Typical sequence of Principle Event during

Contract for Construction


Issue of 8.1 11.9 Issue of the
10.1 Issue of
the Letter Commencement Taking-over Cert Performance
Issue of Date
of Acc. Certificate
Tender Submisson
Doc of the
Tender
Base 8.2 Time for Defect
date Completion Notification
Period

28d <28d <21d


Delay 11 Notifying
attributable to of Defect
the Contractor
Remedying of
Defect
Tender 4.2 Issue of
Period Performance 9.1 Tests on 4.2 Return of the
Security Completion Performance
Security
Typical sequence of Payment Events
envisaged in clause 14

14.3 Contractor 14.7 Employer makes


submit the Payment to the
14.6 Engineer
Statement to Contractor
issues Interim
the Engineer Payment Certificate
Each of the
monthly
< 56 d
(for
otherwise)
interim < 28 d
payments

The final Engineer verifies < 28 d < 56 d


payment statement, Contractor
submits information

14.11 Contractor submits 14.11 Contractor


draft final statement to 14.13 Engineer 14.7 Employer
issues Final issues Final
the Engineer statement and the makes payment
Payment Certificate
14.12 discharge
Typical sequence of Dispute
Events envisaged in Clause 20
20.2 20.4 A Party may 20.6 A Party
Parties 20.4 A Party refers a issue a “ notice of may initiate
8.1
appoint disputes to the DAB dissatisfaction arbitration
Commencement
DAB
Date
Parties present
submissions to
Amicable
the DAB
settlement

< 28 d < 84 d < 28 d > 56 d

DAB Arbitrator/s
gives its Appointed
decision