Single Interlock Valve: Tools That Make People Move

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 20

www.everdigm.

com

Tools that make people move

Single Interlock Valve


CONTENT

1. General

2. Model

3. Characteristic data

4. Replacement the O-ring

5. Cleaning method for SIV

6. Hydraulic circuit for SIV


1. General

1) Purpose : To prevent pulling or pushing loads from accelerating during movement.

2) Application : For load-holding parts (hydraulic lifting, pivoting and turning etc.)

3) Advantage

- It controls the oil flow automatically by spring tension and hydraulic pressure.

- It is specialized in the vibration.

3
2. Model Model : LHDV 33H-B6-350/370
1) LHDV 33H- : Banjo bolt mounting,
consumer side

① ② ③ 2) 15 : shock valve
3) B : When the valve is operated with the
max. flow rate, B is pressure rising.

Adjustable pressure range 0~350 A B C D E

Adjustable pressure range 350~420 L M N P R


Max. flow
80 60 40 25 16
(When the valve fully opened)

4
2. Model Model : LHDV 33H-B6-350/370
4) 6 : Orifice 2 diameter
Coding 4 5 6 7 8 0

④ ⑤ ⑥ Φ(mm) 0.4 0.5 0.6 0.7 0.8 0 (no hole)


Ratio 1:6.3 1:4.45 1:2.9 1:1.84 1:1.18 1:8.2

5) 350 : Selected pressure setting(bar)


for load holding valve
6) 370 : Selected pressure setting(bar)
for shock valve

5
3. Characteristic data
Model : LHDV 33H-B6-350/370
1) Designation - Load holding valve(over center valve), with hydraulic release.
by-pass check valve.
2) Valve design - Load holding valve : cone seated piston valve
By-pass check valve : disk seated valve
3) Alternation of pressure approx.

Alternation of pressure approx. Per turn Per mm approx.


50 ~ 250 bar 45 bar 25 bar
Load holding valve Pressure range 220 ~ 350 bar 50 bar 27.5 bar
280 ~ 420 bar 62 bar 34 bar
Shock valve Pressure range 50 ~ 250 bar 106 bar 80 bar

6
3. Characteristic data
4) SIV pressure setting

When you set the SIV pressure, you need the manual pump and pressure gage.
① The grub screw, serves for locking of ② and must be loosened prior to any pressure
adjustment.
② Perforated disc can be rotated with Allen Key A/F
= Pressure increase
= Pressure decrease
③ Retighten the grub screw ① after performed adjustment.
7
3. Characteristic data
5) Pressure fluid

① Viscosity(theory) : Min. approx. 4mm2/sec ~ Max. approx. 1500mm2/sec


② Viscosity(Optimum) : Min. approx. 4mm2/sec ~ Max. approx. 1500mm2/sec

6) Temperature

① Ambient : approx. -40℃ ~ +80℃


② Fluid : -25℃ ~ +80℃
- If the operating temperature is low(example below -40℃), check the fluid viscosity and
the temperature is 20K higher(compared to -40℃) at least.
- Biological degradable pressure fluid [HEPG(Polyalcylenglycol), HEES(synthetic ester)]
: The operating temperature is below +70℃

8
Before the work(replace O-ring and cleaning)
1. Before the work, you have to fix the boom. Because if you remove the SIV, there will be
no hydraulic pressure in the cylinder. So the boom may retract while at work.

2. When you remove the bolt(A), you have to


release slow. Because there is very high
hydraulic pressure. So someone gets hurt.
C
A And you can miss that bolt.
3. When you screw bolt(C), please screw the
bolt C slowly, Connected portion of 1st cylinder
with SIV is possible to be broken, if you screw
the bolt C too tight.

Read and remember before the work

9
4. Replace the O-ring
Before working – FOR SAFE WORKING, ALL BOOMS HAVE TO BE FOLDED
① Before the working, you have to remove the hydraulic oil in
the SIV. Unscrew the bolt A (13mm spanner).
Warning : The oil pressure remains in the SIV.
C Unscrew slowly.
A ② After releasing the oil, remove the pipes around the SIV.
③ Change B(O-ring)
④ Assemble the SIV and connect the pipe.
Caution : When you screw bolt C, please screw the
bolt C slowly, Connected portion of 1st cylinder with
SIV is possible to be broken, if you screw the bolt C
B too tight.
⑤ After assembling, operate joystick 1st boom fold function
for charging hydraulic oil into SIV and check the boom
movement.
10
5. Cleaning method for SIV
Before working – FOR SAFE WORKING, ALL BOOMS HAVE TO BE FOLDED

① Before the working, you have to remove the


hydraulic oil in the SIV. Unscrew the bolt A
A (13mm spanner).
Warning :
- The oil pressure remains in the SIV.
- Unscrew slowly.

11
5. Cleaning method for SIV
Before working – FOR SAFE WORKING, ALL BOOMS HAVE TO BE FOLDED

① Before the work, check the bolt depth


for same pressure(Fig2).

12
5. Cleaning method for SIV
Before working – FOR SAFE WORKING, ALL BOOMS HAVE TO BE FOLDED

① When you remove the case, Release the


bolt B. And then release the bolt C.
(Fig.3)

13
5. Cleaning method for SIV
Before working – FOR SAFE WORKING, ALL BOOMS HAVE TO BE FOLDED

① Remove the case with


C spanner.
A
② Clean the whole parts.
(You may use the clean oil)
※ Caution : Parts are small.
So Be careful to lose parts.

14
5. Cleaning method for SIV
Before working – FOR SAFE WORKING, ALL BOOMS HAVE TO BE FOLDED

① Assembly sequence is of
dismantlement in reverse sequence.
② Release “C”(for adjusting) to the
maximum(It has to be assembled).
③ Assemble the case with spanner.
Don’t forget to put the washer.
④ Fasten “C”(for adjusting) slowly.
The pressure is getting high.
⑤ Fasten “C”(for adjusting) until same
depth which is measured before
disassemble.
⑥ Fasten “B” (for fixing).
15
5. Cleaning method for SIV
Before working – FOR SAFE WORKING, ALL BOOMS HAVE TO BE FOLDED

⑦ After assembling SIV, assemble the


pipes.
⑧ Before controlling the boom, please
fold all booms for supplying hydraulic
oil at SIV.

16
6. Hydraulic circuit for SIV(MBC block)
B A B A

2 1. 1 : Valve location (Extension)

2 : Valve location (Retraction)

2. P : Pilot line
1
T : Transfer line

P
T
17
6. Hydraulic circuit for SIV Load holding valve

1 2

1. 1 : Cylinder extension

2 : Cylinder retraction

Shock valve

18
6. Hydraulic circuit for SIV
Load holding valve ① F : F line is flow line for hydraulic. The hydraulic moves

through this line to cylinder or tank.

② Z : Z line is to open the check valve. Z line is connected

with F line and oppose valve’s S line.


① ③
③S:

④ R : R line is relief line. If the pressure is too high at the

② ④ load holding valve, the shock valve is opened and

return the oil to tank.

Shock valve

19
www.everdigm.com