Professional Documents
Culture Documents
Underground Distribution System
Underground Distribution System
Distribution
System
Outline
Introduction
Network Architecture
Padmounted Transformer
Padmounted Switchgear
Cables
Terminations and Splices
Direct Burial vs Duct System
Cable Ampacity Rating Factors
Calculation of Pulling Tension
Code Requirements
UG Accessories
Introduction
WHY GO FOR UG DISTRIBUTION?
1. Congestion of Overhead Facilities
2. Aesthetics
Aesthetics
3. Safety
4. Reliability
OTHER REASONS FOR ADOPTING
UG DISTRIBUTION?
Ö ROW constraints
Ö Government regulations
Ö Customer requirement
DISADVANTAGES OF UG SYSTEM
vs.
Underground
Distribution System
Overhead Residential Customers
Network Architecture (OH)
Substation1 Substation2
Distribution Distribution
Transformers Transformers
CONCRETE
SECONDARY
PEDESTAL
CONCRETE
PEDESTAL
SERVICE
BOX
FINISH
GRADE LINE PADMOUNTED
TRANSFORMER SECONDARY
CONDUIT
PRIMARY
CONDUIT
MANHOLE
Typical URD Lay-out
T Y P IC A L U R D L A Y O U T
STREET A
STREET B
U R D T R A N S F O R M E R
S E R V IC E B O X
M A N H O L E
P R IM A R Y C A B L E
S E C O N D A R Y C A B L E
Network
Architecture
1. Primary Radial System
2. Alternate Feed System
3. Loop Feed System
4. Loop Feed with Radial Tap System
5. Loop-On-Loop System
Network Architecture (UG)
Open-Point
Overhead Line
Fuse
Substation
Padmount Padmount
Transformers Transformers
Fuse Open-Point
Substation
Switchgear1 Switchgear2
Padmount Padmount
Transformers Transformers
Flip-top Cover
Transformer tank & cabinet
Bushing with elbow
Parking stand bracket
Low voltage terminal
Bayonet Fuse
Pressure Vacuum Gage
T-Blade Loop-feed
Switch
Parking Stand
High Voltage
Bushing
High Voltage
Neutral Bushing
Three-Phase Padmounted Transformer
SECONDARY
COMPARTMENT
Nameplate
Current Transformer
Mounting Plate
Padmounted Transformer Construction
Bayonet Expulsion
Fuse
Tank
Transformer Winding
and Core
T-blade sectionalizing
switch
Typical Primary Connections on a Live
Front Pad-Mounted Transformer
Submersible Transformer
Padmounted Switchgear
Padmounted Switchgear
• Latest technology
• Low profile
• Low maintenance
• Fast service restoration
• For flooded areas and
high contaminant sites
Basic Switchgear Configuration
Single-Line Diagram
Padmounted Switchgear
Tap-Side
flip-top door
lifting provision
Source: Cooper Power Systems
Cables
Types of Underground Cable
Conductor
Semiconductive Conductor Shield
XLPE Insulation
Semiconductive Insulation Shield
PVC Jacket
• 5 kV
• 15 kV
• 25 kV
• 35 kV
Insulation Level Category
VOLTAGE RATING
CONDUCTOR SIZE 100% 133%
PHASE-TO-PHASE
(AWG-Kcmil) LEVEL (Mil) LEVEL (Mil)
VOLTS
2001-5000 8-1000 90 90
Since Dec 1987, REA now requires 220 mils for 15kV cable
and 345 mils for 25kV cable.
Electro-Chemical Treeing
URD Secondary Cables
Terminations
and
Splices
Cable Termination
Electric Field Flux-Lines on URD Cable
Terminators Used for URD Construction
Cable Splice
Types of Terminations and Splices
Ö Taped
Ö Pre-molded
Ö Cold-Shrink
Ö Heat-Shrink
Ö Slip-on
Direct Burial
vs
Conduit System
Direct Burial vs. Duct System
ADVANTAGES DISADVANTAGES
RESTORED PAVEMENT
0.3M (TYP.)
WARNING TAPE
0.9M (MIN.)
EARTH BACKFILL
CONCRETE SLAB
SAND BACKFILL
(0.075M – 0.15M COVER ALL-AROUND)
0.3M (TYP.)
WARNING TAPE
0.9M (MIN.)
EARTH BACKFILL
CONCRETE SLAB
SAND ENVELOPE
(0.075M – 0.15M COVER ALL AROUND)
DUCT
RESTORED PAVEMENT
0.3M (TYP.)
WARNING TAPE
0.76M (MIN.)
EARTH BACKFILL
CONCRETE ENVELOPE
(0.075M – 0.1M COVER ALL AROUND)
0.025M – 0.1M
PRIMARY CABLE
Manhole, Pulling Box,
and
Service Box
Manhole
PRIVATE
PROPERTY
LINE'
SIDEWALK
ROADWAY
0.3 M
2.72 M to 2.85 M
MANHOLE
DUCT RUN
W 0.6 M
3300
3250
3400
950
2300 1270 1150 950
2420 3400
LAYING DEPTH, m
LOW VOLTAGE HIGH VOLTAGE
L
THERMAL
0.7 1.0 1.2 1.5 2.0 2.5 3.0
RESISTIVITY, K*m/W
De
s s
Rating Factor for
Groups of Cables in the Ground
cc
Rating Factor for Cables in Pipes
In the Ground
SINGLE-CORE SINGLE-
SINGLE-CORE THREE-CORE
CABLES PARTIALLY CORE CABLE
CABLES IN CABLE IN A
INSTALLED IN IN A
SEPARATE PIPE
SEPARATE PIPES COMMON
PIPES
PIPE
0.94 0.90 0.90 0.90
Calculation of
Pulling Tension
Equations for Max. Permissible
Cable Pulling Tension (in Pounds)
Where :
L
Where : T = L*w*f*v
T = total pulling tension in lbs.
L = duct length in ft.
w = cable wt. in lbs/ft
f = coefficient of friction
v = occupancy factor
= 1, for 1 cable per duct
Calculation of Pulling Tension
For Curved Section
L1
L2
T = T1e0.0174*f*θ*v + T2
Where :
T = total pulling tension in Newton (N)
T2 = tension for straight section at pulling PULLING
end in Newton (N) END
T1 = tension for straight section at feeding
end in Newton (N)
Calculation of Pulling Tension
For Curved Section
v = [ 1 – ((D1/D)-1)-2 ] -0.5
Calculation of Pulling Tension
For Curved Section
The occupancy factor (v) for 3 cables per duct random lay
v = 1 + 4/3 * ((D1/D)-1)-2
Where :
3 .0 5
1 PULLING END
30°
M
M
30 61
.5M
5M
9 0°
3 .0
2
3
NON-LEADED
DUCT TYPE LEADED CABLE
CABLE
POLYETHYLENE
0.25 0.25
AND PVC
NUMBER OF CABLES
RUBBER
COVERED
53 31 40 40 40
CABLE 600V &
OVER
LEAD COVERED
55 30 40 38 35
CABLES
ALL OTHER
35 25 25 25 25
CABLES
Percent Fill of Duct by Cables
• Where racked from the same wall, the supply cables should be
racked below the communication cables
Typical Siting Requirements for
Pad-Mounted Transformer
Min. Separation between Supply &
Communication Facilities in Joint-use
Manholes & Vaults
0 TO 15,000 155
1. 77 mm of concrete
2. 100 mm of masonry
3. 305 mm of well tamped earth
Direct-Buried Cable
• Minimum horizontal clearance of 305 mm from other UG structures.
Conditions for Random Separation between
Supply & Communication Cables
• VOLTAGE
a. Grounded supply systems not in excess of
22 kV to ground
b. Ungrounded supply systems not in excess of
5.7 kV to ground
• CABLE
a. With bare or semi-conducting jacketed grounded
conductor with continuous contact with the earth
b. Conductor in contact with the earth of suitable corrosion
resistant material
c. Radial resistivity of semi-conducting jacket not more than
20 m-ohms.
d. Adequate bonding between the supply and communication
cables shield at intervals which should not exceed 305mm
Underground
Accessories
UG Components and Accessories
600 A Deadbreak
Elbow Connector
RTE M.O.V.E.
UG Components and Accessories
Grounding Elbow
Fault Indicator
Conductor
Electrostatic Flux Lines
Equipotential Lines
Shielded Cable
Insulation Shield
Insulation
Conductor
Electrostatic Flux Lines
Conductor Shield
Equipotential Lines
Series II 3-Phase Secter
Cable Splice
Cable Splice
SHIELD WIRE
UG Components and Accessories
SERVICE CONNECTORS
Typical Underground System
Typical Underground System
Single-Phase Padmounted Transformer
T-BLADE
SWITCH
A B
PARTIAL C
RANGE CLF
EXPULSION
FUSE
TRANSFORMER
WINDING
Three-Phase Padmounted Transformer
UG Components and Accessories
200 A Loadbreak Elbow Connector
VOLTAGE RATING
CONDUCTOR SIZE 100% 133%
PHASE-TO-PHASE
(AWG-Kcmil) LEVEL (Mil) LEVEL (Mil)
VOLTS
2001-5000 8-1000 90 90
Since Dec 1987, REA now requires 220 mils for 15kV cable
and 345 mils for 25kV cable.
Suggested Minimum Burial Depths
For Direct Buried Cables
URD
EQUIPMENT ARRESTER IR OVERHEAD
DISTRIBUTION SYSTEM
BIL RATING at SYSTEM
VOLTAGE MARGIN
(KV) (KV) 10KA MARGIN