Professional Documents
Culture Documents
Drum HRSG Layup Procedure
Drum HRSG Layup Procedure
TABLE OF CONTENTS
INTRODUCTION 3
INTRODUCTION
Layup has been defined for two conditions; wet and dry, and for two durations (short and
long) regarding wet layup. A short outage is defined as any period where the HRSGs is out
of service for up to four days. A long outage is defined as any period where the HRSGs is
out of service for more than four days.
For dry layup, the most effective and practical means for excluding oxygen is to maintain an
overpressure of nitrogen. For wet layup, protection against corrosion is provided by an amine
(e.g. ammonia) for pH control and an oxygen scavenger (e.g. hydrazine) to maintain a
protective oxide film and a reducing environment. A nitrogen overpressure is also
established and maintained to preclude oxygen ingress.
Tables 1 and 2 below summarize the Company’s recommended layup procedures for drum-
type HRSGs. These layup procedures are intended to be general guidelines for minimizing
corrosion of HRSG components under outage conditions. Plant-specific circumstances may
dictate alternative layup measures.
Table 1
TYPE OF PROCEDURE
SHUTDOWN
Pre-Operational With the HRSG components (economizers, evaporators, superheaters, and
Period Post-Hydro reheaters, if present) filled to overflowing, pressurize the system with
(See Note 1) nitrogen to 5 psig (See Notes 3, 4, 5, 6).
Note 2: Hydrazine and ammonia should be added in a manner that results in a uniform
concentration throughout. They may be added to the system in several ways, as for
example:
a) By pumping concentrated solutions through the chemical feed equipment and blend
filling to achieve the desired concentration.
b) If condenser leakage is not a cause for shutdown, concentrated solutions can be
introduced directly into the hotwell where they can be mixed to achieve the desired
concentrations. If condensate demineralizers are employed, they must be bypassed
during the operation.
It is important to have the fluid temperature in the cycle below 400°F before the addition
of hydrazine. If this temperature is exceeded, hydrazine will decompose.
The use of hydrazine (N2H4) has been found acceptable as an oxygen scavenger.
However, in cases where the use of hydrazine is prohibited due to local environmental
regulations, ammonia treated water will suffice provided that a pH of 10 is maintained.
When using ammonia for extended layup, it is important to establish and maintain a
nitrogen cap to prevent air ingress.
Note 3. If freezing is a problem, the water can be displaced with nitrogen and the unit laid up
under 5 psig nitrogen pressure.
Note 4. If the reheater cannot be isolated and the outage is expected to extend beyond two
months, provisions should be made to isolate and nitrogen cap the reheater.
Note 5. Nitrogen cap should be applied through the drum vent and superheater outlet
header drain/vent as the unit is cooled, when pressure drops to 5 psig. Admission of air
through atmospheric vents should be avoided.
Note 6. When it is not possible to maintain a nitrogen cap, the pressure parts shall be
maintained completely full of treated water. Compete filling can be proven when water is
vented from the high point vents.
Table 1 (cont.)
Note 1. If freezing is a problem, the water can be displaced with nitrogen and the unit laid
up under 5 psig nitrogen pressure.
Note 2. If the reheater cannot be isolated and the outage is expected to extend beyond two
months, provisions should be made to isolate and nitrogen cap the reheater.
Note 3. Nitrogen cap should be applied through the drum vent and superheater outlet
header drain/vent as the unit is cooled, when pressure drops to 5 psig. Admission of air
through atmospheric vents should be avoided.
Note 4. When it is not possible to maintain a nitrogen cap, the pressure parts shall be
maintained completely full of treated water. Compete filling can be proven when water is
vented from the high point vents.
Short Outage, 1. Maintain the same water chemistry conditions as those present during
4 Days or Less normal operation.
2. Establish and maintain a 5 psig nitrogen cap on the system (See Notes 1
& 2 ).
Note 1. Nitrogen cap should be applied through the drum vent and superheater outlet
header drain/vent as the unit is cooled, when pressure drops to 5 psig. Admission of air
through atmospheric vents should be avoided.
Note 2. When it is not possible to maintain a nitrogen cap, the pressure parts shall be
maintained completely full of treated water. Compete filling can be proven when water is
vented from the high point vents.
Short Outage, 1. Drain and open only those sections requiring repairs.
4 Days or Less, 2. Isolate remainder of system under 5 psig nitrogen pressure where
Unit Partially Drained possible (See Notes 1, 2, 3).
for Repairs Note 1. If the reheater cannot be isolated and the outage is expected to extend beyond two
months, provisions should be made to isolate and nitrogen cap the reheater.
Table 1 (cont.)
Short Outage, Note 2. Nitrogen cap should be applied through the drum vent and superheater outlet
4 Days or Less, header drain/vent as the unit is cooled, when pressure drops to 5 psig. Admission of air
Unit Partially Drained through atmospheric vents should be avoided.
for Repairs
Note 3. When it is not possible to maintain a nitrogen cap, the pressure parts shall be
maintained completely full of treated water. Compete filling can be proven when water is
vented from the high point vents
3) Maintain the same chemistry conditions for water remaining in the cycle
as those present during normal operation.
Long Outage, 1. Fill the superheater and reheater with demineralized or condensate
Longer than 4 Days quality water containing 10 ppm of ammonia and 200 ppm of hydrazine.
The pH of the solution should be about 10. Add the fill water from an
available connection. Do not spill over or fill from the steam drum (See
Notes 1 & 2).
Note 1. If the reheater cannot be isolated and the outage is expected to extend beyond two
months, provisions should be made to isolate and nitrogen cap the reheater.
Note 3. Hydrazine and ammonia should be added in a manner that results in a uniform
concentration throughout. They may be added to the system in several ways, as for
example:
a) By pumping concentrated solutions through the chemical feed equipment and
blend filling to achieve the desired concentration.
b) If condenser leakage is not a cause for shutdown, concentrated solutions can
be introduced directly into the hotwell where they can be mixed to achieve the
desired concentrations. If condensate demineralizers are employed, they must
be bypassed during the operation.
It is important to have the fluid temperature in the cycle below 400°F before the
addition of hydrazine. If this temperature is exceeded, hydrazine will decompose.
The use of hydrazine (N2H4) has been found acceptable as an oxygen scavenger.
However, in cases where the use of hydrazine is prohibited due to local
environmental regulations, ammonia treated water will suffice provided that a pH of
10 is maintained. When using ammonia for extended layup, it is important to
establish and maintain a nitrogen cap to prevent air ingress.
Table 1 (cont.)
Long Outage, Note 4. If freezing is a problem, the water can be displaced with nitrogen and the unit laid
Longer than 4 Days up under 5 psig nitrogen pressure.
Note 6. Nitrogen cap should be applied through the drum vent and superheater outlet
header drain/vent as the unit is cooled, when pressure drops to 5 psig. Admission of air
through atmospheric vents should be avoided.
Note 7. When it is not possible to maintain a nitrogen cap, the pressure parts shall be
maintained completely full of treated water. Compete filling can be proven when water is
vented from the high point vents
Long Outage, 1. Drain and open only those sections requiring repairs.
Longer than 4 Days, 3. Fill the superheater and reheater (if not requiring draining for repairs)
Unit Partially Drained with demineralized or condensate quality water containing 10 ppm of
for Repairs ammonia and 200 ppm of hydrazine. The pH of the solution should be
about 10. Add the fill water from an available connection. Do not spill
over from the steam drum (See Notes 1 & 2).
Note 1. If the reheater cannot be isolated and the outage is expected to extend beyond two
months, provisions should be made to isolate and nitrogen cap the reheater.
Note 3. Hydrazine and ammonia should be added in a manner that results in a uniform
concentration throughout. They may be added to the system in several ways, as for
example:
a) By pumping concentrated solutions through the chemical feed equipment and
blend filling to achieve the desired concentration.
b) If condenser leakage is not a cause for shutdown, concentrated solutions can
be introduced directly into the hotwell where they can be mixed to achieve the
desired concentrations. If condensate demineralizers are employed, they
must be bypassed during the operation.
Table 1 (cont.)
Note 4. If freezing is a problem, the water can be displaced with nitrogen and the unit laid
up under 5 psig nitrogen pressure.
Note 5. If the reheater cannot be isolated and the outage is expected to extend beyond two
months, provisions should be made to isolate and nitrogen cap the reheater.
Note 6. Nitrogen cap should be applied through the drum vent and superheater outlet
header drain/vent as the unit is cooled, when pressure drops to 5 psig. Admission of air
through atmospheric vents should be avoided.
Note 7. When it is not possible to maintain a nitrogen cap, the pressure parts shall be
maintained completely full of treated water. Compete filling can be proven when water is
vented from the high point vents
Note 8. Hydrazine and ammonia should be added in a manner that results in a uniform
concentration throughout. They may be added to the system in several ways, as for
example:
a) By pumping concentrated solutions through the chemical feed equipment and
blend filling to achieve the desired concentration.
b) If condenser leakage is not a cause for shutdown, concentrated solutions can
be introduced directly into the hotwell where they can be mixed to achieve the
desired concentrations. If condensate demineralizers are employed, they
must be bypassed during the operation.
It is important to have the fluid temperature in the cycle below 400°F before the
addition of hydrazine. If this temperature is exceeded, hydrazine will decompose.
Table 1 (cont.)
Note 9. If freezing is a problem, the water can be displaced with nitrogen and the unit laid
up under 5 psig nitrogen pressure.
Note 10. If the reheater cannot be isolated and the outage is expected to extend beyond
two months, provisions should be made to isolate and nitrogen cap the reheater.
Table 2
TYPE OF PROCEDURE
SHUTDOWN
Pre-Operational 1. Inspect the HRSG components (economizers, evaporators,
Period (See Note 1) superheaters, and reheaters, if present) and dry up any visible water (to
the extent practical) which may have inadvertently entered the
components during shipment (See Notes 2 & 3).
Note 1. Pre-operational period is defined as the period > 30 days following mechanical
completion but prior to the initial water filling of the components. Components are shipped
in a dry condition.
Note 4. If the reheater cannot be isolated and the outage is expected to extend beyond
two months, provisions should be made to isolate and nitrogen cap the reheater.
Post Operational 1. Completely drain the components to be laid up. Hot draining of the
Period, Including components using a nitrogen purge will facilitate drying.
Post Hydro 2. Dry the components to the extent practical (See Note 1).
Note 2. If the reheater cannot be isolated and the outage is expected to extend beyond
two months, provisions should be made to isolate and nitrogen cap the reheater.