Professional Documents
Culture Documents
SOF and IM Assurance
SOF and IM Assurance
I
D REFERENCE DOCUMENT
ID DESCRIPTION AND PURPOSE ID-2 REQUIREMENT DEMONSTRATION Responsible Discipline Doc Status TA-2
- NUMBER
3
Process safety risks have been
HAZID review has been undertaken as multidisciplinary team
identified documented and are review to identify all high level hazards associated with the project
managed to ALARP: For each phase of and proposed mitigations. The team composition was in line with
FAH-38-104322-HX-6873-00001-0000-
a. the Opportunity Realization Process, a.1 HAZID Report and Action Closeout. the standard requirement and project scope. The applied
NOF0000F0858-02
PDS13 TSE AFD PDS1
methodology was in line with PR-1971 [Ref. 06]. There is no Major
hazards with the potential to cause Accident Hazard (MAH) identified as part of the project scope.
major harm to people, environment,
assets (Major Accident Hazard) have
DR Report : FAH-04-104322-AA-7403-00002-
been systematically identified, DR Report were issued after work shop and Close out Report 0000-NOF0000F0858-01
a. assessed and controlled, and plans are a.2 Design Review and Action Closeout. were issued with all the 5 Actions were effectively closed and DR DR Close PDAF9 Projects IFI/ AFD PDAF
Close out Report has been issued out Report : FAH-04-104322-AA-7403-00003-
in place for recovery in the event control 0000-NOF0000F0858-01
is lost. The risks associated with these
hazards are tolerable and As Low As
HAZOP Study Report: FAH-38-104322-PX-6875-
Reasonably Practicable (ALARP). 00001-0000-NOF0000F0858-01
a. a.3 HAZOP Study and Action Closeout. Hazop Study was conducted and no actions are identified
No HAZOP closeout report as there is no HAZOP
PDEP17 Process AFD PDEP17
action
A Design HSE Case was not required for this project, due to its
Design HSE Case and Operation HSE
a. a.11 Case, (if applicable).
limited scope. Refer existing Fahud Operations HSE Case NA NA NA NA NA
Document Number MSE-OC-F
The HFE Screening was carried out during BfD Phase and
Human Factor Engineering (HFE) FAH-38-104322-HX-6854-00001-0000-
a. a.13 issues identification and management.
HFE/VA Workshop during FEED+DD Phase.
NOF0000F0858-01
PDS13 TSE AFD PDS1
For more details refer HFE Report .
Material Selection Report is prepared Material Selection Report was not produced under this project
a. a.15 and Approved. scope due its limited scope.
NA PDEC12 MCI NA PDEC12
Relief, Flare and Vent Study and action Relief, Flare and Vent Study was not required due to the nature of
a. a.16 closeout. this project.
NA PDEP17 PROCESS NA PDEP17
Hazardous Area Classification
a. a.17 Drawings / Schedule prepared. Ignition No Hazardous area in Project Scope NA PDS13 TSE AFC PDS1
source control are in place.
Escape evacuation and rescue The Escape Route, Safety & Fire Fighting Equipment layout
a. a.21.1 analysis and action closeout (if drawings were not required, due to no additional safety equipment NA NA NA NA NA
applicable) or changes in existing escape routes due to this project scope.
Facility Emergency Response Plan in The existing facility ERP was not required to be updated under
a. a.22 place this project and the existing ERP will be followed.
NA NA NA NA NA
HAZOP Review was carried out for project scope. The team
composition was in line with the standard requirement and project
Fit for purpose (safe) Isolation HAZOP Study Report: FAH-38-104322-PX-6875-
scope. The applied methodology was in line with PR- 1696 [Ref.
a. a.23 requirement are
10].
00001-0000-NOF0000F0858-01 PDEP17 PROCESS AFD PDEP17
designed/incorporated. No HAZOP closeout as there is no HAZOP action
No actions were raised. For more details refer HAZOP Study
Report.
and process safety requirements have Project has applied DCAF and PCAP is PCAP is NA however Document Distribution Matrix (DDM) FAH-05-104322-JA-6610-00001-0000-
b. been completed and assured by b.3 PDAF9 PROJECTS AFD PDAF
signed and followed prepared for this project NOF0000F0858-02
qualified and competent people.
All deliverables (Control points)
identified in PCAP are generated by PCAP is NA however Document Distribution Matrix (DDM) FAH-05-104322-JA-6610-00001-0000-
b. b.4 PDAF9 PROJECTS AFD PDAF
project team and approved by relevant prepared for this project NOF0000F0858-02
discipline Technical Authority (TA)
Construction & Mechanical completion Approved CMS systemization Procedure is in place FAH-38-104322-BA-5711-00001-0000-
f. f.1 PDUIN4 CSU APP PDUIN4
requirements are completed. CCMS/Zenator AND ITRs A&B verified through Zenator system NOF0000F0858-02
Medical and first aid facilities are Medical team of Fahud is avalable to support Fahud field and no
f. f.13 NA NA NA NA NA
available. extra services been identified based on this project scope.
Appropriate Personal Protection
Equipment (PPE)/Life-saving Existing equipments in Fahud to be used and no additional
f. f.14 NA NA NA NA NA
Equipment are available and relevant equipments been identifed for this project.
staffs are trained.
Personnel in Safety Critical roles have SCE role requirements been met by Fahud operators/technician
f. f.15.3 NA NA NA NA NA
passed fit for work. where no additional SCE role introduced by this project.
f.
been prepared and are available - f.16.4
Well program and change
NA
N
NA NA NA NA NA
Procedures are in place to operate the management documentation. A
f.
safety critical elements within their f.16.5 Updated well risk register. NA
N
NA NA NA NA NA
operational limits. A
f.
(iii) A management system is in place f.16.6 Wells As-built validated. NA
N
NA NA NA NA NA
for the operation of the facility, A
f.
operational controls, competency, f.16.7 Wells operating envelops defined. NA NA NA NA NA NA
maintenance and management of
f.
change. An audit and review program f.16.8 Wells operational status known and
NA
N
NA NA NA NA NA
for that management system is in place. documented. A
###
Remarks / Comments
Date:
--------------------------------
Audit Sponser
Date:
Information Assurance Certificate
PROJECT TITLE : F19099 / 61022 - Fahud Water System Injection Upgrade DATE
RAMZ PROJECT : NOF0000F0858
Notes: Every deliverable identified in the DDR/DCR shall be available and in their latest status; select status from pick list based on the following definitions: Available - Final: As-Built, Final or Latest Revision; In-Progress: under development, not finalized (provide comment); Not Applicable: Not required for development in project;
No Available: could not be located any where (provide reason)
2 Available
DCR/DDR in place with links to DDR deliverables (Assai report template could be configured to produce report)
3 Critical Documentation (Tier1 and Tier2) listed in DDR/ DCR are controlled Available
4 All project information handover deliverables listed in project DDR/ DCR are controlled Available
Link to project workspace with all project management deliverables listed in DDR/DCR are ready for archiving and archive location available
5 Available
Notes: ONGING