Professional Documents
Culture Documents
Texto para Grupo 7
Texto para Grupo 7
Abstract—This paper presents an analysis on a production shop facilities planning. Zhu and Wang (2009) [3] applied SLP
floor layout of a Can manufacturing company and the method to design the overall layout of log yards, that was
application of a systematic layout planning (SLP) procedure as examined the feasibility of SLP method in the layout yards.
an approach to solve the production shop floor layout problem. The result showed the good workflow and practical
The relationship between machines, operation activities and significance. Symptoms that allow us to detect the need for a
material flow are used to determine the optimal location of each re-layout [4, 5] are congestion and bad utilization of space,
machine. SLP technique has been employed to design the two excessive stock in process at the facility, long distances and
alternative production shop floor layouts and compare the interrupt flow path in the work flow process, simultaneous
performance between new layout and present layout in terms of bottle necks and workstations with idle time, qualified workers
material flow distance, traveling time, and traveling cost. The carrying out too many simple operations, labor anxiety and
existing production process was inefficient, showing bottlenecks.
discomfort; accidents at the facility, difficulty for controlling
The alternative layouts were developed based on minimum
operations and personnel.
distance traveled between each pair of machine. It improved the
company existing layout by reduced total movement traveled in
production for material handling. The measurements covered the II. METHODOLOGY
actual sizes of the layout and machines, activities between The company has some problems during the production of
machines, distance between machines, and material flow between
Cans. The production department of Cans has one main
machines in the company. The proposed procedure is illustrated
to be a viable approach for solving production shop floor layout
building. The main problems of the production process of Cans
design problem through a real-world case study. From the are long travel, products cross pass between machines and back
proposed two alternative layouts which are more economical, tracking of semi-finished components being manufacturing
distance of the production flow can be shortened from 389.7m to process. The labor cost of the product is also high due to high
311.2m or 360.6m. The traveling time can be reduced from traveling. In response to the these problems, the need for
901sec. to 750sec. and traveling cost can be reduced from 3.17 facilities layout optimization on new layout proposals to
Birr to 2.98 or 2.19 Birr per each travel resulting increase in evaluate the performance measures related to the
productivity. manufacturing goals of the company is needed. This paper
Keywords—systematic layout planning; production floor; proposes to use SLP as the infra-structure for production shop
material handling; Can manufacturing. floor layout optimization. Department performances
improvements are in terms of reduction in traveling distance
I. INTRODUCTION and reduction in traveling cost, reduction in traveling time,
eliminating back tracking and interrupt flow path.
The efficacy of a manufacturing facility depends mainly on
the layout of machinery and departments. Typical plant layout
A. Can Production Shop Floor Layout
procedures determine how to arrange the various machines and
departments to achieve minimization of overall manufacturing Company produces Crown Corks and Cans and exclusively
time, maximization of turnover of work-in-process, and supplying these products for about twenty beverages, soft
maximization of company output. The capability to reconfigure drink, soda, paint and pharmaceutical product factories. The
an existing manufacturing system is a key factor to maintain Crown Cork and Can production is operates in a one building;
competitiveness in manufacturing business environment. It was the total build up area for the building is 42m × 96m=4032 sq.
estimated that over $250 billion is spent annually in the United meters. From this shop area the half length of width has to the
States on facilities planning and re-planning. Further, between stores (21m × 48m=1008 sq. meters) (Fig. 1). The other
20%-50% of the total costs within manufacturing are related to remains 21m of the width are used for the Crown Cork and Can
material handling and effective facility planning can reduce production process. The Cans (Ø90mm, Ø115mm, Ø 176mm)
these costs 10-30% [1]. Taha et al. (2008) [2] suggested that in production is operates in 7m width and the machineries are
order to be successful in today’s competitive manufacturing installed in to two rows along the length, within 7m of width.
environment, managers have to look for new approaches to Operators for certain components have to walk to-and-fro
within those machineries during production and assembly. The be processed (For this study, the product is an Ø90mm Can),
existing production shop floor layout is shown in Fig. 1 quantity (Q) is the volume of each sub component of the
(workstations/machine names and codes are shown in Table product to be processed, routing (R) is the path a product
IV). Note: All dimensions are in meters and the drawing is travels to be processed, the routing in this case study is
made by Auto CAD (Version 2007) and is not to scale. obtained by making the flow chart for each main component of
the Ø90mm Cans, and time (T) refers to the overall time
required to complete processing. During production process the
observed time (OT) of Can component(s) is determined by
taking the mean of 20 observations for each process. The rating
used for this time study is 85% (0.85) and allowance taken are
personal needs-5%, unavoidable delay-1%, basic fatigue-4%,
noise level (intermittent-loud)-2% [4]. Normal time=Total
observed time × Average rating=25.81 × 0.85 =21.94sec.
Standard time=Normal time+(Normal
time × Allowance)=21.94+(21.94 × 0.12)=24.57sec.
Step 2: Flow of materials for Ø90 mm Can
Process begins with incoming raw material at store. For
production of Ø90mm Cans, operations are performed at the
main production shop floor for their components i.e. bottom,
body, ring, and lid (these components have to travel 92.4m,
119.5m, 87.4m and 90.4m respectively) (Table I). The cross-
over for those subcomponents expressed in terms of cross-over
between machines. As the installed machines are not in a
proper way as per production process of these components,
leads to high traveling distance for the flow path and
interruption of flow path (Fig. 1). In general, the product flow
for components is unsystematic with required resources not
being located close to each other.
TABLE I. PRESENT FLOW PROCESS CHART ANALYSIS. TABLE III. ACTIVITY RELATIONSHIP WORKSHEET.
Details of Present Method Operation Distance Observed Work Centers/Machines:
(Flow process) (S-Store, T-Transport, (meters) Time A E I O U X
O-Operation, D-Delay) (seconds) 1. Store:
2,5 15 3,4,6,9 7,8,10,11,12,16,17 13,14
Bottom for Ø90mm Can:
2. Slitter:
1. Store S
1,3,4,6,9 7,13,14 5,8,10,11,12,16,17 15
2. To slitter machine T 23.7
3. Bottom press:
3. Slitting O 0.23
2,5 11 6,7,8,9,10, 12,13, 14,17 15,16
4. To bottom pressing machine T 14.0
4. Ring press:
5. Bottom pressing O 1.65
2,12 17 13,14 5,6,7,8,9,10,11 15,16
6. To sealing machine T 54.7
5. Plastic liner:
7. Sealing with body O
3,11 17 6,7,8,9,10, 12,13,14 15,16
Sub Total 92.4 1.88
6. Rolling:
Body for Ø90mm Can:
2,7 8 17 9,10,16,11,12 13,14,15
1. Store S
7. Welding:
2. To slitter machine T 23.7
6,8 17 9,10,11, 12,16 13,14,15
3. Slitting O 0.74
8. Flanging:
4. To rolling machine T 50.2
7,11 12 17 13,14,15,16 9,10
5. Rolling O 0.96
9. Lid press:
6. To seam welding T 2.2
2,10 17 11,12 13,14,15,16
7. Welding O 3.07
10. Lid curling:
8. To flanging machine T 42.6
9 17 11,12,13,14,15,16
9. Flanging O 3.36
11. Bottom sealing:
10. To bottom and ring sealing machine T 0.8
5 12 17 16 13,14,15
11. Bottom and ring sealing O 7.45
12. Ring sealing:
Sub Total 119.5 15.60
4 17 16 13,14,15
Ring for Ø90mm Can:
13. Ear press:
1. Store S
16 17 14,15
2. To slitter machine T 23.7
14. Washer press:
3. Slitting O 0.34
16 17 15
4. To ring press machine T 34.1
15. Wire bender:
5. Ring pressing O 1.94
16 17
6. To sealing machine T 29.6
16. Bail sub assemble:
7. Sealing with body O
17
Sub Total 87.4 2.28
17. Final assemble:
Lid for Ø90mm Can:
16 12
1. Store S
2. To slitter machine T 23.7
3. Slitting O 0.22
2) Dimensionless block diagram: The dimensionless block
4. To lid press T 19.6
5. Lid pressing O 2.63 diagram is the first layout attempt (Fig. 3). Even though this
6. To lid curling machine T 47.1 layout is dimensionless, it is the plan for the master layout and
7. Lid curling O 3.98 plot plan. Once size is determined, space will be allocated to
Sub Total 90.4 6.83 each activity as per the dimensionless blocks diagram layout.
If we obey the activity codes, a good layout will results.
TABLE II. DISTANCES (METERS) BETWEEN WORK CENTERS/MACHINES.
Sometimes it is harder laying out the dimensionless block
diagram than when exact sizes are available because large
work centers/machines/departments to have more important
relationships than small machines/departments and can have
many more activities close by them [7].
Step 4: Relationship diagram (String diagram) M8 Ear press 1.3 × 1.2 1.56
M9 Ø115mm ring press (no work) 1.5 × 1.2 1.8
This step positions workstations/machineries spatially. For
those machineries that have strong interactions and/or M10 Ear and wire assemble 0.8 × 0.7 0.56
closeness relationships are placed in proximity. The M11 Wire bending machine 0.8 × 1.4 1.12
relation/string diagram shows near optimal placement without M12 Washer press 1.5 × 1 1.5
consideration for space requirements and exposes possible
M13 Ø115mm cover press (no work) 1.5 × 1 1.5
clustering of machineries (Fig. 4). Through the analysis of the
activity relationship diagram, a better understanding of the M14 Ø115mm ring press 1.5 × 1 1.5
processing functions for all the components has been achieved. M15 Ø176mm ring press (for final shape) 1.5 × 1 1.5
This can be applied to the layout of the physical building in a M16 Ø176mm ring press (only blank shape) 2.3 × 2 4.6
space relationship diagram. M17 Ø176mm cover press (no work) 1.5 × 1 1.5
M18 Rolling 0.4 × 1 0.4
M19 Resistance (seam) welding 1.5 × 4 6
M20 Resistance (seam) welding 1.5 × 4 6
M21 Ø176mm body flanging machine 1.3 × 1.5 1.95
M22 Ø176mm bottom sealing 1.3 × 1 1.3
M23 Ø176mm ring sealing 1.3 × 1 1.3
M24 Spot welding 1.3 × 1.4 1.82
M25 Ø90mm body flanging machine 0.8 × 1.2 0.96
M26 Ø90mm bottom and ring sealing 0.7 × 1 0.7
M27 Ø115mm body flanging machine 2.5 × 7 17.5
M28 Ø115mm bottom sealing 0.6 × 1 0.6
M29 Ø115mm ring sealing 0.6 × 1 0.6
M30 Ø115mm cover press 0.8 × 1.8 1.44
M31 Ø176mm cover press 2.1 × 2.1 4.41
Figure 4. Relationship diagram for work centers/machines.
M32 Ø90mm cover curling machine 0.7 × 0.7 0.49
M33 Ø115mm cover curling machine 0.7 × 0.7 0.49
Step 5: Space requirement
M34 Ø176mm cover curling machine 1.2 × 0.7 0.84
The overall space requirement for the production of Cans in Total 84.06
the production shop floor is determined by taking measurement
150% 126.09
of the foot print of the machine along with the number of
stations and allowances required. From each workstation layout Step 6: Space available
we measured the length and the width to determine the square
footage of each station as: Machine space (Max.) = Length × Based on the space determined under the space
Width+(maintenance+maximum travel+plant service+ operator determination, the space occupied by the production shop is
+material) and Machine space (Min.)=Length × Width. enough for the production of Cans. The space available for the
Multiplying the total sq. meters by 150% allows extra space for production of Cans occupies 420 sq. meters area (7m width
the aisle, work-in-progress (Table IV). The extra 50% space with 60m length), in this floor width machineries were
added to the equipment space requirement will be mostly used arranged by two rows with its length of the floor (Fig. 1). There
for aisles [8]. Based on the space determination the operators are two options for the rearranging of machineries.
can be seated during work comfortably without knocking the
persons behind. The first option is to widened (increase) the width of Cans
production shop floor; reducing the width from raw materials
store (1008 sq. meters), and rearrange machineries by three
TABLE IV. SPACE DETERMINATIONS. rows with their process sequences. The store area will become
Code Workstations/Machines Length × Total sq. rather wide in contrast to be stored raw material, therefore
Width (m) meters reduce 4m width space along the length from store to Cans
production shop floor spaces (Fig. 5).
M1 Slitter machine 1.2 × 2 2.4
M2 Slitter machine 1.2 × 2 2.4 The second option is that enough space is available but the
M3 Ø115mm bottom press machine 1 × 1.8 1.8 width of the Cans production shop floor was narrow,
M4 Ø176mm bottom press machine 1× 2 2 machineries can be arranged only by two rows (Fig. 6). And
M5 Ø90mm cover press 1.2 × 0.8 0.96 additionally we have to remove some unused/dead machines
(M6-plastic liner, M9-Ø115mm ring press, M13-Ø115mm lid
M6 Plastic liner (no work) 1.2 × 0.8 0.96
press, M17-Ø176mm lid press machine) from existing
M7 Plastic liner 2 × 4.8 9.6 production shop floor for both the options.
Step 9: Practical limitations Figure 5. Space relationship diagram and proposed layout alternative design
I (with widened the space of production shop floor).
In the study, the existing facilities were established and
there was limited ability to expand the area for extra space. (ii) Alternative Design II
Other than, some negotiations are needed to rebuild the main
building from one side to have best floor layout for the The second layout alternative design is without increasing
facilities. the width of Cans production shop floor. To minimize the sub-
components traveling distance for the second alternative
Step 10: Develop layout alternatives design, rearrange the machineries in to two rows according to
their process flow sequences, and proposed space for the aisle,
It is also common to find an entire plant arrangement maintenance of the machines, space for the operators etc. also
according to general material flow (fabrication, subassembly, combined (Fig. 6).
and final assembly). Because of the narrow width space of
existing Cans production shop floor layout, machineries were
arranged only by two rows along the length of the floor. A
single part is translated from machine to machine being
production; which results to long distance travels, flow are
across between another machines (interrupt flow path) and
back tracking’s also occurs. And some unused machines lead to
long distance travels and interruption of flow paths and remove
some unused/dead machines from existing Cans production
shop floor. To minimize these problems two layout alternative
designs are proposed.
These results demonstrate the feasibility of the proposed • Wasting time and resource in transporting high volume of
method. materials through long distances, the planned production
volume as well as profit could not be attained in the company.
Designing a better layout for production shop floor is thus
reasonable and mandatory.
• After the current layout has been analyzed, two different
improved new alternative layouts (layout alternative designs I
and II) have been developed/proposed by using SLP.
• The alternative design I layout is proposed with widened the
width of Cans production shop floor (Fig. 7) and the layout
alternative design II layout is proposed without widened the
width of Cans production shop floor (Fig. 8) and remove some
unused machines, then machines are rearranged in to two rows
according to the specific sequence of operations required.
• The two layout alternative designs would have saving in the
distance to be traveled by the components within work centers
(Table V). This reduced distance will reduce the time needed
to process each component thereby decreasing the operation
cost. The traveling between the machines is also minimized,
minimizing the time, eliminating the interrupting flow paths
and backtrackings. Thus, the proposed layout alternative
design I is better and would bring sustainable improvement.
• The traveling cost for the production of Cans is reduced by
using SPL. There is reduction in travel time per travel (Table
VI) and reduction in travel cost per travel (Table VII) for the
developed layout (designs I and II) and this show significant
improvement in terms of the performance measures and the
design is safe.
Figure 7. Layout alternative design I (flow of materials). • Finally, rearranging production floor layout decreased
distance and time consumption in flow of material, resulting in
an increase in productivity.
• The findings are useful in serving as a good example for
small medium enterprises, which do not normally apply
scientific approaches to enhance their production.
REFERENCES
[1] J. Balakrishnan and C.H. Cheng, “Multi-period planning and uncertainty
issues in cellular manufacturing: A review and future directions,”
European Journal of Operational Research, Ed.177, 2007, pp. 281–309.
[2] Z. Taha and F. Tahriri, “A classification of different type of facility
layout design,” in Proceeding of Asia pacific conference on management
of technology and technology entrepreneurship, 2008, pp. 1-5.
[3] Y. Zhu, and F. Wang, “Study on the general plane of log yards based on
systematic layout planning,” IEEE Computer Society, vol. 4, pp. 92-95,
2009.
[4] M. Yilma, “Improvement of production floor layout using systematic
layout planning: A case study on Ethiopian crown cork and can
manufacturing industry,” Mechanical and Vehicle Engineering
Department, Adama Science and Technology University, Adama,
Ethiopia, 2012, Unpublished M.Sc. Thesis.
[5] J.A. Tompkins, J.A. White, Y.A. Bozer, E.H. Frazelle, J.M.A. Tanchoco
and J. Trevino, “Facilities Planning,” 4th ed., John Wiley and Sons, Inc.:
New York, NY, 2010.
[6] R. Muther, “Systematic Layout Planning”, Mc-Graw Hill, New
York, 1976.
[7] F.E. Meyers, “Plant Layout and Material Handling,” Englewood Cliffs,
NJ: Prentice Hall Regents, 1993.
[8] D.R. Sule, “Manufacturing Facilities Location, Planning, and
Design,” 2nd ed., PWS Publishing Company, 1994.