Volume of planned

No. Bridge Position Operation


works total
1 M1 BRIDGE km 45+208 Demolition of old bridge 1
2 M3 BRIDGE km 48+951 Deck slab 2
3 M4 BRIDGE km 50+816 Abutment piers 4
4 M4 BRIDGE km 50+816 Deck slab 2
5 M5 OVERPASS km 51+438 Precast girders 21
6 M6 OVERPASS km 54+014 Foundation 4
7 M6 OVERPASS km 54+014 Middle Piers 2
8 M7 OVERPASS km 56+354 Montage of girders 18
9 M8 BRIDGE km 56+773 Deck slab 2
10 M9 OVERPASS km 58+170 transverse girders 4
11 M9 OVERPASS km 58+170 Deck slab 1
12 M12 BRIDGE km 61+300 Pedestrian walkways 4
13 M13 BRIDGE km 62+350 Pedestrian walkways 4
14 M14 OVERPASS km 62+938 Deck slab 1
Volume of planned works in Volume of executed production from
February 30th of January to 28th of February
1
1 2
1(2x0.5)
1
14 3
4
2
18
1 1
2
0.5
2 2
4
1 1
Volume of executed production from 30th of Description of executed production from 30th of January
January to 5th of February to 5th of February

2 concreted 2 deck slabs.

3 concreted 3 girders.

1 concreted 1 deck slab.

2 concreted 2 pedestrian walkways.

1 concreted 1 deck slab.