Professional Documents
Culture Documents
Work Plan M.gate
Work Plan M.gate
Years→ 2023
Months→ April May June July August Sept Oct
Weeks→ 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1###2 3 4 1
Civil Works
Mobilazation of manpower
Labour camp installation
Mobilization of Equipments at site
Surveying and main building layout
Foundation trenching
Soling ,PCC & RRM wall
RCC Work
Bricks walls & acessories fitting works
Steel work
Plumbing work
Roofing (CGI and Roofing trusses)
Finishing works
Site Development
Electrical Works
Laying of HDPE pipes
Laying of cables & fixing of switch socket with outlets
Wiring of light point, power points
Installation of fittings lamps and accessories
Installation of distribution board including
MCCB,MCBS,RCBOS etc.
Installation of main control panel board & energy meter
Laying of main cables & earthing including connection
Testing & commissioning
Handing/Taking over site
Years→
Months→ April
Weeks→ 10 11 12 13 14 15 16 17 18 19 20 21 22 23 23
Details of works↓
Civil Works
Mobilazation of manpower
Labour camp installation
Mobilization of Equipments at
site
Foundation work
Ground Floor
1st Floor
2nd Floor
3rd Floor
Finishing works
Site Development/Retaining
wall
Electrical Works
Installation of distribution
board including
MCCB,MCBS,RCBOS etc.
2023
May
25 26 27 28 29 1###2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
ction of Main gate at Gyalsung project, Tareythang.
on time period JAN 2015-DEC 2016