SITE TECHNICAL

QUERY

Client: Saudi Aramco Project: (BI-10-09003) - MARJAN INCREMENT Page: 1/1


SULFUR HANDLING FACILITIES
Technical Query No: NP/MIP14/0070 Rev: 0 Contract:
6600044546
System Facility: Civil
Area Location: PIOB & STP RIO Building
Issued by: NESMA AND PARTNERS

Technical Query: Discipline:


Mechanical
Str. Steel
Reference Docs: Electrical
Instrumentation
Piping
Civil X
Subject: Acid Resistance paint for HM doors at Battery Rooms Pipeline
Process

As per the attached Architectural IFC, the 2 doors in battery rooms in PIOB & STP RIO Building are mentioned to have
acid resistant paint upon which this requirement is not indicated in SAES-P-103 sec 6.2 for battery rooms, in addition, the HM
door is away from the battery racks and coated with 2 coats as per the attached Paint inspection report (refer to page 3 of the
attached file HWO023989).

Recommendation:

Design Consultant to remove this requirement in IFC # C972906005V0F2 & C972915005V0F3 since it is not required, also
redline is not accepted by SAPID.

Attachments:
1. IFC # C972906005V0F2 & C972915005V0F3
2. Abstract from SAES-P-103.
3. Paint Inspection Report.

Originator: Signature: Date: 15 Aug 2023


Danilo Santos
Senior Civil Project Engineer

Schedule Impact: Checked by: Approved by:


Balraj Kathan Construction Hassan El Chami
Manager Project Manager
Cost Impact: Badge:

Signature: Signature:
Answer Required by: 17 Aug 2023
Clarifications / Recommendation

Response By: Signature: Date: Organization:

Classification | Company General Use


Classification | Company General Use