Electric Service Application
Electric Service Application
&
Engr. Ronald V. Dollentas
Superintendent & Team Leader
SME Business Technical Support, MERALCO
Outline
I. Background
II. Service Availability
III. Service Application
Background
MERALCO’s Distribution System
Major Statistics
Franchise Area: 9,337 sq. km.
No. of Customers: 4.982 M
Demand and energy purchases
• 5,283 MW peak demand
• 24, 683 GWh
Energy Sales: 22, 725 GWh
System Loss: 7.43%
SERVICE
DROP
Meter
NEAREST
EXISTING
FACILITY
A brief description of
EXTENSION OF LINES & FACILITIES
EXTENSION OF
DISTRIBUTION FACILITIES
TRANSFORMERS
SERVICE
DROP
APPLYING
CUSTOMER Meter
ADDITIONAL EXISTING
FACILITY FACILITY
CUSTOMER MERALCO
Receipt of • Submits initial requirements •Receives and reviews
Application the application
Energize Energize
Service Service
SERVICE APPLICATION PROJECT-COVERED
PROCESS FLOW APPLICATION
CUSTOMER MERALCO
Receipt of • Submits initial requirements •Receives and reviews
Application the application
b. Electrical Plans
• Electrical Plans duly signed and sealed by a
professional electrical engineer
• Type of service
• Voltage requirement
• Biggest Motor Rating
Submission of Requirements
c. Business Document
For partnership
• SEC Registration with Articles of Partnership
• Transfer Certificate Title (TCT) or Deed of Sale if applicant owns the property
(photocopy)
• Bill Deposit
• If applicable, installation
and removal cost
• If applicable, Contribution
In Aid of Construction
(CIAC) or Cash Advance
Agreement for the Sale of Electric
Energy
CC x 0.7
Application Process
1. Submission of requirements.
2. Signing of Notice to Proceed
and Gantt Chart.
3. Completion of Service Entrance
and Technical Requirements
4. Acceptance of Letter
Agreement and Contract for
Electric Service.
5. Payment of the
applicable charges and
submission of CFEI
6. Energization of your service.
Submission of CFEI
Thank you.
www.meralco.com.ph
1. Service Entrance
Definition
Service entrance is defined as that portion
of the customer’s wiring including all
necessary conduits, cable, and
accessories which extends from the
customer’s service switch to the service
drop on the outside of the building.
2. Transformer Vault Room
Definition
Transformer Vault Room is a concrete
enclosure designed and constructed to be
fire-resistant and with adequate structural
strength, exclusively built to house
unattended Meralco-owned transformers
and accessories.
3.Indoor/Outdoor Substation
A. Definition
An indoor substation is defined as a
customer-owned integrated unit--
comprising the power transformer(s),
primary switch with power fuses or circuit
breaker, and the secondary switchgear --
installed indoor and connected to
Meralco’s electrical distribution system
through underground high voltage cables.