PROPINSI : Bengkulu No. Rab :


KABUPATEN : Bengkulu Tengah Program : P3MD KECAMATAN : Merigi Sakti Jenis
Kegiatan 1. Lampu Tenaga Surya 31 Unit
DESA : Rajak Besi
TH. Anggaran : 2023

Volume Harga Satuan Jumlah


No. Uraian Pekerjaan
Volume Pembulatan Sat (Rp.) (Rp.)

1 2 3 4 5 6 7
I. PEK. PEMBANGUNAN LAMPU TENAGA SURYA 31 UNIT

a. Pek. Honorarium TPK 3.00 Bln


Bahan
Upah
Ketua 3.00 Hok
Sekretaris 3.00 3.00 Hok
Hok 350,000.00 1,050,000.00
Anggota 3.00 3.00 300,000.00 900,000.00
3.00 250,000.00 750,000.00
Sub Total 2,700,000.00

b. Papan Nama Kegiatan 1.00 Bh 350,000.00 350,000.00


Bahan
Alat
Upah

Sub Total 350,000.00

c. Prasati Kegiatan 1.00 Bh 1,100,000.00 1,100,000.00


Bahan
Alat
Upah

Sub Total 1,100,000.00

d. Pek. Persiapan/Pembersihan Lokasi 31 M'


Bahan
Alat
Upah
Pekerja 3.41 Hok
Tukang - 4.00 Hok 115,000.00 460,000.00
- - 0.00
Sub Total 460,000.00
e. Pek. Galian Tanah 31.00 M3
Bahan 2.91

Alat
Upah
1 Pekerja hok

3.00 115,000.00 345,000.00

Sub Total 345,000.00

f. Pek. Urugan Pasir 0.39 M3

Bahan
Pasir urug 0.47 1.00 M3 150,000.00 150,000.00
Alat
Upah
Pekerja
0.12 1.00 Hok 115,000.00 115,000.00
Sub Total 265,000.00

g. Pek. Cor Beton 6.2775 M3


Bahan
Semen 37.54 38.00 zak 75,000.00 2,850,000.00
Pasir 3.58 4.00 M3 300,000.00 1,200,000.00
Koral 4.73 4.50 M3 290,000.00 1,305,000.00
Alat
Upah
Pekerja 10.36 hok
11.00 115,000.00 1,265,000.00
Tukang hok
1.73 2.00 150,000.00 300,000.00
Sub Total 6,920,000.00

i. Pek. Begesting 24.80 M2


Bahan
Kayu Kelas IV 0.99 0.50 M3 3,000,000.00 1,500,000.00
Kayu Dolken 62.00 62.00 Batang 15,000.00 930,000.00
Paku 5 - 10 cm 7.44 8.00 Kg 20,000.00 160,000.00
Alat
Upah
Pekerja 12.90 13.00 hok 115,000.00
hok 1,495,000.00
Tukang 6.45 7.00 150,000.00 1,050,000.00
Sub Total 5,135,000.00
j. Pek. Lampu Tenaga Surya 31.00 Unit
Bahan
Lampu + Battery 31.00 Bh 3,650,000.00 113,150,000.00
31.00
Pipa Galvanis 3 inc 13.00 Btg 950,000.00 12,350,000.00
13.00
Pipa Galvanis 2,5 inc 13.00 Btg 880,000.00 11,440,000.00
13.00
Baut Bawah 62.00 Bh 75,000.00 4,650,000.00
62.00
Panel Surya 31.00 Bh 60,016,000.00
31.00 1,936,000.00
Acesoris + Cat 31.00 Bh 7,750,000.00
31.00 250,000.00
Alat
Upah
Upah Pasang 31.00 Unit
31.00 150,000.00 4,650,000.00
Sub Total 214,006,000.00

j. Pek. Finishing 620.00 M'


Bahan
Alat
Upah
Pekerja 16.74 17.00 Hok 115,000.00 1,955,000.00
Tukang - Hok
- 150,000.00 0.00
Sub Total 1,955,000.00

Sub Total 1 233,236,000.00

IV. PERALATAN DAN LAIN-LAIN

Meteran 1.00 Bh 153,872.00 153,872.00

Sub Total 153,872.00

Sub Total 2 153,872.00

JUMLAH 1+2+3+4 233,389,872.00

SWADAYA 0.00

TOTAL BIAYA 233,389,872.00

DIBULATKAN Rp 233,389,872.00

Rajak Besi, 2023


Disetujui Oleh : Dibuat Oleh :
TIM RKP TIM Teknis Desa

Lukman Jaya
Gundel Mankurdi
Diperiksa/Verifikasi Oleh : Mengetahui/Mengesahkan Oleh :
Tenaga Ahli / Profesional Kepala Desa

…………………….. Waja Rilla