PROGRAM PENGECORAN BATCHINGPLAN PROJECT MANDALIKA

Batching Plan 1 Batching Plan 2

Waktu Kubikasi Kumulatif Waktu Kubikasi Kumulatif


No Item Pengecoran No. TM Ritasi 3
Ket. No Item Pengecoran No. TM Ritasi Ket.
Loading Balik BP m m3 Loading Balik BP m3 m3
A Rabat APBN fc 15 mpa R1 08:30 09:30 1 6 6 APBN A Rabat APBN fc 15 mpa 15 09:00 10:00 1 6 36
R2 08:45 09:45 1 6 12 14 09:15 10:15 1 6 42
20 09:00 10:00 1 6 18 13 09:30 10:30 1 6 48 Close APBN
22 09:15 10:15 1 6 24 B Pengecoran dll. 21 09:45 10:45 1 6 6 All Team
5 09:30 10:30 1 6 30 E Rigid Timur/LC Timur 2 10:00 11:00 1 6 6 Carles
B Pengecoran dll. R1 09:45 10:45 1 8 8 All Team 15 10:15 11:15 1 6 12
R2 10:00 11:00 1 6 14 14 10:30 11:30 1 6 18
20 10:15 11:15 1 6 20 13 10:45 11:45 1 6 24
C Precast Kecil BP1 22 10:30 11:30 1 6 6 Firman D Precast 3X3 21 11:00 12:00 1 6 6 Pak Man
5 10:45 11:45 1 6 12 E Rigid Timur/LC Timur 2 11:15 12:15 1 6 30 Carles
R1 11:00 12:00 1 8 20 15 11:30 12:30 1 6 36
D Precast 3X3 R2 11:15 12:30 1 6 12 Pak Man 14 11:45 12:45 1 6 42
20 11:30 12:45 1 6 18 D Precast 3X3 13 12:00 13:00 1 6 30 Pak Man
22 11:45 13:00 1 6 24 21 12:15 13:15 1 6 36
C Precast Kecil BP1 5 12:00 13:00 1 6 26 Firman 2 12:30 13:30 1 6 42
R1 12:15 13:15 1 8 34 E Rigid Timur/LC Timur 15 12:45 13:45 1 6 48
R2 12:30 13:30 1 6 40 14 13:00 14:00 1 6 54 Carles
D Precast 3X3 20 12:45 14:00 1 6 48 Pak Man 13 13:15 14:15 1 6 60
22 13:00 14:15 1 6 54 21 13:30 14:30 1 6 66
F Rigid MUTIP1 5 13:15 14:15 1 6 6 Adit D Precast 3X3 2 13:45 14:45 1 6 60 Pak Man
R1 13:30 14:30 1 8 14 15 14:00 15:00 1 6 66
R2 13:45 14:45 1 6 20 14 14:15 15:15 1 6 72
20 14:00 15:00 1 6 26 E Rigid Timur/LC Timur 13 14:30 15:30 1 6 72 Carles
C Precast Kecil BP1 22 14:15 15:15 1 6 46 Firman 21 14:45 15:45 1 6 78
5 14:30 15:30 1 6 52 2 15:00 16:00 1 6 84
F Rigid MUTIP1 R1 14:45 15:45 1 8 34 D Precast 3X3 15 15:15 16:15 1 6 84 Pak Man
R2 15:00 16:00 1 6 40 14 15:30 16:30 1 6 90
20 15:15 16:15 1 6 46 E Rigid Timur/LC Timur 13 15:45 16:45 1 6 90 Carles
D Precast 3X3 22 15:30 16:30 1 6 78 Pak Man 21 16:00 17:00 1 6 96
F Rigid MUTIP1 5 15:45 16:45 1 6 52 Adit 2 16:15 17:15 1 6 102
R1 16:00 17:00 1 8 60 D Precast 3X3 15 16:30 17:30 1 6 102 Pak Man
R2 16:15 17:15 1 6 66 14 16:45 17:45 1 6 108
C Precast Kecil BP1 20 16:30 17:30 1 6 58 Firman E Rigid Timur/LC Timur 13 17:00 18:00 1 6 108 Carles
D Precast 3X3 22 16:45 17:45 1 6 96 Pak Man G Rigid Parkir Utara 21 17:15 18:15 1 6 6 Carles
C Precast Kecil BP1 5 17:00 18:00 1 6 64 Firman 2 17:30 18:30 1 6 12
D Precast 3X3 R1 17:15 18:15 1 8 116 Pak Man 15 17:45 18:45 1 6 18
R2 17:30 18:30 1 6 122 14 18:00 19:00 1 6 24
F Rigid MUTIP1 20 17:45 18:45 1 6 72 13 18:15 19:15 1 6 30
22 18:00 19:00 1 6 78 21 18:30 19:30 1 6 36
5 18:15 19:15 1 6 84 2 18:45 19:45 1 6 42
D Precast 3X3 R1 18:30 19:30 1 6 128 Close Pak Man 15 19:00 20:00 1 6 48
C Precast Kecil BP1 R2 18:45 19:45 1 6 70 Close Firman 14 19:15 20:15 1 6 54
F Rigid MUTIP1 20 19:00 20:00 1 6 90 Adit 13 19:30 20:30 1 6 60
22 19:15 20:15 1 6 96 21 19:45 20:45 1 6 66
5 19:30 20:30 1 6 102 2 20:00 21:00 1 6 72
R1 19:45 20:45 1 8 110 15 20:15 21:15 1 6 78
R2 20:00 21:00 1 6 116 14 20:30 21:30 1 6 84
20 20:15 21:15 1 6 122 13 20:45 21:45 1 6 90
22 20:30 21:30 1 6 128 21 21:00 22:00 1 6 96
5 20:45 21:45 1 6 134 2 21:15 22:15 1 6 102
R1 21:00 22:00 1 8 142 15 21:30 22:30 1 6 108
R2 21:15 22:15 1 6 148 14 21:45 22:45 1 6 114
20 21:30 22:30 1 6 154 13 22:00 23:00 1 6 120
22 21:45 22:45 1 6 160 21 22:15 23:15 1 6 126
G Rigid Parkir Utara 5 22:00 23:00 1 6 132 Carles 2 22:30 23:30 1 6 164
R1 22:15 23:15 1 8 140 15 22:45 23:45 1 6 170
R2 22:30 23:30 1 6 146 14 23:00 00:00 1 6 176
20 22:45 23:45 1 6 152 13 23:15 00:15 1 6 182
22 23:00 00:00 1 6 158 21 23:30 00:30 1 6 188
Total Produksi BP1 = 374 m3 2 23:45 00:45 1 6 194
15 00:00 01:00 1 6 200 Close Carles
Noted : Total Produksi BP1 = 366 m3
1. POKOK pengecoran BP1 & BP2 Rabat APBN, Precast & Rigid
2. BP1 & BP2 hanya melayani 20 m3 pengecoran dll. (LC, Mortar dan item diluar pengecoran POKOK)
3. Water Tank tetap SUPORT sampai dengan Batchingplan selesai produksi
4. 5 unit TM di masing - masing BP WAJIB sehat
5. Setiap PJ BP WAJIB mengatur/menghubungi TM agar waktu siklus pengecoran tetap terjaga
6. Setiap PJ BP WAJIB menginfokan segera terkait STOK MATERIAL masing - masing BP