Professional Documents
Culture Documents
Drilling Notes
Drilling Notes
Rig rate
Well numbers and well type
Total hole depth
Well layout and spacing
Specifications of equipment
Target tolerances = target size
Water depth for offshore wells
1|Page
The time spent on a well consists of:
An accurate “estimate” of the time required to drill the well must be prepared before AFE.
Non Productive Time (NPT) | reducing drilling time and saving money |
Definition: The time required for any routine or abnormal operation which is carried out as a
result of a failure is defined as Non Productive Time (NPT)
Waiting on weather or on orders, people or equipment is not NPT. This is standby time.
Non-Productive Time in drilling operations currently account for 20% of total drilling time.
A slight reduction in NPT can result in substantial savings.
Classification of NPT
o Rig equipment o Logging equipment
o Surface Equipment o Hole problems and well control
o Downhole Equipment o Stuckpipe and Fishing of BHA
o Drillstring Equipment equipment
o Casing and Cementing Equipment
o Fluids
2|Page
CALCULATION OF NPT
o It is as if these operations are not part of the drilling process and they are merely carried
out to get us to where we were before the problem occurred.
o Accurate calculation of NPT is essential if the operator attempts to improve future drilling
operations.
o Details of the NPT should be recorded by the operator on a daily basis and should be
checked against historical NPT in the area to obtain trends and then arrive at solutions.
o P10 ESTIMATE
This is an estimate which has only a 10% chance of being achieved. This is a highly
optimistic estimate which can only be achieved under exceptional circumstances.
This level may represent the limit of technology or some stretched target that the
company believes can be achieved.
o P50 ESTIMATE
This is the key figure in most well cost estimates.
As implied, there is a 50% chance that the well will be drilled for less than this figure
and a 50% chance that it will cost more.
o P90 ESTIMATE
This is an estimate of well cost which is likely to be met 90% of the time and that well
costs cannot be exceeded except under exceptional cases.
3|Page
TECHNICAL DRILLING LIMIT (TLD)
BASIS OF TLD
o TLD requires detailed numerical answers to the following questions:
What is the current performance? This gives the normal average
What is possible? This gives the theoretical limit
What is needed to get there? This determines the resource investment to achieve TLD.
o TLD requires that drilling estimates are made without the inclusion of invisible lost time
or non-productive time
o Invisible Lost Time: This time is usually absorbed in productive time and is made up of
the total of previously acceptable wasteful events such as lack of personnel.
o Examples of invisible lost time:
Bit trips before reaching TD
Check trips
Mud conditioning
Double checking directional motors and MWD tools
o In summary, time estimates for TLD are meant to use the limits of current technology
with no restriction on equipment or personnel.
Cost Reduction
The objective of all E&P companies is to drill and produce wells in the least possible time,
consistent with safe operations.
The longer an operation takes, the more it will cost.
This is because as you spend more time say on drilling operations, the company will be paying
more money for equipment and people which will make the operation more expensive.
There are two elements of costs which must be controlled:
o Capital Expenditure (CAPEX): This includes the cost of finding and developing an oil/gas
field. The cost of drilling operations is the major cost element and must be kept to an
acceptable value.
o Operating Cost (OPEX): This includes the actual cost of production: cost of maintaining
the platform, wells, pipelines etc. We will not be concerned with these costs as they are
part of production operations.
E&P companies aim to reduce time to develop fields in order to reduce CAPEX and OPEX.
4|Page
In general the more remote the area the more expensive is the final cost of barrel of oil.
There are basically four types of contracts which are currently used in the oil industry:
o Conventional
o Integrated Services (IS)
o Integrated Project Management (IPM)
o Turn Key
The type of drilling contract used can mean the difference between an efficient and a less
efficient operation.
The operator must weigh all the relevant factors before opting to one of the above strategies.
o CONVENTIONAL CONTRACT
In this type, the E&P Company does everything using its own staff or contractors.
This is the most involved type of contract and can mean handling up to 100 contracts
per well.
The operator has total control over the operation and carries full risk.
The contractor has no risk.
This type of contract has the advantage that lessons learnt during drilling operations
are kept within the company and used to improve future operations.
The contractor will be paid a certain percentage of the savings made if operations are
completed ahead of the planned agreed drilling time.
5|Page
o INTEGRATED PROJECT MANAGEMENT (IPM)
In this type, a main contractor is chosen. This contractor is the Integrated Project
Management (IPM) contractor.
The contractor is responsible for 20-30 service companies.
The drilling operation will be controlled by a representative from the IPM contractor.
The operator may hold one or two major contracts.
This type is one of the worst kind of contracts for the operator because there is virtually
no learning for the operator. Lessons learnt are lost as the IPM contractor traditionally
has a large staff turnover.
6|Page
REPORTING DRILLING OPERATIONS
Importance of Reporting Drilling Data
Reducing risk.
Making control on the contractor/operator/third parties.
Improve and optimize drilling operation.
Drilling report is used as a legal documentation/invoicing…
Drilling reports are used to control, to document, to study and analyze, to improve.
Equipment
Personnel
Operations
Environment
Cost
Filing
o Frequency-Based Scheme
Twice a day
• Mud Report
• Geological Report
• Morning & afternoon drilling reports
Daily
• Formal Drilling Reports
• API-IADC Rig Report (International Association Drilling Contractor)
• Catering Report
Weekly
• BOP, Accumulator… etc
• Rig Survey Report
7|Page
Monthly
• Overtime Sheet
• Rig Time Breakdown Report
• Monthly Meetings
o Content-based scheme
o Others-based scheme
Completion
Accidents reports
Casual Services
Work Order
Prerecorded Well Data
Rendered Meals Sheet
Safety
8|Page
DRILLING ORGANIZATION
Drilling Mission
To drill wells in a safe, economic and environmentally sound way according to good oilfield
practices.
Location of Operations
On the rig
In districts near drilling sites
At the main office.
Location:
o On one of the rigs working for the company.
Organizational relationship:
o Reports to the assign team supervisor
o Supervises rig personnel
Functional relationship:
o Contact production, material, and support service personnel.
9|Page
Tasks:
o Plans for short term drilling requirements
o Plans movement of equipment, tools, material, personnel,… between rig and base.
o Supervises all drilling operations.
o Reports drilling information to team supervisor.
o Submits daily drilling report.
o Recommends ways to optimize operations
o Implements contingency plan
o Decides bit type to be used.
o Manages company personnel on rig.
Skills:
o Leadership and managerial skill
o Vision & Sound judgment
o Communication speaking and writing
o Ability to work under pressure
o Being imaginative.
Finance
Administration
Explorations
Projects
Operations Managers
Safety
Contracts
Service Companies
Support services
Materials
Communication
Rig
Others
10 | P a g e
Drilling organization (Main Office)
Drilling Manager & Deputy Drilling Manager
Support services
Planning
Database (Adm.)
Following up activities Database
Invoices
Training Investigation
Contracts
Career planning Long-term planning
Personnel affairs
Budget
Filing
Drilling organization
Rig manager (Office)
Toolpusher
Mechanics
A. Toolpusher Electricians Foremen
Driller Medical Trainee Engineers
A. Driller Galley personnel Geologists
Derickmen Warehouse men Production
Floormen Laundry/Cleaning Third party
Roustabout AR Radio Op. Others
Others
11 | P a g e
DRILLING CONTRACTS
Contracts is a set of rules governs drilling relationships between business partners.
Types
Day rate contracts
Footage rate contracts
Turnkey rate contracts
Contractor’s risk is high in turnkey and footage rates. Operator’s risk is high in day rate.
Footage Contracts:
The contractor is paid a scheduled amount based on depth.
In special operations, the contractor is paid on daily-rate basis.
Footage contract represents a higher risk to the contractor than the daily-rate type.
Turnkey Contracts:
Drilling the well or a part of the well against an agreed lumpsum.
Contractor procures materials.
Minimum control from operator.
Turnkey contracts involve higher risk than any of the other types of contracts.
12 | P a g e
Exhibit A:
Lists basic equipment of the rig for implementing all major and the less major operations
needed for drilling and workover.
Exhibit B:
Lists the necessary personnel on board for the drilling and workover operations
Exhibit C:
Shows schedules of responsibilities supplying of material, equipment and services on for the
contracted operations.
13 | P a g e
Itemized Cost
A breakdown of the drilling operation is made
The accuracy of the forecast depends on the completeness of the analysis of cost centers.
Breakdown operations:
Operations are split into categories and cost centers such as
o Rig, moving, drilling, tripping, casing, cementing, logging.
o Tangibles.
o Intangibles.
o Apply contingency for problems.
Contingency
Contingency of 10%, 15%, or 20% is applied on the estimate of well cost (itemized or others)
depending on
o the type of the well: exploration/development
o well depth
o drilling difficulties
o remoteness
o other risks
o weather
availability of data
personal feelings
14 | P a g e