ZWSC Major Overhaul of Three Elliott Gas Compressor Accomplishment Report
ZWSC Major Overhaul of Three Elliott Gas Compressor Accomplishment Report
• The Contract 144438 was awarded to Elliott who is the • AFE approved for MZ293 = USD 4.0M
registered OEM for these Gas Compressors; the scope of • Estimated expenditure till Dec 2014 = USD 3.4M
work included the major overhaul of the compressors at • Expected Saving = USD 0.6M
site and major overhaul of the spare compressor inner This cost saving was achieved by challenging the repair costs
bundle and rotor at the vendor workshop facility. and modification requirements with the OEM during the
compressor refurbishments.
Challenges
• Each of the Major overhauls had to be completed within the Lessons Learned
contractual time frame and as per the Zakum Integrated
• One of the compressor major overhauls was planned to
Shutdown Master Plan.
coincide with the GG-2 Major Plant shutdown, this strategy
• Initially there was one spare complete inner casing bundle
is to prevent series of shutdowns.
and rotor in Mussafah Stores this was installed in the first
compressor, the inner bundle and rotor assembly that was
• However, the commissioning of this compressor was
removed from the first compressor was sent to Elliott
delayed by several days due to other planned shutdown
workshop facility in Italy for refurbishment and we had to
activities which resulted in additional standby cost for the
ensure that it was returned on time to carry out the next
Elliott Field Service Representative.
compressor major overhaul.