WORK METHODOLOGY FOR GTT1, TRANS - AMADI PLANT, RIVERS STATE.

1. MOBILIZATION OF EQUIPMENT/PERSONNEL TO SITE: A vehicle/van will

convey equipment/personnel to site after a thorough inspection on the vehicle

and confirmation that the driver is competent and acquainted with the

operational requirements, standard and safety of our workers and clients.

2. OFF-LOADING OF TOOLS/EQUIPMENTS AT SITE: Considering the nature of the

job and the means of transport to the work site, there is no heavy equipment

attached or required to be used at the site, so sling belt and sling wire is not

needed during off-loading. The reason being that all tools/equipment can be

manually off-loaded. Meanwhile, to ensure a safe manual off-loading,

instructions and procedures must be followed to avoid accident. All crew

personnel must put on their hand glove before the operation of lifting to avoid

cut from any sharp object.

3. SURFACE PREPARATION: During insulation of the joint or section due for

rehabilitation, the surface cleaning must not be compromised. The area to be

insulated shall be scraped, blown – off, and be free of deleterious amount of

grease, oil and dirt. The materials to be used must be stored in a dry location and

protected from water at all times.


4. CLADDING OF THE PLATE AND SEALS: The proper forward and aft sealing will

be done by removing the stainless plate, remove the ceramics fibre and cloth

and then replaced with second grade 1260 oC. After the replacement and sealing,

the stainless place will be reinstalled and fastened accordingly.

5. REPLACEMENT OF BROKEN STAINLESS PLATE: The thermal exhaust of the unit

has some sections where the stainless at the side walls are totally deformed and

broken. In order to prevent heart loss to the surrounding, the deformed and

broken materials will be replaced with 5mm stainless plate 402 and stainless

bolt and nuts.

6. INTER PHASE OPERATION: To avoid obstruction with other activities at site,

there will be close contact with the site supervisor for up date information

regarding the plant and there should be close supervision of all site operation.

7. EMERGENCY: Emergency situation is an unexpected event that occurs,

therefore IGASHAR engineering will lash to our client emergency plan, Hence,

in case of any medical emergency related case, please contact retainership clinic

or call 08038842065 for Doctor’s assistance.

8. SITE RESTATEMENT/HOUSEKEEPING: Housekeeping is a system whereby work

are kept neat and orderly, maintaining halls and floors free of slip and trip

hazards and removing of waste material e.g particles of aluminum, tie wire,

ceramics woods, high temperature cloth and others for hazards free work areas.

The site restatement will be rechecked to ensure that the unit is back and safe

for operations.
8. WASTE MANAGEMENT

The waste generated on the course of this work will be segregated accordingly.
The following wastes are generated – off-cut banding wire, ceramics fibre
pieces, cloths, blanket, electrode remains, etc. The generated waste will be
gathered and disposed properly.

Signed

12TH SEPTEMBER, 2023

Akpan Aloysius Linus

Operations Manager