Inspection Note-Udaipur
Inspection Note-Udaipur
Please find the attached Inspection Note of Udaipur City Railway Station
Redevelopment project carried out by JD/GS/SD-V on October 4th and 5th, 2023
(Ashish Verma)
JD/GS/SD-V
Railway Board
DA-As above
Copy :
Officials accompanied:
1.Mr. Mayank Kumar Gupta, Dy. CE/C-II/UDZ
2.Mr. Vikas Kumar Sehra, XEN/Udaipur
3.Mr. Hameed Meer, Team Leader, MS
4.Mr. Sanjay Sharma, Resident Engineer
5.Mr. Ajay Patwari, Resident Engineer)
6.Mr. RB Gupta Project In-Charge, Mr. Gurvit, Construction of VPRPL-KSIPL
JV
SN Items Discussed/Observations
o
1 Appointed Date of Project is 27.10.2022 with Completion Period of 36 months
Physical Progress is 6.10 % and Financial Progress is 6.0 %.
Financial progress needs to be expedited.
2 Work of New ORH at ZRTI campus, Basement Excavation on West Side
building, Mezzanine slab work on East Side building is in progress.
Milestones which are lagging behind shall be expedited and monitoring shall
be done as per revised Base Line Programme and effort shall be made to
complete the Project in Scheduled Completion Time.
Progress needs to be expedited with sufficient mobilization of man and
machinery and other parallel activities like works in Platform area like
replacement of COP’s, Modification of OHE’s shall be started.
7 DBR’s has not been approved for the UDZ station.It was told that it is
pending at HQ. Needs to be approved as it forms the basis of design.
Availability of PMS officials and their deployment should be closely
monitored. Dy/CE/C-II/UDZ and CE/C should ensure regular inspection
and should submit Inspection reports
8 GAD, Structural drawings of Air concourse, through roof, FOB, Skywalk is
under review with AE. Needs to be expedited.
9 Internal Quality Audit of project has been done by Authority Engineer (PMS)
on 03-10-2023.Report is yet to be submitted to Authority.
External Audit is being planned. It needs to be done on priority.
10 Quarterly Video Recording of Site for quarter ending September 2023 needs
to be submitted by EPC Contractor.
11 Work of shifting of Electric Cables, Underground Cables, Sub-station etc is in
progress. It needs to be expedited.