Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

Hydrometallurgy 149 (2014) 12–22

Contents lists available at ScienceDirect

Hydrometallurgy
journal homepage: www.elsevier.com/locate/hydromet

Water balance analysis and wastewater recycling investigation in


electrolytic manganese industry of China — A case study
Fuyuan Xu a, Linhua Jiang a,⁎, Zhigang Dan a,⁎, Xiaojuan Gao a, Ning Duan a, Guimei Han a, Hong Zhu b
a
Technology Center for Heavy Metal Cleaner Production Engineerings, Chinese Research Academy of Environmental Sciences, 8 Dayangfang BeiYuan Road, Beijing 100012, China
b
Department of Fundamental Science, Beijing University of Agriculture, Beijing 102206, China

a r t i c l e i n f o a b s t r a c t

Article history: A water balance investigation was performed for a representative electrolytic manganese metal (EMM) enter-
Received 26 July 2013 prise to study the details of water consumption and generation in the production process. A new integrated
Received in revised form 2 April 2014 wastewater treatment approach was put forward to recover useful chemicals from the process wastewater,
Accepted 12 May 2014
which contained high concentrations of Mn2+, Cr(VI), Cr3+, and NH+ 4 . Cr(VI) was recovered from the wastewater
Available online 16 May 2014
by ion exchange techniques and reused as EMM passivant. The remaining wastewater containing Mn2+ and NH+ 4

Keywords:
was returned to the leaching section before the impurity removal procedure to prepare electrolytes. Complete
Water balance wastewater recycling was achieved after water balance regulation and optimization. Final demonstration line re-
Electrolytic manganese metal (EMM) sults proved that the proposed process is feasible and exhibits significant advantages of better treatment effects,
Wastewater lower costs and lower environmental impact compared to the traditional reduction–neutralization–sedimentation
Water treatment treatment method. With the adoption of the proposed approach, solid waste disposal cost and the required area for
Recycling the landfill yard were decreased by 80%. Operating costs for wastewater treatment were lowered by 85%. Around
4.8 kg/t EMM of Mn2+, 5.2 kg/t EMM of NH+ 4 and 0.24 kg/t EMM of Cr(VI) were recovered. The recycled wastewater
proportion was increased from 6.2% to 100.0%. 1.168 m3/t EMM of fresh water was saved and the equivalent
amount of discharging wastewater was reduced to the environment.
© 2014 Published by Elsevier B.V.

1. Introduction the reduced EMM demand and increased production overcapacity.


The capacity and output were found to decrease for the first time in
Metallic manganese is an important alloy element (Hagelstein, 2012. The good news is that export tax has been canceled since January
2009), which is widely used to prepare stainless steels (Zhu and 2013, which can stimulate the market to a certain extent and is helpful
Zhang, 1997) and other alloys with Ni (Kelly et al., 2003; Yang et al., for the EMM industry (Liu et al., 2007; Tan, 2013; Tan and Mei, 2005).
2004), Zn (Díaz-Arista et al., 2009), Te (Galvanauskaite et al., 2011; With the increasing development of the EMM industry, water
Sharma et al., 2004) and Sn (Gong and Zangari, 2003). It is mainly pro- pollution has been a serious problem and a great challenge for the
duced by electrolysis method (Sulcius et al., 2013; Sun et al., 2011). EMM enterprises. It is reported that, to produce 1 t of EMM, approxi-
Since the first EMM production plant was founded in 1956, the Chinese mately 1–3 t of wastewater is discharged into the environment (Duan
EMM industry has developed at a fast rate. China has become the largest et al., 2010). The average annual wastewater amount in the past
EMM producing country, accounting for over 98% of the world's overall 13 years was estimated to be 1.55 million t. High concentrations of
EMM production capability and output. Mn2+ (2000 mg/L), Cr(VI) (300 mg/L), and NH3–N (2800 mg/L) ions
Fig. 1 summarizes detailed data of China's EMM industry in the past (before treatment) were contained in the wastewater (Duan et al.,
13 years. It can be seen that the capacity and output increased year 2011). It's well known that Cr(VI) is extremely carcinogenic and toxic.
by year until 2012. Compared with the capacity and output in 2000, Cr(VI) may cause death to animals and humans (Zayed and Terry,
corresponding values in 2011 were increased 16.1 and 11.0 fold respec- 2003) while Cr3+ is somewhat less toxic and even essential for mam-
tively. However, adverse factors including increased production costs, mals (Pantsar-Kallio and Manninen, 1997; Serkan and Mustafa, 2011).
export tax implementation, and global demand depression all led to Excessive Mn accumulation in human bodies can lead to brain and
respiratory tract damage. Symptoms of manganese poisoning are hallu-
cinations, forgetfulness and nerve damage. Manganese can also cause
⁎ Corresponding authors. Tel.: +86 10 84916046; fax: +86 10 8493 2378. Parkinson's disease, lung embolism and bronchitis. When men are ex-
E-mail addresses: jianglinhuann@163.com (L. Jiang), dash_2001@163.com (Z. Dan). posed to manganese for a longer period of time they may become

http://dx.doi.org/10.1016/j.hydromet.2014.05.002
0304-386X/© 2014 Published by Elsevier B.V.
F. Xu et al. / Hydrometallurgy 149 (2014) 12–22 13

Fig. 1. Chinese EMM production capacity, output, and exportation from 2000 to 2012.

impotent. A syndrome that is caused by manganese has symptoms such further treatment due to higher treatment cost and poor treating effi-
as schizophrenia, dullness, weak muscles, headaches and insomnia (Lee ciency for most EMM enterprises. All those generated solid waste and
et al., 2009; Tobiason et al., 2008). Ammonia nitrogen contributes to wastewater greatly polluted the surrounding environment, and led to
accelerated eutrophication of lakes and rivers, dissolved oxygen deple- crisis for human being's health and ecological environment (Table 1).
tion and fish toxicity in receiving water (Huang et al., 2010). Currently, due to the frequent pollution incidents, the Chinese gov-
Traditionally, the wastewater is treated by the end-of-pipe processes ernment has taken some important measures to effectively control
of reduction–neutralization–sedimentation with ferrous sulfate (or and treat the current pollution such as increasing the management
scrap iron) and lime slurry (Fig. 2) (Duan et al., 2010), so that Cr(VI) and supervision, application of stricter discharge standards and operat-
was reduced to Cr3+ and then co-precipitated with Mn2+ to form resi- ing protocols as well as closure of non-conforming operations of the pol-
dues that need to be disposed. Due to the larger solubility product of lutant emission status for all the related enterprises. Severe financial
Mn(OH)2 (2.0 × 10−13) (Liu et al., 2011), the wastewater pH must be punishment and strict suspending operations for rectifying and improv-
controlled above 9.67 to make sure that Mn2+ can be thermodynami- ing have been carried out to solve the pollution. As the stricter policy
cally deposited and its effluent concentration decreases below 2 mg/L, published, most of the EMM production enterprises can't meet the
which is the level II standard of the “Integrated Wastewater Discharge requirement. Extra funds were invested to further deal with the waste-
Standard of China” (GB 8978-1996). Large amounts of alkali were re- water, being a heavy burden for enterprises and hindering their devel-
quired to fully deposit Mn2+, leading to higher operating cost. Besides, opment. To improve the current situation, the traditional wastewater
Mn and Cr were both discharged as solid waste, leading to severe treatment process must be changed. More challenging work is needed
resource waste and amounts of dangerous solid residues generated. It to be done especially in reducing water consumption, controlling the
should also be pointed out that the NH+ 4 -containing wastewater after process and recovering chemicals and manganese from the discharged
removal of Cr and Mn was always directly discharged without any wastewater. New methods and technology were required urgently. To

Fig. 2. Wastewater treatment process in the EMM production process.


14 F. Xu et al. / Hydrometallurgy 149 (2014) 12–22

Table 1
Discharge standards of EMM process wastewater (unit: mg/L, except pH).

Pollutants Traditional process New process Wastewater discharge


standards of China

pH 6–9 No wastewater discharged 6–9


Cr(VI) ≤0.5 ≤0.5
Cr3+ ≤1.0 ≤1.0
Mn2+ ≤2 ≤2
NH3–N 500–1230 ≤25

achieve the above objectives, it was essential to find out how the water USA). Samples were all filtered through 0.45 μm membrane before
was used in the whole EMM production process, and master the corre- analysis.
sponding water quality and quantity information. Systematic investiga-
tion and analysis of waste generation during the whole process of EMM 2.4. Demonstration line of resource recovery and wastewater recycling in
production were required, which includes the identification of pollut- Taifeng
ants, recognition of waste sources and determination of waste discharge
routes. Note that different EMM enterprises in China mostly adopted A demonstration line was established in Taifeng to achieve resource
similar process using MnCO3 ore as raw material (Zhang and Cheng, recovery and wastewater recycling. The process flowchart was shown
2007). One representative EMM enterprise of Taifeng Mining Co. Ltd. in Fig. 3.
(Taifeng) was firstly chosen as the investigation subject to examine Six fixed-bed up-flow columns (1.0 m in diameter, 1.2 m in bed
the status of the EMM industries, including production units and depth) were packed with anion exchange resin D301R beads. Four col-
operations of the manufacturing processes, the water balance profile, umns were constantly running to treat the generated Cr-containing
and the wastewater treatment situation. This study will present details wastewater with flow rate of 2.6 m3/h, superficial velocity of 3.3 m/h,
of the freshwater consumption and wastewater generation, and also and regeneration period of 7–10 days. The rest two columns were
presents extensive discussions and proposals for a cleaner and rational used for backup purposes. The running process can be described as
wastewater treatment process. the following steps: (1) Neutralization–flocculation–settling: it was
critical to control the neutralization pH in the range of 7.5–8.0 to ensure
2. Materials and methods the full deposition removal of Cr3 + and avoid the co-deposition loss
of Mn2+. Polyacrylamide (PAM) was used as coagulant aids to improve
2.1. Materials the forming and settling of flocs. No other Fe-containing or Al-
containing coagulants were additionally added, because the metallic
NaOH (N99%), H2SO4 (N 98%), and polyacrylamide (PAM, molecular ions contained in the wastewater can easily form flocs with the aids of
weight of 3 × 106), all chemicals used in the demonstration line, were PAM. (2) pH adjustment: the pH of the wastewater after Cr3+ removal
technical reagent grade. Weakly basic anion exchange resin D301R was (effluent of the sedimentation tank) was adjusted back to 3–4, which
provided by Nankai University to recover Cr(VI)(Cr2O2− 7 ) (activated was beneficial to the adsorption of Cr(VI) by the ion exchanging resin.
before use). All standard solutions (Mn2+, NH+ 4 , Zn
2+
, As2+, Pb2+, (3) Two stage filtration: then the wastewater underwent two-stage
2+ 2+ 2+ 2+
Cd , Co , Ni , Cu , and Se(IV)) used for analysis were guaranteed filtration by sand filter and precision filter to further remove solid
reagent level. suspension. (4) Ion exchange: finally the wastewater was pumped
into the ion exchangers to recover Cr(VI). The final effluent from the
2.2. Water amount determination ion exchangers which contained Mn2+ and NH+ 4 was returned to the
leaching section in the electrolyte preparation process. (5) Resin regener-
Quantities of water used within the EMM production process were ation: the saturated resin absorbed Cr(VI) was regenerated by 1 mol/L
determined mostly by water meters installed in pipelines and partially NaOH. The generated concentrated Cr(VI) solution was determined to
by volume measurement. The water volume contained in solid material be over 10 g/L, which can meet with the required concentration of
was calculated by the solid amounts and its water ratio. The water ratio passivant. However, the regeneration solution needed to be neutralized
in solid material (manganese ore, manganese residue, sulfide slag, before being used as passivant. The diluted regeneration solution can be
anode mud, filter cake) was determined by a weighing method. Water used in the next regeneration process to further enrich more amounts
volume in solution was corrected by density difference of solvent and of Cr(VI).
solution. Water balance investigation was performed from November,
2012 to January, 2013 for more than 2 months. For the purposes of 3. Results and discussion
uniformity, all the data acquired were divided by the total production
of EMM. 3.1. Introduction of Taifeng and its EMM production process

2.3. Pollutant analysis Taifeng is a typical representative of the numerous EMM enterprises
with advanced technology and management in China. It is located in the
Mn2+ was analyzed by the periodate method (GB 11906-89) and manganese ore rich Songtao Miao Autonomous County of Guizhou
ammonia nitrogen by Nessler method (GB 7479-87) according to Province. The enterprise possesses its private mines with 4.8 million t
China National Methods. Cr(VI) was determined by spectrophotometry of manganese carbonate ore reserves. The average content of manga-
using diphenylcarbazide method (APHA, 1995) after suitable dilutions. nese reached up to 20.65%. Current Mn content in the used ores was
The concentration of Cr3+ was calculated from the difference between around 14–15% during the investigation period. Taifeng has three
total Cr and Cr(VI) concentrations. Total Cr was analyzed by oxidizing EMM production workshops and six production lines (Fig. 4) with
the chromium with KMnO4, followed by determination of Cr(VI). PH 18,000 t of annual EMM output.
was determined by pH meter. Ion concentrations (Zn2+, As2 +, Pb2 +, Fig. 5 shows the EMM production process of Taifeng, using manga-
Cd2+, Fe2+/Fe3+, Co2+, Ni2+, Cu2+, and Se(IV)) in the treated waste- nese carbonate ore as raw material. The process is described briefly as
water were determined by inductively coupled plasma/atomic emission follows: (1) the leaching step: Sulfuric acid together with the recycled
spectroscopy (ICP–AES, IRIS Intrepid, Thermo Electron Corporation, anolyte were added to the crushed and milled ores to leach manganese
F. Xu et al. / Hydrometallurgy 149 (2014) 12–22 15

Fig. 3. Wastewater treatment process by resource recovery and recycling.

ions. The MnSO4-containing slurry was obtained; (2) Fe2+ oxidation electrolyte with pH 6.5 was constantly pumped into electrolytic cells for
and removal: Fe2 + in the slurry was oxidized to Fe3 + by H2O2 and electrolysis and manganese is deposited on the cathode plates as prod-
further deposited into the sediments after neutralization by ammonia, ucts. The anolyte was recycled to the leaching section for reuse;
followed by solid-solution separation by pressure filter; (3) Heavy (5) Post-electrolysis: the cathode plates with EMM products deposited
metal sulfidation and removal: Heavy metal ions were sulfidized by so- were pulled out of the cells after 24 h electrolysis. Final products of
dium dimethyl dithiocarbamate (SDD) and removed by pressure filter. EMM were obtained after passivating, washing, drying, and stripping.
Finally, the electrolyte was pumped into a tank for use after adding elec- Bare plates after stripping were returned to the cell for repeated use
trolytic additives of SeO2 and (NH4)2SO3; (4) Electrolysis: The prepared after consecutive treatment of finishing pickling/polishing and dipping
of Na2SiO3.

3.2. Water balance analysis

3.2.1. Water balance analysis in the whole EMM process


The water balance obtained is shown in Fig. 6. It can be seen that two
subsystem balances were contained in the whole water balance of the
EMM production process: the electrolyte balance and the wastewater
balance. The electrolyte balance was mainly related to the preparation
and application of the electrolyte, and the wastewater balance con-
cerned generation and treatment of the wastewater.
In order to analyze the water balance clearly, all the water sites
were classified into several different categories. Fig. 6 was simplified
and redrawn in Fig. 7. The category subdivisions were shown
in Table 2. It can be seen from Fig. 6 and Table 1 that overall 4.994 m3
of water was consumed to produce 1 t of EMM products. The inlet
and outlet water both included four major categories. The largest two
proportions of the inlet water were used for making up solutions
(47.40%, v/v) and cleaning (34.84%, v/v). The corresponding water
Fig. 4. One EMM production line of Taifeng. amounts were 2.367 m3/t EMM and 1.740 m3/t EMM, respectively.
16 F. Xu et al. / Hydrometallurgy 149 (2014) 12–22

Fig. 5. The EMM production process in Taifeng.

Fig. 6. Water balance of the Taifeng EMM production process (m3/t EMM).
F. Xu et al. / Hydrometallurgy 149 (2014) 12–22 17

4.994(outlet)
Evaperated Electrolyzed Wastewater Water
water water in solid waste

0.618 0.596 1.645 2.135

EMM production process

2.367 1.74 0.377 0.51

Water for Cleaning water Water with raw Newly added water
making up solutions material

4.994(inlet)

Fig. 7. Simplified water balance of Taifeng.

Besides, 0.510 m3/t EMM (10.21%, v/v) of water was newly added into 3.2.2. Electrolyte balance analysis
the electrolyte preparation process to replenish the electrolyte loss, The electrolyte balance is one subsystem balance that is extremely
and raw material of manganese ore and H2SO4 also introduced 0.377 critical for steady electrolysis. The total electrolyte amount variation
m3/t EMM (7.55%, v/v) of water into the whole system. 4.994 m3/t must be kept in a reasonable range to maintain the normal electrolysis
EMM of water flowed out of the whole system, including 42.75% and obtain a higher current efficiency and lower consumption. The
(2.135 m3/t EMM) of water discharged with the solid wastes of manga- detailed constitutes of the inlet and outlet of the electrolyte system
nese residue, sulfide flag, anode mud, and filter cake, 32.94% of water were shown in Fig. 8.
(1.645 m3/t EMM) in the form of wastewater, 12.37% (0.618 m3/t It can be calculated from Fig. 8 that the total water amount flowing in
EMM) of water lost via evaporation, and 11.93% (0.596 m3/t EMM) of and out of the electrolyte system every day reached up to 3.253 m3/t
water decomposed by electrolysis. EMM. Around 66.26% (2.161 m3/t EMM) of the inlet water was used

Table 2
Subdivision of the inlet and outlet water of the EMM production process in Taifeng.

Water types Water category Water site Water amount (m3/t EMM) Proportion (%)

Inlet water Water introduced by raw material Mn ore 0.023 0.46


H2O2 0.123 2.46
H2SO4 0.354 7.09
Sum1 0.377 7.55
Water for making up solutions NH3·H2O during the electrolyte preparation process 1.017 20.36
SeO2 during the electrolyte preparation process 0.060 0.20
NH3·H2O during the electrolysis process 0.948 18.98
SeO2 during the electrolysis process 0.010 0.20
(NH4)2SO3 0.023 0.46
Passivant 0.048 0.96
Polishing solution 0.010 0.20
Pickling solution 0.029 0.58
Na2SiO3 0.096 1.92
SDD 0.003 0.06
Sum2 2.367 47.40
Cleaning water Diaphragm cloth washing 0.010 0.20
Electrolysis workshop ground flushing 0.115 2.30
Plate washing 1.538 30.80
Copper bar flushing 0.010 0.20
Cell flushing 0.067 1.34
Sum3 1.740 34.84
Replenishing water Pressure filter-pump cooling water 0.510 10.21
Sum4 0.510 10.21
Outlet water Evaporated water Evaporated water 0.618 12.37
Sum1 0.618 12.37
Electrolyzed water Electrolyzed water 0.596 11.93
Sum2 0.596 11.93
Wastewater Wastewater 1.645 32.94
Sum3 1.645 32.94
Water in solid waste Manganese residue and sulfidation slag 1.962 39.29
Anode mud 0.096 1.92
Filter cake 0.077 1.54
Sum4 2.135 42.75
Overall Sum 4.994 100.00
18 F. Xu et al. / Hydrometallurgy 149 (2014) 12–22

(a)

(b)

Fig. 8. The constitutes of the (a) inlet and (b) outlet water of the electrolyte balance (NH3-A represents water for making up ammonium solution in the electrolyte preparation process.
NH3-B represents water for making up ammonium solution in the electrolysis process).

for making up solutions mainly including 1.017 m3/t EMM of ammoni- purity and quality. Using less water for each step of the process will re-
um solution during the electrolyte preparation process, and 0.948 m3/t sult in less generation of wastewater but there is a threat of reducing the
EMM during the electrolysis process. Besides, 0.625 m3/t EMM of inlet quality of the EMM product. The wastewater constitutes were depicted
water was added to replenish the electrolyte loss. Amongst the added in Fig. 9. The total amount of wastewater reached up to 1.856 m3/t EMM,
water, 0.510 m3/t EMM was from the filter pump cooling water and 82.87% (1.538 m3/t EMM) of which was generated from the plate wash-
0.115 m3/t EMM was from the recycled wastewater (Fig. 8(a)). The ing water. The other parts contributed to only 17.13% (0.318 m3/t EMM)
outlet water of the electrolyte system was mainly discharged in three of proportion (Fig. 9(a)). It is seen from Fig. 9(b) that 5.17% (0.096 m3/t
different routes including 62.68% (2.039 m3/t EMM) of water by solid EMM) of the wastewater after being treated was discharged with the fil-
waste emission, 19.00% (0.618 m3/t EMM) of water lost via evaporation, ter cake, and only 6.20% (0.115 m3/t EMM) was recycled to the former
and 18.22% (0.596 m3/t EMM) of water decomposed by electrolysis. It electrolyte preparation process. The rest 88.63% (1.645 m3/t EMM)
is indicated that the solid residue took away the largest proportion of was directly discharged into the environment.
water including 1.962 m3/t EMM of water in the residues (manganese
residue and sulfidation slag) and 0.077 m3/t EMM of water in anode
mud. 3.3. EMM production process wastewater treatment

3.3.1. Identification and source tracing of pollutants in the wastewater


3.2.3. Wastewater balance analysis The major pollutants contained in the generated wastewater of the
The wastewater balance was the other subsystem balance in the EMM production process were identified to be Mn2 +, Cr(VI), Cr3 +,
whole EMM production process. The total amount of the generated and NH+ 4 . Tracing back to the pollutant source, it was found out that
wastewater was dependent on the amount of water fed to each unit Mn2+ was introduced by the carried concentrated electrolyte on plates
operation within the production process. The inlet water was mainly (Mn2+: 30–45 g/L) and oxidation dissolution of EMM by K2Cr2O7 in the
used in the plate treatment process for passivating, cleaning, pickling, passivation tank and the pickling tank. The concentrations of Mn2+ in
polishing, etc. in the post-electrolysis to assure the final production the passivant and the pickling solution were determined to be 3.0–
F. Xu et al. / Hydrometallurgy 149 (2014) 12–22 19

0.01, 0.54%
0.029, 1.56%
(a) 0.01, 0.54%
0.096, 5.17% 0.115, 6.20%
(b) 0.115, 6.20% 0.096, 5.17%

0.048, 2.59%
0.01, 0.54%

1.538, 82.87% 1.645, 88.63%

diaghram cloth washing workshop ground flushing plate washing


copper bar washing passivation solution polishing solution filter cake discharged recycled
pickling solution Na2SiO3

Fig. 9. Water amount and proportion of the (a) inlet and (b) outlet water of the wastewater balance system.

4.5 g/L and 16.0–20.0 g/L after one day use. NH+
4 were mainly generated improved; ④ recovering Cr(VI) from solid waste reduces the toxicity
from the carried electrolyte with 90–120 g/L of (NH4)2SO4 and the dis- of wastes that are disposed. The total waste that must be disposed is
solution of the (NH4)2SO4 crystalline on plates during washing plate reduced and is less toxic. However, two key points must be considered.
process. Chromium was mainly introduced from the passivant and the ① Whether the quality of the wastewater can meet the requirements of
pickling solution which were made up of 10–30 g/L of K2Cr2O7. The the consumed water? ② Whether all the wastewater can be completely
whole tank of Cr-containing solution was dumped into the wastewater reused by the whole EMM production process without breaking the
as a discard. Cr3+ was mainly generated due to the reduction of K2Cr2O7 water balance? ③ Whether the performance of the ion exchange pro-
by EMM during passivation and pickling process. Results showed that cess can be sustained over extended periods of continuous operation.
the concentrations of Cr3 + in the passivant and the pickling solution
were 5–50 mg/L and 2000–3000 mg/L, indicating that the pickling 3.3.3. Feasibility analysis of resource recovery and wastewater recycling
solution was the major source of Cr3+, because the pH in the pickling (1) Quality analysis of the treated wastewater.
solution was much lower, which was beneficial to K2Cr2O7 oxidation Once the treated wastewater was reused, quality to ensure
and Cr3+ generation. the electrolyte purity for production and avoid the influences of
impurities on the electrolytic efficiency. In considering the trace
3.3.2. New concept for EMM production process wastewater treatment amounts of impurities that could be contained in the treated
Previously, the wastewater was treated by traditional reduction– wastewater, it is recommended that the wastewater should
neutralization–sedimentation technology as introduced in Introduction be reused to water sites before the purifying process. If trace
section. The discharged wastewater still contained high concentrations amounts of impurities exist in the treated wastewater, they can
of NH3–N. With the tightening of government requirements on the still be further removed in the following impurity removal
NH3–N discharging standard of wastewater, the wastewater can't be steps of the electrolyte preparation. It should be pointed out
directly discharged. Considering that Mn2+ and NH+ 4 were the main that the wastewater cannot be directly reused to add into the
components of the electrolyte, and Cr(VI) was also useful for EMM pas- electrolyte during the electrolysis, flush the copper bar, or flush
sivating, we proposed a novel method to recover Cr(VI) from the EMM the cell, because the added wastewater can easily pollute the
production process wastewater and complete recycling the wastewater electrolyte and decrease the current efficiency.
which contained Mn2+ and NH+ 4 . The new wastewater treatment pro- (2) Quantity analysis of the treated wastewater.
cess is shown in Fig. 3. Previously, the amounts of waste water were too large to be
As shown in Fig. 3, Cr3 + was firstly removed by neutralization– completely recycled back to the production process. Of the
flocculation–sedimentation, and finally transferred to filter cake after 1.856 m3/t EMM generated wastewater, only 6.20% (0.115 m3/t
pressure filter of the precipitates. Cr(VI) was recovered by ion exchange EMM) was reused as the replenishing water. In order to achieve
techniques, then reused as passivant after regenerated by NaOH solu- complete recycling of the wastewater, the recycling waste-
tion from the saturated ion exchange resins. The remaining wastewater water amount should be smaller than the required amount of
after recovery of Cr(VI), which contained Mn2+, NH+ 2−
4 , and SO4 , can be replenishing water in the electrolyte preparation system. Water
directly recycled to prepare electrolyte. There are several advantages for usage must be regulated and optimized to change the water
the novel treatment process: ① Smaller amount of solid residue was distribution to match to the required quality. The following
generated, because Mn2+ and Cr(VI) were recovered as useful compo- proposals were suggested.
nent instead of transferring into the residue as wastes; ② lower operat- ① Reduce the generated wastewater amount by improving tech-
ing cost was invested due to lower dose of alkaline consumed. Expenses niques and strengthening management of water usage. Previous-
on solid waste disposal and areas for landfill yard were decreased ly, plates were washed by high pressure running water. Water
sharply; ③ pollutants can be recovered as useful resources, so that was commonly used for one time, then discharged directly as
water and reagent were saved. The resource utilization efficiency was wastewater, leading to huge volume of water consumed. The
20 F. Xu et al. / Hydrometallurgy 149 (2014) 12–22

washing capability of water has not been fully developed. Accu- water consumption can be further reduced by increasing
rate water controlling by water meter was proposed. In situ the making up concentration of ammonium solution. Water
water collection and multistage counter current washing tech- consumed for making up ammonium solution during the electro-
nique were also introduced, so that water can be used repeatedly lyte preparation can be decreased by 0.40 m3/t EMM if the
until poor rinsing effects were achieved. Then the water was concentration of ammonium is increased from 10% to 16%. Simi-
discharged as wastewater. In addition, a “hanging and dropping” larly, 0.135 m3/t EMM of water can be saved if the concentration
technique was adopted to recover the electrolyte and passivant of ammonium solution in the electrolysis is increased from 3.0%
to further reduce the carried wastewater. It's pointed out that to 3.5%. Therefore, 0.658 (=0.123 + 0.400 + 0.135) m3/t EMM
the water saving effects of technique improvement is heavily of inlet water was reduced totally, and equivalent amount of
dependent on stricter management and implementation. With replenishing water was required additionally to achieve water
the adoption of above technique, the whole generated wastewa- balance.
ter was deceased by 36.10% from 1.856 to 1.186 m3/t EMM. Based on the water regulation as discussed in ② and
② Completely use the treated water as the replenishing water of the ③, replenishing water was increased from 0.625 to 1.283
electrolyte system. The previous system adopted the cooling (= 0.625 + 0.658) m 3/t EMM. The required replenishing
water of pressure filter pump as part of the replenishing water water amount (1.283 m3/t EMM) was smaller than the entire
to compensate the electrolyte loss. Note that the concentration wastewater amount (1.186 m3/t EMM). Therefore, the wastewa-
of Mn2+ and NH+ 4 in the wastewater was much higher. It is pro- ter can be completely recycled as replenishing water. The
posed to substitute treated wastewater for the cooling water of improved water balance figure was shown in Fig. 10.
pressure filter pump to add into the electrolyte. Therefore, 0.51 (3) Long-term performance stability analysis.
m3/t EMM of treated wastewater was required. The long term performance of the process is a key aspect which
③ Increase the replenishing water amount by decreasing the determines the feasibility of the process. The influential factors
other part of inlet water in the electrolyte system. The addition include the following aspects.
of H2O2 can be substituted by introducing air to oxidize and ① The influent wastewater quality: the influent wastewater must
remove Fe. 0.123 m3/t EMM of inlet water can be saved. Inlet be well pretreated to remove the SS (suspension solid), organic

residue
1.962 Fresh water 0.116
0.023 0.060
Mn ore SeO2
1.283 Water used infiltration
0.354 Electrolyte Replenishing water 0.067
H2SO4 workshop
preparation 0.003
SDD
0.617 47.365 1.100
NH3.H2O Reculated anolyte

47.743
Electrolyte balance electrolyte
47.743
0.01 0.067
SeO2 Cell flushing and cleaning
0.813 0.596 electrolyzed water
NH3.H2O
0.023 electrolysis 47.365
(NH4)2SO3
0.077 0.618
Anode mud Evaporated water

Plate

0.010 0.096
Diagram cloth washing Na2SiO3
0.115
Workshop ground flushing 0.029
pickling solution
Post-electrolysis 0.010
Plate washing 0.868 Polishing solution
0.048
Copper bar washing 0.010 Passivation solution

1.186
Wastewater balance wastewater
1.186
Recycled treated
Wastewater wastewater 1.167
treatment

0.019
Filter cake

Fig. 10. Improved water balance after regulation and optimum.


F. Xu et al. / Hydrometallurgy 149 (2014) 12–22 21

Table 3
Impurity concentrations in the treated wastewater.

Sample no. Metallic ion concentration (mg/L)

Zn As Pb Cd Fe Co Ni Cu Se

1 0.149 0.014 0.062 0.006 0.012 0.066 1.245 1.322 0.839


2 0.183 0.018 0.099 0.009 0.036 0.116 2.099 1.940 1.355
3 0.323 0.020 0.111 0.010 0.023 0.134 2.427 2.155 1.540
4 0.273 0.020 0.094 0.008 0.002 0.120 2.327 1.726 1.257
5 0.105 0.023 0.087 0.009 0.071 0.144 2.977 1.786 1.430
Average 0.207 0.019 0.091 0.008 0.029 0.116 2.215 1.786 1.284

Table 4
Limited concentration of metallic ions in electrolyte.

Fig. 11. 100 m3/d demonstration line of resource recovery and wastewater recycling Metallic ion Zn As Pb Cd Fe Co Ni Cu Se
in Taifeng.
Concentration (mg/L) b3 b2.4 – – b1.0 b0.5 b1.0 b0.5 –

pollutants, and common cationic ions like Fe3+. Otherwise, the


resin will be covered and blocked by those pollutants. This will Mn2+, NH3–N, Cr(VI),and Cr3+ in raw wastewater was determined to
lead to the resin poison or inreversible deactivation. It should be in the range of 3200–4700 mg/L, 500–1230 mg/L, 25–250 mg/L,
also be pointed out that the Cr(VI) selectivity efficiency was and 5–50 mg/L. The final concentrations of Cr3+ and Cr(VI) in the efflu-
also influenced by the anion type and concentration. SO2− 4 was ent of the ion exchanger varied in the range of 0.0–0.03 mg/L and 0.0–
the major competitive anion which can decrease the Cr6+ selec- 0.8 mg/L. Impurity concentrations were determined in detail by ICP–
tivity especially at high concentrations. However, SO2−
4 only led AES to master the comprehensive impurity information contained in
to the decrease in Cr(VI) selectivity and adsorption capacity, the treated wastewater. Results were shown in Table 3.
but it wouldn't poison the resin or affect the long term stability It can be seen from Table 2 that Ni and Cu exceeded the limit value of
of the process. Because it can easily be exchanged by OH− during qualified electrolyte reported by other researchers (Table 4) (Zhang and
the generation process and wouldn't accumulate on the resins Shi, 2009; Zhang et al., 2004). Practical running results indicated that
during the long term operation. Other anions of NO− −
3 , Cl , etc. those impurities can be effectively removed in the purification proce-
had lower concentration and had little influences on the Cr(VI) dure. Qualified electrolytes were obtained when whole wastewater
selectivity and adsorption capacity. was recycled. The long-term performance was stable and satisfactory.
② The anion exchanging conditions: appropriate conditions includ- With the adoption of the proposed process, solid waste disposal cost
ing Cr concentration, solution pH, and temperature were also im- and the required area for landfill yard were decreased by 80%, because
portant for the long-term stability to avoid the resin oxidation only 20% of filter cake was generated. Operating costs for wastewater
and deactivation. treatment were decreased from 30.0 yuan (RMB)/m3 to 4.5 yuan
③ The stability of the regeneration process: regeneration contains (RMB)/m3 (Table 5) due to lower dose of alkaline and acid consumed.
series of processes including Mn(II) removal, alkaline elution, The capital cost of the new process was 5 million yuan (RMB). It was
water washing, acid transition, and final water washing. All estimated that around 4.8 kg/t EMM of Mn2 +, 5.2 kg/t EMM of NH+ 4
the above processes should be well controlled and finished, so and 0.24 kg/t EMM of Cr(VI) were recovered. The recycled wastewater
that the resin adsorption ability can be totally recovered after proportion was increased from 6.2% to 100%. 1.168 m3/t EMM of fresh
generation. water was saved and equivalent amount of wastewater was reduced
to the environment simultaneously.
3.3.4. Operational effects of the demonstration line
The demonstration line was established to test the running effects in
resource recovery and wastewater recycling in Taifeng. The major 4. Conclusion
equipments of ion-exchangers were shown in Fig. 11. Wastewater
was sampled from every key treating unit as shown in Fig. 12. Water balance results indicated that 4.994 m3/t EMM of water was
All the operating conditions were controlled strictly as required to required by the whole EMM production process. 47.40% of the inlet
make sure that the process can perform stably. The concentration of water was used for making up solutions, and 34.84% was used for

Fig. 12. Wastewater samples from different treatment units. (a) Raw wastewater (Mn2+, NH+ 4 , Cr(VI), Cr
3+
); (b) wastewater after neutralization–coagulation–sedimentation and
pH adjustment (Mn2+, NH+4 , Cr(VI)); (c) wastewater after two-stage filter (Mn
2+
, NH+
4 , Cr(VI)); (d) effluent from ion-exchanger (Mn
2+
, NH+
4 ).
22 F. Xu et al. / Hydrometallurgy 149 (2014) 12–22

Table 5 Pollution Control and Management Technology Major Projects (Grant


Operating cost of the wastewater treatment process. No. 2010ZX212-006), and the National Science and Technology Support
Items Previous operating cost Current operating cost Program (Grant No. 2012BAF03B03).
(yuan (RMB)/m3) (yuan (RMB)/m3)

NaOH 18.3 1.8 References


FeSO4·7H2O 7.2 0
Díaz-Arista, P., Ortiz, Z.I., Ruiz, H., Ortega, R., Meas, Y., Trejo, G., 2009. Electrodeposition
H2SO4 1.4 0.3
and characterization of Zn–Mn alloy coatings obtained from a chloride-based acidic
PAM 0.6 0.1
bath containing ammonium thiocyanate as an additive. Surf. Coat. Technol. 203,
Power energy 1.3 1.1
1167–1175.
Labor 1.2 1.2 Duan, N., Wang, F., Zhou, C.B., Zhu, C.L., Yu, H.B., 2010. Analysis of pollution materials
Sum up 30.0 4.5 generated from electrolytic manganese industries in China. Resour. Conserv. Recycl.
54, 506–511.
Duan, N., Dan, Z.G., Wang, F., Pan, C.X., Zhou, C.B., Jiang, L.H., 2011. Electrolytic manganese
metal industry experience based China's new model for cleaner production promo-
cleaning. Of the outlet water, 43.0% was released via solid waste emis- tion. J. Clean. Prod. 19, 2082–2087.
sion, and 33.0% was discharged in the form of wastewater. Galvanauskaite, N., Sulcius, A., Griskonis, E., Diaz-Arista, P., 2011. Influence of Te (VI) ad-
Electrolyte balance was one critical subsystem contained in the ditive on manganese electrodeposition at room temperature and coating properties.
Trans. IMF 89, 325–332.
whole water balance, which decided the stability and capability of the
Gong, J., Zangari, G., 2003. Electrodeposition of sacrificial tin/manganese alloy coatings.
production process. 3.253 m3/t EMM of water was consumed in Mater. Sci. Eng. A - Struct. 344, 268–278.
the electrolyte system daily, 66.26% of which was used for making up Hagelstein, K., 2009. Globally sustainable manganese metal production and use. J. Environ.
solutions mainly including ammonium solution preparation. 19.71% of Manag. 90, 3736–3740.
Huang, H.M., Xiao, X.M., YAN, B., 2010. Ammonium removal from aqueous solutions by
inlet water was added as the replenishing water to compensate the using natural Chinese (Chende) zeolite as adsorbent. J. Hazard. Mater. 175, 247–252.
electrolyte loss. The outlet water of the electrolyte system was mainly Kelly, J.J., Goods, S.H., Yang, N.Y.C., 2003. High performance nanostructured Ni–Mn alloy
discharged with residues and anode muds. The proportion reached up for microsystem applications. Electrochem. Solid-State Lett. 6, C88–C91.
Lee, S.M., Tiwari, D., Choi, K.M., 2009. Removal of Mn(II) from aqueous solutions using
to 62.68%. manganese-coated sand samples. J. Chem. Eng. Data 54 (6), 1823–1828.
Wastewater balance was the other subsystem in the whole water Liu, T.J., Tan, Z.J., Liao, S.H., 2007. An analysis of trend of EMM industry. China's Manganese
balance, which influenced the product quality and wastewater amounts. Industry, 24 pp. 9–12.
Liu, Y.Y., Chen, K.F., Luo, K., Li, J., Mo, L.H., 2011. Using Mg(OH)2 in peroxide bleaching of
Of the 1.856 m3/t EMM of inlet water, 82.87% was used for washing wheat straw soda-AQ pulp. Bioresources 6, 1230–1241.
plates. Meanwhile, equivalent amount of wastewater was generated Pantsar-Kallio, M., Manninen, P.K.G., 1997. Simultaneous determination of toxic arsenic
from the system. 88.63% of the wastewater was directly discharged and chromium species in water samples by ion chromatography–inductively coupled
plasma mass. Chromatography 779, 139–146.
after traditional reduction–neutralization–sedimentation treatment.
Serkan, S., Mustafa, Y., 2011. Synthesis of a new calixarene derivative and its immobiliza-
Only 6.2% was reused to the electrolyte preparation process. tion onto magnetic nanoparticle surfaces for excellent extractants toward Cr(VI),
Resource recovery and whole recycling of the Cr-containing waste- As(V), and U(VI). J. Chem. Eng. Data 56, 2020–2029.
Sharma, R.K., Rastogi, A.C., Gurmeet, S., 2004. Electrochemical growth and characteriza-
water was proposed. Cr(VI) was recovered from the wastewater by
tion of manganese telluride thin films. Mater. Chem. Phys. 84, 46–51.
ion exchange techniques to prepare EMM passivant. The remaining Sulcius, A., Griskonis, E., Kantminiene, K., Zmuidzinaviciene, N., 2013. Influence of different
wastewater containing Mn2+ and NH+ 4 was recommended to recycle electrolysis parameters on electrodeposition of γ- and α-Mn from pure electrolytes —
to the leaching unit before impurity removal procedures. Water distri- a review with special reference to Russian language literature. Hydrometallurgy 137,
33–37.
bution was regulated to satisfy the water quantity match to achieve Sun, Y., Tian, X.K., He, B.B., Yang, C., Pi, Z.B., Wang, Y.X., Zhang, S.X., 2011. Studies of the
complete wastewater recycling. It was highlighted that the successful reduction mechanism of selenium dioxide and its impact on the microstructure of
implementation of the proposed process is mainly dependent on the manganese electrodeposit. Electrochim. Acta 56, 8305–8310.
Tan, Z.Z., 2013. Chinese EMM Industry in 2012: Reviews and Prospects. http://www.
quality and quantity match between the recycled wastewater and the doc88.com/p-8065956338986.html.
consumed water. Tan, Z.Z., Mei, G.G., 2005. Metallurgy of Manganese. Press of Central South University of
Finally, a demonstration line was established to test the running ef- Technology, Changsha.
Tobiason, J.E., Knocke, W.R., Goodwill, J., Hargette, P., Bouchard, R., Zuravnsky, L., 2008.
fects of the proposed wastewater treatment process. Results showed Characterization of Performance of Filter Media for Manganese Control. AWWA
that it should be feasible to recover resource and recycle wastewater gen- Research Foundation p. 7.
erated in EMM production process. After the new process was adopted, Yang, N.Y.C., Headley, T.J., Kelly, J.J., Hruby, J.M., 2004. Metallurgy of high strength Ni–Mn
microsystems fabricated by electrodeposition. Scr. Mater. 51, 761–766.
over 90% of valuable chemicals in the wastewater were recovered. Solid
Zayed, A., Terry, N., 2003. Chromium in the environment: factors affecting biological
waste disposal cost and the required area for landfill yard were decreased remediation. Plant Soil 249, 139–156.
by 80%. Operating costs for wastewater treatment were decreased by 85% Zhang, W.S., Cheng, C.Y., 2007. Manganese metallurgy review. Part II. Manganese separa-
tion and recovery from solution. Hydrometallurgy 89, 160–177.
from 30.0 yuan (RMB)/m3 to 4.5 yuan (RMB)/m3. Assuming an average of
Zhang, W.S., Shi, Z.J., 2009. Effect, source and removal of impurities in electrolyzed man-
0.77 million t of EMM output annually, 0.9 million t of wastewater was ganese metal. J. Jishou Univ. (Nat. Sci. Ed.) 30, 97–99.
reduced into the environment and 0.9 million t of fresh water will be Zhang, W.S., Mei, G.G., Zhou, Y.M., Liu, R.Y., Zhu, M.J., Mei, J., 2004. Theoretical analysis
saved every year, if the proposed process is popularized in the whole eliminating heavy and production practice of sulfuration for metals in electrolytic
manganese metal. China's manganese industry, 22 pp. 8–10.
EMM production industry. In conclusion, the proposed process exhibits Zhu, X.M., Zhang, Y.S., 1997. Corrosion behaviour of an Fe–Mn–Si shape memory alloy in
significant advantages of better treatment effects, lower costs and aqueous solutions. J. Mater. Sci. Lett. 6, 1516–1517.
environment-friendly over traditional end-of-pipe treatment process.

Acknowledgment

This work was supported by the National Natural Science Founda-


tion of China (Grant No. 51304178, No. 21207077), National Water

You might also like