Professional Documents
Culture Documents
G5 - Setting Out Report Final
G5 - Setting Out Report Final
G5 - Setting Out Report Final
TECHNOLOGY
Setting out
Group - Group 5
Instructor - Mr. Pasindu
Members - EN20424800 - Silva T.B.S.
EN20398316 - Rosilda I.L
EN20410322 - Weerakoon W.M.K.
EN20411008 - Nagahawatte D.A.
EN20209216 - Moragoda H.D.P.C.
EN20423360 - Amarasinghe N.S.
EN20410704 - Kumarasinghe M.G.N.S.
EN20421762 - Gamaetige S.N.
1
Contents
1. Introduction ............................................................................................................................ 3
2. Client Requirements............................................................................................................... 4
2.1 Client brief ....................................................................................................................... 4
3. Materials and Apparatus ........................................................................................................ 5
4. Methodology .......................................................................................................................... 6
4.1 Setting-out procedure ....................................................................................................... 6
4.2 Procedure of Leveling and Centering the Total Station. .................................................. 6
5. Boundaries of Proposed Building and Land Area ................................................................. 7
5.1 Selected Area ................................................................................................................... 7
5.2 Selected 20 perch land area ............................................................................................. 8
5.3 Site plan ........................................................................................................................... 9
5.4 Ground Floor Plan with Dimensions for Proposed House ............................................. 10
5.5 Set out Coordinates of Proposed House and Selected Land .......................................... 10
5.6 Doors and Windows Schedule ..................................................................................... 112
6. Planning and Building Regulation Calculations .................................................................. 13
7. Cost Estimation .................................................................................................................... 15
7.1 Land Acquisition............................................................................................................ 15
7.2 Reinforcement ................................................................................................................ 15
7.3 Formwork....................................................................................................................... 16
7.4 Concreting ...................................................................................................................... 16
7.5 Plastering ....................................................................................................................... 17
7.6 Block work ..................................................................................................................... 17
7.7 Water Proofing ............................................................................................................... 18
7.8 Tiling.............................................................................................................................. 18
7.9 Painting .......................................................................................................................... 19
7.10 Doors and Windows..................................................................................................... 19
7.11 Swimming pool ............................................................................................................ 20
7.12 Final cost ...................................................................................................................... 20
8. Discussion ............................................................................................................................ 21
9. Conclusion ........................................................................................................................... 24
10. References .......................................................................................................................... 25
11 Work Breakdown ................................................................................................................ 26
2
1. Introduction
Setting out can be defined as the process of locating points for necessary structural
parts such as columns, site boundaries, levels etc. according to the construction drawing. Setting
out also known as ‘staking’ out or ‘laying out’.
The main reason for setting out is to ensure that the construction remains within the
legal boundaries. So that it prevents the legal dispute that can occur due to misusing of property
boundaries etc. Other than that, it is very essential to setting out accurately with all the
requirements such as lengths, angles and levels since the whole structure of the building depends
on the setting out. Although this is a very important task in constructions, many small scale
developments neglected this an ended up with unnecessary expenses due to the errors occur.
The main equipment used for setting out is the ‘total station’. It is a modern theodolite
mounted on a tripod and fitted with an EDM (electric distance meter). There is a movable
telescope in it to measure both vertical and horizontal planes. In order to measure the slope
distances accurately, total station uses an electronic transit theodolites in conjunction with a
distance meter. In all the projects, nylon strings are stung between the pegs hammered in to the
ground at pivotal points to demarcate the distances and boundaries of the development.
As the second task of the survey camp, we were assigned to do a setting out project
according to the given details of a client and their requirements in a 20 perch area land. The
proposed site for the task was SLIIT playground.
Boundary of
the play ground
3
2. Client Requirements
Client Requirements means the materials and information which is required from
the Client for the Company to provide the Services, as set out in the Order Form, or as
subsequently becomes necessary from time to time while providing the Services. The client was
asked lots of requirements and as an Engineer it is our responsibility to fulfill client’s
requirements for their preference.
Dr. Pradeep Liyanage requires a luxury house and prefer two-storied building.
Following are the requirements for the ground and first floors.
4
3. Materials and Apparatus
Figure 9-Mallet
Figure 8-Pegs Figure 10- Strings
5
4. Methodology
• This report details the layout of a two-story house that a doctor requirements are satisfied.
The residence should be constructed on a 20-acre plot of land near a cul-de-sac.
• First, the north was indicated, and the four control locations, designated as CP1, CP2, CP3,
and CP4 were located. The center CP1 and CP4 was then measured and identified as the
center. This place was chosen as the Cal-de-focal sac's point. The curve's coordinates were
acquired and marked with pegs at a 300 angle.
• The total station was used to determine the land's boundaries, which was then drawn in
AutoCAD software. The 20-perch land area was calculated, and the land's location was
determined using AutoCAD, and the home layout was created to meet the client's
requirements.
• The coordinates of the 20-perch area and the house layout were determined using AutoCAD.
The land and house were plotted in the ground using Total Station using these coordinates.
Pegs were used to mark the locations, and strings were connected to the pegs to indicate the
borders.
• Firstly, the tripod was placed on top of a control point. Extend the tripod's legs and raise it
to around chin height.
• Then, the legs were spread out and the tripod level was get and the leg bolts were tightened.
• After that, the Total station was placed on top of the tripod level (keeping one hand on top
of the TS at all times). The tripod bolt was inserted into the tri branch. The TS was centered
on the tripod so that subsequent adjustments can be made. After the TS was secured onto
the tripod, make sure to close the TS box.
• Then to target the benchmark, the optical scope was used on the TS. If the TS was not
above the benchmark, carefully adjust the tripod so the reticle is centered on it (placing a
foot over the benchmark may help orientation). The tripod's leg tips were stamped into the
ground to secure it.
• Then, the optical scope was used to double-check that the TS was still centered on the
benchmark. If it was not the tripod bolt was unscrewed and adjusted the TS slowly until it
was centered. And then the bolt was tightening again) To get the TS level, the tripod legs
6
were adjusted and utilized the level bubble.
• Then, the TS was on. When the TS starts counting down, enter button was pressed to enter
the precision leveling panel.
• Then, the TS was adjusted accordingly, how the TS's front to be parallel to two screws (one
screw behind) and using the complete station screws, the e-bubble was center and press
down.
• This was continued until 1:10 is in the center, then press Exit.
• Then, for the setting out of a co-ordinate5. , the MENU button was pressed. And then the
occupied orientation was entered accordingly (Co=ordinate of CP1). And then, the back
sight co-ordinate (C0-ordinate of CP2) was entered, observed through the optical scope and
measured to make sure the coordinates were corrected and TS placed accordingly.
• After that, TS the display and SO, SO-DATA buttons were pressed respectively. And then
the co-ordinate of a boundary point was entered and the HA-R was adjusted using
horizontal lock in the TS.
• Then, the prism was focused on the above mentioned point, and it was measured through
the optical scope and the peg was placed where the tolerance of the plotted point is 0.005m.
• These above steps were repeated to plot the boundary location of the building and pool
area.
7
5.1.1 Land Boundary Coordinates
No N E
1 4066.1003 2004.2279
2 4103.8473 2004.2279
3 4118.5503 2043.3679
4 4105.9523 2056.1599
5 4083.7293 2057.9939
6 4068.6703 2056.5159
7 4064.6463 2027.4129
No N E
1 4066.1003 2083.1848
2 4092.7203 2083.1848
3 4092.7203 2102.1848
4 4066.1003 2102.1848
8
5.3 Site Plan
9
5.4 Ground Floor Plan with Dimensions for Proposed House
10
5.5 Set out Coordinates of Proposed House and Selected Land
11
5.6 Doors and Windows Schedule
12
6. Planning and Building Regulation Calculations
Limits in
Item Regulation Workout Satisfactory
s
Minimum Frontage min - 3m 3.5m ok
Plot Coverage max - 66.67% 28% ok
Rear Space min - 2.25m 2.5m ok
Side Space min - 80cm 1m ok
Visitors room 12.46m2 ok
Dispensary 29.75m2 ok
Kitchen 11.3m2 ok
Dinning and pantry area 13.1m2 ok
Minimum Area Maid room 7.5m2 ok
ofRoom min - 7.5m2
Servant room 7.5m2 ok
Driver room 7.5m2 ok
Visitors room 4.225m ok
Dispensary 3.225m ok
Kitchen ok
2.825m
Dinning and pantry area 3.275m ok
The width Maid room 2.5m ok
ofrooms min - 2.4m
Servant room 2.5m ok
Driver room 2.5m ok
Visitors room 3m ok
Dispensary 3m ok
Kitchen 3m ok
Dinning and pantry area 3m ok
Maid room 3m ok
Internal Height
ofthe room min - 2.7m
Servant room 3m ok
Driver room 3m ok
13
WC1 2.1m ok
WC2 1.95m ok
Length WC3 min - 1.7m 2.28m ok
WC4 2.775m ok
WC1 1m ok
WC2 1.5m ok
Width WC3 min - 0.9m 1m ok
Toilet
WC4 1m ok
with
bathroom WC1 3m ok
WC2 3m ok
Height WC3 min - 2.1m 3m ok
WC4 3m ok
Visitors room Min – 1.78m2 2.7m2 ok
Natural Light Dispensary Min – 4.25m2 5m2 ok
and Kitchen Min – 1.61m2 2.5m2 ok
ventilation Dinning and pantry area Min – 1.87m2 2.5m2 ok
14
7. Cost Estimation
Amount
Item Description Quantity Unit Rate (LKR)
(LKR)
1.1 Land Value
Acquisition of land for
1.1.1 20 Perch 1,300,000.00 26,000,000.00
construction of house
7.2 Reinforcement
Rate Amount
Item Description Quantity Unit
(LKR) (LKR)
2.1 Slab Reinforcement
2.1.1 LANWA QT Bar - Ø 12 mm 3.5 t 295,000
1,032,000.00
Total
1,692,000.00
15
7.3 Formwork
Rate Amount
Item Description Quantity Unit
(LKR) (LKR)
3.1 Timber
3.1.1 2 by 2 timber 1000 m3 500 500,000.00
3.2 Plywood
1.44 m by 2.44 m plywood
3.2.2 100 Nos 6500 650,000.00
15mm th
3.3 Nails
3.2.3 2" Wire nails (25 kg bags) 4 Nos 5000 20,000.00
Total 1,170,000.00
7.4 Concreting
Rate Amount
Item Description Quantity Unit
(LKR) (LKR)
4.1 Concreting
4.1.1 Grade 25 ready mix concrete 60 m3 20,000
1,200,000.00
Total
1,200,000.00
16
7.5 Plastering
Rate Amount
Item Description Quantity Unit
(LKR) (LKR)
5.1 RCC Column Plastering
5.1.1 Cement 5 Nos 2,750
13,750.00
5.1.2 Sand 1 m3 18,000
18,000.00
Total
221,350.00
Rate Amount
Item Description Quantity Unit
(LKR) (LKR)
6.1 Block work
6.1.1 200 mm thick solid block work 4000 Nos 170
680,000.00
Total
793,250.00
17
7.7 Water Proofing
Rate Amount
Item Description Quantity Unit
(LKR) (LKR)
High performance elastomeric
7.1
waterproof coating
7.1.1 Powder Component (15 kg) 3 Nos 6000 18,000.00
7.1.2 Liquid Component (4.85 l) 3 Nos 1700 5,100.00
Total 23,100.00
7.8 Tiling
Rate Amount
Item Description Quantity Unit
(LKR) (LKR)
8.1 Floor Tiling
Mac Tile Super White 600mm *
8.1.1 475 Nos 2050 973,750.00
600mm
Total 1,468,250.00
18
7.9 Painting
Rate Amount
Item Description Quantity Unit
(LKR) (LKR)
9.1 Internal Skim Coating
9.1.1 SF Skim Coat (White) 60 Nos 1200 72,000.00
9.3 Painting
9.3.1 Dulux Brilliant white paint (10 l) 7 Nos 19020 133,140.00
Total 227,640.00
Rate Amount
Item Description Quantity Unit
(LKR) (LKR)
10.1 Wood Doors
10.1.1 Door size (800mm * 2200mm) - Teak 2 Nos 12000
24,000.00
10.1.2 Door size (900mm * 2000mm) - Teak 5 Nos 10500
52,500.00
10.1.3 Door size (700mm * 2000mm) - Teak 4 Nos 8250
33,000.00
10.1.4 Door size (800mm * 2200mm) - Teak 2 Nos 10500
21,000.00
10.1.5 Door size (800mm * 2200mm) - Jack 1 Nos 14250
14,250.00
10.2 Windows
10.2.1 Window Size (450mm * 2000mm) 15 Nos 15000
225,000.00
10.2.2 Window Size (450mm * 500mm) 4 Nos 12000
48,000.00
10.2.3 Window Size (600mm * 400mm) 4 Nos 10500
42,000.00
10.2.4 Window Size (450mm * 800mm) 4 Nos 10000
40,000.00
10.2.5 Window Size (450mm * 750mm) 6 Nos 9500
57,000.00
Total
412,000.00
19
7.11 Swimming pool
Rate Amount
Item Description Quantity Unit (LKR) (LKR)
11.1 Swimming pool
11.1.2 Mac Tile 2N Mat 600mm * 600mm 200 Nos 1450 290,000.00
Total 338,750.00
20
8. Discussion
• Checking verticality
21
i. Plumb Bob (For buildings less than 20m in height).
ii. Optical Plummet (A transparent plastic sheet is used as a target for
checking verticality of tall buildings).
iii. Theodolite
• 3 4 5 method
The 3–4–5 technique specifies the relative lengths of a triangle's sides with
one 90-degree or square corner. If two walls intersecting in a corner were truly 90 degrees to
each other, we could measure three feet from the corner on one wall and four feet on the other
wall, and then calculate the hypotenuse between those two sites. That would be five feet if the
walls were 90 degrees to each other. We always utilized tape measures at least 20 feet long in
the field, therefore we scaled up our triangle to 12–16–20 or whatever size works best for the
circumstance.
• Instrumental errors
22
• Human errors
• Advantages
✓ This method is less time consuming compared to the other setting-out methods.
✓ The accuracy of the total station is higher than other machines.
✓ Also, this TS can be used to calculate over a long distance.
✓ And there is a laser plummet involved in this total station. It is helpful to identify the
next location quickly.
• Disadvantages
23
9. Conclusion
During the second week of survey camp, we conducted a setting-out survey for a
proposed house. Setting out is done for most engineering and construction projects. And this
plays a major role in the civil and construction engineering fields. Consider about the setting-
out work; Firstly, the boundary coordinates of the land were identified using TS machine, and
then these coordinates were added to an AutoCAD plot. After that, the design of the house was
carried out on that AutoCAD plot. Then, that design plot can be taken onto the land by using
the coordinates identified in the AutoCAD. This method might also have a direct impact on the
house's outcome. The design plan can be finished after the setting out. It may provide direction
to employees on how to continue the construction process. Not only that, but we may also take
preventative measures before any legal issues arise throughout the construction process.
We learned a variety of skills, including how to operate a total station machine,
identify UDA rules for a dwelling, perform calculations, and use software. Also, getting hands-
on experience at survey camp would help on the day we become industry engineers. This
provides us with the opportunity to improve our leadership and teamwork abilities. Our survey
camp expertise will be invaluable in managing and understanding our site and field activities.
We hope that the suggestions we made will be helpful and that the experience we received over
the course of four days will help us become better engineers in the future.
24
10. References
25
11 Work Breakdown
Final report
26