Professional Documents
Culture Documents
Week 4 (Lec 14-19)
Week 4 (Lec 14-19)
EL
Vinod Gupta School of Management
PT
IIT Kharagpur
N
Module 06: Developing Project Plan
Lecture 14: Extended Network Techniques to Represent Reality
Concepts Covered:
• Developing Project Network
• Constructing a Project Network
• Activity-on-Node (AON), Activity-on-Arrow (AOA)
• Network Computation Process
EL
• Forward Pass and Backward Pass Computation
PT
• Level of Details for Activities
• Extended Network Techniques
N
• Concepts of Lags, Laddering, Hammock Activities
• Uncertainty in activities - three time estimates
• Probability of Completion of Project on Time
Extended Network Techniques to Come Close to Reality
• Laddering
EL
PT
N
Source: Project Management, Gray and Larson
Extended Network Techniques to Come Close to Reality
• Lags
Use of Lags
Finish-to-Start Relationship
EL
PT
N
Start-to-Start Relationship
Use of Lags
Finish-to-Finish Relationship
EL
PT
N
Start-to-Finish Relationship
• Lags
Use of Lags to Reduce Project Duration
Combination Relationship
EL
PT
Source: Project Management, Gray and Larson N
EL
PT
N
New Product Development Process
Network using Lags
EL
PT
N
Hammock Activities
EL
PT
N
Conclusion:
• Further to the previous lecture, this class discusses the extended network techniques
that represent the reality. It introduces the concept of lags and how to fast track a
project, and develop network using lag.
• It further illustrates the concept of laddering, Hammock activities etc., which are widely
used by the practitioners.
EL
PT
N
References:
1. Project Management – The Managerial Process, Gray, C.F., Larson, E.W., and
Joshi, R., McGraw Hill Education, 8th edition.
2. Project Management – Achieving Competitive Advantage, Jeffrey K. Pinto, Pearson
Publishing Ltd., 5th edition.
EL
3. Project Management: A Managerial Approach, Meredith, J.R. and Mantel, S.J.,
Wiley, PMBOK Guidelines Book
PT
4. Project Management, Pradeep Pai, Pearson India Education Services Pvt Ltd.,
N
2019, 1st edition.
N
PT
EL
PROJECT MANAGEMENT: PLANNING, EXECUTION,
EVALUATION AND CONTROL
Prof. Sanjib Chowdhury
EL
Vinod Gupta School of Management
PT
IIT Kharagpur
N
Module 06: Developing Project Plan
Lecture 15: Probability of Completion of Project on Time
Concepts Covered:
• Developing Project Network
• Constructing a Project Network
• Activity-on-Node (AON), Activity-on-Arrow (AOA)
• Network Computation Process
EL
• Forward Pass and Backward Pass Computation
PT
• Level of Details for Activities
• Extended Network Techniques
N
• Concepts of Lags, Laddering, Hammock Activities
• Uncertainty in activities - three time estimates
• Probability of Completion of Project on Time
Incorporating Uncertainty in Activity Times
F(D)
P(D<A) = .01
P(D>B) = .01
EL
TIME
PT
A M D B
N
optimistic most pessimistic
likely
_ A+ 4M + B
Expected Duration: D=
6
2
B − A Problem Solving
Variance: V =
6
Activity and Project Frequency Distributions
EL
PT
‒ Three time estimates
N
‒ Average activity time
‒ Standard deviation for each activity
‒ Standard deviation for the project
Probability of Completion of Project on time
f (X)
13.6% 13.6%
EL
0.1% 2.1% 2.1%
0.1%
PT
μ-3σ μ-2σ μ-σ μ μ+σ μ+2σ μ+3σ X
68.2%
N
95.4%
99.7%
Figure: Normal distribution with mean (μ) and standard deviation (σ) depicting areas under
each segment of the curve; shaded area left to the z-value is the probability of occurrence
Source: Optimization and Business Improvement Studies in Upstream Oil and Gas Industry, Sanjib Chowdhury, Wiley & Sons Inc., NJ, USA., 2016.
Question
The activity times of a project network is given below:
Activity aopt mml bpess
1-2 17 29 47
2-3 6 12 24
2-4 16 19 28
3-5 13 16 19
EL
4-5 2 5 14
5-6 2 5 8
PT
1. Compute the expected time and variance of activities
N
2. Compute the expected project duration, and determine critical path
showing early start (ES), early finish (EF), late start (LS), late finish (LF),
and slack for each activity.
3. What is the probability of completing the project by 67 days? And within
60 days?
Activity Times and Variances
EL
PT
N
N
PT
EL
N
PT
EL
Conclusion:
• Further to the last lecture, this chapter illustrates the uncertainty in activities such as
new product development, R&D work etc. It introduces three time estimates, namely,
optimistic, pessimistic, and most likely times, which are generally used in PERT.
• It further determines the probability of project completion on time to assist project
EL
managers and senior management to take decision and plan accordingly.
PT
N
References:
1. Project Management – The Managerial Process, Gray, C.F., Larson, E.W., and
Joshi, R., McGraw Hill Education, 8th edition.
2. Project Management – Achieving Competitive Advantage, Jeffrey K. Pinto, Pearson
Publishing Ltd., 5th edition.
EL
3. Project Management: A Managerial Approach, Meredith, J.R. and Mantel, S.J.,
Wiley, PMBOK Guidelines Book
PT
4. Project Management, Pradeep Pai, Pearson India Education Services Pvt Ltd.,
N
2019, 1st edition.
N
PT
EL
PROJECT MANAGEMENT: PLANNING, EXECUTION,
EVALUATION AND CONTROL
Prof. Sanjib Chowdhury
EL
Vinod Gupta School of Management
PT
IIT Kharagpur
N
Module 07: Project Risk Management
Lecture 16: Managing Risk and Risk Identification
Concepts Covered:
• Risk Management Process
• Risk Identification
• Risk Assessment
• Risk Response Development
EL
• Contingency Planning
PT
• Contingency funding and Time buffers
N
• Risk Response Control
• Change Control Management
• Risk Assessment of Capital Project
Basic Concepts of Risk Management
• What is Risk?
EL
PT
• Benefits of Risk Management
N
- Proactive approach, ↓ surprises and -ve consequences, prepares PM
and team, ↑ control, ↑ performance, achieve goals
Risk Event and Cost Relation
EL
PT
N
Source: Project Management, Gray and Larson
Risk Management Process
Risk
Risk Risk Response
Risk Assessment Response
Identification Development
Control
•Brainstorming - •Scenario analysis - •Develop strategy ↓ •Risk control
Involve stakeholders likelihood, impact damage ‒Execute risk response
•RBS – macro •Risk assessment ‒ Mitigating (identify root strategy; Monitor
matrix causes e.g. vendor unable to triggering events,
risk, specific risk
EL
supply on time, safety training,
•Risk profile •Failure Mode and using high-quality materials, Initiate contingency
•External risk, Effects Analysis scheduling outdoor events) plans, Watching for
PT
•Probability analysis - ‒ Avoiding new risks
common mistakes
Decision tree, NPV, ‒ Transferring •Establish Change
N
PERT ‒ Retaining Mgmt. system
•Develop Contingency ‒Monitor & report
plan risk; Foster open org.
‒ Technical risks, environ; Repeat
Schedule risks, Cost exercise; Assign
risks, Funding risks responsibility
•Opportunity mgmt.
Risk Breakdown Structure (RBS)
EL
PT
N
Source: Project Management, Gray and Larson
Partial Risk Profile for Product Development Project
EL
PT
N
Source: Project Management, Gray and Larson
Conclusion:
• This module deals with risk management process and explains risk is an event or
conditions, if it happens has a negative or positive effect on the (project) objective. The
module also describes risk management process, and its benefits.
• This chapter also discusses how to manage risks in a systematic way. The steps in
EL
managing risk starts with (1) risk identification, followed by (2) risk assessment, (3) risk
PT
response development, and (4) risk response control. Risk identification process has
been discussed in detail in this lecture.
N
References:
1. Project Management – The Managerial Process, Gray, C.F., Larson, E.W., and
Joshi, R., McGraw Hill Education, 8th edition.
2. Project Management – Achieving Competitive Advantage, Jeffrey K. Pinto, Pearson
Publishing Ltd., 5th edition.
EL
3. Project Management, Pradeep Pai, Pearson India Education Services Pvt Ltd.,
2019, 1st edition.
PT
4. Project Management: A Managerial Approach, Meredith, J.R. and Mantel, S.J.,
N
Wiley, PMBOK Guidelines Book
N
PT
EL
PROJECT MANAGEMENT: PLANNING, EXECUTION,
EVALUATION AND CONTROL
Prof. Sanjib Chowdhury
EL
Vinod Gupta School of Management
PT
IIT Kharagpur
N
Module 07: Project Risk Management
Lecture 17: Risk Assessment
Concepts Covered:
• Risk Management Process
• Risk Identification
• Risk Assessment
• Risk Response Development
EL
• Contingency Planning
PT
• Contingency funding and Time buffers
N
• Risk Response Control
• Change Control Management
• Risk Assessment of Capital Project
Risk Management Process
Risk
Risk Risk Response
Risk Assessment Response
Identification Development
Control
•Brainstorming - •Scenario analysis - •Develop strategy ↓ •Risk control
Involve stakeholders likelihood, impact damage ‒Execute risk response
•RBS – macro •Risk assessment ‒ Mitigating (identify root strategy; Monitor
matrix causes e.g. vendor unable to triggering events,
risk, specific risk
EL
supply on time, safety training,
•Risk profile •Failure Mode and using high-quality materials, Initiate contingency
•External risk, Effects Analysis scheduling outdoor events) plans, Watching for
PT
•Probability analysis - ‒ Avoiding new risks
common mistakes
Decision tree, NPV, ‒ Transferring •Establish Change
N
PERT ‒ Retaining Mgmt. system
•Develop Contingency ‒Monitor & report
plan risk; Foster open org.
‒ Technical risks, environ; Repeat
Schedule risks, Cost exercise; Assign
risks, Funding risks responsibility
•Opportunity mgmt.
What is Risk Severity Matrix?
EL
3
PT
2 System freezing
N
Hardware
1 malfunctioning
1 2 3 4 5
Impact
• What is Failure Mode and Effects Analysis (FMEA)?
Defined Conditions for Impact Scales of a Risk on Major Project Objectives
(Examples for Negative Impacts Only)
EL
PT
Source: Project Management, Gray and Larson
N
Risk Assessment Form
EL
PT
Source: Project Management, Gray and Larson N
Risk Assessment
Based on the following information, prioritize the risk events. Which event
should you be most concerned about?
EL
PT
N
Measuring Risk Illustrative
e.g., XYZ Co.
0 1 – Frequent - 0 - NA
EL
5 2 - Likely 1 1 - Incidental
PT
N
10 3 - Possible 5,000,000 2 - Minor
EL
1 - Frequent
Medium High High Very High Very High
PT
2 - Likely
Likelihood
N
Medium Medium High High Very High
3 - Possible
EL
• It also illustrates scales of likelihood and impact followed by large reputed companies
in real-life.
PT
N
References:
1. Project Management – The Managerial Process, Gray, C.F., Larson, E.W., and
Joshi, R., McGraw Hill Education, 8th edition.
2. Project Management – Achieving Competitive Advantage, Jeffrey K. Pinto, Pearson
Publishing Ltd., 5th edition.
EL
3. Project Management, Pradeep Pai, Pearson India Education Services Pvt Ltd.,
2019, 1st edition.
PT
4. Project Management: A Managerial Approach, Meredith, J.R. and Mantel, S.J.,
N
Wiley, PMBOK Guidelines Book
N
PT
EL
PROJECT MANAGEMENT: PLANNING, EXECUTION,
EVALUATION AND CONTROL
Prof. Sanjib Chowdhury
EL
Vinod Gupta School of Management
PT
IIT Kharagpur
N
Module 07: Project Risk Management
Lecture 18: Risk Response Development and Contingency Planning
Concepts Covered:
• Risk Management Process
• Risk Identification
• Risk Assessment
• Risk Response Development
EL
• Contingency Planning
PT
• Contingency funding and Time buffers
N
• Risk Response Control
• Change Control Management
• Risk Assessment of Capital Project
Risk Management Process
Risk
Risk Risk Response
Risk Assessment Response
Identification Development
Control
•Brainstorming - •Scenario analysis - •Develop strategy ↓ •Risk control
Involve stakeholders likelihood, impact damage ‒Execute risk response
•RBS – macro •Risk assessment ‒ Mitigating (identify root strategy; Monitor
matrix causes e.g. vendor unable to triggering events,
risk, specific risk
EL
supply on time, safety training,
•Risk profile •Failure Mode and using high-quality materials, Initiate contingency
•External risk, Effects Analysis scheduling outdoor events) plans, Watching for
PT
•Probability analysis - ‒ Avoiding new risks
common mistakes
Decision tree, NPV, ‒ Transferring •Establish Change
N
PERT ‒ Retaining Mgmt. system
•Develop Contingency ‒Monitor & report
plan risk; Foster open org.
‒ Technical risks, environ; Repeat
Schedule risks, Cost exercise; Assign
risks, Funding risks responsibility
•Opportunity mgmt.
Contingency Planning
• What is a Contingency Plan?
EL
‒ Schedule risks
‒ Costs risks
PT
‒ Funding risks
N
• What is an Opportunity in the context of Risk Management?
‒ Exploit
‒ Share
‒ Enhance
‒ Accept
Risk Response Matrix
EL
PT
N
Source: Project Management, Gray and Larson
Contingency Funding and Time Buffers
Contingency Funds
• Funds to cover project risks—identified and unknown
‒ Size of funds reflects overall risk of a project
• Budget reserves
‒ Are linked to the identified risks of specific work packages.
EL
• Management reserves
PT
‒ Are large funds to be used to cover major unforeseen risks (e.g.,
change in project scope) of the total project
N
Contingency Funding and Time Buffers Illustrative
EL
WBS 3 150 5 155
PT
Subtotal 1550 93 1643
Management - - 60
N
reserve
EL
‒ Noncritical activities to reduce likelihood of creating another critical path
PT
‒ Activities that require scarce resources
N
Conclusion:
• In continuation with the previous lecture, this session deals with developing risk
response plan that includes mitigating risk, avoiding risk, transferring risk, and
retaining risk.
• It further illustrates contingency planning which is an alternative plan in case of
EL
eventualities, that is, if risk becomes reality. Contingency plan is associated with four
types of risks, namely, technical risk, schedule risk, cost risk, and funding risk.
PT
• The module further elucidates opportunity in the context of risk management, which
N
are essentially of four types viz. exploit, share, enhance, and accept.
References:
1. Project Management – The Managerial Process, Gray, C.F., Larson, E.W., and
Joshi, R., McGraw Hill Education, 8th edition.
2. Project Management – Achieving Competitive Advantage, Jeffrey K. Pinto, Pearson
Publishing Ltd., 5th edition.
EL
3. Project Management, Pradeep Pai, Pearson India Education Services Pvt Ltd.,
2019, 1st edition.
PT
4. Project Management: A Managerial Approach, Meredith, J.R. and Mantel, S.J.,
N
Wiley, PMBOK Guidelines Book
N
PT
EL
PROJECT MANAGEMENT: PLANNING, EXECUTION,
EVALUATION AND CONTROL
Prof. Sanjib Chowdhury
EL
Vinod Gupta School of Management
PT
IIT Kharagpur
N
Module 07: Project Risk Management
Lecture 19: Risk Response Control, and Change Control Management
Concepts Covered:
• Risk Management Process
• Risk Identification
• Risk Assessment
• Risk Response Development
EL
• Contingency Planning
PT
• Contingency funding and Time buffers
N
• Risk Response Control
• Change Control Management
• Risk Assessment of Capital Project
Risk Management Process
Risk
Risk Risk Response
Risk Assessment Response
Identification Development
Control
•Brainstorming - •Scenario analysis - •Develop strategy ↓ •Risk control
Involve stakeholders likelihood, impact damage ‒Execute risk response
•RBS – macro •Risk assessment ‒ Mitigating (identify root strategy; Monitor
matrix causes e.g. vendor unable to triggering events,
risk, specific risk
EL
supply on time, safety training,
•Risk profile •Failure Mode and using high-quality materials, Initiate contingency
•External risk, Effects Analysis scheduling outdoor events) plans, Watching for
PT
•Probability analysis - ‒ Avoiding new risks
common mistakes
Decision tree, NPV, ‒ Transferring •Establish Change
N
PERT ‒ Retaining Mgmt. system
•Develop Contingency ‒Monitor & report
plan risk; Foster open org.
‒ Technical risks, environ; Repeat
Schedule risks, Cost exercise; Assign
risks, Funding risks responsibility
•Opportunity mgmt.
Managing risks
EL
o Monitoring of triggering events
PT
o Initiating contingency plans
N
o Watching for new risks
Managing risks
EL
o Repeating risk identification/assessment exercises
PT
o Assigning and documenting responsibility for managing risk
N
Change Management Control
Sources of Change
EL
2. Implementation of contingency plans –
change in baseline cost and schedule
PT
3. Improvement changes
N
Change Management Control
EL
– Track allocation and use of budget and management reserve funds
– Clarify responsibility for implementation
PT
– Ensure visibility of effect of changes
N
– Monitor implementation of change
– Scope changes to be reflected in baseline and performance measures
Sample Change
Request
EL
PT
N
Illustrative
Some Common Project Risks
• Pre-completion risks: • Post completion risk
Accuracy of resource base Price risk
Technology risk Production & transportation
Construction challenges risk
Partner/contractor risk Environmental risk
EL
Estimation risk Geopolitical risk (Govt
PT
interface)
Stakeholder risk
N
• Macroeconomic risk
Inflation & economic
disruption
Currency risk
Blow-out at BP Deepwater Horizon drilling rig
operating in Gulf of Mexico (20th April 2010)
EL
PT
N
Role of contractors
in project execution
Few High-profile Accidents
Contractor Risk
• Capsize of Crude carrier Alexander Kielland (1980)
• Grounding of Exxon Valdez in Alaska (1989)
• Fire at Piper alpha platform in North sea (1989)
• Fire at BHN platform complex (2005)
• Destruction in Gulf of Mexico caused by Hurricane Katrina
EL
PT
N
Conclusion:
• This session deals with the final step of risk management process, that is, risk
response control that includes maintaining risk register, monitoring triggering events
for risk, watching for new risks, establishing change management control system,
sources of change, benefits of change control system, and so on.
EL
• The module also highlights some common project risks, and contractor risk, which
may lead to catastrophic effect if not attended to or proper risk management system is
PT
not in place in an organization.
N
References:
1. Project Management – The Managerial Process, Gray, C.F., Larson, E.W., and
Joshi, R., McGraw Hill Education, 8th edition.
2. Project Management – Achieving Competitive Advantage, Jeffrey K. Pinto, Pearson
Publishing Ltd., 5th edition.
EL
3. Project Management, Pradeep Pai, Pearson India Education Services Pvt Ltd.,
2019, 1st edition.
PT
4. Project Management: A Managerial Approach, Meredith, J.R. and Mantel, S.J.,
N
Wiley, PMBOK Guidelines Book
N
PT
EL