PURANIK CITY RESERVA – IV

CONTENTS

 ROAD MAP FOR COMPLETION

 SEPT 23 MONTH PLAN vs ACTUAL

 LAST SIX MONTHS ACTIVITIES COMPLETION STATUS

 PROJECT HIGHLIGHTS

 IMPACT ON CONSTRUCTION COST & TIMELINE


ROAD MAP FOR COMPLETION GIVEN IN JUNE 23

Jun 23 July 23 Aug 23 Sept 23 Oct 23

• Common area • Drainage • OC application • OC application • Possession


finishes application • SWD • Possession • Stack parking
completion • SWD application application • SWD NOC expected • Compound wall
(s/case and lift • •
• Stack parking • FAPA FAPA NOC expected Approach road
lobby)
• Compound wall completion • CFO NOC expected
• Solar
• Approach road • CFO • Drainage NOC
• RWH Stability
• Tree application application expected
• OWC
• FAPA completion
• CFO application
AUG’23 MONTH – BUILDING COMMITMENT

Month of AUG’23 Month of AUG’23


Project Activities Remarks
Planned Actual Status

Work completion certificate


FAPA 100% completion Application raised, Officer visited
received for OC

Work completion certificate Application raised, Officer visited


CFO FIRE 100% completion
received for OC

100% completion Work completion certificate Application raised, Officer visited


DRAINAGE
received for OC

STACK PARKING 100% completion 30% completed WIP

TREE 100% completion 100% completed WIP Application raised, Officer visited
LAST SIX MONTHS ACTIVITIES COMPLETION STATUS

Month of Jan’23 Month of June’23 Month of Sept’23


Project Activities
status Actual Status Actual Status

Podium 20 % completed Completed

Completed
STP Not started

Completed
Fire Pump room 5 % completed

Completed
Domestic & flushing tanks 30 % completed

Completed
Doors 60 % completed

Completed
Podium Fire fighting works Not started 95 % completed

Lift works
60 % completed Completed
LAST SIX MONTHS ACTIVITIES COMPLETION STATUS
Month of June’23 Month of Sept’23
Project Activities Month of Jan’23 status
Actual Status Actual Status
Completed
Substation Not started 90 % Completed

Completed
Drainage Not started 80 % Completed

Sliding windows Completed


60 % completed

Stair case finishing Not started WIP


WIP

Completed
Common lift lobby gypsum Not started 95 % Completed

Completed
Flooring 70% completed

Plumbing donwtakes 40% completed Completed


LAST SIX MONTHS ACTIVITIES COMPLETION STATUS

Month of June’23 Month of Sept’23


Project Activities Month of Jan’23 status
Actual Status Actual Status

80% Completed Completed


Fire chute 10 % completed

Not started 95 % Completed Completed


OWC

30 % completed Completed
RWH

Not started 80 % Completed Completed


Main cable line ducting

Not started 70 % Completed 90 % Completed


Temporary access road
MAJOR NOC’S APPLICATION STATUS

Project Activities July/Aug’23 NOC application status Sept’23 Official visit status

Drainage NOC NOC applied TMC officials visited

TMC officials visited


SWD NOC NOC applied

TMC officials visited


Tree NOC NOC Applied

CFO NOC NOC Applied Chief Fire officer visited

STP NOC NOC Applied TMC officials visited

OWC NOC NOC Applied TMC officials visited


PROJECT HIGHLIGHTS (FROM JAN’23 TO SEPT’23)

 More than 320- 350 average labours working daily till date.

 More than Rs. 110 cr work done in last 06 months of span.

 Approx. 1.2 lacs sft of podium area constructed in 06 months.

 Approx. Rs. 25 cr worth long lead items delivered like DG, Transformer, fire pumps etc.

 CP & Sanitary materials procured for final possession and it will be installed at the time of final

handover.

 Switches, final paint touch up and housekeeping will be done during handover.
IMPACT ON CONSTRUCTION COST & TIME DUE TO MATERIAL RATE ESCALATION

 All Infra related works hampered due to heavy rainfall.

 Overall Rs. 4 cr balance recovery from customers affected progress.

 Overall cost impact is approx. Rs.350 per sft

 Steel prices have increased by 110%

 Concrete prices increased by 25%

 Plumbing material increased by 62%

 Electrical copper material increased by 45%

 Covid’19 affects labour movement more than 1.5 years.


MAJOR HIGHLIGHTS

 HT ELECTRICAL LINE PERMISSION RECEIVED

 TMC WATER LINE CONNECTED

 PODIUM COMPLETED

 CFO FIRE VISIT DONE

 ALL MAJOR NOC’S APPLIED

 ALL COMMON LOBBIES COMPLETED

 FIRE CHUTE COMPLETED


T5 -106 sample Flat ready for visit
BUILDING FRONT SIDE PHOTOS
BUILDING ELEVATION
BUILDING ELEVATION
FLAT COMPLETED PHOTOS
FLAT COMPLETED PHOTOS
Flat completed
Flat completed
Flat completed
Flat completed
LIFT LOBBY AREA

T4/T5 common area Lobby Gypsum ,Tiling, and light fixing completed
LIFT LOBBY
LIFT LOBBY
ACCESS ROAD PHOTOS
ACCESS ROAD PHOTOS
ACCESS ROAD PHOTOS

APPROACH ROAD
T4/T5 PODIUM –ENTRY 1 PHOTOS

APPROACH ROAD
T4/T5 PODIUM –ENTRY 1 PHOTOS

APPROACH ROAD
T4/T5 PODIUM

APPROACH ROAD
T4/T5 PODIUM ENTRY

APPROACH ROAD
CFO VISIT PHOTOS
CFO VISIT PHOTOS
CFO VISIT PHOTOS
SUBSTATION AND DG

CONNECTION COMPLETED
METER ROOM TO SUB STATION CONNECTION

CONNECTION COMPLETED
METER ROOM IN PROGRESS
FLAT WIRING IN PROGRESS
PODIUM FAPA WORKS
PODIUM FAPA WORKS
FIRE CHUTE COMPLETION
FIRE WORK- T4 T5 COMPLETED

Fire Pump room work completed


FIRE NOC WORK
FIRE WORK- T4 T5

Fire Pump room work completed


FIRE ACCESSORIES WORK

Building Fire accessories fixing completed


FIRE FIGHTING AND FAPA WORK
FIRE FIGHTING AND FAPA WORK
PODIUM PARKING
PODIUM PHOTOS

Podium Fire fighting work in progress


PODIUM WORK

TREMIX works at P1 level work In Progress


PAVER FIXING WORK IN PROGRESS

Pavers at completion stage


PAVER FIXING WORK IN PROGRESS

Pavers at completion stage


TMC WATER CONNECTION COMPLETED
STP WORK WITH SIGNAGE COMPLETED
OWC completed
TREE work completed

MIYAWAKI 650 trees planted Geo-tagging done. Lawn grass planted.


Labours working at site
WORK AFFECTED DUE TO RAIN -COMPOUND WALL

Compound wall work in progress


WORK AFFECTED DUE TO RAIN –ACCESS ROAD

Road work in progress


WORK AFFECTED DUE TO RAIN – DRAINAGE WORKS
CURRENT LABOUR STRENGTH
PCR Infra
PCR Building
Civil work 45 numbers
Civil work 24 numbers
Infra SWD drainage work 25 numbers
Waterproofing 16 numbers
InfraElectrical work 40 numbers
Tiling Work 20 numbers

Electrical Work 23 numbers

FirefightingWork 19 numbers

FAPA work 14 numbers


Current labour strength 510 numbers
Paintingwork 19 Numbers
Sept month strength 525 numbers
Miscellaneouswork 134 Number

Departmental Labour 124 numbers Oct month strength 325 numbers


Some Ready Flats
THANK YOU