Monitoring Pekerjaan Jembatan 1 (15 Okt)
Monitoring Pekerjaan Jembatan 1 (15 Okt)
- Catatan :
= Sudah di cor
= Belum di cor
- P4N04 over beton 13 m3
MONITORING PEKERJAAN PILE CAP, PIER LEG, PILE HEAD & PIER HEAD JEMBATAN 1 TOL IKN PAKET 3A 1
STATUS KIRI (A) 3
A1 - A2
15 Oktober 2023 KANAN (B) 1
A1 PH2 EJ PH2 EJ P1 P2 P3
UTARA / KIRI (A)
ABT A1A
PH P1A
PH P2A
PH P3A
PH2A
PH1A
PH1A
PH1A
PH2A
DENAH
A1 PH2 EJ PH2 EJ P1 P2 P3
SELATAN / KANAN (B)
ABT A1B
PH P1B
PH P2B
PH P3B
PH2B
PH1B
PH1B
PH1B
PH2B
DENAH
P4 A2
UTARA / KIRI (A)
ABT A2A
PH P4A
DENAH
P4 A2
SELATAN / KANAN (B)
ABT A2B
PH P4B
DENAH