Professional Documents
Culture Documents
F Construction Material
F Construction Material
F Construction Material
Engineering Faculty
Civil Department
Submit:
1402 /7/18
Table of contents
➢ Introduction
➢ Objectives Of Planning
➢ Stages Of Planning
➢ Scheduling Procedures
➢ Scheduling Technique Use
➢ Site Clearance
➢ Job Layout
➢ Temporary Sheds
7/24/2023 2
INTRODUCTION
➢ Planning is the process of devising of a scheme for doing, making or arranging a project or
programme before the commencement of a work.
➢ In any project the sequence through which the project is to develop should be decided. The
requirement is met in a systematic manner by scheduling or programming. Scheduling considers
the main construction activity and also supporting elements such as labor, material, equipment
and expenditure. All the activities consume resources of three kinds, viz., time, labor and
material
7/24/2023 3
OBJECTIVES OF PLANNING
➢ The main objective of any planning, particularly construction planning, is to execute the project
most economically both in terms of money and time. Elective planning includes the following
factors:
7/24/2023 4
STAGES OF PLANNNING
➢ During the planning of a construction project, the entire project is phased out identifying
the sequence of construction. Secondly each phase is divided for operation into a number
of jobs or units of construction. Different stages of planning are as follows:
1. Job planning
2. Technical planning
3. Contract planning
7/24/2023 5
STAGES OF PLANNNING (con…)
➢ Job Planning
Each job or unit of construction has to be further planned with respect to the following:
7/24/2023 6
STAGES OF PLANNNING (con…)
3. Planning of Resources
Resources of a construction project comprises of the following:
7/24/2023 7
STAGES OF PLANNNING (con…)
➢ Technical Planning
Technical planning is done by engineer or concerned authority for economical execution of the
construction project. It starts after the administrative approval of the work is obtained for technical
sanction. Technical planning is carried out in order to satisfy the following objects:
7/24/2023 8
STAGES OF PLANNNING (con…)
Contract Planning
Contract planning is divided into the following two categories:
1. Pre-tender planning
2. Post-tender planning
1. Pre-tender Planning
Planning required for the time of inviting of tenders up to the receipt of the same is termed as pre-tender
planning. It consists of the following works:
7/24/2023 9
STAGES OF PLANNNING (con…)
2. Post-tender Planning
In post-tender planning the following aspects are considered irrespective of the work done by contractor or
departmentally:
7/24/2023 10
STAGES OF PLANNNING (con…)
(i) Decision of network or bar chart makes the contractor to know more about the job.
(ii) With proper planning, the financial burden will be lessened for the contractor.
(iii) By proper programming, weekly supply of Laboure can be attended.
(iv)Programming provides a standard against which actual work can be measured.
2. Limitations
SCHEDULING PROCEDURES
• Construction Schedule
• Laboure Schedule
• Material Schedule
• Equipment Schedule
• Expenditure Schedule
7/24/2023 12
SCHEDULING TECHNIQ UES
➢ In any project the sequence through which the project is to develop should be decided. The requirement
is met in a systematic manner by scheduling techniques. The project scheduling techniques are concerned
with the resource time. One of the objectives of project management is to optimize the use of resources.
Scheduling techniques offer solutions to optimization of project time.
➢ Technical scheduling can be done by different methods depending on the size of the project.
The methods used are as follows:
1. Bar charts
2. Milestone charts
3. Network analysis
7/24/2023 13
SITE CLEARANCE
➢ Clearing of vegetation and trees is usually necessary before undertaking any construction operation. It is
very difficult to handle equipment and materials in the presence of trees, bushes, grass and weeds.
➢ Type of vegetation, condition of soil and topography, quantity of clearance needed, and the purpose for
which cleaning is done are the factors to be considered in planning the sequence of operation.
The factors are:
7/24/2023 14
SCHEDULING TECHNIQ UES(con…)
➢ Bar Charts
➢ A bar chart consists of two coordinate axes, viz., one representing the time elapsed and the other representing
the job or activities to be performed. The jobs are represented in the form of bars as shown in Fig. 31.1
7/24/2023 15
16
--------------------------------------------------------
--------------------------------------------------------
40
--------------------------------------------------------
Activity - B
-------------------------------------------------------- 30
The jobs are represented in the form of bars as shown in Fig.
--------------------------------------------------------
Activity - D
SCHEDULING TECHNIQ UES(con…)
-------------------------------------------------------
20
-------------------------------------------------------
Activity - C
Activity - E
Activity - A
-------------------------------------------------------
10
-------------------------------------------------------
0
Activity
➢ Bar Charts
7/24/2023
JOB LAYOUT
➢ Overall economy of a project can be achieved by a thorough coordination in planning of services and the
construction plant. Such coordinated work will frequently lead to modification in plant facilities and in
layout of services.
Thus layout of a construction project camp is governed by the following factors:
7/24/2023 17
TEMPORARY SHEDS
➢ As explained in job layout different facilities have to be provided. Since the project has to be completed in
a short period facilities can not be made permanently. Thus only temporary sheds made out of sheets are
provided with adequate safety.
➢ Facilities like drinking water, sleeping areas, dwelling areas, 0ffice, store and all are to be provided in
temporary sheds. However, depending on the period of construction the sheds are made big or small with
additional strength and durability.
➢ The sheds should withstand all weather conditions and unexpected storm on heavy rain. No water
logging should be allowed.
7/24/2023 18
Thank you !