Method Statement - NCR 01

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

METHOD STATEMENT FOR ANCHORAGE REBAR RECTIFICATION WORKS (NCR 02)

ITEM DESCRIPTION MATERIALS/WORKERS REMARKS

1. PREPARATION FOR REBAR PLACEMENT INTO COLUMN 1. Drilling Machine


2. 1 General Worker
- As the column already been concreted, we need to drill a
hole to insert the rebar into the column
- For the height of the beam is 600mm, we need another
400mm depth to insert the rebar.
- As for this purpose, we drill a hole approximately 400mm
Figure 1 ; Drill Bit measured before drilling works
depth using drilling machine (The length of Drill bit is
measured; approximately 400mm).

Figure 2 ; Drilling process completed with full depth

2. REBAR PLACEMENT INTO COLUMN

- After the hole are ready, we insert the rebar into the hole.
- For this purpose, we use anchoring adhesive agent to secure
1. SIKA ANCHORFIX – universal
the rebar into the drilled concrete structure.
anchorage adhesive agent
- Following the supplier instruction, the anchoring adhesive
2. 2 General Worker
agent will be injected to fill up the hole before placing the
rebar into it. Figure 3 ; Measuring and testing before secure rebar
- with anchoring agent into the hole
Figure 4 ; SIKA Anchorfix Anchorage Adhesive Agent

3. CONCRETING WORKS

- Concreting work shall commence after the rebar are


secured into the place. 1. SIKA Latex 118 bonding agent
- However, the concrete bonding agent shall be use to 2. 4 General Worker
maintain/improve the structural strength after the drilling 3. Vibrator
/hacking process on the existing concrete surface.
- The Concrete bonding agent to be used is SIKA LATEX 118
Bonding Agent.
- The bonding agent will be poured onto the disturbed Figure 5 ; SIKA LATEX 118 concrete bonding Agent
surface before pouring the concrete.

4. CURING PERIOD
- After concreting works, the curing period will begin for 7
days