CONTRACTOR'S ENTITLEMENT CLAIMS ( CITADINES - BACOLOD )

Subclause Cost Time Profit Instructions REMARKS

ARTICLE IV: CONSIDERATION

The Contractor shall have the right to suspend work in case the
OWNER fails to pay the progress billings within forty (45) days from
receipt of the billing. Furthermore, the Contractor shall claim Extension
4.8
of Time and incurred cost during the suspension of work. However, in
case this right is exercised, the Contractor shall immediately resume
work upon receipt of the payment for the progress billing;

ARTICLE VI: COMPLETION TIME,


LIQUIDATED DAMAGES

Should the CONTRACTOR be delayed in the implementation of the


Contract due to delays caused by the OWNER, the CONTRACTOR shall
6.2 be entitled to claim for standby time charges/disruption claim and
extension of time which will be determined by the OWNER to cover
the overhead expenses;
ARTICLE VII: OWNER-SUPPLIED
MATERIALS
In the event that the OWNER will take on CONTRACTOR's supplied
7.3 material into an Owner Supplied Materials, incurred cost by the
Contractor shall be compensated accordingly.
ARTICLE VIII: EXTENSION OF CONTRACT
TIME

Extension of contract time shall be granted for rainy/unworkable days


considered unfavorable for the execution of the works at the site,
based on the actual conditions obtained at the site, for such period in Provided, that the OWNER is not bound to take into
excess of the number of rainy/unworkable days predetermined by the account any claim for an extension of time unless
OWNER and/or for the equivalent period of delay due to major the CONTRACTOR has, prior to the expiration of the
calamities such as exceptionally destructive typhoons, floods and contract time and within thirty (30) Calendar Days after
earthquakes, and epidemics, and for causes such as non-delivery on such work has been commenced or after the
time of materials, working drawings, or written information to be circumstances leading to such claim has arisen,
delivered to the OWNER written notices in order that it
furnished by the OWNER, for delay on the part of artists, tradesman or
could have investigated them at the time. Failure to
others engaged by the OWNER, in executing work not forming part of
8.5 provide such notice shall constitute a waiver by the
this Contract, non-acquisition of permit to enter private properties
CONTRACTOR of any claim. No extension of the
within the right-of-way resulting in complete stoppage of construction contract time shall be granted to the CONTRACTOR due
activities, and other meritorious causes as determined by the to (a) ordinary unfavorable weather conditions; (b)
OWNER'S authorized Project Manager and approved by the OWNER. inexcusable failure or negligence of the CONTRACTOR
Shortage of construction material, general labor strikes, peace and to provide the required equipment, supplies or
order, state of calamities, problems that disrupt construction materials; or (c) other causes for which the OWNER is
operations through no fault of the CONTRACTOR may be considered as not directly responsible for;
additional grounds for extension of contract time provided, they are
publicly felt and certified by appropriate government agencies such as
DTI, DOLE, DILG, and DND, among others.

ARTICLE X: SUSPENSION OF WORK

The OWNER or its duly authorized representative shall have the


authority to suspend the work wholly or partly by written order for
such period as may be deemed necessary, due to force majeure or any
fortuitous events or for failure on the part of the public to carry out
valid orders given by the Government or to perform any provisions of
the Contract, or due to adjustment of plans to suit field conditions as
found necessary during construction. The CONTRACTOR shall
immediately comply with such order to suspend the work wholly or
partly. In case of total suspension, or suspension of activities along the
critical path, which is not due to any fault of the CONTRACTOR, the
elapsed time between the effective order of suspending operation and
the order to resume work shall be allowed the CONTRACTOR by
adjusting the contract time accordingly and shall be entitled for any
incurred cost;

Prepared by: Checked and Approved by:


Danica Y. Jaramillo Man Kwong Wong