECTRODE RESISTANCE REPORT

Site: Location:
Date of Test: Ground Conditions:
Test Engineer: Megger No:
Test Method: As per BS7430 Next Test due: N/A
Test Witnessed by:

Distance Distance
Resistance to Earth
Earth Ref. Between Between
(Ohms)
P1 & P2 P1 & C2

EP LP-01 8m 16m R=

8m 16m R=
EP LP-02

EP LP-03 8m 16m R=

EP LP-04 8m 16m R=

EP LP-05 8m 16m R=

EP LP-06 8m 16m R=

EP LP-07 8m 30m R=

EP LP-08 8m 16m R=

EP LP-09 8m 16m R=
EP LP-10 8m 16m R=

EP LP-11 8m 16m R=

Supplier Contractor Consultant


Company: SAFE LINE

Name :

Signature:

Date :
VISUAL INSPECTIONS OF LIGHTNING PROTECTION SYSTEM

PROJECT:

LOCATION: INSPECTION DATE: BUILDINGS :

CLIENT / END USER: CONSULTANT: CONTRACTOR:

DESCRIPTION OK NOT REMARKS, IF NOT OK


OK
1. LEVEL OF PROTECTION:
2. ROOF MESH:
3. DOWN CONDUCTORS SPACING:
4. ROLLING SPHERE DIA:
5. INSTALLATION CONFORMS THE STANDARD
6. NO LOOSE CONNECTIONS AND BREAKS
7. NO PART OF THE SYSTEM HAS BEEN WEAKENED BY
CORRISION
8. ALL VISIBLE CONNECTIONS ARE INTACT
9. ALL VISIBLE CONDUCTORS ARE FASTENED TO
MOUNTING SURFACES AT RECOMMENDED INTERVALS

Supplier Contractor Consultant

Name :

Signature:
Date :

PO Box # 45350
3rd Floor | Al Masaood Tower | Najda Street | Abu Dhabi | UAE
APPENDIX- C
(Risk Assessment)

Page 15 of 15
Lightning protection risk management calculations
To BS EN 62305-2:2012 (Edition 2)

Full case report

Project name: PROPOSED ZEE STORE ON PLOT NO. KHIA9-18M, KIZAD, ABU DHABI
Project ref: 8585
Case name: Original Case
Client: ZEE STORES
Prepared by: Nihad
Issue date: 25/10/2023

StrikeRisk v6.0.0 Run identification 25/10/2023 - 12:21:11 Page 1 of 8


PROPOSED ZEE STORE ON PLOT NO. KHIA9-18M, KIZAD, ABU DHABI

Project details
Project name: PROPOSED ZEE STORE ON PLOT NO. KHIA9-18M, KIZAD, ABU DHABI

Client: ZEE STORES


Standard: BS EN 62305-2:2012 (Edition 2)
Project address: PLOT NO. KHIA9-18M, KIZAD, ABU DHABI
Project ref: 8585
Calculation ref: BS EN 62305-2:2012
Calculation notes: BS EN 62305-2:2012
Project author: Nihad
Created: 25/10/2023
Modified: 25/10/2023

Case details
Case name: Original Case

Case title: PROPOSED ZEE STORE ON PLOT NO. KHIA9-18M, KIZAD, ABU DHABI
Case notes: 1. The building is considered to be fitted with less than 100 persons at any given point of time.
2. The building is considered to be fitted with automated fire alarm system.
3. The project is located in a place where there are buildings of same height.
4. Telecom line is considered to be fiber optic.
5. The risk of loss of fire is considered to be ordinary as per BS EN 62305.

The following primary risks and their relevant tolerable risks have been taken into consideration as part of this risk
management calculation

R1 3.7974E-06 Risk of loss of human life in the structure.


The tolerable risk of 1E-05 is not exceeded based on the application of the
protection measures listed below.

R2 7.343E-06 Risk of loss of service to the public in the structure


The tolerable risk of 0.0001 is not exceeded based on the application of the
protection measures listed below.

Protection system design parameters


Structural LPS Requirement for a structural lightning protection system (LPS) and where
necessary the chosen Lightning protection level (LPL)

Lightning protection level (LPL) IV

Imax Maximum peak current

100 kA

ProbImax Probability that lightning current parameters are smaller than the maximum value
defined above

StrikeRisk v6.0.0 Run identification 25/10/2023 - 12:21:11 Page 2 of 8


PROPOSED ZEE STORE ON PLOT NO. KHIA9-18M, KIZAD, ABU DHABI

97%

Imin Minimum peak current

16 kA

ProbImin Probability that lightning current parameters are greater than the minimum value
defined above

84%

r Radius of rolling sphere

60 m

ISPD Maximum peak current of SPDs for each of the 1 lines considered (based on the
simple current division concept).

NOTE: The worst case surge that could be expected on a two-wire telephone or data line is 2.5kA
(10/350 µs) per line (Category D test to IEC/EN 61643-21) to earth or 5 kA (10/350 µs) per pair.

50 kA

Line 1
Power
Service entrance SPD Requirement to protect Line 1 at its entrance to the structure with an equipotential
bonding SPD (rated to ISPD above) in accordance with BS EN 62305-2:2012
(Edition 2)

NOTE: Where SPDs are required but an LPS is not (ISPD = 0), protect overhead lines with Type 1 SPDs
(mains 12.5kA 10/350µs, data/telecom 2.5kA 10/350µs), protect underground lines with overvoltage or
Type 2 SPDs (tested with an 8/20 µs waveform)

Lightning protection level (LPL) IV

Coordinated SPD set Requirement to protect all internal systems connected to Line 1 with a coordinated
set of SPDs in accordance with BS EN 62305-2:2012 (Edition 2)

Lightning protection level (LPL) IV

Zone 1
PROPOSED ZEE STORE
Fire protection system Automatic extinguishing or alarm installations

Environmental factors

StrikeRisk v6.0.0 Run identification 25/10/2023 - 12:21:11 Page 3 of 8


PROPOSED ZEE STORE ON PLOT NO. KHIA9-18M, KIZAD, ABU DHABI

NG 0.5 Lightning ground flash density (Flashes/km²/year)


CD 0.5 Location factor
CE 0.5 Environmental factor

Primary structure
Structure ID: 1 - PROPOSED ZEE STORE
Lb 90 m Length of structure (metres)
Wb 66 m Width of structure (metres)
Hb 24 m Height of structure (metres)

Line factors
Line 1 - Power
KS3 0.2 Factor relevant to the characteristics of internal wiring
PEB 0.05 Probability of failure of internal systems or a service when
SPDs are provided for equipotential bonding (in accordance
with BS EN 62305-3)
PSPD 0.05 Probability of failure of internal systems or a service when
coordinated SPDs are provided
UW 4 kV Rated impulse withstand voltage of a system (kV)
CLD 1 Factor depending on shielding, grounding and isolation
conditions of the line for flashes to a line
CLI 0.3 Factor depending on shielding, grounding and isolation
conditions of the line for flashes near a line
Type 1
Connected structure:
LL (Section 1) 50 m Length of line section (metres)
LH (Section 1) 0m Height of line section (metres)
CT (Section 1) 1 Factor taking into account the presence of an HV/LV
transformer on a line section
CI (Section 1) 0.5 Factor relating to the routing of a line section

Zone factors
nt2 100 Total number of users served by the structure
Zone 1 - PROPOSED ZEE STORE
Zone Location Inside the structure LPZ 1...n
rp 2E-01 Factor reducing the loss due to provisions against fire in zone
rf 1E-02 Factor reducing the loss due to the risk of fire in zone
rt 1E-03 Factor reducing the loss due to the type of floor/surface in
zone
hz1 2E00 Factor increasing the loss of human life due to presence of
special hazard in zone
LT1 1E-02 Loss due to injury due to touch and step voltages in zone
LF1 4.2E-01 Loss to structure due to physical damage in zone

StrikeRisk v6.0.0 Run identification 25/10/2023 - 12:21:11 Page 4 of 8


PROPOSED ZEE STORE ON PLOT NO. KHIA9-18M, KIZAD, ABU DHABI

LO1 0E00 Loss to structure due to failure of internal systems in zone


LF2 1E-01 Loss to structure due to physical damage in zone
LO2 1E-02 Loss to structure due to failure of internal systems in zone
nz2 100 Number of users served by zone

Assessment of Ax - Collection areas


PROPOSED ZEE STORE
AD 44,690.02 m² Collection area of structure (square metres)
AM 941,398.16 m² Collection area of surrounding ground (square metres)
AL 2,000.00 m² Collection area of flashes striking line (square metres)
AI 200,000.00 m² Collection area of flashes near line (square metres)
Line 1 - Power (Section 1)
AL 2,000.00 m² Collection area of flashes striking line (square metres)
AI 200,000.00 m² Collection area of flashes near line (square metres)

Assessment of Nx - Annual number of dangerous events


PROPOSED ZEE STORE
ND 1.1173E-02 Average number of flashes to main structure
NM 4.707E-01 Average number of flashes to surrounding ground
Line 1 - Power (Section 1)
NL 2.5E-04 Average number of flashes to line
NI 2.5E-02 Average number of flashes near line
Line 1 - Power
NL 2.5E-04 Average number of flashes to line
NI 2.5E-02 Average number of flashes near line

Assessment of Px - Probability of damage for a structure


PB 2E-01 Probability that a flash to a structure will cause physical
damages
PC 5E-02 Probability that a lightning flash near to the structure will cause
failure of internal systems
KS1 1E00 Factor relating to screening effectiveness of the structure
Zone 1 - PROPOSED ZEE STORE
PTA 1E00 Probability that lightning will cause injuries to living beings
PA 2E-01 Probability that lightning will cause injuries to living beings
present in zone
KS2 1E00 Factor relating to screening effectiveness of shields internal to
the structure
PM 1.25E-04 Probability that a lightning flash near to the structure will cause
failure of internal systems
Zone 1 - PROPOSED ZEE STORE (Power)

StrikeRisk v6.0.0 Run identification 25/10/2023 - 12:21:11 Page 5 of 8


PROPOSED ZEE STORE ON PLOT NO. KHIA9-18M, KIZAD, ABU DHABI

PMS 2.5E-03 Probability of failure of internal systems (with protection


measures) associated with line
PM 1.25E-04 Probability that a lightning flash near to the structure will cause
failure of internal systems
PU 5E-02 Probability that injuries of living beings will be caused by a
flash to line
Line 1 - Power
PC 5E-02 Probability that a lightning flash near to the structure will cause
failure of internal systems
KS3 2E-01 Factor relevant to the characteristics of internal wiring
KS4 2.5E-01 Factor relating to the impulse withstand voltage of a system
associated with line
PLD 1E00 Probability of failure of internal systems (flashes to a
connected service) associated with line
PLI 1.6E-01 Probability of failure of internal systems (flashes near a
connected service) associated with line
PV 5E-02 Probability that physical damage will be caused by a flash to
line
PW 5E-02 Probability that failure of internal systems will be caused by a
flash to line
PZ 2.4E-03 Probability that failure to internal systems will be caused by a
flash near to line
Assessment of Lx - Amount of loss for a structure
Zone 1 - PROPOSED ZEE STORE
LA1 1E-05 Loss related to injury to living beings in zone
LB1 1.68E-03 Loss in a structure related to physical damage (flashes to
structure) in zone
LC1 0E00 Loss related to failure of internal systems (flashes to structure)
in zone
LM1 0E00 Loss related to failure of internal systems (flashes near
structure) in zone
LU1 1E-05 Loss related to injury of living beings (flashes to service) in
zone
LV1 1.68E-03 Loss in a structure due to physical damage (flashes to service)
in zone
LW1 0E00 Loss related to failure of internal systems (flashes to service)
in zone
LZ1 0E00 Loss related to failure of internal systems (flashes near a
service) in zone
LB2 2E-04 Loss in a structure related to physical damage (flashes to
structure) in zone
LC2 1E-02 Loss related to failure of internal systems (flashes to structure)
in zone
LM2 1E-02 Loss related to failure of internal systems (flashes near
structure) in zone
LV2 2E-04 Loss in a structure due to physical damage (flashes to service)
in zone
LW2 1E-02 Loss related to failure of internal systems (flashes to service)

StrikeRisk v6.0.0 Run identification 25/10/2023 - 12:21:11 Page 6 of 8


PROPOSED ZEE STORE ON PLOT NO. KHIA9-18M, KIZAD, ABU DHABI

in zone
LZ2 1E-02 Loss related to failure of internal systems (flashes near a
service) in zone
Assessment of Rx - Risk components
Zone 1 - PROPOSED ZEE STORE
RA1 2.2345E-08 Risk component of risk R1 due to injury to living beings (D1)
caused by flashes to a structure (S1) in zone
RB1 3.754E-06 Risk component of risk R1 due to physical damage to a
structure (D2) caused by flashes to a structure (S1) in zone
RC1 0E00 Risk component of risk R1 due to failure of internal systems
(D3) caused by flashes to a structure (S1) in zone
RM1 0E00 Risk component of risk R1 due to failure of internal systems
(D3) caused by flashes near a structure (S2) in zone
RB2 4.469E-07 Risk component of risk R2 due to physical damage to a
structure (D2) caused by flashes to a structure (S1) in zone
RC2 5.5863E-06 Risk component of risk R2 due to failure of internal systems
(D3) caused by flashes to a structure (S1) in zone
RM2 5.8837E-07 Risk component of risk R2 due to failure of internal systems
(D3) caused by flashes near a structure (S2) in zone
Zone 1 - PROPOSED ZEE STORE (Line 1 - Power)
RU1 1.25E-10 Risk component of risk R1 due to injury to living being (D1)
caused by flashes to a connected service (S3) associated with
line
RV1 2.1E-08 Risk component of risk R1 due to physical damage to
structure (D2) caused by flashes to a connected service (S3)
associated with line
RW1 0E00 Risk component of risk R1 due to failure of internal systems
(D3) caused by flashes to a connected service (S3) associated
with line
RZ1 0E00 Risk component of risk R1 due to failure of internal systems
(D3) caused by flashes near a service (S4) associated with
line
RV2 2.5E-09 Risk component of risk R2 due to physical damage to
structure (D2) caused by flashes to a connected service (S3)
associated with line
RW2 1.25E-07 Risk component of risk R2 due to failure of internal systems
(D3) caused by flashes to a connected service (S3) associated
with line
RZ2 5.94E-07 Risk component of risk R2 due to failure of internal systems
(D3) caused by flashes near a service (S4) associated with
line
Primary risk totals
R1_T 3.7974E-06 Risk of loss of human life in the structure.
R2_T 7.343E-06 Risk of loss of service to the public in the structure
Primary risk totals with respect to source of damage
R1_D 3.7763E-06 Risk of loss of human life in the structure due to flashes to the
structure (S1)

StrikeRisk v6.0.0 Run identification 25/10/2023 - 12:21:11 Page 7 of 8


PROPOSED ZEE STORE ON PLOT NO. KHIA9-18M, KIZAD, ABU DHABI

R2_D 6.0332E-06 Risk of loss of service to the public in the structure due to
flashes to the structure (S1)
R1_I 2.1125E-08 Risk of loss of human life in the structure due to flashes
influencing, but not striking the structure (S2, S3, & S4)
R2_I 1.3099E-06 Risk of loss of service to the public in the structure due to
flashes influencing, but not striking the structure (S2, S3, &
S4)
Primary risk totals with respect to type of damage
R1_S 2.247E-08 Risk of loss of human life in the structure due to injury to living
beings (D1)
R2_S 0E00 Risk of loss of service to the public in the structure due to
injury to living beings (D1)
R1_F 3.775E-06 Risk of loss of human life in the structure due to physical
damage (D2)
R2_F 4.494E-07 Risk of loss of service to the public in the structure due to
physical damage (D2)
R1_O 0E00 Risk of loss of human life in the structure due to failure of
internal systems (D3)
R2_O 6.8936E-06 Risk of loss of service to the public in the structure due to
failure of internal systems (D3)

StrikeRisk v6.0.0 Run identification 25/10/2023 - 12:21:11 Page 8 of 8

You might also like