Technical Proposal For Exhaust Rehabilitation 2
Technical Proposal For Exhaust Rehabilitation 2
Technical Proposal For Exhaust Rehabilitation 2
nature of the job and the means of transport to the work site, there is no
and sling wire is not needed during off-loading. The reason being that
followed to avoid accident. All crew personnel must put on their hand
glove before the operation of lifting to avoid cut from any sharp object.
deleterious amount of grease, oil and dirt. The materials to be used must
ceramics fibre and cloth and then replaced with second grade 1260 oC.
After the replacement and sealing, the stainless place will be reinstalled
the unit has some sections where the stainless at the side walls are
site, there will be close contact with the site supervisor for up date
whereby work are kept neat and orderly, maintaining halls and floors
free of slip and trip hazards and removing of waste material e.g particles
rechecked to ensure that the unit is back and safe for operations.
8. WASTE MANAGEMENT
Signed
Operations Manager
TECHNICAL PROPOSAL FOR EXHAUST BELLOW REHABILITATION, AFAM POWER
PLANT, RIVERS STATE.
a. Procurement of Material
b Mobilization to site
c. Surface Preparations
3. PROCUREMENT OF MATERIAL:
and galvanize wire will be procured from a dealer. The ceramic fiber
required for this work is second grade (1260 oCelcius ) materials because
stainless wire mesh, high temperature jacket, etc. Since the aim of the
used.
4. SURFACE PREPARATION:
grease, oil and dirt. The materials to be used must be stored in a dry
materials are all worn-out. The existing materials (ceramics wool, high
Meanwhile, before the worn – out materials will be removed, the bolts
and nuts will be removed. Because of the number of bolts and nuts on
the bellow, pneumatic wrench will be used so that the work will be
(50mm) cloths which must be second grade 1260 oC. Each stage will be
wrapped and sown with high temperature cloth and high temperature
material will be used and will be held in position by the help of stainless
banding wire and 19mm clips. Tin Smith or fabricator will carry out all
After the installation of the insulated materials are completed, the plate
holding the bellow will be installed and all the bolts and nuts fastened.
6. SITE RESTATEMENT/HOUSEKEEPING: Housekeeping is a system
whereby work sites are kept neat and orderly, maintaining halls and
floors free of slip and trip hazards and removing of waste material e.g
old ceramic wool, tie wire, high temperature cloth and others for
9 WORK SCHEDULE/PLAN
Installaton of Scaffolding
wool
wool
Removing of scaffoldings
Housekeeping/Site restatement
10. ORGANOGRAM
PROJECT ENGR
HSE QA/AC
Tin Smith
Insulation
Technician
Helper
11. WASTE MANAGEMENT
The waste generated on the course of this work will be segregated accordingly.
The following wastes are generated – off-cut banding wire, ceramics fibre
pieces, cloths, blanket, etc. The generated waste will be gathered and disposed
properly.
12. LOCATION: The work location is Afam Power plant, Oyigbo, Rivers State.
The whole process will be on site.
Signed
Operations Manager