PCR Current Updates
PCR Current Updates
CONTENTS
PROJECT HIGHLIGHTS
TREE 100% completion 100% completed WIP Application raised, Officer visited
LAST SIX MONTHS ACTIVITIES COMPLETION STATUS
Completed
STP Not started
Completed
Fire Pump room 5 % completed
Completed
Domestic & flushing tanks 30 % completed
Completed
Doors 60 % completed
Completed
Podium Fire fighting works Not started 95 % completed
Lift works
60 % completed Completed
LAST SIX MONTHS ACTIVITIES COMPLETION STATUS
Month of June’23 Month of Sept’23
Project Activities Month of Jan’23 status
Actual Status Actual Status
Completed
Substation Not started 90 % Completed
Completed
Drainage Not started 80 % Completed
Completed
Common lift lobby gypsum Not started 95 % Completed
Completed
Flooring 70% completed
30 % completed Completed
RWH
Project Activities July/Aug’23 NOC application status Sept’23 Official visit status
More than 320- 350 average labours working daily till date.
Approx. Rs. 25 cr worth long lead items delivered like DG, Transformer, fire pumps etc.
CP & Sanitary materials procured for final possession and it will be installed at the time of final
handover.
Switches, final paint touch up and housekeeping will be done during handover.
IMPACT ON CONSTRUCTION COST & TIME DUE TO MATERIAL RATE ESCALATION
PODIUM COMPLETED
T4/T5 common area Lobby Gypsum ,Tiling, and light fixing completed
LIFT LOBBY
LIFT LOBBY
ACCESS ROAD PHOTOS
ACCESS ROAD PHOTOS
ACCESS ROAD PHOTOS
APPROACH ROAD
T4/T5 PODIUM –ENTRY 1 PHOTOS
APPROACH ROAD
T4/T5 PODIUM –ENTRY 1 PHOTOS
APPROACH ROAD
T4/T5 PODIUM
APPROACH ROAD
T4/T5 PODIUM ENTRY
APPROACH ROAD
CFO VISIT PHOTOS
CFO VISIT PHOTOS
CFO VISIT PHOTOS
SUBSTATION AND DG
CONNECTION COMPLETED
METER ROOM TO SUB STATION CONNECTION
CONNECTION COMPLETED
METER ROOM IN PROGRESS
FLAT WIRING IN PROGRESS
PODIUM FAPA WORKS
PODIUM FAPA WORKS
FIRE CHUTE COMPLETION
FIRE WORK- T4 T5 COMPLETED
FirefightingWork 19 numbers