Recovery PLTGU Keramasan #1-1

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

ID Task Task Name Duration Start Finish Predecessors

% Mon 27 Feb Tue 28 Feb Wed 01 Mar Thu 02 Mar Fri 03 Mar Sat 04 Mar Sun 05 Mar Mon 06 Mar
Mode Complete 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6 12 18 0 6
0 RECOVERY PLTGU #1 7,08 days Mon 27/02/23 Sun 05/03/23 84%
1 1 Shut Down 1 day Mon 27/02/23 Mon 27/02/23 100%
2 1.1 Cooling Down 1 day Mon 27/02/23 Mon 27/02/23 100%
3 2 Perbaikan PMG 6,75 days Mon 27/02/23 Sun 05/03/23 90%
4 2.1 Disassembly 3 days Mon 27/02/23 Wed 01/03/23 100%
5 2.1.1 Melepas sistem instrumentasi 3 hrs Mon 27/02/23 Mon 27/02/23 2SS 100%
6 2.1.2 Pembongkaran cover bearing generator 8 hrs Tue 28/02/23 Tue 28/02/23 100%
7 2.1.3 Melepas bearing upper dan lower generator2 hrs Tue 28/02/23 Tue 28/02/23 6 100%
8 2.1.4 Pembongkaran cover PMG 2 hrs Tue 28/02/23 Tue 28/02/23 7 100%
9 2.1.5 Pebongkaran PMG 4 hrs Wed 01/03/23 Wed 01/03/23 8 100%
10 2.1.6 Pembongkaran magnet 8 hrs Wed 01/03/23 Wed 01/03/23 9 100%
11 2.2 Inspeksi 3,42 days Wed 01/03/23 Sat 04/03/23 100%
12 2.2.1 Tap and drill baut magnet PMG 4 hrs Wed 01/03/23 Wed 01/03/23 9SS 100%
13 2.2.2 Membongkar lilitan PMG 5 hrs Wed 01/03/23 Wed 01/03/23 12SS 100%
14 2.2.3 Rewinding PMG 2 days Wed 01/03/23 Fri 03/03/23 13 100%
15 2.2.4 Sirlak dan pemanasan lilitan 1 day Fri 03/03/23 Sat 04/03/23 14 100%
16 2.3 Assembly 4,42 days Wed 01/03/23 Sun 05/03/23 60%
17 2.3.1 Pemasangan magnet 8 hrs Wed 01/03/23 Wed 01/03/23 12 100%
18 2.3.2 Pemasangan PMG 5 hrs Sat 04/03/23 Sat 04/03/23 15 50%
19 2.3.3 Pemasangan cover generator 2 hrs Sat 04/03/23 Sat 04/03/23 18 0%
20 2.3.4 Pemasangan bearing upper dan lower generator
8 hrs Sun 05/03/23 Sun 05/03/23 19 50%
21 2.3.5 Pemasangan instrumentasi 1 hr Sun 05/03/23 Sun 05/03/23 20 0%
22 3 Pekerjaan Tambahan 2 days Mon 27/02/23 Tue 28/02/23 75%
23 3.1 Pemasangan vacuum pump 8 hrs Tue 28/02/23 Tue 28/02/23 70%
24 3.2 Pengecekan vibrasi steam turbine LP side 1 day Tue 28/02/23 Tue 28/02/23 23SS 100%
25 3.3 Perbaikan valve blow down 1 day Tue 28/02/23 Tue 28/02/23 24SS 100%
26 3.4 Pengujian proteksi undervoltage 4 hrs Mon 27/02/23 Mon 27/02/23 2SS 10%
27 3.5 Simulasi black out dan pengujian DC sistem 4 hrs Mon 27/02/23 Mon 27/02/23 26 0%
28 4 Start Up 0,33 days Sun 05/03/23 Sun 05/03/23 0%
29 4.1 Final check 1 hr Sun 05/03/23 Sun 05/03/23 21 0%
30 4.2 Turning Gear 3 hrs Sun 05/03/23 Sun 05/03/23 21 0%
31 4.3 Start Up 1 hr Sun 05/03/23 Sun 05/03/23 30 0%

Task Project Summary Manual Task Start-only Deadline

Project: RECOVERY PLTGU #1 Split Inactive Task Duration-only Finish-only Progress


Date: Thu 02/03/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
PT PLN INDONESIA POWER
UNIT PELAKSANA PENGENDALIAN PEMBANGKITAN KERAMASAN

PLANNED ACTUAL
DAY DATE
(%) (%) S-CURVE PLANNED VS ACTUAL COMPLETE
0 26 February 2023 0% 0%
1 27 February 2023 12% 13%
2 28 February 2023 36% 38%
3 01 March 2023 59% 60%
4 02 March 2023 73% 84%
5 03 March 2023 80%
6 04 March 2023 88%
7 05 March 2023 100%
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45

You might also like