Grouting of Compressor Base
Grouting of Compressor Base
1|Page
PERSONNEL
11 GROUTING SUPERVISOR 7 1 70,000 490,000.00
12 GROUTING TECHNICIANS 7 8 35,000 1,960,000.00
13 CARPENTER 7 2 25,000 350,000.00
14 COMMUNITY LABOUR 7 4 12,000 336,000.00
SUB – TOTAL 3,136,000.00
15. MOB AND DEMOB NIL 2 120,000 240,000.00
Total 16,922,150.00
VAT 7.5% 1,269,161.00
GRAND – TOTAL 18,191,311.00
NOTE:
1. PAYMENT FOR MATERIALS AND EQUIPMENT = 100%
2. PERSONNEL AND ACCOMMODATION/FEEDING = 80% PAYMENT.
3. UPON MOBILIZATION OF MATERIIALS, EQUIPMENT AND PERSONNEL ON SITE
(WITHIN 2 DAYS) = 20%.
4. COMMUNITY RELATION/LEVY IS THE CLIENT’S RESPONSIBILITY.
Valid: 30 days.
Material delivery: Within 5 days
Delivery: Within 7 days after the materials are delivered on site.
AKPAN ALOYSIUS
Operations Manager