Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

MONITORING PEKERJAAN BORED PILE JEMBATAN 1 TOL IKN PAKET 3A

SISI A (KIRI) DAN SISI B (KANAN) (ɸ 1000 mm DAN ɸ 800 mm)

SISI A KIRI (UTARA) SISI B KANAN (SELATAN)


No TANGGAL TANGGAL No.TITIK TANGGAL TANGGAL No.TITIK KETERANGAN
KODE KODE
BORED COR BORED BORED COR BORED
ABUTMEN Progress titik bored pile (ɸ 1000 mm) sudah di Cor
1 03/06/23 04/06/23 A1N01 1 29/07/23 29/07/23 A1S03 3 S/D Tgl 30/09/23
2 04/06/23 04/06/23 A1N03 3 29/07/23 29/07/23 A1S01 1 Titik Bored Sisi A = 22/22
3 06/06/23 06/06/23 A1N05 5 30/07/23 30/07/23 A1S05 5 Titik Bored Sisi B = 22/22
4 06/06/23 06/06/23 A1N02 2 30/07/23 30/07/23 A1S02 2 Total = 44/44
5 06/06/23 06/06/23 A1N04 4 31/07/23 31/07/23 A1S04 4 Progress titik bored pile (ɸ 1000 mm) belum di Cor
6 07/06/23 08/06/23 A1N10 10 31/07/23 31/07/23 A1S08 8 S/D Tgl 30/09/23
7 07/06/23 08/06/23 A1N08 8 01/08/23 01/08/23 A1S06 6 Titik Bored Sisi A = 0
8 08/06/23 08/06/23 A1N06 6 01/08/23 01/08/23 A1S09 9 Titik Bored Sisi B = 0
9 09/06/23 11/06/23 A1N07 7 02/08/23 02/08/23 A1S07 7 Total = 0
10 09/06/23 11/06/23 A1N09 9 06/08/23 06/08/23 A1S10 10 ABUTMEN A1 ABUTMEN A2
11 20/08/23 20/08/23 A2N07 7 22/08/23 22/08/23 A2S10 10 SISI A KIRI (UTARA) SISI A KIRI (UTARA)
12 20/08/23 20/08/23 A2N09 9 22/08/23 22/08/23 A2S12 12
13 20/08/23 20/08/23 A2N12 12 24/08/23 24/08/23 A2S11 11
14 21/08/23 21/08/23 A2N08 8 25/08/23 25/08/23 A2S09 9 A1N05 A1N10 A2N06 A2N12
15 21/08/23 21/08/23 A2N06 6 26/08/23 26/08/23 A2S07 7
16 21/08/23 21/08/23 A2N10 10 27/08/23 27/08/23 A2S02 2 A1N04 A1N09 A2N05 A2N11
17 22/08/23 22/08/23 A2N11 11 28/08/23 28/08/23 A2S06 6
A1N03 A1N08 A2N04 A2N10
18 22/08/23 22/08/23 A2N01 1 28/08/23 28/08/23 A2S03 3
19 22/08/23 22/08/23 A2N03 3 28/08/23 28/08/23 A2S04 4 A1N02 A1N07 A2N03 A2N09
20 24/08/23 24/08/23 A2N02 2 29/08/23 30/08/23 A2S01 1
21 24/08/23 24/08/23 A2N04 4 29/08/23 30/08/23 A2S05 5 A1N01 A1N06 A2N02 A2N08
22 31/08/23 31/08/23 A2N05 5 31/08/23 31/08/23 A2S08 8
SISI B KANAN (SELATAN)
A2N01 A2N07
SISI B KANAN (SELATAN)
A1S05 A1S10

A1S04 A1S09 A2S06 A2S12

A1S03 A1S08 A2S05 A2S11

A1S02 A1S07 A2S04 A2S10

A1S01 A1S06 A2S03 A2S09

- Catatan : A2S02 A2S08


= Sudah di cor
= Belum di cor A2S01 A2S07
MONITORING PEKERJAAN BORED PILE JEMBATAN 1 TOL IKN PAKET 3A
SISI A (KIRI) DAN SISI B (KANAN) (ɸ 1000 mm DAN ɸ 800 mm)

SISI A KIRI (UTARA) SISI B KANAN (SELATAN)


No TANGGAL TANGGAL No.TITIK TANGGAL TANGGAL No.TITIK KETERANGAN
KODE KODE
BORED COR BORED BORED COR BORED
SLAB ON PILE Progress titik bored pile (ɸ 800 mm) sudah di Cor
1 14/06/23 18/06/23 PH1AN12 12 17/06/23 30/07/23 PH2BS18 18 S/D Tgl 30/09/23
2 14/06/23 17/06/23 PH1AN16 16 29/07/23 29/07/23 PH2BS17 17 Titik Bored Sisi A = 20/20
3 14/06/23 16/06/23 PH2AN20 20 29/07/23 30/07/23 PH2BS20 20 Titik Bored Sisi B = 20/20
4 18/06/23 18/06/23 PH1AN08 8 31/07/23 31/07/23 PH1BS15 15 Total = 40/40
5 21/06/23 21/06/23 PH2AN04 4 02/08/23 02/08/23 PH1BS13 13 Progress titik bored pile (ɸ 800 mm) belum di Cor
6 22/06/23 22/06/23 PH2AN19 19 02/08/23 02/08/23 PH1BS12 12 S/D Tgl 30/09/23
7 23/06/23 23/06/23 PH2AN01 1 02/08/23 02/08/23 PH2BS19 19 Titik Bored Sisi A = 0
8 23/06/23 23/06/23 PH1AN11 11 06/08/23 06/08/23 PH2BS01 1 Titik Bored Sisi B = 0
9 24/06/23 24/06/23 PH2AN18 18 06/08/23 06/08/23 PH1BS16 16 Total = 0
10 24/06/23 25/06/23 PH1AN05 5 06/08/23 06/08/23 PH1BS07 7 PILE SLAB SISI A KIRI (UTARA)
11 04/07/23 04/07/23 PH1AN15 15 07/08/23 07/08/23 PH1BS05 5 PH2A PH1A PH1A PH1A PH2A
12 04/07/23 04/07/23 PH1AN07 7 07/08/23 07/08/23 PH1BS14 14
13 06/07/23 06/07/23 PH1AN06 6 07/08/23 07/08/23 PH1BS08 8 N04 N08 N12 N16 N20
14 08/07/23 08/07/23 PH1AN14 14 08/08/23 08/08/23 PH1BS09 9
15 09/07/23 09/07/23 PH1AN09 9 08/08/23 09/08/23 PH2BS02 2
N03 N07 N11 N15 N19
16 11/07/23 11/07/23 PH2AN17 17 08/08/23 09/08/23 PH2BS04 4
17 13/07/23 14/07/23 PH1AN13 13 09/08/23 09/08/23 PH1BS06 6
18 14/07/23 14/07/23 PH1AN10 10 10/08/23 10/08/23 PH1BS11 11 N02 N06 N10 N14 N18
19 17/07/23 17/07/23 PH2AN02 2 11/08/23 11/08/23 PH1BS10 10
20 20/07/23 20/07/23 PH2AN03 3 13/08/23 13/08/23 PH2BS03 3 N01 N05 N09 N13 N17
PILE SLAB SISI B KANAN (SELATAN)
PH2B PH1B PH1B PH1B PH2B

S04 S08 S12 S16 S20

S03 S07 S11 S15 S19

S02 S06 S10 S14 S18

S01 S05 S09 S13 S17


- Catatan :
= Sudah di cor
= Belum di cor
- Titik PH1BS09 kurang beton 6m
MONITORING PEKERJAAN BORED PILE JEMBATAN 1 TOL IKN PAKET 3A
SISI A (KIRI) DAN SISI B (KANAN) (ɸ 1000 mm DAN ɸ 800 mm)

SISI A KIRI (UTARA) SISI B KANAN (SELATAN)


No TANGGAL TANGGAL No.TITIK TANGGAL TANGGAL No.TITIK KETERANGAN
KODE KODE
BORED COR BORED BORED COR BORED
PIER
1 13/06/23 13/06/23 P1N06 6 21/05/23 22/05/23 P2S04 4 Progress titik bored pile (ɸ 1000 mm) sudah di Cor
2 13/06/23 13/06/23 P1N01 1 23/05/23 23/05/23 P2S09 9 S/D Tgl 15/10/23
3 13/06/23 16/06/23 P1N18 18 24/05/23 24/05/23 P2S01 1 Titik Bored Sisi A = 57/72
4 14/06/23 15/06/23 P1N03 3 24/05/23 25/05/23 P2S06 6 Titik Bored Sisi B = 63/72
5 19/06/23 19/06/23 P1N02 2 25/05/23 25/05/23 P2S13 13 Total = 120/144
6 19/06/23 19/06/23 P1N04 4 25/05/23 26/05/23 P2S18 18 Progress titik bored pile (ɸ 1000 mm) belum di Cor
7 21/06/23 21/06/23 P1N11 11 26/05/23 26/05/23 P2S03 3 S/D Tgl 15/10/23
8 22/06/23 22/06/23 P1N13 13 27/05/23 27/05/23 P2S02 2 Titik Bored Sisi A = 0
9 23/06/23 23/06/23 P1N12 12 28/05/23 28/05/23 P2S05 5 Titik Bored Sisi B = 0
10 26/06/23 26/06/23 P1N17 17 28/05/23 28/05/23 P2S07 7 Total = 0
11 27/06/23 27/06/23 P1N05 5 29/05/23 29/05/23 P2S08 8
PIER P1 PIER P2
12 27/06/23 27/06/23 P1N14 14 29/05/23 29/05/23 P2S11 11
SISI A KIRI (UTARA) SISI A KIRI (UTARA)
13 04/07/23 04/07/23 P1N10 10 30/05/23 30/05/23 P2S12 12
14 05/07/23 05/07/23 P1N07 7 30/05/23 30/05/23 P2S15 15
15 09/07/23 09/07/23 P1N16 16 01/06/23 02/06/23 P2S14 14
P1N06 P1N12 P1N18 P2N06 P2N12 P2N18
16 17/07/23 17/07/23 P1N08 8 02/06/23 03/06/23 P2S17 17
17 19/07/23 19/07/23 P1N15 15 06/06/23 06/06/23 P2S16 16 P1N05 P1N11 P1N17 P2N05 P2N11 P2N17
18 25/07/23 25/07/23 P1N09 9 08/06/23 10/06/23 P2S10 10
19 20/08/23 20/08/23 P4N18 18 14/06/23 16/06/23 P1S03 3 P1N04 P1N10 P1N16 P2N04 P2N10 P2N16
20 20/08/23 20/08/23 P4N15 15 16/06/23 18/06/23 P1S18 18
21 21/08/23 21/08/23 P4N06 6 21/06/23 21/06/23 P1S02 2 P1N03 P1N09 P1N15 P2N03 P2N09 P2N15
22 22/08/23 22/08/23 P4N13 13 21/06/23 21/06/23 P1S06 6
23 22/08/23 22/08/23 P4N17 17 23/06/23 23/06/23 P1S15 15 P1N02 P1N08 P1N14 P2N02 P2N08 P2N14
24 24/08/23 24/08/23 P4N12 12 24/06/23 24/06/23 P1S13 13
25 24/08/23 25/08/23 P4N16 16 27/06/23 27/06/23 P1S01 1 P1N01 P1N07 P1N13 P2N01 P2N07 P2N13
26 24/08/23 25/08/23 P4N01 1 28/06/23 28/06/23 P1S04 4 PIER P1 PIER P2
27 26/08/23 26/08/23 P4N14 14 01/07/23 01/07/23 P1S07 7 SISI B KANAN (SELATAN) SISI B KANAN (SELATAN)
28 28/08/23 28/08/23 P4N05 5 01/07/23 01/07/23 P1S16 16
29 29/08/23 29/08/23 P4N08 8 08/07/23 08/07/23 P1S10 10 P1S06 P1S12 P1S18 P2S06 P2S12 P2S18
30 02/09/23 04/09/23 P3N17 17 09/07/23 09/07/23 P1S08 8
31 04/09/23 04/09/23 P3N06 6 18/07/23 19/07/23 P1S14 14 P1S05 P1S11 P1S17 P2S05 P2S11 P2S17
32 06/09/23 06/09/23 P4N11 11 20/07/23 22/07/23 P1S09 9
33 06/09/23 07/09/23 P4N07 7 23/07/23 23/07/23 P1S05 5 P1S04 P1S10 P1S16 P2S04 P2S10 P2S16
34 06/09/23 07/09/23 P3N10 10 25/07/23 25/07/23 P1S17 17
35 07/09/23 07/09/23 P3N18 18 26/07/23 26/07/23 P1S11 11 P1S03 P1S09 P1S15 P2S03 P2S09 P2S15
36 08/09/23 08/09/23 P3N05 5 27/07/23 27/07/23 P1S12 12
37 09/09/23 09/09/23 P3N12 12 21/08/23 21/08/23 P4S18 18 P1S02 P1S08 P1S14 P2S02 P2S08 P2S14
38 09/09/23 09/09/23 P3N16 16 24/08/23 24/08/23 P4S16 16
P1S01 P1S07 P1S13 P2S01 P2S07 P2S13
39 11/09/23 11/09/23 P3N09 9 24/08/23 25/08/23 P4S05 5
40 11/09/23 13/09/23 P3N15 15 26/08/23 27/08/23 P4S17 17 PIER P3 PIER P4
41 13/09/23 13/09/23 P4N10 10 03/09/23 03/09/23 P4S04 4 SISI A KIRI (UTARA) SISI A KIRI (UTARA)
42 14/09/23 14/09/23 P4N02 2 14/09/23 14/09/23 P4S11 11
43 15/09/23 15/09/23 P4N03 3 15/09/23 15/09/23 P4S12 12
P3N06 P3N12 P3N18 P4N06 P4N12 P4N18
44 18/09/23 18/09/23 P4N04 4 18/09/23 19/09/23 P4S10 10
45 19/09/23 20/09/23 P4N09 9 20/09/23 20/09/23 P4S15 15 P3N05 P3N11 P3N17 P4N05 P4N11 P4N17
46 22/09/23 22/09/23 P3N04 4 22/09/23 22/09/23 P3S03 3
47 23/09/23 24/09/23 P3N14 14 23/09/23 24/09/23 P3S13 13 P3N04 P3N10 P3N16 P4N04 P4N10 P4N16
48 26/09/23 26/09/23 P3N03 3 23/09/23 24/09/23 P3S09 9
49 27/09/23 27/09/23 P3N08 8 25/09/23 25/09/23 P3S01 1 P3N03 P3N09 P3N15 P4N03 P4N09 P4N15
50 29/09/23 29/09/23 P2N13 13 26/09/23 26/09/23 P3S14 14
51 02/10/23 02/10/23 P2N14 14 27/09/23 27/09/23 P3S02 2 P3N02 P3N08 P3N14 P4N02 P4N08 P4N14
52 02/10/23 02/10/23 P2N01 1 29/09/23 29/09/23 P3S16 16
P3N01 P3N07 P3N13 P4N01 P4N07 P4N13
53 02/10/23 03/10/23 P2N04 4 30/09/23 30/09/23 P3S07 7
54 04/10/23 04/10/23 P2N07 7 30/09/23 30/09/23 P3S04 4 PIER P3 PIER P4
55 05/10/23 05/10/23 P2N15 15 02/10/23 02/10/23 P3S08 8 SISI B KANAN (SELATAN) SISI B KANAN (SELATAN)
56 14/10/23 14/10/23 P3N01 1 02/10/23 05/10/23 P3S15 15
57 15/10/23 15/10/23 P3N13 13 04/10/23 04/10/23 P3S05 5 P3S06 P3S12 P3S18 P4S06 P4S12 P4S18
58 05/10/23 06/10/23 P3S10 10
59 06/10/23 07/10/23 P3S06 6 P3S05 P3S11 P3S17 P4S05 P4S11 P4S17
60 07/10/23 08/10/23 P3S11 11
61 09/10/23 09/10/23 P3S12 12 P3S04 P3S10 P3S16 P4S04 P4S10 P4S16
62 13/10/23 13/10/23 P3S17 17 P3S03 P3S09 P3S15 P4S03 P4S09 P4S15
63 14/10/23 14/10/23 P3S18 18
15/10/23 15/10/23 P4S14 14 P3S02 P3S08 P3S14 P4S02 P4S08 P4S14

P3S01 P3S07 P3S13 P4S01 P4S07 P4S13

- Catatan :
= Sudah di cor
= Belum di cor
- P4N04 over beton 13 m3
MONITORING PEKERJAAN PILE CAP, PIER LEG, PILE HEAD & PIER HEAD JEMBATAN 1 TOL IKN PAKET 3A 1
STATUS KIRI (A) 3
A1 - A2
15 Oktober 2023 KANAN (B) 1

A1 PH2 EJ PH2 EJ P1 P2 P3
UTARA / KIRI (A)

ABT A1A

PH P1A

PH P2A

PH P3A
PH2A

PH1A

PH1A

PH1A

PH2A
DENAH
A1 PH2 EJ PH2 EJ P1 P2 P3
SELATAN / KANAN (B)

ABT A1B

PH P1B

PH P2B

PH P3B
PH2B

PH1B

PH1B

PH1B

PH2B

DENAH
P4 A2
UTARA / KIRI (A)

ABT A2A
PH P4A

DENAH
P4 A2
SELATAN / KANAN (B)

ABT A2B
PH P4B

DENAH

You might also like